A fully automatic carton packaging machine
Through the design of a fully automatic carton packaging machine, the automatic processing and bagging of cartons is achieved using components such as lifting racks and hot melt adhesives, which solves the problems of high operation difficulty, large land and high cost in the existing technology, and improves the problem of Efficiency and cost reduction.
Patent Information
- Application Number
- CN201811560700.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-12-20
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2038-12-20
AI Technical Summary
The existing tissue box packaging machine is difficult to operate, difficult for non-professional personnel, low efficiency, large area, high cost, and requires multiple people to operate, which wastes resources.
Design a fully automatic carton packaging machine, including a workbench, lifting rack and hot melt adhesive machine, and realize automatic processing and spraying of cartons by forming synchronous conveyor belts, turntables, suction cups, cylinders, edge folding devices and box pressing devices. The glue and bag are equipped with mechanical transmission and pneumatic, which simplifies operation, reduces manual operation and reduces the equipment footprint.
It improves work efficiency by 50%, reduces manual operation volume, reduces equipment floor area by more than 50%, and reduces packaging cost by 30%, making it suitable for mass production.
Smart Images

Figure CN109551815B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of paper boxes, and in particular to a fully automatic paper box packaging machine. Background Art
[0002] With the continuous improvement of people's living standards, the demand for paper towel boxing is increasing. The existing paper towel boxing packaging machine is difficult to operate. It is difficult for non-professionals to master the operation and adjust the specifications. The whole process operation will make people's work efficiency low, and more people are required to operate. A fully automatic packaging machine can be designed to provide convenience for the staff. The paper towel boxing packaging machine occupies a large area, which is not conducive to the placement of other equipment. The overall cost is high and a certain amount of resources will be wasted. Summary of the invention
[0003] The object of the present invention is to provide a fully automatic carton packaging machine to solve the problems raised in the above background technology.
[0004] To achieve the above-mentioned purpose, the present invention provides the following technical scheme: a fully automatic carton packaging machine, comprising a workbench, a lifting frame and a hot-melt glue machine, wherein a lifting frame is arranged on one side of the upper surface of the workbench, a hot-melt glue machine is arranged on the other side of the upper surface of the workbench, a forming synchronous conveyor belt is arranged between the lifting frame and the hot-melt glue machine, the bottom of the workbench is fixedly connected to the bracket, the bottom of the bracket is fixedly connected to a horizontally placed pad through a support rod, the top of the lifting frame is symmetrically fixedly connected to a fixed bracket, a slide rail is connected to the inner side of the fixed bracket, the slide rail is movably connected to a slider, the slider is fixedly connected to the outer side of a vertically placed carton slot plate, a fixing rod is arranged inside the carton slot plate, the lower ends of the fixing rod and the carton slot plate extend into the lifting frame, a first adjusting motor is fixedly connected to the upper right side of the lifting frame, a turntable is arranged inside the lifting frame, a first bevel gear is connected to the turntable, and the first bevel gear is fixedly connected to the second bevel gear through a connecting rod. The second bevel gear is located on one side of the workbench, and a synchronous belt is sleeved on the second bevel gear. The other end of the synchronous belt is connected to the main motor, and the main motor is fixedly connected to the inner side of the bracket, and the main motor and the lifting frame are located on the same side. The workbench is fixedly connected with a second motor, and a paper feeding conveyor belt is arranged inside the second motor. The second motor and the second bevel gear are located on the same side, and the second bevel gear is connected to the third bevel gear through a forming synchronous conveyor belt. The second bevel gear and the third bevel gear are located on the same horizontal line. A second adjusting motor is arranged between the second bevel gear and the third bevel gear. The second adjusting motor is fixedly connected to one side of the workbench, and conveyor belt baffles are evenly and fixedly connected to the forming synchronous conveyor belt. Folding devices are arranged on both sides of the forming synchronous conveyor belt, and the folding device is located between adjacent conveyor belt baffles. One end of the forming synchronous conveyor belt is located inside the lifting frame, and the other end of the forming synchronous conveyor belt is located inside the hot melt adhesive machine.
