Battery conversion voltage calculation system, method, battery and battery charging device

By calculating the equivalent charging resistance of the lithium-ion battery and setting the actual conversion voltage value in real time, the problem of voltage failure due to temperature changes during the charging process of the lithium-ion battery is solved, the charging efficiency is improved, and the charging time is ensured.

CN109738819BActive Publication Date: 2024-10-18SHANGHAI AWINIC TECH CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN201811502180.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-12-10
Publication Date
2024-10-18
Estimated Expiration
2038-12-10

AI Technical Summary

Technical Problem

During the charging process of lithium-ion batteries, due to changes in parameters such as temperature, the actual battery voltage fails to reach the set conversion voltage value, resulting in a prolonged charging process and reduced charging efficiency.

Method used

By calculating the equivalent charging resistance of the battery during the charging process, the actual conversion voltage value of the battery is set in real time, so that when the battery is converted to constant voltage charging at the set conversion voltage value, the actual voltage can reach the rated voltage of the battery, thereby improving charging efficiency.

Benefits of technology

It effectively avoids the prolongation of the charging process due to the influence of parameters such as temperature, improves the charging efficiency of lithium-ion batteries, and ensures the optimization of battery charging time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109738819B_ABST
    Figure CN109738819B_ABST
Patent Text Reader

Abstract

The present application discloses a battery conversion voltage calculation system, method, battery and battery charging device, wherein the battery conversion voltage calculation system calculates the equivalent charging resistance of the battery during the charging process by collecting the average voltage of the battery during the same charging time at different charging currents. After obtaining the equivalent charging resistance, the actual conversion voltage value of the battery is determined according to the equivalent charging resistance, thereby avoiding the problem in the prior art that the rated voltage of the battery is directly used as the conversion voltage, which leads to the influence of parameters such as temperature, and the charging process is prolonged due to the premature conversion from constant current charging mode to constant voltage charging mode, thereby reducing the battery charging efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of lithium-ion batteries, and more specifically, to a battery conversion voltage calculation system, method, battery, and battery charging device. Background Art

[0002] In portable devices, lithium-ion (Li-Ion) batteries have been widely used due to their small size, large capacity, and repeated charge and discharge capabilities.

[0003] The process of charging a lithium-ion battery generally includes a pre-charging process, a constant current charging process and a constant voltage charging process. Generally, when a lithium-ion battery starts to charge, its voltage is low. It is first pre-charged with a small current, and then converted to a large current to quickly charge the lithium-ion battery in a constant current charging manner. As charging proceeds, when the battery voltage gradually increases and reaches the set conversion voltage (the rated voltage of the battery), the charging process will transition from a constant current charging mode to a constant voltage charging mode, and the charging current will gradually decrease until it is fully charged.

[0004] However, in actual application, it is found that as the charging process proceeds, due to changes in parameters such as temperature, when the measured battery voltage reaches the set conversion voltage, the actual battery voltage does not reach the conversion voltage value, thereby prolonging the battery charging process to a certain extent and reducing the battery charging efficiency. Summary of the invention

[0005] In order to solve the above technical problems, the present application provides a battery conversion voltage calculation system, method, battery and battery charging device, which calculates the equivalent charging resistance of the battery during the charging process and sets the actual conversion voltage value of the battery in real time, so that when the battery is converted to a constant voltage charging mode at the set actual conversion voltage value, the actual voltage can reach the rated voltage of the battery, thereby achieving the purpose of improving the charging efficiency of the battery.

[0006] To achieve the above technical objectives, the present application provides the following technical solutions:

[0007] A battery conversion voltage calculation system, comprising:

[0008] a voltage sampling module, used for sampling the voltage of the battery during the process of charging with a first preset current for a first preset time, so as to obtain a plurality of first sampled voltages; and used for sampling the voltage of the battery during the process of charging with a second preset current for a first preset time, so as to obtain a plurality of second sampled voltages, wherein the first preset current is different from the second preset current;

[0009] an internal resistance calculation module, configured to average a plurality of the first sampled voltages to obtain a first average voltage, and average a plurality of the second sampled voltages to obtain a second average voltage; and to calculate an equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage;

[0010] The conversion voltage calculation module is used to calculate the conversion voltage value of the battery according to the equivalent charging resistance of the battery calculated by the internal resistance calculation module, the rated voltage of the battery and the constant current charging current of the battery, and use the conversion voltage value as the actual conversion voltage value of the battery.

[0011] Optionally, also include:

[0012] The voltage comparison module is used to determine whether the current voltage of the battery is greater than a preset voltage, and if so, send a first enabling signal to the voltage sampling module to trigger the voltage sampling module.

