An intelligent cable with replaceable monitoring elements and its preparation, installation and construction method
By reserving holes in the smart cable and installing monitoring elements in the finished product or during construction, the problem of insufficient force of the optical fiber sensor and synchronization of the monitoring element and the cable is solved in the existing technology, and efficient and accurate cable status monitoring is achieved. and replacement, extending the service life of monitoring components.
Patent Information
- Application Number
- CN201810929075.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-08-15
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2038-08-15
AI Technical Summary
When making the existing smart cable, the fiber Bragg grating sensor and the cable are stressed simultaneously. As a result, the strain of the optical fiber is less than that of the steel, and the monitoring element is difficult to synchronize with the life of the cable, resulting in inaccurate or ineffective force measurement and inability to effectively monitor. Russo's health.
Design a smart cable with replaceable monitoring elements. By reserving a longitudinal hole in the cable, the monitoring element is stretched to the design force value according to the design requirements during finished cable or on-site construction, and then penetrates into the hole and applies tension. Tightly fixed to ensure effective survival and replaceability of monitoring components. Monitoring components include fiber Bragg grating sensors, Brillouin optical fibers, vibrating wire sensors, etc., which can monitor cable force and temperature and humidity changes in real time, and replace them when necessary.
It achieves a 100% survival rate of monitoring components and can synchronize with the life of the cable, improving monitoring accuracy and service life. It also facilitates operation and maintenance and avoids the failure of monitoring components during use.
Smart Images

Figure CN110835864B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an intelligent cable, and in particular to an intelligent cable with replaceable monitoring elements and a preparation, installation and construction method thereof. Background Art
[0002] Bridge cables play a key role in structural stress. Due to environmental corrosion, fatigue damage, and redistribution of internal forces in service, cables are easily damaged. Without a long-term monitoring system, it is difficult to understand the actual health of the cables. Fiber Bragg grating testing technology is an absolute measurement technology based on wavelength information, which has many advantages such as good electrical insulation, good durability, high temperature resistance and corrosion resistance. As early as 2003, China carried out the development of intelligent cables. A number of invention patent application technologies have successively disclosed some fiber Bragg grating intelligent cables for cable systems such as inclined cables, suspender arch bridges, cables, and suspension bridges, which have the function of automatically monitoring the stress of cables. However, all of the above patent application technical solutions have one thing in common: when making the cable, the fiber Bragg grating sensor and the cable are made as a whole. When the cable is stressed, the fiber Bragg grating sensor and the cable are stressed synchronously to measure the cable force. However, optical fiber is a brittle material, and its tensile strain after being stressed is less than that of steel. The above patent application technologies all have the problem of failure after the optical fiber is implanted, during the cable calibration process or after a period of engineering use. Therefore, such products have not been introduced to the market in large quantities. According to the existing technical solutions, if the monitoring element is replaced with Brillouin optical fiber, there is still the problem that the tensile strain of the optical fiber after being stressed is smaller than that of the steel; if the monitoring element is replaced with a vibrating string sensor or other forms of strain gauge, there is also the problem of inaccurate force measurement or failure due to relaxation during long-term monitoring. The monitoring element is difficult to synchronize with the life of the cable. Once it fails or the force measurement is inaccurate, the monitoring function preset in the structural component will not work. Summary of the invention
[0003] The purpose of the present invention is to provide an intelligent cable with replaceable monitoring elements for civil engineering structures. The intelligent cable with replaceable monitoring elements adopts fiber grating sensors, Brillouin optical fibers, vibrating string sensors or other forms of sensitive components that can monitor the state of the cable, monitors the change of cable force in real time, and can easily replace various sensor systems that can monitor the state of the cable. During service, it can not only detect the change of cable force, but also monitor the change of temperature and humidity. When replacing the sensor system that can monitor the state of the cable, an endoscope can be used to observe the internal corrosion of the cable body. The present invention also provides a preparation and installation construction method of the intelligent cable with replaceable monitoring elements, and the preparation and installation construction method is simple and efficient.
[0004] The technical solution to the above problem is: an intelligent cable with replaceable monitoring element, including two major parts: a monitoring element and a cable. The cable includes a finished cable and a cable installed on site, and is characterized in that:
[0005] The cable has at least one hole along its entire length in the longitudinal direction, and a monitoring element is arranged in the hole, and the monitoring element is connected to the outside world through a data line;
[0006] The monitoring element includes a fiber grating sensor monitoring element assembly, a Brillouin optical fiber monitoring element assembly, a vibrating string sensor monitoring element assembly, and other forms of strain gauges, temperature and humidity sensors or other monitoring element assemblies composed of sensitive components capable of monitoring the state of the cable;
[0007] The monitoring element is tensioned to the design force value according to the design requirements during the production process of the finished cable, and then inserted into the channel, and the two ends are locked and fixed after a certain tensioning force is applied; or the cable is tensioned to the design force value according to the design requirements during the on-site construction and installation, and then inserted into the channel after the construction is completed, and the two ends are locked and fixed after a certain tensioning force is applied.
