Coordinated urban path control method considering speed guidance
By dividing coordination sub-areas in urban path coordination control, establishing a speed guidance model and optimizing green wave bandwidth allocation, the problem of speed guidance in path coordination sub-sections in complex urban road networks is solved, traffic efficiency and vehicle speeds are improved, and delays are reduced .
Patent Information
- Application Number
- PCT/CN2023/108846
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-04-06
- Filing Date
- 2023-07-24
- Publication Date
- 2024-10-10
AI Technical Summary
Existing signal coordination control methods are difficult to achieve continuous speed guidance between path coordination sub-areas in complex urban road networks, resulting in low vehicle passing efficiency and multiple delays.
An urban path coordination control method considering speed guidance is adopted. By dividing coordination sub-areas, establishing a speed guidance model and an asymmetric green wave bandwidth coordination model, fuzzy mathematical membership functions and vehicle acceleration models are used to conduct uniform speed, acceleration and deceleration guidance to adapt to Turn to path control to optimize green wave bandwidth allocation.
It improves path traffic efficiency, reduces vehicle delays, and increases vehicle driving speed. It is suitable for regional signal coordination control during peak periods and has been verified through model simulation and actual cases.
Smart Images

Figure CN2023108846_10102024_PF_FP_ABST
Abstract
Description
A coordinated control method for urban paths considering speed guidance Technical Field The present invention relates to the field of urban traffic planning and management traffic control technology, and in particular to an urban path coordination control method considering speed guidance. Background Art In the context of increasingly serious urban congestion, signal coordination control is one of the conventional means, and the improvement of its coordination control method and the research on the object of coordination control are of great significance. However, the current signal coordination control method is still mainly based on trunk coordination control or single-point signal control at a single intersection. For a regional scope, in addition to the main roads, the regional scope also consists of secondary roads or branches around the main roads. For a more complex urban road network, it is more important to coordinate the path by managing the traffic flow on the urban roads to improve the network performance. Urban path signal coordination control is different from trunk line coordination control. Usually, there are vehicle turning behaviors, so the path needs to be divided into sub-areas. However, each sub-area is relatively independent, which makes the path control lack continuity. Therefore, it is necessary to solve how to reasonably guide the speed between the coordinated sub-areas of each path. Summary of the invention The present invention aims to provide a method for coordinated control of urban paths taking into account speed guidance, so as to overcome the deficiencies existing in the prior art. To solve the above technical problems, the technical solution of the present invention is: a method for coordinated control of urban paths taking into account speed guidance, comprising the following steps: Step 1, divide the determined path into coordinated sub-areas, and perform coordinated control on each sub-area and the connecting sections of the sub-areas; Step 2, establish a speed guidance model, which is used to give a recommended speed to vehicles at the upstream intersection so that the vehicles can assemble into a convoy and pass the downstream intersection efficiently and orderly. The speed guidance model includes a uniform speed guidance method, an acceleration guidance method, and a deceleration guidance method; Step 3, based on the coordination sub-area division of the path and the establishment of the speed guidance model, an asymmetric green wave bandwidth coordination model is established. The model uses the green light time in each direction and is suitable for the path coordination control with turning. As an improvement of the urban path coordination control method considering speed guidance of the present invention, in step 1, the setting of the sub-area division coordination control threshold refers to the membership function principle in fuzzy mathematics, the independent variable is the association degree of adjacent intersection sections, and its function value conforms to the normal distribution. The function representation is shown in formula (1): x is the road section association degree. When x < 0.25, there is no need to coordinate the division of the road section; when x ≥ 0.5, it is necessary to coordinate the division of the road section; when 0.25 ≤ x < 0.5, according to the membership function, the critical value τ(x0) at the inflection point of the function is calculated. If τ(x) ≥ τ(x0), coordinated division is required. As an improvement of the urban path coordination control method considering speed guidance of the present invention, in step 2, when selecting the speed guidance model, it is necessary to make a judgment based on the phase moment when