[0013] Optionally, the voltage sampling module includes: a charging current setting unit and a sampling unit; wherein,

[0014] The charging current setting unit is used to set the charging current of the battery to a first preset current upon receiving the first enable signal, and control the sampling unit to sample the output voltage of the battery within a first preset time to obtain a plurality of first sampled voltages; and is used to set the charging current of the battery to a second preset current upon receiving the second enable signal, and control the sampling unit to sample the output voltage of the battery within the first preset time to obtain a plurality of second sampled voltages;

[0015] The internal resistance calculation module is specifically used to average the multiple first sampling voltages to obtain the first average voltage, and send the second enable signal to the charging current setting unit; and is used to average the multiple second sampling voltages after receiving the multiple second sampling voltages to obtain the second average voltage.

[0016] Optionally, the internal resistance calculation module calculates the equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage and the second average voltage, and is specifically used to substitute the first preset current, the second preset current, the first average voltage and the second average voltage into a first preset formula to calculate and obtain the equivalent charging resistance of the battery;

[0017] The first preset formula is: BIR =(V BAT2 -V BAT1 ) / (I CHG -I CHG1 ), where RBIR Represents the equivalent charging resistance of the battery; V BAT2 represents the second average voltage, V BAT1 represents the first average voltage, I CHG represents the second preset current, I CHG1 represents the first preset current.

[0018] Optionally, the conversion voltage calculation module uses the conversion voltage value as the actual conversion voltage value of the battery for:

[0019] According to the conversion voltage value, a charging voltage lookup table of the battery is queried, and a charging voltage in the charging voltage lookup table that is closest to the conversion voltage value is used as the actual conversion voltage value of the battery.

[0020] Optionally, the second preset current is greater than the first preset current;

[0021] And the second preset current is the constant current charging current of the battery.

[0022] A method for calculating battery conversion voltage, comprising:

[0023] Collecting a first average voltage of the battery during charging with a first preset current for a first preset time;

[0024] collecting a second average voltage of the battery during charging for a first preset time at a second preset current, where the first preset current is different from the second preset current;

[0025] Calculating an equivalent charging resistance of a battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage;

[0026] The conversion voltage value of the battery is calculated according to the equivalent charging resistance of the battery, the rated voltage of the battery and the constant current charging current of the battery obtained by the internal resistance calculation module, and the conversion voltage value is used as the actual conversion voltage value of the battery.

[0027] Optionally, the collecting of a first average voltage of the battery during a first preset time when the charging current is a first preset current; collecting of a second average voltage of the battery during a first preset time when the charging current is a second preset current, before the first preset current is different from the second preset current, further includes:

[0028] Determine whether the current voltage of the battery is greater than the preset voltage. If so, enter the step of collecting the first average voltage of the battery during the first preset time when the charging current is a first preset current; and collect the second average voltage of the battery during the first preset time when the charging current is a second preset current.

[0029] Optionally, collecting a first average voltage of a battery during charging with a first preset current for a first preset time includes:

[0030] The charging current of the battery is set to a first preset current, and the output voltage of the battery is sampled within a first preset time to obtain a plurality of first sampled voltages;

[0031] Averaging a plurality of the first sampled voltages to obtain the first average voltage;

[0032] The collecting of the second average voltage of the battery during the charging process of the battery with a second preset current for a first preset time comprises:

[0033] The charging current of the battery is set to a second preset current, and the output voltage of the battery is sampled within a first preset time to obtain a plurality of second sampled voltages;

[0034] A plurality of the second sampling voltages are averaged to obtain the second average voltage.

[0035] Optionally, calculating the equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage includes:

[0036] Substituting the first preset current, the second preset current, the first average voltage and the second average voltage into a first preset formula to calculate and obtain the equivalent charging resistance of the battery;

[0037] The first preset formula is: BIR =(V BAT2 -V BAT1 ) / (I CHG -I CHG1 ), where R BIR Represents the equivalent charging resistance of the battery; V BAT2 represents the second average voltage, V BAT1 represents the first average voltage, I CHG represents the second preset current, I CHG1 represents the first preset current.

[0038] Optionally, taking the converted voltage value as the actual converted voltage value of the battery includes:

[0039] According to the conversion voltage value, a charging voltage lookup table of the battery is queried, and a charging voltage in the charging voltage lookup table that is closest to the conversion voltage value is used as the actual conversion voltage value of the battery.

[0040] A battery comprises the battery conversion voltage calculation system as described in any one of the above items.

[0041] A battery charging device comprises the battery conversion voltage calculation system as described in any one of the above items.

