Screeds and Pavers
By arranging adjustable hooking blocks and opening structures on the screed, rapid assembly of screed sections is achieved, which solves the problem of frequent adjustments in the prior art and significantly reduces assembly time and manpower consumption.
Patent Information
- Application Number
- CN201811431230.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-11-28
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2038-11-28
AI Technical Summary
Existing screeds require frequent adjustments in height and front-to-back direction during assembly, which consumes a lot of time and manpower.
Design a screed that includes an adjustable hooking block and an opening structure. The hooking block can be adjusted in the height direction, and precise positioning is achieved through the adjusting rod and fixed plate, reducing the need for adjustment during subsequent assembly.
The rapid assembly of screed sections is achieved, reducing the time and manpower required for subsequent assembly and improving construction efficiency.
Smart Images

Figure CN109577145B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a screed and a paving machine. Background Art
[0002] The screed plate is a very important working device on the paver, which is used to compact, smooth and shape the road surface. In order to adapt to different paving widths, a set of screed plates often includes multiple screed plate sub-segments such as a basic segment and an extended segment that can be assembled together by fasteners such as bolts. During transportation, for convenience, only the basic segment is often retained on the main body of the paver, and the extended segment is removed and transported separately; each time the construction is carried out, according to different paving width requirements, the user needs to assemble the extended segments of different widths on both sides to the basic segment in the middle in sequence. In order to achieve a good construction effect, when assembling multiple screed plate sub-segments, it is often necessary to ensure that the multiple screed plate sub-segments are flush in the height direction and the front-to-back direction. The prior art has set an adjustment mechanism on the screed plate sub-segment so that the height or front-to-back direction of the screed plate sub-segments can be adjusted when assembling the screed plate sub-segments to ensure that the multiple screed plate sub-segments are flush. However, a defect of the prior art is that the screed plate sub-segments usually need to be adjusted in height and / or front-to-back direction each time they are assembled, which is time-consuming and labor-intensive. Summary of the invention
[0003] The purpose of the present invention is to provide a screed plate with which screed plate sub-sections can be quickly assembled. After the adjustment mechanism of the screed plate sub-sections is initially installed and adjusted, there is no need to adjust the screed plate sub-sections in height or in the front-to-back direction when the screed plate is subsequently assembled, thereby greatly reducing the time and manpower required for assembling the screed plate.
[0004] To achieve the above object, the technical solution adopted by the present invention is:
[0005] A screed plate comprises at least two screed plate sub-segments which can be assembled together by fasteners, characterized in that a hanging block which can be adjusted in the height direction or an opening which can accommodate the hanging block is provided on the end plate of one of the screed plate sub-segments, and an opening which can accommodate the hanging block or a hanging block which can be adjusted in the height direction is provided on the end plate of the other screed plate sub-segment, and the opening limits the hanging block in the height direction and in the front-rear direction of movement of the screed plate.
[0006] The hanging block passes through a window on the end plate where it is located, and the hanging block can be adjusted in the height direction in the window.
[0007] One end of the hanging block is located on the inner side of the end plate, and the other end is located on the outer side of the end plate. The inner end has a threaded hole that can accommodate the adjustment rod to pass vertically and be threadedly connected with the threaded hole, and the outer end corresponds to the opening on the end plate of another ironing plate sub-section.
[0008] The end portion of the hanging block located on the outer side of the end plate where the hanging block is located has a hook.
[0009] At least one fixed plate for accommodating the passage of the adjusting rod is arranged on the inner side of the end plate located above and / or below the window. The adjusting rod and the fixed plate are rotatably connected to each other. While supporting the adjusting rod, the fixed plate can realize the height adjustment movement of the hanging block by rotating the adjusting rod.
[0010] The upper parts of the two side surfaces of the opening are initial hanging parts formed by slope surfaces opened outward, and the hanging blocks entering the opening are guided by the initial hanging parts.
[0011] The width of the lower parts of the two side surfaces of the opening matches the width of the accommodated hanging blocks.
[0012] A plurality of the hanging blocks or a plurality of the openings are arranged on the end plate of one of the screed plate sub-sections, and a plurality of the openings or a plurality of hanging blocks are arranged on the end plate of the other screed plate sub-section.
[0013] A paving machine, characterized by having an ironing plate as described in any one of items 1-8.