[0008] A further technical solution for the intelligent cable with replaceable monitoring element is: when the cable is a cold-cast steel wire finished cable, a cold-cast extruded steel strand finished cable or an extruded steel strand finished cable, each finished cable has at least one channel along the entire length in the longitudinal direction, and the monitoring element is in the production process of the finished cable, when the cold-cast steel wire finished cable, the cold-cast extruded steel strand finished cable or the extruded steel strand finished cable is tensioned to the design force value according to the design requirements and then passes through the channel, and the carrier of the monitoring element is fixed after force is applied; the cold-cast steel wire finished cable intelligent cable, the cold-cast steel strand finished cable intelligent cable or the extruded steel strand finished cable intelligent cable that constitutes the replaceable monitoring element.
[0009] A further technical solution of the intelligent cable with replaceable monitoring element may be: the cable is a clip-type steel strand cable installed on-site, at least one through hole is reserved in the anchors at both ends of the clip-type steel strand cable along the entire length in the longitudinal direction, at least one channel is reserved in the cable body along the entire length in the longitudinal direction, the monitoring element passes through the through hole and the channel, and is connected to the outside world through a data line;
[0010] The monitoring element is inserted into the clip-type steel strand cable after the steel strand bundle threading, tensioning and cable adjustment work is completed during construction, and the carrier of the monitoring element is force applied and then fixed, forming a clip-type steel strand cable intelligent cable with a replaceable monitoring element.
[0011] A further technical solution for the intelligent cable of the replaceable monitoring element is: the monitoring element is a fiber grating sensor monitoring element assembly, which includes a carrier, an optical fiber, and a nut. At least one groove is arranged on the carrier in the longitudinal direction, and the optical fiber is placed in the groove. A grating is engraved on the optical fiber, and the fiber grating is reliably coupled to the carrier in its groove.
[0012] A further technical solution for the intelligent cable of the replaceable monitoring element may be: the monitoring element is a Brillouin optical fiber monitoring element assembly, which includes a carrier, an optical fiber, and a nut. At least one groove is arranged on the carrier in the longitudinal direction, and the optical fiber is placed in the groove. The Brillouin optical fiber is reliably coupled to the carrier by an adhesive or crimping method.
[0013] A further technical solution for the intelligent cable of the replaceable monitoring element may be: the monitoring element is a vibrating string sensor monitoring element assembly, which includes a carrier, a vibrating string sensor, and a nut. At least one groove is arranged on the carrier in the longitudinal direction, and the vibrating string sensor is placed in the groove and fixed at both ends by welding.
[0014] A further technical solution of the intelligent cable of the replaceable monitoring element is that the carrier is a steel wire or a carbon fiber rod or a glass fiber rod or a mixed fiber rod.
[0015] In the anchoring area of the cable, the hole is a steel pipe, a plastic pipe or other pipes with sufficient strength, and the cable body part of the cable is a spiral steel wire pipe with sufficient expansion and contraction function, a tubular space formed by a steel belt or a plastic pipe.
[0016] The diameter of the hole is 1 mm to 20 mm, and the cross-sectional shape of the hole is polygonal, elliptical, circular or elliptical ring.
[0017] Another related technical solution is: a preparation and installation construction method of a cable of a replaceable monitoring element, which is a preparation and installation construction method of a cold-cast steel wire finished cable intelligent cable, a cold-cast steel strand finished cable intelligent cable or an extruded steel strand finished cable intelligent cable of the above-mentioned replaceable monitoring element, and it comprises the following steps:
[0018] A. Construction preparation:
[0019] A1. Prepare materials:
[0020] ① Prepare all the cables and other parts of anchorage according to the materials required for conventional cold-cast steel wire finished cables, cold-cast extruded steel strand finished cables or extruded steel strand finished cables;
[0021] ②Prepare monitoring components and make hole-forming pipe materials;
[0022] A2. Cutting: Cut the cable wire or steel strand and hole-forming pipe materials to a fixed length according to the cable length and working conditions;
[0023] B. Twisting and wrapping: Steel wires or steel strands are arranged closely with twist angles according to the requirements of different types of cables, and the hole-forming pipes are placed in them and wrapped tightly with wrapping tape;
[0024] C. Extrusion: hot extrude HDPE onto the wrapped steel wire or steel strand bundle;
[0025] D. Fixed-length cable cutting: Calculate the cable length and cut the cable according to the project requirements;
[0026] E. Anchoring: Align the hole in the cable body with the hole in the anchor and connect them with heat shrink tubing or plug-in tubing, and make the rest of the anchoring in the conventional way according to the anchor form;
[0027] F. Super tensioning: tension the finished cable according to standard requirements;
[0028] G. Pack and transport to the construction site, hang cables and tension them to the designed cable force;
[0029] H. Install monitoring elements: insert a carrier equipped with a monitoring element assembly including a fiber Bragg grating sensor monitoring element assembly, a Brillouin optical fiber monitoring element assembly, a vibrating string sensor monitoring element assembly, and other forms of strain gauges, temperature and humidity sensors, or other sensitive components capable of monitoring the state of the cable into the reserved hole of the cable, and fix the two ends with nuts;
[0030] I. Connection: Connect the detection terminal to the measuring instrument;
[0031] J. Tensioning the carrier: tensioning the carrier to a set force value, which is between the difference between the actual force value of the cable and the minimum possible force value and the actual force value; locking the nut on the anchor plate or wire plate of the cable, or locking the nut on the end cover surface of the cable anchor;
[0032] K. Cable adjustment: adjust the force of each cable in a cycle across the entire bridge;
[0033] L. Protection: Install anchor protection devices at both ends of the cable.