[0042] It can be seen from the above technical scheme that the embodiments of the present application provide a battery conversion voltage calculation system, method, battery and battery charging device, wherein the battery conversion voltage calculation system calculates the equivalent charging resistance of the battery during the charging process by collecting the average voltage of the battery during the same charging time with different charging currents. After obtaining the equivalent charging resistance, the actual conversion voltage value of the battery is determined according to the equivalent charging resistance, thereby avoiding the problem in the prior art that the rated voltage of the battery is directly used as the conversion voltage, which leads to the influence of parameters such as temperature, and the charging process is prolonged due to the premature conversion from constant current charging mode to constant voltage charging mode, thereby reducing the battery charging efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying any creative work.

[0044] Figure 1 A schematic diagram of a battery charging circuit in the prior art;

[0045] Figure 2 It is a schematic diagram comparing the ideal charging voltage curve and the actual charging voltage curve;

[0046] Figure 3 It is a schematic diagram for comparing the ideal charging current curve and the actual charging current curve;

[0047] Figure 4 A schematic diagram of the structure of a battery conversion voltage calculation system provided by one embodiment of the present application;

[0048] Figure 5 A structural schematic diagram of a battery conversion voltage calculation system provided for another embodiment of the present application;

[0049] Figure 6 A schematic diagram comparing the charging voltage curve of the present solution with the charging voltage curve in the prior art;

[0050] Figure 7 A schematic diagram comparing the charging current curve of the present solution with the charging current curve in the prior art;

[0051] Figure 8 A schematic diagram of a circuit structure of a specific battery conversion voltage calculation system provided for one embodiment of the present application;

[0052] Fig. 9 A schematic diagram of the structure of a battery conversion voltage calculation method provided for one embodiment of the present application. DETAILED DESCRIPTION

[0053] As described in the background art, in the prior art, directly using the rated voltage of the battery as the conversion voltage for converting the battery from a constant current charging mode to a constant voltage charging mode will reduce the charging efficiency of the battery.

[0054] Specifically, during the battery charging process, the circuit formed by the battery charging device and the battery is referenced Figure 1 , Figure 1 VIN in the figure indicates the input voltage of the battery charger system, VBAT indicates the output voltage of the battery charger system, and V BATO Indicates the battery voltage, C BAT Represents the equivalent capacitance of the battery. In this circuit, there is an equivalent charging resistance R from the output end of the battery charger to the output end of the battery. BIR , usually the contact resistance R from the printed circuit board (PCB) mainboard to the battery CONTACT , the trace resistance R on the printed circuit board PCB And the battery internal resistance R CELL Composition, namely:

[0055] R BIR =R CONTACT +R PCB +R CELL (1);

[0056] In formula (1), the contact resistance R CONTACT and the trace resistance R on the printed circuit board PCB The difference is large in different application scenarios, and the battery internal resistance R CELL There will be large differences due to changes in ambient temperature and battery usage time.

[0057] If the battery rated voltage V is directly BAT_FULL As the conversion voltage V from constant current charging to constant voltage charging REG , then the measured battery voltage is equal to the conversion voltage V REG When the equivalent charging resistance R BIR The voltage division will make the actual voltage of the battery less than the rated voltage V BAT_FULLIn this case, the constant voltage charging stage is entered in advance, which reduces the charging current in advance, resulting in a lower charge amount in the same time and a longer charging time. The actual charging curve is compared with the ideal charging curve for reference Figure 2 and Figure 3 , Figure 2 This is a schematic diagram comparing the ideal charging voltage curve and the actual charging voltage curve. Figure 3 Figure 2 is a comparison diagram of the ideal charging current curve and the actual charging current curve. Figure 2 and Figure 3 It can be seen that this method of setting the battery conversion voltage will extend the battery charging time and reduce the charging efficiency.

[0058] To address this problem, some solutions have taken measures to directly raise the conversion voltage by a fixed voltage difference △V based on the rated voltage of the battery, that is:

[0059] V REG =V BAT_FULL +△V;

[0060] The principle of this solution is to increase the constant voltage charging voltage, compensate for the voltage drop on the equivalent charging resistor, thereby delaying the conversion point from constant current to constant voltage, and increasing the charging time in the constant current stage, so that the charging characteristic curve is closer to the ideal value.

[0061] However, the disadvantage of this solution is that it only works when △V=I cc ×R BIR Only when △V cc ×R BIR When △V>I cc ×R BIR This solution will still cause the battery to enter the constant voltage charging stage early during the charging process and cannot effectively improve the charging efficiency; cc Represents constant current charging current; and it will vary greatly with factors such as ambient temperature and battery life. Therefore, this solution is difficult to compensate for the equivalent charging resistance voltage drop in practical applications.