the vehicle arrives at the downstream: assuming that the vehicle's driving speed on the road section is v0; the distance between the vehicle and the downstream intersection stop line is l; the intersection signal cycle length is C; t0 is the moment of the current phase in the signal cycle; a is the acceleration of the vehicle; V m is the maximum speed of the vehicle, the time it takes for the vehicle to reach the stop line of the downstream intersection from the guidance point is t, the moment of the signal cycle when the vehicle arrives is t1, [0,X] is the green light time, and [X,C] is the red light time. When the vehicle is moving at a constant speed, formulas (2) and (3) can be obtained: when When the vehicle reaches the speed limit, there is no need to guide the vehicle's speed and the vehicle continues to travel at this speed. As an improvement of the urban path coordination control method considering speed guidance of the present invention, in step 2, when By accelerating the vehicle, it can catch up with the green light time of the downstream intersection, even if Accelerate and guide it, assuming its guiding speed is v g , where v g ≤v m , v m is the maximum speed limit of the road section. The vehicle undergoes two stages: uniform acceleration to the guide speed and uniform speed driving. At this time, the travel time of the vehicle from the guide point to the downstream intersection is: Among them, the vehicle's driving speed on the road section is v0; the guidance speed is v g , a is the acceleration of the vehicle; the time it takes for the vehicle to reach the stop line of the downstream intersection from the guidance point is t. As an improvement of the urban path coordination control method considering speed guidance of the present invention, in step 2, when If the vehicle is accelerated and driven at the maximum speed limit of the road section, and cannot pass the downstream intersection within the current green light time, it will be decelerated and guided to form a new convoy at the intersection and pass the downstream intersection within the green light time of the next cycle. at this time: t=C-t0 (5) The vehicle goes through two stages: uniform deceleration and uniform speed. Suppose their travel times are t a and t b , and t = t a +t b ,but Among them, the time it takes for the vehicle to reach the downstream intersection stop line from the guidance point is t, the intersection signal cycle length is C, t0 is the moment of the current phase in the signal cycle, the distance between the vehicle and the downstream intersection stop line is l, the vehicle's driving speed on the road section is v0, a is the vehicle's acceleration, and the guidance speed is v g . As an improvement of the urban path coordination control method considering speed guidance of the present invention, in step 3, the asymmetric green wave bandwidth coordination model is constructed by adding a 0-1 variable and a left turn coefficient. The steering behavior is represented by △ i The same intersection is used to define the difference between the midpoints of the red lights in the exit and exit directions, and the difference in the duration correction of the left turn phase in different directions. The expression is: The constraints of the model on the conflict variable and the left turn coefficient can be obtained: Among them, L i and Two variables representing the green light time for the left turn phase in the direction of entering and leaving the intersection, r i and At intersection S i The two side roads with red light durations for leaving and entering the intersection, w i and is the conflicting variable for two variables defined as the time length of the red light start and end time and the green wave band centerline, τ i and are two variables for the dissipation time of the downstream intersection vehicle queue, t i and These are two variables for the travel time from the current intersection to the downstream intersection in the upward and downward directions. As an improvement of the urban path coordination control method considering speed guidance of the present invention, in step 3, the path signal coordination control model is obtained by adding path turning and speed guidance conditions through the asymmetric green wave bandwidth model as follows: st Where z is the periodic frequency defined as the reciprocal of the common period; C1 is the minimum period; C2 is the maximum period; k i is the demand ratio of upstream and downstream bandwidth; a i and The saturation of the upstream and downstream sections is variables; d i and are two variables for the distance between adjacent intersections in the up and down directions; f i and are two variables for the upper speed limit of the uplink and downlink sections; e i and are two variables for the lower speed limit of the upward and downward sections; v g and Two variables for the speed reduction guidance of the upward and downward sections; v g 'and h is the two variables for the acceleration guidance speed of the upward and downward sections; i and g are two variables for the upper limit of speed fluctuation in the up and down directions; i and These are two variables for the lower limits of speed fluctuations in the up and down directions. Compared with the prior art, the beneficial effects of