[0034] Another related technical solution is: it is a method for preparing and installing the above-mentioned clip-type steel strand cable intelligent cable with replaceable monitoring elements, characterized in that it includes the following steps:
[0035] A. Construction preparation:
[0036] A1. Prepare materials:
[0037] ① Prepare all other parts of the anchorage required for conventional clip-type stranded wire group anchors;
[0038] ②Prepare monitoring components and make hole-forming pipe materials;
[0039] A2. Cutting: Cut the cable steel wire or steel strand and the hole-forming pipe material to a fixed length according to the cable length and working conditions;
[0040] B. Installation of upper and lower anchors: at least one through hole is reserved in the anchors at both ends of the clip-type stranded wire cable, and a rigid hole-forming pipe made of a steel pipe, plastic pipe or other pipe material with sufficient strength is placed in the hole. The rest of the installation is carried out according to the conventional method;
[0041] C. HDPE sheath pipe installation:
[0042] D. Place the hole-forming pipe and tension the single steel strand cable:
[0043] A flexible hole-forming pipe made of spiral steel wire pipe, tubular space formed by steel belt or transparent plastic pipe with sufficient expansion and contraction function is placed in the cable body and connected with the rigid hole-forming pipe previously placed in the center of the upper and lower anchors. The rest of the installation is carried out according to the conventional method, and the steel strands are tensioned one by one;
[0044] E. Overall tensioning and cable adjustment: proceed in the conventional way;
[0045] F. Install monitoring components: insert the carrier with the monitoring component assembly including one of the fiber Bragg grating sensor monitoring component assembly, the Brillouin fiber monitoring component assembly, the vibrating string sensor monitoring component assembly, and other forms of strain gauges, temperature and humidity sensors or other sensitive components capable of monitoring the state of the cable from one end of the anchor into the other end and fix it with a nut;
[0046] G. After the carrier is stretched to a set force value, the nut is locked; the force value is between the difference between the actual force value of the cable and the minimum possible force value and the actual force value;
[0047] H. Install the cable hoop shock absorber;
[0048] I. Cyclic adjustment of the forces on each cable;
[0049] J. Install anchor protection devices at both ends of the cable.
[0050] Due to the above structure, the present invention "An intelligent cable with replaceable monitoring elements and its preparation, installation and construction method" has the following beneficial effects:
[0051] 1. During the maintenance of the cable during its service life, the monitoring element can be replaced without interrupting traffic, and the internal condition of the cable can be detected and protected, which is convenient for operation and maintenance:
[0052] Since at least one channel 2 is reserved along the entire length of the intelligent cable with replaceable monitoring elements of the present invention, and a monitoring element 3 is arranged in the channel 2, during construction, the finished cable or the cable installed on site is tensioned to the design force value according to the design requirements, and then the monitoring element is inserted into the channel and fixed at both ends. Therefore, the monitoring element 3 can be conveniently taken out at any time, and the internal condition of the cable can be checked by using the channel 2 using the internal vision technology; when the humidity in the cable body exceeds the standard, the channel 2 can also be used as a channel for dry air to remove moisture from the cable body, and inert gas can be introduced or vacuum can be drawn to protect the stress-bearing reinforcement of the cable body.
[0053] 2. The life of the intelligent cable with replaceable monitoring element of the present invention is long and can be synchronized with the life of the cable:
[0054] In the manufacturing process of the smart cables in the prior art, the monitoring element is made together with the cable, and they are installed and stressed simultaneously. Since the stress that the detection element can withstand is smaller than the cable material, the survival rate of the system cannot be guaranteed; secondly, since the monitoring element is made together with the cable, the monitoring element is fixed inside the cable or fixedly connected to the cable, when the monitoring element fails, it cannot be replaced;
[0055] In the intelligent cable with replaceable monitoring element of the present invention, at least one channel 2 is reserved along the entire length in the longitudinal direction, and a monitoring element 3 is arranged in the channel. During construction, the finished cable or the cable installed on site is tensioned to the design force value according to the design requirements, and then the monitoring element is inserted into the channel and fixed at both ends. This installation and construction method can ensure that the monitoring element is 100% effective. In addition, a tensile force is applied to the monitoring element to lock it, and its strain is not less than the difference between the actual strain value of the cable and its minimum possible strain value. Therefore, the monitoring element can monitor the stress of the cable in a higher strain state at a lower strain level, thereby increasing the service life of the monitoring element. It can also be replaced at any time, synchronized with the life of the cable.