[0005] Preferably, a cooling plate is provided at the bottom of the hot melt adhesive machine, one end of the cooling plate is connected to the molding synchronous conveyor belt, and the other end of the cooling plate extends into the bagging device, and the bagging device is fixedly connected to the outer side of the bracket.
[0006] Preferably, the turntable is fixedly connected with cylinders, the cylinders are arranged in a cross shape, and suction cups are fixedly connected to both ends of the cylinders, and the outer ends of the suction cups are located outside the turntable.
[0007] Preferably, a box pressing device is connected to one side of the hot melt adhesive machine, one end of the box pressing device is located on one side of the lifting frame, and the bottom of the box pressing device is located on the conveyor belt baffle.
[0008] Preferably, the folding device has the same height as the conveyor belt baffle, the folding device is flush with the upper end of the paper feed conveyor belt, and the folding device and the second adjustment motor are located between the lifting frame and the hot melt adhesive machine.
[0009] Preferably, the bracket is a U-shaped rod, and a cooling water trough and an air pump are fixedly connected to the inner side of the bottom of the U-shaped rod. The cooling water trough is located under the cooling plate, and the air pump is located under the lifting frame.
[0010] Compared with the prior art, the beneficial effects of the present invention are as follows: a lifting frame is set up to perform preliminary processing on the original paper box, the paper box enters the lifting frame through the paper box slot plate, is opened by using a turntable, a suction cup and a cylinder, and then is placed on a forming synchronous conveyor belt for subsequent processing, and finally passes through a hot melt glue machine, a cooling plate and a bagging device to automatically spray glue and seal it, and finally is bagged; a foot pad is set up to prevent the bracket from rubbing against the ground and causing damage to the bracket itself; a slide rail and a slider are set up to increase the speed of putting the paper box in, improve work efficiency, and prevent the paper box from being stuck, causing the equipment to fail to operate normally; the paper feed conveyor belt provides sufficient materials for the paper box, which provides convenience for designing paper boxes of different sizes; the folding device and the box pressing device cooperate with each other to control the height of the paper box The length and size of the carton are controlled by the machine. The operation is simple and the size of the carton is adjusted digitally, which increases the work efficiency by 50%. The carton is finally automatically sprayed with glue at a fixed point by a hot melt glue machine. After spraying, it passes through a cooling plate and enters a bagging device, which can automatically bag the carton according to the size of the carton. In the carton production process, integration is adopted, that is, one person is required to operate, which reduces the workload of manual labor. The preliminary processing of the carton and the final spraying and bagging are all completed on the workbench, which changes the situation where multiple devices work in different places, reduces the floor area by about 50%, and provides more other space for people. Mechanical transmission and pneumatics are used in the carton packaging process, which reduces the cost of carton packaging by 30%, making it suitable for mass production. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0012] Figure 2 It is a structural schematic diagram of the workbench of the present invention.