the present invention are: the control method can be well applied to the research on commuting path optimization in urban road networks. Different from the traditional single-point signal optimization and trunk green wave coordination optimization, the signal coordination control can be carried out for the main routes of inter-regional travel during peak hours; it has been demonstrated through model simulation analysis and actual case applications, and is beneficial to improving path efficiency, reducing vehicle delays and increasing vehicle driving speeds. BRIEF DESCRIPTION OF THE DRAWINGS In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work. Figure 1 is a diagram of the membership function of path coordination partitioning; Figure 2 shows the speed guidance principle; Figure 3 is a time-distance diagram of the asymmetric green wave bandwidth model; Figure 4 shows four schemes involving a dedicated left-turn phase; Figure 5 is a plan view of the research path; FIG6 is a simulation diagram of the path in Synchro. DETAILED DESCRIPTION The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. A method for coordinated control of urban paths considering speed guidance comprises the following steps As shown in FIG1 , step 1 is to divide the determined path into coordinated sub-areas, and to perform coordinated control on each sub-area and the connecting sections of the sub-areas respectively. The setting of the sub-area division coordination control threshold refers to the membership function principle in fuzzy mathematics. The independent variable is the correlation between adjacent intersection sections. The function value conforms to the normal distribution. The function representation is shown in formula (1):
[0014] : x is the road section association degree. When x < 0.25, there is no need to coordinate the division of the road section; when x ≥ 0.5, it is necessary to coordinate the division of the road section; when 0.25 ≤ x < 0.5, according to the membership function, the critical value τ(x0) at the inflection point of the function is calculated. If τ(x) ≥ τ(x0), coordinated division is required. As shown in FIG2 , step 2 is to establish a speed guidance model. The speed guidance model is used to give a recommended speed to vehicles at the upstream intersection so that the vehicles can be assembled into a convoy to pass through the downstream intersection efficiently and orderly. The speed guidance model includes a uniform speed guidance method, an acceleration guidance method, and a deceleration guidance method. Among them, in step 2, when selecting the speed guidance model, it is necessary to make a judgment based on the phase time when the vehicle arrives at the downstream: assuming that the vehicle's driving speed on the road section is v0; the vehicle is at a distance from the downstream intersection The stop line distance is l; the intersection signal cycle length is C; t0 is the moment of the current phase in the signal cycle; a is the acceleration of the vehicle; V m is the maximum speed of the vehicle, the time it takes for the vehicle to reach the stop line of the downstream intersection from the guidance point is t, the moment of the signal cycle when the vehicle arrives is t1, [0,X] is the green light time, and [X,C] is the red light time. When the vehicle is moving at a constant speed, formulas (2) and (3) can be obtained: when When the vehicle reaches the speed limit, there is no need to guide the vehicle's speed and the vehicle continues to travel at this speed. In step 2, when By accelerating the vehicle, it can catch up with the green light time of the downstream intersection, even if Accelerate and guide it, assuming its guiding speed is v g , where v g ≤v m , v m is the maximum speed limit of the road section. The vehicle undergoes two stages: uniform acceleration to the guide speed and uniform speed driving. At this time, the travel time of the vehicle from the guide point to the downstream intersection is: Among them, the vehicle's driving speed on the road section is v0; the guidance speed is v g , a is the acceleration of the vehicle; the time it takes for the vehicle to reach the stop line of the downstream intersection from the guidance point is t. In step 2, when If the vehicle is accelerated and driven at the maximum speed limit of the road section, and cannot pass the downstream intersection within the current green light time, it will be decelerated and guided to form a new convoy at the intersection and pass the downstream intersection within the green light time of the next cycle. at this time: t=C-t0 (5) The vehicle goes through two stages: uniform deceleration and uniform speed. Suppose their travel times are t a and t b , and t = t a +t b ,but Among them, the time it takes for the vehicle to reach the downstream intersection stop line from the guidance point is t, the intersection signal cycle length is C, t0 is the moment of the current phase in the signal cycle, the distance between the vehicle and the downstream intersection stop line is l, the vehicle's driving speed on the road section is v0, a is the vehicle's acceleration, and the guidance speed is v g . As shown in Figure 3, after studying the coordination sub-area division and speed guidance control of the path, it is necessary to conduct reasonable