A chip production error control method based on the Internet of Things
By using the positioning and fixing device of IoT technology during chip packaging, combined with glue injection around the chip, the packaging error problem caused by chip offset is solved, and the precise positioning and stability of the chip is achieved, ensuring the soldering point and the welding point are Accurate correspondence of pins.
Patent Information
- Application Number
- CN201911235282.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-05
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2039-12-05
AI Technical Summary
During the chip packaging process, since glue curing takes time, the chip is prone to offset and lead to installation errors, and it is difficult for the prior art to achieve accurate positioning and effectively prevent offsets.
The chip production error control method based on the Internet of Things is adopted, and the chip base is accurately positioned and fixed through components such as positioning devices, sliding mechanisms, adsorption devices, telescopic devices and magnet blocks, and glue is applied around the chip to prevent deviation.
Effectively prevent chip offset, ensure accurate correspondence between solder points and pins, minimize packaging errors, and ensure accurate positioning and stability of the chip.
Smart Images

Figure CN110911317B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of chip production, and more specifically, to a chip production error control method based on the Internet of Things. Background Art
[0002] Chip packaging refers to the shell used to install semiconductor integrated circuit chips. It plays the role of placing, fixing, sealing, protecting the chip and enhancing the electrical and thermal performance. It is a bridge between the internal world of the chip and the external circuit (the contacts on the chip are connected to the pins of the package shell with wires, and these pins are connected to other devices through wires on the printed circuit board).
[0003] During the chip packaging process, glue is needed to stick the chip to the base. Since it takes some time for the glue to solidify, if the chip is not fixed at this time, the chip is prone to offset and cause installation errors, resulting in the inability of the soldering points on the chip to connect to the corresponding pins. Summary of the invention
[0004] 1. Technical issues to be solved
[0005] In view of the problems existing in the prior art, the purpose of the present invention is to provide a chip production error control method based on the Internet of Things, which can achieve precise positioning of the base and the chip, and bond the chip by injecting glue around the chip, which can effectively prevent packaging errors caused by chip deviation.
[0006] 2. Technical solution
[0007] To solve the above problems, the present invention adopts the following technical solutions.
[0008] A chip production error control method based on the Internet of Things includes a chip base and a chip, and the control method is as follows:
[0009] S1, firstly, the chip base is installed in the positioning device for positioning, so as to prevent the chip base from shifting during the packaging process and causing packaging failure;
[0010] S2, moving the adsorption device through the sliding mechanism to move the adsorption device to the top of the conveying device, adjusting the telescopic device to move the lower end of the adsorption device downward, and starting the adsorption device to absorb the chip on the conveying device;
[0011] S3, moving the sliding mechanism again so that the adsorption device moves to the top of the positioning device, and the sliding mechanism moves until it is fixed by the fixing device. At this time, the telescopic device is adjusted again so that the adsorption device puts the chip into the positioning device;
[0012] S4, after the chip is placed in place, start injecting glue, close the adsorption device after the glue solidifies, and adjust the telescopic device back to its original position for the next operation.
[0013] Furthermore, the positioning device in the S1 method includes a base, the upper surface of the base is fixedly connected to a positioning seat, and the upper surface of the positioning seat is provided with a positioning groove, a chip base is arranged in the positioning groove, a transversely arranged gas spring is fixedly connected to an inner wall of one side of the positioning groove, and the end of the gas spring is fixedly connected to a top plate, the side wall of the top plate away from the chip base is fixedly connected to two transversely arranged pull rods, and both pull rods penetrate the side wall of the positioning seat, and when the pull rod is pulled outward, the gas spring is compressed and has elastic force, and when the chip base is placed in the positioning groove and the pull rod is released, the elastic force of the gas spring causes the top plate to fix the chip base in the positioning groove, so as to realize the positioning of the chip base.
[0014] Furthermore, the sliding mechanism in the S2 method includes two pillars, both of which are fixedly connected to the upper surface of the base, and the two pillars are respectively arranged on both sides of the positioning seat, a crossbeam is fixedly connected between the upper ends of the two pillars, a guide rail is provided inside the crossbeam, and a guide block is slidably connected in the guide rail, and the guide block slides in the guide rail to facilitate the absorption and placement of the chip.