[0013] In the figure: 1. workbench; 2. lifting frame; 3. slider; 4. slide rail; 5. cylinder; 6. turntable; 7. suction cup; 8. first bevel gear; 9. connecting rod; 10. paper box slot plate; 11. fixed bracket; 12. first adjusting motor; 13. hot melt glue machine; 14. cooling plate; 15. bagging device; 16. cooling water trough; 17. foot pad; 18. air pump; 19. first motor; 20. second bevel gear; 21. paper feeding conveyor belt; 22. synchronous belt; 23. main motor; 24. second adjusting motor; 25. third bevel gear; 26. box pressing device; 27. folding device; 28. conveyor belt baffle; 29. forming synchronous conveyor belt; 30. bracket. DETAILED DESCRIPTION
[0014] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0015] In the description of the present invention, it should be noted that the terms "vertical", "up", "down", "horizontal", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0016] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0017] See also Figure 1-2The present invention provides a technical solution: a fully automatic carton packaging machine, comprising a workbench 1, a lifting frame 2 and a hot melt glue machine 13, wherein the lifting frame 2 is arranged on one side of the upper surface of the workbench 1, and the hot melt glue machine 13 is arranged on the other side of the upper surface of the workbench 1, and a forming synchronous conveyor belt 29 is arranged between the lifting frame 2 and the hot melt glue machine 13, the bottom of the workbench 1 is fixedly connected to the bracket 30, and the bottom of the bracket 30 is fixedly connected to the horizontally placed pad 17 through a support rod, and the lifting frame 2 is arranged to perform preliminary processing on the original carton, and the carton passes through the carton slot plate 10 and enters the lifting frame. In the frame 2, the turntable 6, the suction cup 7 and the cylinder 4 are used to cooperate to open it, and then it is placed on the molding synchronous conveyor belt 29 for subsequent processing, and finally it passes through the hot melt glue machine 13, the cooling plate 14 and the bagging device 15, and it is automatically sprayed with glue and sealed, and finally bagged. A foot 17 is provided to prevent the bracket 30 from rubbing against the ground and causing damage to the bracket 30 itself. The slide rail 4 and the slider 3 are provided, and the carton enters the lifting frame 2 along the carton slot plate 10, which can increase the speed of carton placement, improve work efficiency, and prevent the carton from being stuck, causing the equipment to not be able to work properly. Normal operation, the main motor 23 drives the synchronous belt 22 to move, the first bevel gear 8 and the second bevel gear 20 are connected by the connecting rod 9, which can drive the turntable 6 to rotate in coordination. When the turntable 6 rotates, it can drive the upper, middle and lower cylinders to move. At this time, the upper position sucks the box, the middle position opens the box, and the lower position puts the box. The carton is preliminarily processed and falls on the forming synchronous conveyor belt 29. The second motor 19 drives the paper feed conveyor belt 21 to move. The paper feed conveyor belt 21 provides sufficient materials for the carton, which is convenient for designing cartons of different sizes. The second bevel gear 20 The third bevel gear 25 drives the forming synchronous conveyor belt 29 to move horizontally. During the movement, the second adjusting motor 24 drives the folding device 27 to work. The folding device 27 and the box pressing device 26 cooperate with each other to control the height and length of the carton and the size of the carton. The operation is simple and the size of the carton is adjusted digitally, which improves the work efficiency by 50%. The carton is finally automatically sprayed with glue at a fixed point by the hot melt glue machine 13. After spraying, it passes through the cooling plate 14 and enters the bagging device 15. The bagging device 15 can automatically bag the carton according to the size of the carton.The top of the lifting frame 2 is symmetrically fixedly connected with a fixed bracket 11, the inner side of the fixed bracket 11 is connected with a slide rail 4, the slide rail 4 is movably connected with the slider 3, the slider 3 is fixedly connected to the outer side of the vertically placed carton slot plate 10, a fixed rod is arranged inside the carton slot plate 10, the lower ends of the fixed rod and the carton slot plate 10 extend into the lifting frame 2, a first adjusting motor 12 is fixedly connected to the upper right side of the lifting frame 2, a turntable 6 is arranged inside the lifting frame 2, a first bevel gear 8 is connected to the turntable 6, the first bevel gear 8 is fixedly connected to the second bevel gear 20 through a connecting rod 9, the second bevel gear 20 is located on one side of the workbench 1, a synchronous belt 22 is sleeved on the second bevel gear 20, the other end of the synchronous belt 22 is connected to the main motor 23, the main motor 23 is fixedly connected to the inner side of the bracket 30, and the main motor 23 and the lifting frame 2 are located on the same side, the working A second motor 19 is fixedly connected to the workbench 1, a paper feed conveyor belt 21 is arranged inside the second motor 19, the second motor 19 and the second bevel gear 20 are located on the same side, the second bevel gear 20 is connected to the third bevel gear 25 through a forming synchronous conveyor belt 29, the second bevel gear 20 and the third bevel gear 25 are located on the same horizontal line, a second adjusting motor 24 is arranged between the second bevel gear 20 and the third bevel gear 25, the second adjusting motor 24 is fixedly connected to one side of the workbench 1, and conveyor belt baffles 28 are evenly and fixedly connected to the forming synchronous conveyor belt 29, folding devices 27 are arranged on both sides of the forming synchronous conveyor belt 29, the folding devices 27 are located between adjacent conveyor belt baffles 28, one end of the forming synchronous conveyor belt 29 is located inside the lifting frame 2, and the other end of the forming synchronous conveyor belt 29 is located inside the hot melt adhesive machine 13.