[0056] 3. Easy transportation, construction and installation:
[0057] The hole-forming pipe of the finished cable such as the cold-cast steel wire finished cable intelligent cable, the cold-cast extruded steel strand finished cable intelligent cable and the extruded steel strand finished cable intelligent cable, which can replace the monitoring element in service and is manufactured in the factory of the present invention, is a tubular space formed by a spiral steel wire or steel belt, such as Figure 6 , Figure 7 As shown, it can be coiled together with the cable and stretched together with the force, which is convenient for transportation, construction and installation; the channel can also be a transparent plastic tube, and the strip tube or plastic tube can also be punched in the tube wall as a vent to facilitate operation and maintenance.
[0058] The technical features of the intelligent cable with replaceable monitoring elements and the preparation, installation and construction method thereof of the present invention are further described below in conjunction with the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0059] Figure 1 It is a schematic diagram of the structure of the cold-cast steel wire finished cable intelligent cable and the cold-cast extruded steel strand finished cable intelligent cable with replaceable monitoring elements of the present invention;
[0060] Figure 2 It is a schematic diagram of the monitoring element structure;
[0061] Figure 3 yes Figure 2 Right view of;
[0062] Figure 4 It is a schematic diagram of the structure of an extruded steel strand finished cable intelligent cable with replaceable monitoring elements;
[0063] Figure 5 It is a schematic diagram of the structure of a clip-type steel strand cable intelligent cable with replaceable monitoring elements;
[0064] Figure 6 It is a schematic diagram of the structure of a spiral steel wire pipe hole-forming pipeline with sufficient telescopic function;
[0065] Figure 7 It is a schematic diagram of a tubular space perforated pipeline structure formed by a steel strip with vent holes thereon;
[0066] Figure 8 It is a schematic diagram of the structure of the monitoring element assembly equipped with fiber grating and temperature and humidity sensors;
[0067] Fig. 9 is a schematic diagram of the structure of a monitoring element assembly equipped with Brillouin optical fiber;
[0068] Fig.10 yes Fig. 9 Right view of;
[0069] Fig.11 It is a schematic diagram of the structure of the monitoring element assembly with a vibrating wire sensor installed.
[0070] Fig.12 yes Fig.11 Right view of;
[0071] Fig.13 This is one of the schematic diagrams of the cross-sectional structure of the intelligent cable body of the steel wire finished cable with replaceable monitoring elements of the present invention (there is a hole in the center of the cable body);
[0072] Fig.14 This is one of the schematic diagrams of the cross-sectional structure of the intelligent cable body of the finished steel strand cable with replaceable monitoring elements of the present invention (there is a hole in the center of the cable body);
[0073] Fig.15 , Fig.17This is the second schematic diagram of the cross-sectional structure of the intelligent cable body of the steel wire finished cable with replaceable monitoring elements of the present invention (there are 3 holes in the cable body);
[0074] Fig.16 , Fig.18 This is the second schematic diagram of the cross-sectional structure of the intelligent cable body of the steel strand finished cable with replaceable monitoring elements of the present invention (there are two holes in the cable body);
[0075] Fig.19 : The present invention discloses a cold-cast steel wire finished cable intelligent cable with replaceable monitoring elements and a cold-cast extruded steel strand finished cable intelligent cable.
[0076] In the figure:
[0077] 1-cable, 1a-cold cast steel wire finished cable intelligent cable or cold cast extruded steel strand finished cable intelligent cable, 1b-extruded steel strand finished cable intelligent cable, 1c-clip steel strand cable intelligent cable; 2-hole, 21-spiral steel wire tube holed pipe, 22-steel belt holed pipe with vents, 221-vents;
[0078] 3-monitoring element; 4-nut; 5-thread; 6-groove, 7-carrier, 8-grating, 9-optical fiber, 10-adhesive;
[0079] 11-data line, 12-temperature and humidity sensor, 13-reserved hole; 14-steel wire, 15-PE sheath outside the finished steel wire rope, 16-steel strand, 17-PE sheath outside the finished steel strand rope;
[0080] 18- Brillouin fiber, 19- vibrating wire sensor. DETAILED DESCRIPTION
[0081] The intelligent cable with replaceable monitoring element of the present invention comprises two parts, namely, the monitoring element and the cable. The cable comprises a finished cable and a cable installed on site. At least one hole 2 is reserved in the cable 1 along the entire length in the longitudinal direction. A monitoring element 3 is arranged in the hole 2. The monitoring element 3 is connected to the outside world through a data line 11.
