A frp-concrete assembly method based on bim model

An assembly method and concrete technology, applied in geometric CAD, design optimization/simulation, special data processing applications, etc., can solve problems such as weak model visualization ability, conflict of reserved holes and steel bars, hidden dangers of structural safety, etc., to achieve operation and maintenance Effects of visual management, reduction of project cost, and structural safety

CN108133107BInactive Publication Date: 2021-07-23CENT RES INST OF BUILDING & CONSTR CO LTD MCC GRP +1
4 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Publication Date
2021-07-23
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
Patent Text Reader

Abstract

The invention discloses a FRP-concrete assembly method based on a BIM model. The specific steps include: decomposing the structural system based on the BIM model—decomposing into composite components of different FRP composite materials and concrete—prefabrication based on the BIM model—based on the BIM On-site assembly of the model - based on the BIM model for post-maintenance; use the BIM model to solve problems arising from scheme-construction-post-maintenance, etc. A BIM model-based FRP-concrete assembly method provided by the present invention uses the BIM model to integrate all the data together to realize resource sharing, realize visual management of operation and maintenance, avoid secondary processing, thereby shortening the construction period and further making the structure Greater safety and the ability to quickly locate building components.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the field of civil engineering, in particular to a BIM model-based FRP-concrete assembly method. Background technique

[0002] In areas such as coastal areas and remote sea islands and reefs, traditional reinforced concrete structures and steel structure projects have shortcomings such as serious corrosion and short maintenance periods. According to estimates, in 2009, the economic loss caused by corrosion in my country exceeded 1 trillion yuan, and 1.5 tons of steel were corroded every second. The corrosion loss of the marine industry accounts for about 1 / 3 of the country's total corrosion loss, reaching more than 600 billion yuan. Ocean engineering, especially construction projects on remote sea islands and reefs far from the land, still faces technical difficulties such as difficult sea transportation of raw materials, high construction costs, long construction periods, and poor structural durability. Resource development ...

Examples

Embodiment Construction

[0039] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0040]The embodiment of the present invention discloses a FRP-concrete assembly method, which uses the BIM model to integrate all the data together, realize resource sharing, realize visual management of operation and maintenance, avoid secondary processing, thereby shorten the construction period, and further make the structure more secure , but also to quickly locate building components.

[0041] A BIM model-based FRP-concrete assembly method specifically in...