[0062] In view of this, an embodiment of the present application provides a battery conversion voltage calculation system, characterized by comprising:

[0063] a voltage sampling module, used for sampling the voltage of the battery during the process of charging with a first preset current for a first preset time, so as to obtain a plurality of first sampled voltages; and used for sampling the voltage of the battery during the process of charging with a second preset current for a first preset time, so as to obtain a plurality of second sampled voltages, wherein the first preset current is different from the second preset current;

[0064] ​an internal resistance calculation module, configured to average a plurality of the first sampled voltages to obtain a first average voltage, and average a plurality of the second sampled voltages to obtain a second average voltage; and to calculate an equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage;

[0065] The conversion voltage calculation module is used to calculate the conversion voltage value of the battery according to the equivalent charging resistance of the battery calculated by the internal resistance calculation module, the rated voltage of the battery and the constant current charging current of the battery, and use the conversion voltage value as the actual conversion voltage value of the battery.

[0066] The battery conversion voltage calculation system calculates the equivalent charging resistance of the battery during the charging process by collecting the average voltage of the battery during the same charging time at different charging currents. After obtaining the equivalent charging resistance, the actual conversion voltage value of the battery is determined according to the equivalent charging resistance, thereby avoiding the problem in the prior art that the rated voltage of the battery is directly used as the conversion voltage, which causes the charging process to be prolonged due to the influence of parameters such as temperature, thereby reducing the battery charging efficiency.

[0067] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0068] The present application embodiment provides a battery conversion voltage calculation system, such as Figure 4 As shown, including:

[0069] a voltage sampling module, used for sampling the voltage of the battery during the process of charging with a first preset current for a first preset time, so as to obtain a plurality of first sampled voltages; and used for sampling the voltage of the battery during the process of charging with a second preset current for a first preset time, so as to obtain a plurality of second sampled voltages, wherein the first preset current is different from the second preset current;

[0070] an internal resistance calculation module, configured to average a plurality of the first sampled voltages to obtain a first average voltage, and average a plurality of the second sampled voltages to obtain a second average voltage; and to calculate an equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage;

[0071] The conversion voltage calculation module is used to calculate the conversion voltage value of the battery according to the equivalent charging resistance of the battery calculated by the internal resistance calculation module, the rated voltage of the battery and the constant current charging current of the battery, and use the conversion voltage value as the actual conversion voltage value of the battery.

[0072] By using the battery conversion voltage calculation system provided in the embodiment of the present application, the equivalent charging resistance of the battery during the charging process can be calculated in real time. After obtaining the equivalent charging resistance, the actual conversion voltage value of the battery is determined according to the equivalent charging resistance, thereby avoiding the problem in the prior art of directly using the rated voltage of the battery as the conversion voltage, or increasing a fixed voltage value based on the rated voltage as the conversion voltage, which results in the charging process being prolonged due to the influence of parameters such as temperature, thereby reducing the battery charging efficiency.

[0073] Furthermore, since the conversion voltage value is calculated based on the equivalent charging resistance of the battery, the rated voltage of the battery and the cross-current charging current of the battery, the battery will not be overcharged after the conversion voltage value is used as the actual conversion voltage value of the battery.

[0074] Optionally, the specific process of the conversion voltage calculation module calculating the conversion voltage value of the battery according to the equivalent charging resistance of the battery calculated by the internal resistance calculation module, the rated voltage of the battery, and the constant current charging current of the battery may be:

[0075] Substituting the equivalent charging resistance of the battery, the rated voltage of the battery and the constant current charging current of the battery calculated by the internal resistance calculation module into a second preset formula to calculate a conversion voltage value of the battery;

[0076] The second preset formula is: REG =V BAT_FULL +I CHG ×R BIR ; Among them, V REG Represents the calculated conversion voltage value of the battery, V BAT_FULL Indicates the rated voltage of the battery, I CHG represents the cross-current charging current of the battery, R BIR It represents the equivalent charging resistance of the battery calculated by the internal resistance calculation module.

[0077] Optionally, in one embodiment of the present application, the second preset current is greater than the first preset current, and the second preset current is the constant current charging current of the battery. In this way, only one charging current switching is required in the process of obtaining the first average voltage and the second average voltage. In another embodiment of the present application, the first preset current may be greater than the second preset current, and the first preset current is the constant current charging current of the battery. The present application does not limit this, and it depends on the actual situation.

[0078] Based on the above embodiments, in one embodiment of the present application, Figure 5 As shown, the battery conversion voltage calculation system also includes:

[0079] The voltage comparison module is used to determine whether the current voltage of the battery is greater than a preset voltage, and if so, send a first enabling signal to the voltage sampling module to trigger the voltage sampling module.

[0080] The voltage comparison module triggers the voltage sampling module by sending a first enable signal to the voltage sampling module only when the current voltage of the battery is greater than a certain value (preset voltage). This can avoid the battery conversion voltage calculation system from calculating the battery equivalent charging resistance and the conversion voltage value when the battery voltage is low. The above calculation can be performed when the current voltage value of the battery is close to the rated voltage of the battery, so that the calculated equivalent charging resistance can be closer to the actual equivalent charging resistance when the current voltage of the battery is close to the rated voltage, thereby making the calculated conversion voltage value more accurate.