[0014] The beneficial effects of the present invention are:
[0015] The present invention provides a screed plate capable of quickly assembling screed plate sub-sections and a paving machine using the screed plate. After the adjustment mechanism of the screed plate sub-sections is initially installed and adjusted, the screed plate sub-sections do not need to be adjusted in height or in the front-rear direction when the screed plate is subsequently assembled, thereby greatly reducing the time and manpower required for assembling the screed plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a three-dimensional schematic diagram of the ironing plate of Example 1;
[0017] Figure 2 It is a three-dimensional schematic diagram of a screed sub-section of Example 1;
[0018] Figure 3 A side view of a screed sub-section of Example 1;
[0019] Figure 4 It is a two-dimensional and three-dimensional schematic diagram of a screed sub-segment of Example 1;
[0020] Figure 5 This is a front view of the second screed sub-section of the first embodiment (viewed from the back to the front);
[0021] Figure 6 It is a side view of the second screed sub-section of the first embodiment;
[0022] Figure 7 It is a cross-sectional view of the AA section 2 of the screed plate of the first embodiment;
[0023] Figure 8 This is a three-dimensional schematic diagram of the ironing board of Example 2;
[0024] Fig. 9 This is a three-dimensional schematic diagram of a screed sub-segment of Example 2;
[0025] Fig.10 A side view of a screed sub-section of the second embodiment;
[0026] Fig.11 It is a two-dimensional and three-dimensional schematic diagram of the screed sub-section of the second embodiment;
[0027] Fig.12 This is a front view of the second screed sub-section of the second embodiment (viewed from the back to the front);
[0028] Fig.13 It is a side view of the second screed sub-section of the second embodiment;
[0029] Fig.14 It is a cross-sectional view of the AA section of the second screed plate of the second embodiment;
[0030] In the figure, 1-ironing plate sub-segment one, 2-ironing plate sub-segment two, 11-ironing plate frame one, 12-opening one, 13-opening two, 14-connecting hole one, 111-end plate one, 121-initial hanging position, 21-ironing plate frame two, 22-hanging block, 23-adjusting rod, 24-connecting hole two, 211-end plate two, 212-window, 213-fixing plate, 221-hook. DETAILED DESCRIPTION
[0031] The screed plate generally includes multiple screed plate sub-segments. For the convenience of description, only two screed plate sub-segments are considered in this embodiment, namely, screed plate sub-segment 1 and screed plate sub-segment 2, wherein screed plate sub-segment 1 is a basic segment or an extended segment installed to the basic segment, and screed plate sub-segment 2 is an extended segment to be installed. Those skilled in the art can know that in other embodiments, more screed plate sub-segments can be added in the same manner.
[0032] In order to reduce the transport width, the mounting block is preferably arranged on the inner side of the extension section to be installed, and an opening that matches the mounting block is arranged on the outer side of the basic section or the extension section. At this time, under the action of deadweight, the mounting block matches the lower part of the opening to limit the height direction of the screed sub-section to be installed. However, it is conceivable that the reverse is also feasible.
[0033] Embodiment 1
[0034] like Figures 1 to 7As shown, in the first embodiment, the screed plate sub-segment 2 includes a hanging block 22, a screed plate frame 21 and an adjustment rod 23. The screed plate sub-segment 1 includes a screed plate frame 11 and an opening (such as opening 12) that matches the hanging block 22. The screed plate frame 11 has an end plate (end plate 111) on the side, and the screed plate frame 21 has an end plate (end plate 211) with a window 212 on the side. The hanging block 22 passes through the window 212 on the end plate 211 of the screed plate sub-segment 2. The opening size of the window 212 matches the cross-sectional clearance of the hanging block 22 passing therethrough, so that the hanging block 22 can be adjusted in the height direction in the window 222. One end of the hanging block 22 is located inside the second end plate 211, and the other end is located outside the second end plate 211. The end located inside has a threaded hole, which can accommodate the adjustment rod 23 to pass vertically and be threadedly connected with the threaded hole. The end located outside has a hook 221. When the screed plate sub-segment 2 is assembled with the screed plate sub-segment 1, the hook 221 is hooked in the opening on the end plate 111 of the screed plate sub-segment 1, so that the position of the screed plate sub-segment 2 relative to the screed plate sub-segment 1 in the paving width direction can be limited. A fixing plate 213 that can accommodate the adjustment rod 23 passing through is respectively arranged above and below the window inside the second end plate 211. The fixing plate 213 is rotatably connected with the adjustment rod 23, so that the adjustment movement of the hanging block 22 in the vertical direction can be realized by rotating the adjustment rod 23. The two side edges of the opening 12 are initial hanging parts 121 formed by outwardly open slope surfaces. The size of the initial hanging part 121 in the front-to-back direction (i.e., the width size of the open edge) is larger than the width size of the end of the hanging block 22 located on the outside, so that when the ironing plate sub-segment 2 is hung close to the ironing plate sub-segment 1, it only needs to be roughly positioned. When the hanging block 22 is inserted into the initial hanging part 121 of the opening, the ironing plate sub-segment 2 falls by its own weight, so that the hanging block 22 and the lower part of the opening 12 can be matched, thereby limiting the height direction of the ironing plate sub-segment 2; the front and rear side edges of the lower part of the opening 12 can simultaneously accurately limit the hanging block 22 and then the ironing plate sub-segment 2 in the front and rear directions.
[0035] When there is only one hanging block 22, the matching portion between the hanging block 22 and the opening is preferably in surface contact (eg, plane contact) to prevent the screed sub-segment 2 from swinging back and forth relative to the screed sub-segment 1.