coordination control of each coordination sub-area. By adding the advantage of bandwidth asymmetry on the basis of the MULTIBAND model, an asymmetric green wave bandwidth coordination model is established. This model can better utilize the green light time in each direction and is suitable for the coordinated control of the path with turning. The meanings of the parameters in the figure are as follows: S i (S i+1 ): intersection number; In the up (down) direction, the width of the green wave belt between adjacent intersections; In the uplink (downlink) direction, the bandwidth width is on the left side of the bandwidth center line; In the uplink (downlink) direction, the bandwidth width on the right side of the bandwidth center line; Intersection S i The duration of the red light in the direction of leaving (entering) the intersection; The conflict variable is defined as the time length between the start (end) time of the red light and the center line of the green wave band; The time it takes for the vehicle queue at the downstream intersection to dissipate; The red light offset is defined as the difference between the midpoints of the red lights in the exit and exit directions at the same intersection; The travel time from the current intersection to the downstream intersection in the upward (downward) direction; Phase difference is defined as the difference between the midpoint times of the same-phase red lights at adjacent intersections. In step 3, the asymmetric green wave bandwidth coordination model is constructed by adding 0-1 variables and left Turning coefficient Represents the steering behavior. There are four main phase modes for setting up a dedicated left-turn phase, as shown in Figure 4, and the corresponding left-turn coefficient values are shown in Table 1. Table 1 Left turn coefficient values in different phase modes Use △ i The same intersection is used to define the difference between the midpoints of the red lights in the exit and exit directions, and the difference in the duration correction of the left turn phase in different directions. The expression is: The constraints of the model on the conflict variable and the left turn coefficient can be obtained: Among them, L i and Two variables representing the green light time for the left turn phase in the direction of entering and leaving the intersection, r i and At intersection S i The two side roads with red light durations for leaving and entering the intersection, w i and is the conflicting variable for two variables defined as the time length of the red light start and end time and the green wave band centerline, τ i and are two variables for the dissipation time of the downstream intersection vehicle queue, t i and These are two variables for the travel time from the current intersection to the downstream intersection in the upward and downward directions. In step 3, the path signal coordination control model is obtained by adding path steering and speed guidance conditions through the asymmetric green wave bandwidth model as follows: st Where z is the periodic frequency defined as the reciprocal of the common period; C1 is the minimum period; C2 is the maximum period; k iis the demand ratio of upstream and downstream bandwidth; a i and are two variables of the saturation of the upstream and downstream sections; d i and are two variables for the distance between adjacent intersections in the up and down directions; f i and are two variables for the upper speed limit of the uplink and downlink sections; e i and are two variables for the lower speed limit of the upward and downward sections; v g and Two variables for the speed reduction guidance of the upward and downward sections; v g 'and h is the two variables for the acceleration guidance speed of the upward and downward sections; i and g are two variables for the upper limit of speed fluctuation in the up and down directions; i and Two variables for the lower limit of speed fluctuation in the up and down directions Note: The unit of period is s; the unit of distance is m; the unit of speed is km / h. In order to verify the feasibility of this application, the case selected the main commuting routes in a regional road network in Suzhou Industrial Park, Jiangsu Province, for model programming solution and simulation data analysis. The research route consists of 6 intersections, represented by S1 to S6, and its adjacent sections are represented by L1 to L5. The east-west direction is the two main roads of Dushu Lake Avenue and Jinji Lake Avenue, and the north-south direction is Xingtang Street. Its road plan is shown in Figure 5. Considering that the main traffic on this route is commuters, and the traffic volume is larger during the evening peak, and there are vehicle queues at the intersection, the case location was investigated during the evening peak on weekdays to obtain the peak hour traffic and signal timing schemes of each intersection. According to the definition of correlation, intersections S1 to S4 are divided into the first sub-area, intersections S5 and S6 are divided into the second sub-area, and speed guidance is carried out on the connecting sections (from Xingtang Street to Lianfeng Road on Jinji Lake Avenue). The average speed of vehicles that finally pass through the deceleration guidance is about 