[0081] In addition, in another embodiment of the present application, the conversion voltage calculation module uses the conversion voltage value as the actual conversion voltage value of the battery for:

[0082] According to the conversion voltage value, a charging voltage lookup table of the battery is queried, and a charging voltage in the charging voltage lookup table that is closest to the conversion voltage value is used as the actual conversion voltage value of the battery.

[0083] In actual applications, the charging voltage of some batteries cannot be changed continuously and only supports several feasible charging voltages. The corresponding relationship between these charging voltages and charging currents is stored in the charging voltage lookup table of the battery.

[0084] Therefore, in this case, after calculating the conversion voltage value, it is necessary to look up the charging voltage lookup table of the battery and use the charging voltage in the charging voltage lookup table that is closest to the conversion voltage value as the actual conversion voltage value of the battery.

[0085] On the basis of the above embodiment, in another embodiment of the present application, the voltage sampling module includes: a charging current setting unit and a sampling unit; wherein,

[0086] The charging current setting unit is used to set the charging current of the battery to a first preset current upon receiving the first enable signal, and control the sampling unit to sample the output voltage of the battery within a first preset time to obtain a plurality of first sampled voltages; and is used to set the charging current of the battery to a second preset current upon receiving the second enable signal, and control the sampling unit to sample the output voltage of the battery within the first preset time to obtain a plurality of second sampled voltages;

[0087] The internal resistance calculation module is specifically used to average the multiple first sampling voltages to obtain the first average voltage, and send the second enable signal to the charging current setting unit; and is used to average the multiple second sampling voltages after receiving the multiple second sampling voltages to obtain the second average voltage.

[0088] In this embodiment, the first average voltage can be expressed as:

[0089] V BAT1 =(V BAT1_T1 +V BAT1_T2 +V BAT1_T3 +…+V BAT1_TN ) / N; where N represents the number of first sampling voltages, V BAT1_TN represents the Nth first sampling voltage;

[0090] The second average voltage can be expressed as:

[0091] V BAT2 =(V BAT2_T1 +V BAT2_T2 +V BAT2_T3 +…+V BAT2_TN ) / N;V BAT2_TN represents the Nth second sampling voltage.

[0092] Since the sampling is performed by the same sampling unit within the first preset time, the number of the first sampling voltages is equal to the number of the second sampling voltages.

[0093] After receiving the first enable signal, the charging current setting unit first performs voltage sampling when the charging current of the battery is a first preset current condition, and then performs voltage sampling when the charging current of the battery is a second preset current condition. In other embodiments of the present application, the voltage sampling may be performed first when the charging current of the battery is a second preset current condition, and then the voltage sampling may be performed when the charging current of the battery is a first preset current condition. The present application does not limit this, and it depends on the actual situation.

[0094] In addition, the number of sampled voltages obtained by the sampling unit within the first preset time is related to the sampling rate of the sampling unit and the first preset time. Specifically, the number of sampled voltages obtained by the sampling unit within the first preset time is equal to the product of the sampling rate of the sampling unit and the first preset time.

[0095] On the basis of the above embodiment, in another embodiment of the present application, the internal resistance calculation module calculates the equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage and the second average voltage, and is specifically used to substitute the first preset current, the second preset current, the first average voltage and the second average voltage into a first preset formula to calculate and obtain the equivalent charging resistance of the battery;

[0096] The first preset formula is: BIR =(V BAT2 -V BAT1 ) / (I CHG -I CHG1 ), where R BIR Represents the equivalent charging resistance of the battery; V BAT2 represents the second average voltage, V BAT1 represents the first average voltage, I CHG represents the second preset current, I CHG1 represents the first preset current.

[0097] The derivation process of the first preset formula is as follows:

[0098] The first average voltage can also be expressed as:

[0099] V BAT1 =V BATO +I CHG1 ×R BIR

[0100] The second average voltage can also be expressed as:

[0101] V BAT2 =V BATO +I CHG ×R BIR

[0102] Since the first average voltage and the second average voltage are sampled continuously and the sampling time is usually short, it can be considered that when the first sampling voltage and the second sampling voltage are sampled, the voltage value V at both ends of the battery is BATO same;

[0103] In addition, since the sampling time is the first preset time, the first preset formula can be obtained:

[0104] R BIR =(V BAT2 -V BAT1 ) / (I CHG -I CHG1 ).