[0082] The monitoring element 3 includes a fiber grating sensor monitoring element assembly, a Brillouin optical fiber monitoring element assembly, a vibrating string sensor monitoring element assembly, and other forms of strain gauges, temperature and humidity sensors or other sensitive components capable of monitoring the state of the cable.
[0083] The monitoring element can be inserted into the channel 2 after being tensioned to the design force value according to design requirements during the production process of the finished cable, and the two ends are locked and fixed after a certain tensioning force is applied; or the cable can be installed on-site and tensioned to the design force value according to design requirements after the construction is completed, and then inserted into the channel 2, and the two ends are locked and fixed after a certain tensioning force is applied.
[0084] The structural features of the cables will be further described below in conjunction with the accompanying drawings, depending on whether the cables are finished cables or cables installed on-site.
[0085] Embodiment 1
[0086] A cold-cast steel wire finished cable intelligent cable and a cold-cast extruded steel strand finished cable intelligent cable with replaceable monitoring elements made in a factory:
[0087] like Figure 1 As shown, the cable is a cold-cast steel wire finished cable or a cold-cast extruded steel strand finished cable, and a hole 2 is reserved in the center of the cold-cast steel wire finished cable or the cold-cast extruded steel strand finished cable.
[0088] The hole 2 has a monitoring element 3, which is connected to the outside world via a data line 11;
[0089] like Figure 2 As shown, the monitoring element 3 comprises a steel wire 7 as a carrier, an optical fiber 9, and a nut 4. The carrier 7 is provided with at least one groove 6 in the longitudinal direction, and the optical fiber 9 is placed in the groove (see Figure 3 ), a grating 8 is engraved on the optical fiber, and the optical fiber grating is reliably coupled to the carrier in its groove by a durable adhesive or mechanical crimping method;
[0090] The monitoring element 3 is manufactured by stretching the cold cast steel wire finished cable or the cold cast extruded steel strand finished cable to the design force value according to the design requirements and then passing it through the hole 2. The steel wire 7 of the carrier of the monitoring element 3 is stressed and then fixed; the cold cast steel wire finished cable intelligent cable or the cold cast extruded steel strand finished cable intelligent cable 1a (its structure is shown in FIG. 1 ) constituting the replaceable monitoring element Figure 1 , the cross-section of the cable body is shown in Fig.13 , Fig.14 ).
[0091] As a variation of the first embodiment of the present invention, the cable is an extruded steel strand finished cable made of an extruded steel strand finished cable and the basic structure of the cold-cast extruded steel strand finished cable intelligent cable 1a described in the first embodiment is the same, and a hole 2 is reserved in the center of the extruded steel strand finished cable intelligent cable 1b along its entire length, and a monitoring element 3 is arranged in the hole 2, and the monitoring element 3 is connected to the outside world through a data line 11; the monitoring element 3 is as follows Figure 2 As shown, the monitoring element 3 is manufactured when the extruded steel strand finished cable is stretched to the design force value according to the design requirements and then passed through the channel 2. The carrier 7 of the monitoring element 3 is stressed and then fixed; the extruded steel strand finished cable intelligent cable 1b (see Figure 4 ).
[0092] The structural diagram of the cable body of the above-mentioned intelligent cable with replaceable monitoring elements is shown in Fig.13 , Fig.14 , Fig.13 This is a schematic diagram of the cross-sectional structure of the finished steel wire intelligent cable with replaceable monitoring elements. Fig.14 It is a schematic diagram of the cross-sectional structure of the intelligent cable body of the finished steel strand cable with replaceable monitoring elements.
[0093] The preparation and installation construction method of the above-mentioned cold-cast steel wire finished cable intelligent cable and cold-cast extruded steel strand finished cable intelligent cable made in the factory and capable of replacing monitoring elements in service comprises the following steps:
[0094] A. Construction preparation:
[0095] A1. Prepare materials:
[0096] ① Prepare all the cables and other parts of anchorage according to the materials required for conventional cold-cast steel wire finished cables, cold-cast extruded steel strand finished cables or extruded steel strand finished cables;
[0097] ②Prepare monitoring elements and make hole-forming pipe materials (see Figure 2 );
[0098] A2. Cutting: Cut the cable wire or steel strand and hole-forming pipe materials to a fixed length according to the cable length and working conditions;
[0099] B. Twisting and wrapping: Place the holed pipe in the center, arrange the steel wires or steel strands closely with twist angles according to the requirements of different types of cables, and wrap them tightly with wrapping tape;
[0100] C. Extrusion: hot extrude HDPE onto the wrapped steel wire or steel strand bundle;
[0101] D. Fixed-length cable cutting: Calculate the cable length and cut the cable according to the project requirements;
[0102] E. Anchor making: Align the center holed pipe with the end face of the anchor;
[0103] F. Super tensioning: tension the finished cable according to standard requirements;
[0104] G. Pack and transport to the construction site, hang cables and tension them to the designed cable force;
[0105] H. Install monitoring components: insert the carrier with the fiber grating sensor and temperature and humidity sensor pasted into the reserved hole in the center of the cable, and fix the two ends with nuts;
[0106] I. Connection: Connect the detection terminal to the measuring instrument;
[0107] J. Tension carrier: tension the carrier to the minimum stress of the cable design, and lock the nut on the anchor plate of the cable (see Figure 1 ) or tighten the nut on the end cap of the cable anchor (see Fig.19 );
[0108] K. Cable adjustment: adjust the force of each cable in a cycle across the entire bridge;
[0109] L. Protection: Install anchor protection devices at both ends of the cable.