[0018] Furthermore, a cooling plate 14 is provided at the bottom of the hot melt adhesive machine 13 , one end of the cooling plate 14 is connected to the molding synchronous conveyor belt 29 , and the other end of the cooling plate 14 extends into the bagging device 15 , and the bagging device 15 is fixedly connected to the outer side of the bracket 30 .
[0019] Furthermore, the turntable 6 is fixedly connected with cylinders 4 , which are arranged in a cross shape, and both ends of the cylinders 4 are fixedly connected with suction cups 7 , and the outer ends of the suction cups 7 are located outside the turntable 6 .
[0020] Furthermore, a box pressing device 26 is connected to one side of the hot melt adhesive machine 13 , one end of the box pressing device 26 is located on one side of the lifting frame 2 , and the bottom of the box pressing device 26 is located on the conveyor belt baffle 28 .
[0021] Furthermore, the folding device 27 has the same height as the conveyor belt baffle 28 , the folding device 27 is flush with the upper end of the paper feed conveyor belt 21 , and the folding device 27 and the second adjustment motor 24 are located between the lifting frame 2 and the hot melt adhesive machine 13 .
[0022] Furthermore, the bracket 30 is a U-shaped rod, and a cooling water tank 16 and an air pump 18 are fixedly connected to the inner side of the bottom of the U-shaped rod. The cooling water tank 16 is located under the cooling plate 14, and the air pump 18 is located under the lifting frame 2.
[0023] Working principle: the carton enters the lifting frame 2 along the carton slot plate 10, and the slide rail 4 and the slider 3 are set to increase the speed of carton placement, improve work efficiency, and prevent the carton from being stuck, causing the equipment to not operate normally. The main motor 23 drives the synchronous belt 22 to move, and the first bevel gear 8 and the second bevel gear 20 are connected by the connecting rod 9, which can drive the turntable 6 to rotate in coordination. When the turntable 6 rotates, it can drive the upper, middle and lower cylinders to move. At this time, the upper position sucks the box, the middle position opens the box, and the lower position puts the box, and the carton is preliminarily processed. The carton falls on the forming synchronous conveyor belt 29, and the second motor 19 drives the paper feeding conveyor belt 21 to move. The paper feeding conveyor belt 21 is The carton provides sufficient materials and facilitates the design of cartons of different sizes. The second bevel gear 20 and the third bevel gear 25 drive the forming synchronous conveyor belt 29 to move horizontally. During the movement, the second adjusting motor 24 drives the folding device 27 to work. The folding device 27 and the box pressing device 26 cooperate with each other to control the height and length of the carton and the size of the carton. The operation is simple and the size of the carton is adjusted digitally, which improves the work efficiency by 50%. The carton is finally automatically sprayed with glue at a fixed point by the hot melt glue machine 13. After spraying, it passes through the cooling plate 14 and enters the bagging device 15. The bagging device 15 can automatically bag according to the size of the carton.
[0024] It is worth noting that the entire device is controlled by a main control button. Since the device matched with the control button is a common device and belongs to the existing common technology, its electrical connection relationship and specific circuit structure will not be described in detail here.