[0105] After the actual conversion voltage value of the battery is set by the battery conversion voltage calculation system provided by the embodiment of the present application, the comparison diagram of the battery charging voltage curve (charging voltage curve of the present solution) and the charging voltage curve in the prior art (traditional charging voltage curve) is shown in FIG. Figure 6 , the comparison diagram of the battery charging current curve (charging current curve of this solution) and the charging current curve in the prior art (traditional charging current curve) is shown in FIG. Figure 7 .from Figure 6 and Figure 7 It can be seen that after the actual conversion voltage value of the battery is set by the battery conversion voltage calculation system provided by the embodiment of the present application, the charging time of the battery charging process is closer to the theoretical value, and because in the actual application process, the first preset time is compared with the complete charging time T of the battery. chg_full The difference is very small, so the extension of charging time caused by the current reduction in the first preset time can be ignored.

[0106] Based on the above embodiments, a specific embodiment of the present application provides a feasible circuit structure of a battery conversion voltage calculation system, such as Figure 8 As shown, it is composed of a comparator D_CMP, a timer Time_cnt, a current conversion circuit, a first digital-to-analog converter, a second digital-to-analog converter, a first analog-to-digital converter and a calculation device. The specific connection relationship is referenced Figure 8 .exist Figure 8 Also shown is a power conversion module CHG_ANALOG_TOP of the battery charging device; Figure 8 RBIR in it represents the equivalent charging resistance of the battery, and BATTERY represents the battery.

[0107] Among them, the comparator, the timer, the current conversion circuit and the first digital-to-analog converter constitute the charging BIR compensation circuit startup module; the second digital-to-analog converter, the first analog-to-digital converter and the calculation device constitute the charging BIR calculation and compensation module. The charging BIR compensation circuit startup module and the charging BIR calculation and compensation module jointly realize the functions of the voltage comparison module, the voltage sampling module, the internal resistance calculation module and the conversion voltage calculation module in the battery conversion voltage calculation system provided in this application.

[0108] Figure 8 The circuit structure shown can be implemented in a battery charging device by means of an ASIC, or in a battery integrated device (such as a mobile phone) using a module integrated in a SOC. BAT >V REG1 When , the comparator D_CMP outputs a dynamic BIR detection enable signal EN_ACT_BIR=1; the digital configuration code D_ICHG in the current conversion circuit is changed to D_ICHG1, so that the configuration code is converted into the corresponding charging current reference voltage V_ICHG through the first digital-to-analog converter DAC1; at the same time, the timer Time_cnt is started, and the voltage of the VBAT port is sampled in real time by using the first analog-to-digital converter ADC in the BIR calculation and compensation module, and the sampling data within the first preset time Tcnt1 is stored in the calculation device D_CALCULATE, and the average value is calculated and recorded as VBAT1; when the timer Time_cnt counts up to Tcnt1, the charging current configuration code is switched back to the preset value D_ICHG, and the timing Tcnt2 is restarted. (Tcnt2 = Tcnt1); at this time, the voltage of the VBAT port is sampled in real time by the first analog-to-digital converter ADC in the BIR calculation and compensation module, and the sampled data within the Tcnt2 timing is stored in the calculation device D_CALCULATE, and the average value is calculated and recorded as VBAT2; after Tcnt2 ends, the updated conversion voltage value is calculated using VBAT1 and VBAT2, and converted into V by the second digital-to-analog converter DAC2. REG Transmitted to the power conversion module CHG_ANALOG_TOP of the battery charging device.

[0109] The battery conversion voltage calculation method provided in an embodiment of the present application is described below. The battery conversion voltage calculation method described below can be referenced to the battery conversion voltage calculation system described above.

[0110] Accordingly, the present application embodiment also provides a method for calculating the battery conversion voltage, such as Fig. 9 As shown, including:

[0111] S101: collecting a first average voltage of a battery during charging with a first preset current for a first preset time;

[0112] S102: collecting a second average voltage of the battery during charging for a first preset time at a second preset current, where the first preset current is different from the second preset current;

[0113] S103: calculating an equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage;

[0114] S104: Calculate the conversion voltage value of the battery according to the equivalent charging resistance of the battery calculated by the internal resistance calculation module, the rated voltage of the battery, and the constant current charging current of the battery, and use the conversion voltage value as the actual conversion voltage value of the battery.

[0115] Optionally, the collecting of a first average voltage of the battery during a first preset time when the charging current is a first preset current; collecting of a second average voltage of the battery during a first preset time when the charging current is a second preset current, before the first preset current is different from the second preset current, further includes:

[0116] Determine whether the current voltage of the battery is greater than the preset voltage. If so, enter the step of collecting the first average voltage of the battery during the first preset time when the charging current is a first preset current; and collect the second average voltage of the battery during the first preset time when the charging current is a second preset current.