[0015] Furthermore, the telescopic device in the S2 method includes a first suspension rod, which is fixedly connected to the guide block, a cavity is opened at the lower end of the first suspension rod, and a second suspension rod is inserted in the cavity, an inner wall of one side of the cavity is rotatably connected to a transversely arranged rotating rod, and the rotating rod passes through the side wall of the first suspension rod, a worm gear is fixedly sleeved on the side wall of the rotating rod, and a vertical worm is rotatably connected to the upper inner wall of the cavity, the lower end of the worm is fixedly connected to a screw, and a threaded hole matching the screw is opened on the upper side wall of the second suspension rod, the lower end of the second suspension rod is fixedly connected to a mounting seat, and a glue injection positioning box is sleeved on the outer side of the mounting seat The side walls on both sides of the mounting are fixedly connected with connecting rods, and the connecting rods are fixedly connected to the glue injection positioning box. When the rotating rod is rotated, the rotating rod drives the worm wheel to engage with the worm, and the worm drives the screw to engage with the threaded hole. Since the first suspension rod and the second suspension rod are both square columns, the axial rotation of the second suspension rod is restricted. In this way, the second suspension rod can move up and down only when the screw is engaged with the threaded hole. In addition, when the second suspension rod moves down, the glue injection positioning box and the chip are in contact with the chip base at the same time, and the glue injection positioning box surrounds the chip. At this time, glue is injected into the glue injection positioning box, and the glue surrounds the chip in the middle. After the glue is cured, the chip can be effectively prevented from running off.
[0016] Furthermore, the adsorption device in the S2 method includes a vacuum generator, which is fixedly connected to the first suspension rod and is connected to a suction cup via a hose. The suction cup is fixedly connected to the lower end of the mounting seat. The vacuum generator generates negative pressure on the suction cup, and the suction cup sucks up the chip to complete the grasping and placing of the chip.
[0017] Furthermore, the conveying device in the S2 method includes a conveyor belt, which is fixedly connected to the upper surface of the base and is arranged on one side of the positioning seat. The conveyor belt is used to continuously convey chips to the production process.
[0018] Furthermore, the fixing device in the S3 method includes a magnet block, which is fixedly connected to the side wall of the beam, and the side wall of the first suspension rod is fixedly connected with an iron block matching the magnet block. When the magnet block attracts the iron block, the first suspension rod and the device below will not shake, which can effectively prevent the chip from shifting.
[0019] Furthermore, both inner walls of the cavity are provided with sliding grooves, and both side walls of the second suspension rod are rotatably connected with pulleys slidably connected to the sliding grooves. When the second suspension rod moves up and down in the first suspension rod, the pulley slides in the sliding grooves, which can prevent the second suspension rod from being offset when moving and avoid the occurrence of errors.
[0020] Furthermore, a handle is fixedly connected to one side wall of the first suspension rod, and the handle facilitates the hand to move the device left and right.
[0021] Furthermore, one end of the rotating rod located outside the cavity is fixedly connected to a crank, and the crank facilitates manual rotation of the rotating rod.
[0022] 3. Beneficial effects
[0023] Compared with the prior art, the advantages of the present invention are:
[0024] (1) The elastic force of the gas spring is used to fix the chip base to prevent the chip base from shifting during packaging. The telescopic device is fixed by the adsorption effect of the magnet block and the iron block to prevent shaking when the chip is placed. The chip is bonded by injecting glue around the chip. This mutual cooperation can minimize the occurrence of errors and ensure that the chip's welding points can accurately correspond to the pins.
[0025] (2) The guide block slides in the guide rail to facilitate the pickup and placement of the chip.
[0026] (3) When the rotating rod is rotated, the rotating rod drives the worm wheel to engage with the worm, and the worm drives the screw to engage with the threaded hole. Since the first suspension rod and the second suspension rod are both square columns, the axial rotation of the second suspension rod is restricted. In this way, the second suspension rod can move up and down when the screw is engaged with the threaded hole. In addition, when the second suspension rod moves down, the glue injection positioning box and the chip are in contact with the chip base at the same time. The glue injection positioning box surrounds the chip. At this time, glue is injected into the glue injection positioning box. The glue surrounds the chip in the middle. After the glue is cured, it can effectively prevent the chip from running off.