[0025] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A fully automatic carton packaging machine, comprising a workbench (1), a lifting frame (2) and a hot melt glue machine (13), wherein the lifting frame (2) is arranged on one side of the upper surface of the workbench (1), the hot melt glue machine (13) is arranged on the other side of the upper surface of the workbench (1), a forming synchronous conveyor belt (29) is arranged between the lifting frame (2) and the hot melt glue machine (13), the bottom of the workbench (1) is fixedly connected to a bracket (30), the bottom of the bracket (30) is fixedly connected to a horizontally placed pad (17) through a support rod, the top of the lifting frame (2) is symmetrically fixedly connected to a fixed bracket (11), the inner side of the fixed bracket (11) A slide rail (4) is connected, the slide rail (4) is movably connected to the slider (3), the slider (3) is fixedly connected to the outer side of a vertically placed carton slot plate (10), a fixing rod is arranged inside the carton slot plate (10), the lower ends of the fixing rod and the carton slot plate (10) extend into the lifting frame (2), a first regulating motor (12) is fixedly connected to the upper right side of the lifting frame (2), a rotating disk (6) is arranged inside the lifting frame (2), a first bevel gear (8) is connected to the rotating disk (6), the first bevel gear (8) is fixedly connected to the second bevel gear (20) through a connecting rod (9), and the second bevel gear (20) is located on one side of the workbench (1) The second bevel gear (20) is sleeved with a synchronous belt (22), the other end of the synchronous belt (22) is connected to a main motor (23), the main motor (23) is fixedly connected to the inner side of the bracket (30), and the main motor (23) and the lifting frame (2) are located on the same side, the workbench (1) is fixedly connected with a second motor (19), the inner side of the second motor (19) is provided with a paper feed conveyor belt (21), the second motor (19) and the second bevel gear (20) are located on the same side, the second bevel gear (20) is connected to the third bevel gear (25) through a molded synchronous conveyor belt (29), and the second bevel gear (20) and the third bevel gear (25) are located on the same horizontal line, a second regulating motor (24) is arranged between the second bevel gear (20) and the third bevel gear (25), the second regulating motor (24) is fixedly connected to one side of the workbench (1), and a conveyor belt baffle (28) is evenly and fixedly connected to the molding synchronous conveyor belt (29), a folding device (27) is arranged on both sides of the molding synchronous conveyor belt (29), and the folding device (27) is located between adjacent conveyor belt baffles (28), one end of the molding synchronous conveyor belt (29) is located inside the lifting frame (2), and the other end of the molding synchronous conveyor belt (29) is located inside the hot melt adhesive machine (13); A cooling plate (14) is provided at the bottom of the hot melt adhesive machine (13), one end of the cooling plate (14) is connected to the molding synchronous conveyor belt (29), and the other end of the cooling plate (14) extends into the bagging device (15), and the bagging device (15) is fixedly connected to the outer side of the bracket (30); The rotating disk (6) is fixedly connected to a cylinder (5), the cylinders (5) are arranged in a cross shape, and suction cups (7) are fixedly connected to both ends of the cylinders (5), and the outer ends of the suction cups (7) are located outside the rotating disk (6); One side of the hot melt adhesive machine (13) is connected to a box pressing device (26), one end of the box pressing device (26) is located on one side of the lifting frame (2), and the bottom of the box pressing device (26) is located on the conveyor belt baffle (28); The folding device (27) has the same height as the conveyor belt baffle (28), the folding device (27) is flush with the upper end of the paper feeding conveyor belt (21), and the folding device (27) and the second adjustment motor (24) are located between the lifting frame (2) and the hot melt adhesive machine (13); The bracket (30) is a U-shaped rod, and a cooling water trough (16) and an air pump (18) are fixedly connected to the inner side of the bottom of the U-shaped rod. The cooling water trough (16) is located under the cooling plate (14), and the air pump (18) is located under the lifting frame (2).