[0110] Embodiment 2
[0111] An intelligent cable with replaceable monitoring components installed on site - a clip-type steel strand cable intelligent cable:
[0112] Through holes are reserved at the center of the anchors at both ends of the clip-type steel strand cable, and a hole 2 is reserved in the center of the cable body along its entire length. The monitoring element 3 passes through the through hole and the hole and is connected to the outside world through a data line 11;
[0113] like Figure 2 As shown, the monitoring element 3 comprises a carrier 7, an optical fiber 9, and a nut 4. The carrier 7 is provided with at least one groove 6 in the longitudinal direction, and the optical fiber 9 is placed in the groove (see Figure 3 ), a grating 8 is engraved on the optical fiber, and the optical fiber grating is pasted in the carrier groove;
[0114] During construction, after the strands are bundled, tensioned, and adjusted, the monitoring element 3 is inserted into the clip-type strand cable, and the carrier 7 of the monitoring element 3 is stressed and then fixed; the clip-type strand cable intelligent cable (see Figure 5 ).
[0115] The preparation process of the intelligent cable with replaceable monitoring elements installed on-site in the present invention, i.e., the clip-type steel strand cable, comprises the following steps:
[0116] A. Construction preparation:
[0117] A1. Prepare materials:
[0118] ① Prepare all other parts of the anchorage required for conventional clip-type stranded wire group anchors;
[0119] ② Prepare monitoring components (see Figure 2 ) and materials for making hole-forming pipes;
[0120] A2. Cutting: Cut the cable wire or steel strand and the hole-forming pipe material to a fixed length according to the cable length and working conditions;
[0121] B. Installation of upper and lower anchors: reserve a through hole in the center of the anchors at both ends of the clip-type steel strand cable, and place a rigid hole-forming pipe made of a steel pipe, plastic pipe or other pipe material with sufficient strength in the hole. The rest of the installation is carried out according to the conventional method;
[0122] C. HDPE sheath pipe installation:
[0123] D. Place the hole-forming pipe and tension the single steel strand cable:
[0124] A flexible hole-forming pipe made of a spiral steel wire pipe, a tubular space formed by a steel belt or a transparent plastic pipe with sufficient expansion and contraction function is placed at the center of the cable body and connected to the rigid hole-forming pipe previously placed at the center of the upper and lower anchors. A single steel strand is placed around the flexible hole-forming pipe, and the cables are tensioned one by one.
[0125] E. Overall tensioning and cable adjustment: proceed in the conventional way;
[0126] F. Install the monitoring element: insert the monitoring element consisting of the carrier with the fiber grating sensor and the temperature and humidity sensor pasted on it from one end of the anchor into the other end and fix it with a nut;
[0127] G. Tension monitoring element carrier, locking nut (see Figure 5 );
[0128] H. Install the cable hoop shock absorber;
[0129] I. Cyclic adjustment of the forces on each cable;
[0130] J. Install anchor protection devices at both ends of the cable.
[0131] In the above embodiments, the carrier 7 in the monitoring element can be a steel wire or a carbon fiber rod or a glass fiber rod of the same diameter or other reinforcing materials that can be grooved along the longitudinal direction, such as a mixed fiber rod.
[0132] In the above embodiments, the channel is divided into two types: rigid and flexible. In the anchoring area of the cable, the channel is a steel pipe, a plastic pipe or other pipes with sufficient strength to avoid the influence of the reserved channel on the anchoring performance; the cable body part of the cable is a spiral steel wire tube with sufficient expansion and contraction function, a tubular space formed by a steel belt or a transparent plastic tube to avoid the cable from collapsing and squeezing the monitoring element due to the expansion and contraction of the cable.
[0133] In order to reduce the impact on the outer diameter of the cable body and facilitate the insertion of monitoring elements, the diameter of the channel is 1mm to 20mm, and the cross-sectional shape of the channel is polygonal (including rectangular, square, hexagonal), elliptical, circular or elliptical ring (runway type).