[0027] (4) The vacuum generator generates negative pressure on the suction cup, which then sucks up the chip to complete the chip grabbing and placing.
[0028] (5) The conveyor belt is used to continuously transport chips to the production process.
[0029] (6) When the magnet block attracts the iron block, the first suspension rod and the device below no longer move, which can effectively prevent the chip from shifting.
[0030] (7) When the second suspension rod moves up and down in the first suspension rod, the pulley slides in the slide groove, which can prevent the second suspension rod from being offset when moving and avoid the occurrence of errors.
[0031] (8) The handle facilitates the hand to move the device left and right.
[0032] (9) The crank handle allows for easy hand rotation of the lever. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention;
[0034] Figure 2 It is a schematic diagram of the cross-sectional structure of the guide rail of the present invention;
[0035] Figure 3 It is a schematic diagram of the cross-sectional structure of the positioning seat of the present invention;
[0036] Figure 4 for Figure 3 The structural diagram at A in the middle;
[0037] Figure 5 for Figure 3 Schematic diagram of the structure at B in the middle;
[0038] Figure 6 It is a schematic cross-sectional structural diagram of a first suspension rod of the present invention;
[0039] Figure 7 for Figure 6 Schematic diagram of the structure at C in the middle.
[0040] Description of the numbers in the figure:
[0041] 1 base, 2 positioning seat, 3 positioning groove, 4 chip base, 5 gas spring, 6 top plate, 7 pull rod, 8 pillar, 9 beam, 10 guide rail, 11 guide block, 12 first suspension rod, 13 magnet block, 14 iron block, 15 second suspension rod, 16 rotating rod, 17 worm gear, 18 worm, 19 screw, 20 threaded hole, 21 mounting seat, 22 glue injection positioning box, 23 conveyor belt, 24 connecting rod, 25 suction cup, 26 chip, 27 vacuum generator, 28 hose, 29 slide groove, 30 pulley, 31 crank, 32 handle. DETAILED DESCRIPTION
[0042] The following will combine the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all the embodiments. All other embodiments obtained by ordinary technicians in this field without creative work based on the embodiments of the present invention belong to the scope of protection of the present invention.
[0043] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top / bottom" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0044] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "mounted / connected", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0045] Embodiment 1:
[0046] See also Figure 1-7 , a chip production error control method based on the Internet of Things, including a chip base 4 and a chip 26, the control method is as follows:
[0047] See also Figure 1-4, S1, first install the chip base 4 in the positioning device for positioning, so as to prevent the chip base 4 from shifting during the packaging process and causing packaging failure. The positioning device includes a base 1, the upper surface of the base 1 is fixedly connected with a positioning seat 2, and the upper surface of the positioning seat 2 is provided with a positioning groove 3, the chip base 4 is arranged in the positioning groove 3, the inner wall of one side of the positioning groove 3 is fixedly connected with a transversely arranged gas spring 5, and the end of the gas spring 5 is fixedly connected with a top plate 6, the top plate 6 is fixedly connected with two transversely arranged pull rods 7 away from the side wall of the chip base 4, and the two pull rods 7 are both arranged through the side wall of the positioning seat 2, the pull rod 7 is pulled outward, the gas spring 5 is compressed and has elastic force, when the chip base 4 is placed in the positioning groove 3, the pull rod 7 is released, and the elastic force of the gas spring 5 causes the top plate 6 to fix the chip base 4 in the positioning groove 3, so as to realize the positioning of the chip base 4;
[0048] S2, the adsorption device is moved to the top of the conveying device by the sliding mechanism, the telescopic device is adjusted to move the lower end of the adsorption device downward, and the adsorption device is started to absorb the chip 26 on the conveying device. The sliding mechanism includes two pillars 8, both of which are fixedly connected to the upper surface of the base 1, and the two pillars 8 are respectively arranged on both sides of the positioning seat 2, and a crossbeam 9 is fixedly connected between the upper ends of the two pillars 8, a guide rail 10 is provided inside the crossbeam 9, and a guide block 11 is slidably connected in the guide rail 10, and the guide block 11 slides in the guide rail 10 to facilitate the absorption and placement of the chip 26;