50km / h, and the speed at which they finally reach and pass through the downstream intersection is about 20km / h. According to the path signal coordination control model proposed in steps 1-3 of this application, each sub-area is studied and the road section guidance speed is input. Lingo linear programming software is used for programming and solving. The common cycle of the path intersection is obtained to be 112s, and the road section bandwidth, intersection conflict variable and phase difference are obtained. Furthermore, as shown in FIG6 , a path model is established in the Synchro software, and data such as flow and timing are input. The common cycle, phase difference, and section guide speed obtained from the model are also input, and the output results are compared and analyzed through simulation. In order to prove the feasibility of the coordination scheme in this paper, the signal timing optimization function of Synchro is used to optimize the current path and simulate the output results. The data of the coordination scheme in this paper, the Synchro optimization scheme and the current path scheme are compared and analyzed. The evaluation indicators such as green wave bandwidth, delay and number of stops are shown in Tables 2 and 3. Comparative analysis shows that, since the demand ratio of uplink bandwidth is higher than that of downlink bandwidth, Synchro ensures the green wave bandwidth in the uplink direction during optimization, and therefore abandons the green wave bandwidth in the downlink direction at sections L2 and L3. Although the green wave bandwidth of the model in this paper is narrower than that of the Synchro optimization solution in some sections, the green wave band is more continuous considering the two-way traffic. Table 2 shows the comparison of bidirectional green wave bandwidth Table 3 shows the comparison of main evaluation indicators Compared with the current path plan, the total path delay obtained by the model in this paper is reduced by 10.8%, the total number of path stops is reduced by 219 times, accounting for 6.7%, and the average vehicle speed is increased by 5.6%; compared with the Synchro optimization plan, the total path delay is reduced by 5.6%, the total number of path stops is slightly different, and the average vehicle speed is increased by 2.2%. It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates. In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A method for coordinated control of urban paths taking into account speed guidance, characterized in that: The following steps are included: Step 1, divide the determined path into coordinated sub-areas, and perform coordinated control on each sub-area and the connecting sections of the sub-areas; Step 2, establish a speed guidance model, which is used to give a recommended speed to vehicles at the upstream intersection so that the vehicles can assemble into a convoy and pass the downstream intersection efficiently and orderly. The speed guidance model includes a uniform speed guidance method, an acceleration guidance method, and a deceleration guidance method; Step 3, based on the coordination sub-area division of the path and the establishment of the speed guidance model, an asymmetric green wave bandwidth coordination model is established. The model uses the green light time in each direction and is suitable for the path coordination control with turning.
2. The urban path coordination control method considering speed guidance according to claim 1 is characterized in that: In step 1, the setting of the sub-area division coordination control threshold refers to the membership function principle in fuzzy mathematics. The independent variable is the correlation between adjacent intersection sections. The function value conforms to the normal distribution. The function representation is shown in formula (1): x is the road section correlation degree. When x<0.25, there is no need to coordinate the division of the road section; when x≥0.5, it is necessary to coordinate the division of the road section; when 0.25≤x<0.5, according to the membership function, the critical value τ(x0) at the inflection point of the function is calculated. If τ(x)≥τ(x0), coordinated division is required.
3. The urban path coordination control method considering speed guidance according to claim 1 is characterized in that: In step 2, when selecting the speed guidance model, it is necessary to make a judgment based on the phase moment when the vehicle arrives at the downstream: assuming that the vehicle's driving speed on the road section is v0; the distance between the vehicle and the downstream intersection stop line is l; the intersection signal cycle length is C; t0 is the moment of the current phase in the signal cycle; a is the acceleration of the vehicle; V m is the maximum speed of the vehicle, the time it takes for the vehicle to reach the stop line of the downstream intersection from the guidance point is t, the moment of the signal cycle when the vehicle arrives is t1, [0,X] is the green light time, and [X,C] is the red light time. When the vehicle is moving at a constant speed, formulas (2) and (3) can be obtained: when When the vehicle reaches the speed limit, there is no need to guide the vehicle's speed and the vehicle continues to travel at this speed.