[0134] As a variation of the first and second embodiments of the present invention, the number of holes 2 arranged along the entire length of the cable 1 in the longitudinal direction may be more than one, and may be 2, 3, 4, 5 or more holes. Depending on the diameter of the cable and the needs, the hole 2 may be located at the center of the cable 1 or at other locations of the cable. Fig.15, Fig.16 , Fig.17 and Fig.18 , Fig.15 , Fig.17 In the cable body, there are three holes. Fig.15 One of them is located at the center of cable 1, and the other two are symmetrically located on both sides; Fig.17 Among them, one is located at the center of the cable 1, and the other two are symmetrically located on both sides; Fig.16 , Fig.18 In the cable body, there are two holes. Fig.16 One of them is located at the center of the cable 1, and the other one is located at the edge of the cable body; Fig.18 In the figure, both holes are located at the edge of the cable body.
[0135] As a variation of the first and second embodiments of the present invention, the monitoring element assembly may also be a monitoring element assembly composed of a Brillouin optical fiber monitoring element assembly, a vibrating string sensor monitoring element assembly, and other forms of strain gauges, temperature and humidity sensors, or other sensitive components capable of monitoring the state of the cable;
[0136] Fig. 9 , Fig.10 is a schematic diagram of the structure of a monitoring element assembly equipped with Brillouin optical fiber;
[0137] Fig.11 , Fig.12 It is a schematic diagram of the structure of the monitoring element assembly equipped with a vibrating wire sensor;
[0138] The installation methods of other forms of strain gauges, temperature and humidity sensors or other sensitive components capable of monitoring the state of the cable can be implemented by those skilled in the art and will not be described in detail here.
Claims
1. An intelligent cable with replaceable monitoring element, comprising a monitoring element and a cable, wherein the cable comprises a finished cable and a cable installed on site, and is characterized in that: The cable (1) has at least one hole (2) along its entire length in the longitudinal direction, and a monitoring element (3) is provided in the hole (2). The monitoring element (3) is connected to the outside world via a data line (11); The monitoring element (3) comprises a fiber grating sensor monitoring element assembly, a Brillouin optical fiber monitoring element assembly, a vibrating string sensor monitoring element assembly or other forms of strain gauges, temperature and humidity sensors or other sensitive components capable of monitoring the state of the cable. When the monitoring element is a fiber Bragg grating sensor monitoring element assembly, the fiber Bragg grating sensor monitoring element assembly comprises a carrier (7), an optical fiber (9), and a nut (4); at least one groove (6) is provided on the carrier in the longitudinal direction; the optical fiber is placed in the groove; a grating (8) is engraved on the optical fiber; and the fiber Bragg grating and the carrier are reliably coupled in the groove; When the monitoring element is a Brillouin optical fiber monitoring element assembly, the Brillouin optical fiber monitoring element assembly comprises a carrier (7), an optical fiber (9), and a nut (4); at least one groove (6) is provided on the carrier in the longitudinal direction; the optical fiber is placed in the groove and is reliably coupled to the carrier (7) by adhesive or crimping; and threads (5) are provided at both ends of the carrier (7); When the monitoring element is a vibrating-wire sensor monitoring element assembly, the vibrating-wire sensor monitoring element assembly comprises a carrier (7), a vibrating-wire sensor (19), and a nut (4); at least one groove (6) is provided on the carrier in the longitudinal direction; the vibrating-wire sensor is placed in the groove and fixed at both ends by welding; The carrier (7) is a steel wire, a carbon fiber rod, a glass fiber rod, or a mixed fiber rod; In the anchoring area of the cable, the hole (2) is a steel pipe, a plastic pipe or other pipes with sufficient strength; in the cable body part of the cable, the hole (2) is a spiral steel wire pipe with sufficient expansion and contraction function, a tubular space formed by a steel belt or a plastic pipe; The monitoring element is inserted into the hole (2) after being tensioned to the design force value according to the design requirements during the production process of the finished cable, and the two ends are locked and fixed after applying a certain tension force; or the cable is tensioned to the design force value according to the design requirements during the on-site construction and installation, and then inserted into the hole (2) after the construction is completed, and the two ends are locked and fixed after applying a certain tension force.
2. The intelligent cable with replaceable monitoring element according to claim 1, characterized in that: When the cable is a cold-cast steel wire finished cable, a cold-cast extruded steel strand finished cable or an extruded steel strand finished cable, each finished cable has at least one hole (2) along its entire length in the longitudinal direction. The monitoring element (3) is formed during the production process of the finished cable. When the cold-cast steel wire finished cable, the cold-cast extruded steel strand finished cable or the extruded steel strand finished cable is tensioned to a design force value according to design requirements and then passes through the hole (2), the carrier (7) of the monitoring element (3) is force-applied and then fixed. This constitutes a cold-cast steel wire finished cable intelligent cable, a cold-cast steel strand finished cable intelligent cable or an extruded steel strand finished cable intelligent cable with a replaceable monitoring element.