[0049] See also Figure 5-7The telescopic device in the S2 method includes a first suspension rod 12, a handle 32 is fixedly connected to one side wall of the first suspension rod 12, and the handle 32 is convenient for the hand to move the device left and right. The first suspension rod 12 is fixedly connected to the guide block 11, and a cavity is opened at the lower end of the first suspension rod 12. The inner walls on both sides of the cavity are opened with a slide groove 29, and the side walls on both sides of the second suspension rod 15 are rotatably connected to the pulley 30 slidably connected to the slide groove 29. When the second suspension rod 15 moves up and down in the first suspension rod 12, the pulley 30 moves in the slide groove 29. The second suspension rod 15 can slide in the middle, so as to prevent the second suspension rod 15 from deviating when moving and avoid the generation of errors. The second suspension rod 15 is inserted in the cavity, and the inner wall of one side of the cavity is rotatably connected with a horizontally arranged rotating rod 16. One end of the rotating rod 16 located outside the cavity is fixedly connected with a crank 31. The crank 31 is convenient for the hand to rotate the rotating rod 16, and the rotating rod 16 passes through the side wall of the first suspension rod 12. The side wall of the rotating rod 16 is fixedly sleeved with a worm gear 17, and the upper inner wall of the cavity is rotatably connected with a vertical worm 18. The worm 18 The lower end of the second suspension rod 15 is fixedly connected with a screw rod 19, and the upper side wall of the second suspension rod 15 is provided with a threaded hole 20 matching the screw rod 19, the lower end of the second suspension rod 15 is fixedly connected with a mounting seat 21, and the outer side of the mounting seat 21 is sleeved with a glue injection positioning box 22, and the side walls on both sides of the 21 are fixedly connected with connecting rods 24, and the connecting rods 24 are fixedly connected with the glue injection positioning box 22. When the rotating rod 16 is rotated, the rotating rod 16 drives the worm wheel 17 to mesh with the worm 18, and the worm 18 drives the screw 19 to mesh with the threaded hole 20, and the Since the first suspension rod 12 and the second suspension rod 15 are both square columns, the axial rotation of the second suspension rod 15 is restricted, so that the second suspension rod 15 can move up and down only when the screw rod 19 is engaged with the threaded hole 20. In addition, when the second suspension rod 15 moves down, the glue injection positioning box 22 and the chip 26 are in contact with the chip base 4 at the same time, and the glue injection positioning box 22 surrounds the chip 26. At this time, glue is injected into the glue injection positioning box 22, and the glue surrounds the chip 26 in the middle. After the glue is cured, the chip 26 can be effectively prevented from deviating.
[0050] See also Figure 5 The adsorption device in the S2 method includes a vacuum generator 27, which is fixedly connected to the first suspension rod 12, and the vacuum generator 27 is connected to a suction cup 25 through a hose 28, and the suction cup 25 is fixedly connected to the lower end of the mounting seat 21. The vacuum generator 27 generates negative pressure on the suction cup 25, and the suction cup 25 sucks up the chip 26 to complete the grasping and putting down of the chip 26;
[0051] The conveying device in the S2 method includes a conveyor belt 23, the conveyor belt 23 is fixedly connected to the upper surface of the base 1, and the conveyor belt 33 is arranged on one side of the positioning seat 2, and the conveyor belt 23 is used to continuously convey the chip 26 to the production process;
[0052] S3, the sliding mechanism is moved again to move the adsorption device to the top of the positioning device, and the sliding mechanism is moved until it is fixed by the fixing device. At this time, the telescopic device is adjusted again so that the adsorption device puts the chip 26 into the positioning device;
[0053] The fixing device in the S3 method includes a magnet block 13, which is fixedly connected to the side wall of the crossbeam 9. The side wall of the first suspension rod 12 is fixedly connected with an iron block 14 matching the magnet block 13. When the magnet block 13 attracts the iron block 14, the first suspension rod 12 and the device below will not shake, which can effectively prevent the chip from shifting.