[0117] Optionally, collecting a first average voltage of a battery during charging with a first preset current for a first preset time includes:

[0118] The charging current of the battery is set to a first preset current, and the output voltage of the battery is sampled within a first preset time to obtain a plurality of first sampled voltages;

[0119] Averaging a plurality of the first sampled voltages to obtain the first average voltage;

[0120] The collecting of the second average voltage of the battery during the charging process of the battery with a second preset current for a first preset time comprises:

[0121] The charging current of the battery is set to a second preset current, and the output voltage of the battery is sampled within a first preset time to obtain a plurality of second sampled voltages;

[0122] A plurality of the second sampling voltages are averaged to obtain the second average voltage.

[0123] Optionally, calculating the equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage includes:

[0124] Substituting the first preset current, the second preset current, the first average voltage and the second average voltage into a first preset formula to calculate and obtain the equivalent charging resistance of the battery;

[0125] The first preset formula is: BIR =(V BAT2 -V BAT1 ) / (I CHG -I CHG1 ), where R BIR Represents the equivalent charging resistance of the battery; V BAT2 represents the second average voltage, V BAT1 represents the first average voltage, I CHG represents the second preset current, I CHG1 represents the first preset current.

[0126] Optionally, taking the converted voltage value as the actual converted voltage value of the battery includes:

[0127] According to the conversion voltage value, a charging voltage lookup table of the battery is queried, and a charging voltage in the charging voltage lookup table that is closest to the conversion voltage value is used as the actual conversion voltage value of the battery.

[0128] Correspondingly, an embodiment of the present application further provides a battery, comprising a battery conversion voltage calculation system as described in any of the above embodiments.

[0129] Correspondingly, an embodiment of the present application further provides a battery charging device, comprising a battery conversion voltage calculation system as described in any of the above embodiments.

[0130] In summary, the embodiments of the present application provide a battery conversion voltage calculation system, method, battery and battery charging device, wherein the battery conversion voltage calculation system calculates the equivalent charging resistance of the battery during the charging process by collecting the average voltage of the battery during the same charging time at different charging currents. After obtaining the equivalent charging resistance, the actual conversion voltage value of the battery is determined according to the equivalent charging resistance, thereby avoiding the problem in the prior art that the rated voltage of the battery is directly used as the conversion voltage, which leads to the influence of parameters such as temperature, and the charging process is prolonged due to the premature conversion from constant current charging mode to constant voltage charging mode, thereby reducing the battery charging efficiency.

[0131] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments, and the same and similar parts between the embodiments can be referred to each other. The above description of the disclosed embodiments enables professionals and technicians in this field to implement or use the present application. Various modifications to these embodiments will be obvious to professionals and technicians in this field, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will comply with the widest range consistent with the principles and novel features disclosed herein.

Claims

1. A battery conversion voltage calculation system, characterized in that: include: A voltage sampling module, used for sampling the voltage of the battery during charging with a first preset current for a first preset time, so as to obtain a plurality of first sampled voltages; and for sampling the voltage of the battery during charging with a second preset current for a first preset time to obtain a plurality of second sampled voltages, wherein the first preset current is different from the second preset current; an internal resistance calculation module, configured to average a plurality of the first sampled voltages to obtain a first average voltage, and average a plurality of the second sampled voltages to obtain a second average voltage; and for calculating an equivalent charging resistance of a battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage; The internal resistance calculation module calculates the equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage and the second average voltage, and is specifically used to substitute the first preset current, the second preset current, the first average voltage and the second average voltage into a first preset formula to calculate the equivalent charging resistance of the battery; the first preset formula is: R BIR =(V BAT2 -V BAT1 ) / (I CHG -I CHG1 ), where R BIR Represents the equivalent charging resistance of the battery; V BAT2 represents the second average voltage, V BAT1 represents the first average voltage, I CHG represents the second preset current, I CHG1 represents the first preset current; a conversion voltage calculation module, used to calculate a conversion voltage value of the battery according to the equivalent charging resistance of the battery calculated by the internal resistance calculation module, the rated voltage of the battery and the constant current charging current of the battery, and use the conversion voltage value as the actual conversion voltage value of the battery; It also includes: a voltage comparison module, which is used to determine whether the current voltage of the battery is greater than the preset voltage. If so, a first enable signal is sent to the voltage sampling module to trigger the voltage sampling module to sample the voltage of the battery when the charging current is a first preset current and the first preset time is charged, so as to obtain multiple first sampled voltages; and to sample the voltage of the battery when the charging current is a second preset current and the first preset time is charged, so as to obtain multiple second sampled voltages; when the current voltage value of the battery is close to the rated voltage of the battery, the internal resistance calculation module and the conversion voltage calculation module perform corresponding calculations, so that the equivalent charging resistance obtained by calculation is close to the actual equivalent charging resistance when the current voltage of the battery is close to the rated voltage, and then the conversion voltage value obtained by the equivalent charging resistance calculation is used as the actual conversion voltage value of the battery.