3. The intelligent cable with replaceable monitoring element according to claim 1, characterized in that: The cable is a clip-type steel strand cable installed on-site, at least one through hole is reserved in the anchors at both ends of the clip-type steel strand cable along the entire length in the longitudinal direction, at least one channel (2) is reserved in the cable body along the entire length in the longitudinal direction, and the monitoring element (3) passes through the through hole and the channel and is connected to the outside world via a data line (11); The monitoring element (3) is inserted into the clip-type steel strand cable after the steel strand bundle threading, tensioning and cable adjustment work is completed during construction, and the carrier (7) of the monitoring element (3) is force-applied and then fixed, forming a clip-type steel strand cable intelligent cable with a replaceable monitoring element.
4. The intelligent cable with replaceable monitoring element according to claim 1, 2 or 3, characterized in that: The diameter of the hole is 1 mm to 20 mm, and the cross-sectional shape of the hole is polygonal, elliptical, circular or elliptical ring.
5. A method for preparing and installing a cable of a replaceable monitoring element, which is a method for preparing and installing a cold-cast steel wire finished cable intelligent cable, a cold-cast steel strand finished cable intelligent cable or an extruded steel strand finished cable intelligent cable of a replaceable monitoring element as claimed in claim 2, characterized in that: It includes the following steps: A. Construction preparation: A1. Prepare materials: ① Prepare all the cables and other parts of anchorage according to the materials required for conventional cold-cast steel wire finished cables, cold-cast extruded steel strand finished cables or extruded steel strand finished cables; ②Prepare monitoring components and make hole-forming pipe materials; A2. Cutting: Cut the cable wire or steel strand and hole-forming pipe materials to a fixed length according to the cable length and working conditions; B. Twisting and wrapping: Steel wires or steel strands are arranged closely with twist angles according to the requirements of different types of cables, and the hole-forming pipes are placed in them and wrapped tightly with wrapping tape; C. Extrusion: hot extrude HDPE onto the wrapped steel wire or steel strand bundle; D. Fixed-length cable cutting: Calculate the cable length and cut the cable according to the project requirements; E. Anchoring: Align the hole in the cable body with the hole in the anchor and connect them with heat shrink tubing or plug-in tubing. The rest of the anchoring is done in the conventional way according to the anchor type. F. Super tensioning: tension the finished cable according to standard requirements; G. Pack and transport to the construction site, hang cables and tension them to the designed cable force; H. Install monitoring elements: insert a carrier equipped with a monitoring element assembly including a fiber Bragg grating sensor monitoring element assembly, a Brillouin optical fiber monitoring element assembly, a vibrating string sensor monitoring element assembly or other forms of strain gauges, temperature and humidity sensors or other sensitive components capable of monitoring the state of the cable into the reserved hole of the cable, and fix the two ends with nuts; I. Connection: Connect the detection terminal to the measuring instrument; J. Tensioning the carrier: tensioning the carrier to a set force value, which is between the difference between the actual force value of the cable and the minimum possible force value and the actual force value; locking the nut on the anchor plate or wire plate of the cable, or locking the nut on the end cover surface of the cable anchor; K. Cable adjustment: adjust the force of each cable in a cycle across the entire bridge; L. Protection: Install anchor protection devices at both ends of the cable.
6. A method for preparing and installing a cable of a replaceable monitoring element, which is a method for preparing and installing a clip-type steel strand cable intelligent cable of a replaceable monitoring element as claimed in claim 3, characterized in that: It includes the following steps: A. Construction preparation: A1. Prepare materials: ① Prepare all other parts of the anchorage required for conventional clip-type stranded wire group anchors; ②Prepare monitoring components and make hole-forming pipe materials; A2. Cutting: Cut the cable steel wire or steel strand and the hole-forming pipe material to a fixed length according to the cable length and working conditions; B. Installation of upper and lower anchors: reserve at least one through hole in the anchors at both ends of the clip-type stranded cable, and the rest of the installation shall be carried out in the conventional way; C. Installation of HDPE sheathed pipe: D. Place the hole-forming pipe and connect it to the through hole of the anchor plate, and then tension the single steel strand cable: A flexible hole-forming pipe with sufficient expansion and contraction function made of spiral steel wire pipe, steel belt formed tubular space, segmented plastic pipe or transparent plastic pipe is placed in the cable body and connected with the through holes of the upper and lower anchors. The rest of the installation is carried out according to the conventional method, and the steel strands are hung and tensioned one by one; E. Overall tensioning and cable adjustment: proceed in the conventional way; F. Install monitoring elements: Install a carrier with a monitoring element assembly including a fiber Bragg grating sensor monitoring element assembly, a Brillouin optical fiber monitoring element assembly, a vibrating string sensor monitoring element assembly or other forms of strain gauges, temperature and humidity sensors or other sensitive components capable of monitoring the state of the cable, through one end anchorage through the other end and fix with a nut; G. After the carrier is stretched to a set force value, tighten the nut; This force value is between the difference between the actual force value of the cable and the minimum possible force value and the actual force value; H. Install the cable hoop shock absorber; I. Circularly adjust the force of each cable; J. Install anchor protection devices at both ends of the cable.