A technology of sliding form and injection roadway, which is applied in the direction of earthwork drilling, pillar/bracket, wellbore lining, etc. It can solve the problems of not being able to move as a whole, and achieve the effect of easy transportation and use, simple structure and strong applicability
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2010-12-08
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to a gob-side entry support technology of a coal mine recovery roadway, in particular to a gob-side entry support method in which the side of a gob-side entry is supported by a concrete pouring side filling wall. The utility model also includes a filling mold slip form for filling a wall next to a concrete pouring road. Background technique
[0002] In order to reduce the loss of coal pillars between the transportation lane and the return airway in the coal mining section, coal pillarless mining is adopted, that is, it is close to the goaf, and the transportation channel of the previous section is reserved and maintained as the return air of the lower section Along the trough, no coal pillars are left in between, which saves the process of digging a roadway for the mining of the next working face. In order to achieve the above purpose, it is necessary to strengthen the support on the side of the goaf behind the support while mini...
Examples
Embodiment Construction
[0031] The present invention will be further described below in conjunction with drawings and embodiments.
[0032] exist figure 1 Fig. 1 shows the arrangement of the entry slip form 6, bunker brackets 3 and 5, head bracket 1 and other equipment in the gob-side entry retaining support method of the present invention at the lower end of the fully mechanized mining face.
[0033] The gob-side entry retaining support method of the present invention is to move along with the fully mechanized mining face, after the header support 1, transport the goaf 7 side of the trough 13, use the concrete pump to transport the concrete long-distance through the pipeline, and pour it to the filling mold , the filling concrete 9 in the filling mold is solidified, and the roadside filling wall 8 (or the roadside filling body) is constructed to form the roadside support belt. Maintain the transport chute in the previous section and use it as the return air chute in the lower section.
[0034] For...