4. The urban path coordination control method considering speed guidance according to claim 3 is characterized in that: In step 2, when By accelerating the vehicle, it can catch up with the green light time of the downstream intersection, even if Accelerate and guide it, assuming its guiding speed is v g , where v g ≤v m , v m is the maximum speed limit of the road section. The vehicle undergoes two stages: uniform acceleration to the guide speed and uniform speed driving. At this time, the travel time of the vehicle from the guide point to the downstream intersection is: Among them, the vehicle's driving speed on the road section is v0; the guidance speed is v g , a is the acceleration of the vehicle; the time it takes for the vehicle to reach the stop line of the downstream intersection from the guidance point is t.
5. The urban path coordination control method considering speed guidance according to claim 4 is characterized in that: In step 2, when If the vehicle is accelerated and driven at the maximum speed limit of the road section, and cannot pass the downstream intersection within the current green light time, it will be decelerated and guided to form a new convoy at the intersection and pass the downstream intersection within the green light time of the next cycle. at this time: t=C-t0 (5) The vehicle goes through two stages: uniform deceleration and uniform speed. Suppose their travel times are t a and t b , and t = t a +t b ,but Among them, the time it takes for the vehicle to reach the downstream intersection stop line from the guidance point is t, the intersection signal cycle length is C, t0 is the moment of the current phase in the signal cycle, the distance between the vehicle and the downstream intersection stop line is l, the vehicle's driving speed on the road section is v0, a is the vehicle's acceleration, and the guidance speed is v g .
6. The urban path coordination control method considering speed guidance according to claim 1 is characterized in that: In step 3, the asymmetric green wave bandwidth coordination model is constructed by adding a 0-1 variable and a left turn coefficient. The steering behavior is represented by △ i The same intersection is used to define the difference between the midpoints of the red lights in the exit and exit directions, and the difference in the duration correction of the left turn phase in different directions. The expression is: The constraints of the model on the conflict variable and the left turn coefficient can be obtained: Among them, L i and Two variables representing the green light time of the left turn phase in the direction of entering (leaving) the intersection, r i and At intersection S i The two sides of the red light duration for the direction of leaving and entering the intersection Road, w i and is the conflicting variable for two variables defined as the time length of the red light start and end time and the green wave band centerline, τ i and are two variables for the dissipation time of the downstream intersection vehicle queue, t i and These are two variables for the travel time from the current intersection to the downstream intersection in the upward and downward directions.
7. The urban path coordination control method considering speed guidance according to claim 6 is characterized in that: In step 3, the path signal coordination control model is obtained by adding path steering and speed guidance conditions through the asymmetric green wave bandwidth model as follows: Where z is the periodic frequency defined as the reciprocal of the common period; C1 is the minimum period; C2 is the maximum period; k i is the demand ratio of upstream and downstream bandwidth; a i and are two variables of the saturation of the upstream and downstream sections; d i and are two variables for the distance between adjacent intersections in the up and down directions; f i and are two variables for the upper speed limit of the uplink and downlink sections; e i and are two variables for the lower speed limit of the upward and downward sections; v g and Two variables for guiding vehicle speed reduction in the upward and downward directions; v g 'and h is the two variables for the acceleration guidance speed of the upward and downward sections; i and g are two variables for the upper limit of speed fluctuation in the up and down directions; i and These are two variables for the lower limits of speed fluctuations in the up and down directions.
Citation Information
Patent Citations
Method capable of dynamically partitioning traffic control subregion
CN101639978A
Signal control intersection vehicle speed guiding system and guiding method in vehicle road coordination environment
CN108765982A
Signal coordination control sub-region division method and device, storage medium and terminal equipment
CN111341110A
Urban path coordination control method considering speed guidance
CN116386363A
Method for controlling traffic lights at crossings to design green wave, involves changing speed of vehicles for co-ordination of green waves in both directions along street
DE102007033899A1
Cited By
Long trunk road multi-path coordination green wave optimization method and system based on electronic police data
CN119132079A
Motorcade driving control method, system and device and readable storage medium
CN119479261A
Multipath signal coordination control method oriented to bus priority
CN119541231A
A multi-path signal coordination control method for public transport priority
CN119541231B
Multi-path main road signal cooperative control method considering speed fluctuation
CN119580509A