[0036] The screed plate sub-segment 1 also has 4 connection holes (such as the connection hole 14); the screed plate sub-segment 2 also has 4 connection holes (such as the connection hole 24). Through the above adjustment and matching, the positions of the screed plate sub-segment 1 and the screed plate sub-segment 2 have been adjusted to the right position, and can be connected and fixed together through the connection holes 14 and the connection holes 24 that match in size and position.
[0037] Embodiment 2
[0038] like Figures 8 to 14 As shown, in the second embodiment, the screed plate sub-segment 2 includes two hanging blocks 22, and the screed plate sub-segment 1 includes two openings (opening 12 and opening 2 13) that match the hanging blocks. The structure and matching relationship of opening 12 and hanging block 22 are the same as those of the first embodiment. In addition to limiting the hanging block 22 in the height direction, opening 12 also limits the hanging block 22 in the front and rear directions at the same time. The bottom width of opening 2 13 is greater than the width of the hanging block to be accommodated, and only limits the hanging block in the height direction. However, it can be known that opening 12 and opening 2 13 can also limit the hanging block 22 in the height direction and the front and rear directions at the same time, or opening 12 limits the hanging block in the height direction and the front direction, while opening 2 13 limits the hanging block in the height direction and the rear direction. Since there are two hanging blocks, the hanging block 22 and the opening can be in line contact at the matching position in the height direction, and the two line contacts are sufficient to prevent the screed sub-segment 2 from swinging forward and backward relative to the screed sub-segment 1. It should be noted that the front refers to the forward direction of the paver or the direction from the screed to the main machine of the paver, and the rear refers to the backward direction of the paver or the direction from the main machine of the paver to the screed.
[0039] The adjusting rod 23 is rotatably assembled with the screed frame 21, and the adjusting rod 23 is assembled with the hanging block 22 by threaded fit, so that the height of the hanging block 22 relative to the screed frame 21 can be adjusted by rotating the adjusting rod 23, so that the manufacturing error or the wear of different degrees caused by use can be compensated. The size of the initial hanging part 121 in the front-to-back direction is larger than the size of the hanging block 22, so that when the screed sub-segment 22 is hung close to the screed sub-segment 1, only rough positioning is required; when the hanging block 22 is inserted into the initial hanging part 121 of the opening, the screed sub-segment 22 is made to fall by its own weight, so that the hanging block 22 can be matched with the lower part of the opening, thereby limiting the height direction of the screed sub-segment 22; the front and rear sides of the lower part of the opening can simultaneously accurately limit the hanging block 22 and then the screed sub-segment 2 in the front and rear directions. The hook 221 arranged at the end of the hanging block 22 can limit the distance between the screed plate sub-segment 2 and the screed plate sub-segment 1 in the paving width direction, so as to facilitate fastening of bolts, nuts and other fasteners through the connecting hole 14 on the screed plate sub-segment 1 and the connecting hole 24 on the screed plate sub-segment 2 for fastening.
[0040] Due to the arrangement of the hanging block and the opening, the height of the hanging block 22 only needs to be adjusted once during the initial installation. During subsequent assembly, there is no need to adjust the height or front-to-back direction of the ironing plate sub-section. It is only necessary to hang the ironing plate sub-section in place and install fasteners such as bolts, thereby greatly reducing the ironing plate assembly time and manpower.
Claims
1. A screed plate, comprising at least two screed plate sub-sections which can be assembled together by fasteners, characterized in that: A hanging block adjustable in height direction or an opening for accommodating the hanging block is provided on the end plate of one of the screed plate sub-sections, and an opening for accommodating the hanging block or a hanging block adjustable in height direction is provided on the end plate of the other screed plate sub-section, and the opening limits the hanging block in height direction and in the front-rear direction of the screed plate movement; The hanging block is inserted into a window on the end plate where it is located, and the hanging block can be adjusted in the height direction in the window; One end of the hanging block is located on the inner side of the end plate, and the other end is located on the outer side of the end plate. The inner end has a threaded hole that can accommodate the adjustment rod to pass vertically and be threadedly connected with the threaded hole, and the outer end corresponds to the opening on the end plate of another ironing plate sub-section.
2. The ironing screed according to claim 1, characterized in that: The end portion of the hanging block located outside the end plate where the hanging block is located has a hook.
3. The ironing plate according to claim 1, characterized in that: At least one fixing plate capable of accommodating the passage of the adjusting rod is arranged on the inner side of the end plate located above and / or below the window, and the adjusting rod is rotatably matched with the fixing plate.
4. The ironing plate according to claim 1, characterized in that: The upper parts of the two side surfaces of the opening are initial hanging parts formed by slope surfaces opened outward, and the hanging blocks entering the opening are guided by the initial hanging parts.
5. The ironing plate according to claim 1, characterized in that: The width of the lower parts of the two side surfaces of the opening matches the width of the accommodated hanging blocks.
6. The ironing screed according to claim 1, characterized in that: A plurality of the hanging blocks or a plurality of the openings are arranged on the end plate of one of the screed plate sub-sections, and a plurality of the openings or a plurality of hanging blocks are arranged on the end plate of the other screed plate sub-section.
7. A paver, characterized in that: A screed as claimed in any one of claims 1 to 6.