2. The system according to claim 1, characterized in that The voltage sampling module includes: a charging current setting unit and a sampling unit; wherein, The charging current setting unit is used to set the charging current of the battery to a first preset current upon receiving the first enable signal, and control the sampling unit to sample the output voltage of the battery within a first preset time to obtain a plurality of first sampled voltages; and is used to set the charging current of the battery to a second preset current upon receiving the second enable signal, and control the sampling unit to sample the output voltage of the battery within the first preset time to obtain a plurality of second sampled voltages; The internal resistance calculation module is specifically used to average the multiple first sampling voltages to obtain the first average voltage, and send the second enable signal to the charging current setting unit; and is used to average the multiple second sampling voltages after receiving the multiple second sampling voltages to obtain the second average voltage.

3. The system according to claim 1, characterized in that The conversion voltage calculation module uses the conversion voltage value as the actual conversion voltage value of the battery for: According to the conversion voltage value, a charging voltage lookup table of the battery is queried, and a charging voltage in the charging voltage lookup table that is closest to the conversion voltage value is used as the actual conversion voltage value of the battery.

4. The system according to claim 1, characterized in that The second preset current is greater than the first preset current; And the second preset current is the constant current charging current of the battery.

5. A method for calculating battery conversion voltage, characterized in that: include: Collecting a first average voltage of the battery during charging with a first preset current for a first preset time; collecting a second average voltage of the battery during charging for a first preset time at a second preset current, where the first preset current is different from the second preset current; Calculating an equivalent charging resistance of a battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage; The calculating of the equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage and the second average voltage comprises: substituting the first preset current, the second preset current, the first average voltage and the second average voltage into a first preset formula to calculate the equivalent charging resistance of the battery; the first preset formula is: R BIR =(V BAT2 -V BAT1 ) / (I CHG -I CHG1 ), where R BIR Represents the equivalent charging resistance of the battery; V BAT2 represents the second average voltage, V BAT1 represents the first average voltage, I CHG represents the second preset current, I CHG1 represents the first preset current; Calculating a conversion voltage value of the battery according to the calculated equivalent charging resistance of the battery, the rated voltage of the battery, and the constant current charging current of the battery, and using the conversion voltage value as the actual conversion voltage value of the battery; The method further comprises the steps of collecting a first average voltage of the battery during a first preset time when the charging current is a first preset current; and collecting a second average voltage of the battery during a first preset time when the charging current is a second preset current. Before the first preset current is different from the second preset current, the method further comprises: determining whether the current voltage of the battery is greater than the preset voltage, and if so, entering the step of collecting the first average voltage of the battery during a first preset time when the charging current is the first preset current; and collecting the second average voltage of the battery during a first preset time when the charging current is the second preset current; when the current voltage value of the battery is close to the rated voltage of the battery, entering the step of calculating the equivalent charging resistance of the battery according to the first preset current, the second preset current, the first average voltage, and the second average voltage, and then entering the step of calculating the conversion voltage value of the battery according to the calculated equivalent charging resistance of the battery, the rated voltage of the battery, and the constant current charging current of the battery.

6. The method according to claim 5, characterized in that The collecting of the first average voltage of the battery during the charging process of the battery with a first preset current and a first preset time comprises: The charging current of the battery is set to a first preset current, and the output voltage of the battery is sampled within a first preset time to obtain a plurality of first sampled voltages; Averaging a plurality of the first sampled voltages to obtain the first average voltage; The collecting of the second average voltage of the battery during the charging process of the battery with a second preset current for a first preset time comprises: The charging current of the battery is set to a second preset current, and the output voltage of the battery is sampled within a first preset time to obtain a plurality of second sampled voltages; A plurality of the second sampling voltages are averaged to obtain the second average voltage.

7. The method according to claim 5, characterized in that The using the conversion voltage value as the actual conversion voltage value of the battery comprises: According to the conversion voltage value, a charging voltage lookup table of the battery is queried, and a charging voltage in the charging voltage lookup table that is closest to the conversion voltage value is used as the actual conversion voltage value of the battery.

8. A battery, characterized in that: It comprises a battery conversion voltage calculation system as described in any one of claims 1-4.

9. A battery charging device, characterized in that: It comprises a battery conversion voltage calculation system as described in any one of claims 1-4.

Citation Information

Patent Citations

  • Battery conversion voltage calculation system, battery and battery charging device

    CN209728137U

  • Charger and radiation image detection system

    JP2012151994A

  • Method of monitoring and controlling electrochemical systems and processes

    US6008624A