[0054] S4, after the chip 26 is placed in place, glue injection begins, and after the glue is cured, the adsorption device is closed, and the telescopic device is adjusted back to the original position for the next operation.
[0055] When the present invention is operated, the chip base 4 is first positioned to prevent the chip base 4 from shifting during the packaging process and causing packaging failure. When fixing, the pull rod 7 is pulled outward, and the gas spring 5 is compressed and has elastic force. When the chip base 4 is placed in the positioning groove 3, the pull rod 7 is released. The elastic force of the gas spring 5 causes the top plate 6 to fix the chip base 4 in the positioning groove 3 to achieve the positioning of the chip base 4. Then the first suspension rod 12 is moved, and the guide block 11 slides in the guide rail 10. When the suction cup 25 is located above the conveyor belt 23, the vacuum generator 27 is started. The vacuum generator 27 causes the suction cup 25 to generate negative pressure. The suction cup 25 sucks up the chip 26, and then the chip 26 is moved to the top of the chip base 4. The rotating rod 16 is rotated, and the rotating rod 16 drives the worm wheel 17 to engage with the worm 18, and the worm 18 drives The screw 19 is engaged with the threaded hole 20. Since the first suspension rod 12 and the second suspension rod 15 are both square columns, the axial rotation of the second suspension rod 15 is restricted, so that the second suspension rod 15 can move up and down only when the screw 19 is engaged with the threaded hole 20. When the second suspension rod 15 moves down, the glue injection positioning box 22 and the chip 26 are in contact with the chip base 4 at the same time and thereby press the chip base 4. The glue injection positioning box 22 surrounds the chip 26. At this time, glue is injected into the glue injection positioning box 22. The glue surrounds the chip 26 in the middle. After the glue is cured, the chip 26 can be effectively prevented from deviating. It can realize accurate positioning of the chip base 4 and the chip 26, and the chip 26 is bonded by injecting glue around the chip 26, which can effectively prevent the packaging error caused by the offset of the chip 26.
[0056] The above is only a preferred specific implementation manner of the present invention; but the protection scope of the present invention is not limited thereto; any technician familiar with the technical field within the technical scope disclosed by the present invention; any equivalent replacement or change based on the technical solution and improved concept of the present invention shall be covered by the protection scope of the present invention.
Claims
1. A chip production error control method based on the Internet of Things, comprising a chip base (4) and a chip (26), characterized in that: The control method is as follows: S1, firstly, the chip base (4) is installed in a positioning device for positioning, so as to prevent the chip base (4) from being offset during the packaging process and causing packaging failure, the positioning device comprising a base (1), the upper surface of the base (1) is fixedly connected to a positioning seat (2), and the upper surface of the positioning seat (2) is provided with a positioning groove (3), the chip base (4) is arranged in the positioning groove (3), and a gas spring (5) arranged transversely is fixedly connected to an inner wall of one side of the positioning groove (3), and the end of the gas spring (5) is fixedly connected to the inner wall of the positioning groove (3). A top plate (6) is fixedly connected thereto. The top plate (6) is fixedly connected to two laterally arranged pull rods (7) at a side wall away from the chip base (4). Both pull rods (7) penetrate the side wall of the positioning seat (2). When the pull rods (7) are pulled outward, the gas spring (5) is compressed and has elastic force. When the chip base (4) is placed in the positioning groove (3), the pull rods (7) are released. The elastic force of the gas spring (5) causes the top plate (6) to fix the chip base (2) in the positioning groove (3), thereby realizing the positioning of the chip base (2). S2, moving the adsorption device through the sliding mechanism to move the adsorption device to the top of the conveying device, adjusting the telescopic device to move the lower end of the adsorption device downward, starting the adsorption device to adsorb the chip (26) on the conveying device, the sliding mechanism includes two pillars (8), the two pillars (8) are fixedly connected to the upper surface of the base (1), and the two pillars (8) are respectively arranged on both sides of the positioning seat (2), a crossbeam (9) is fixedly connected between the upper ends of the two pillars (8), a guide rail (10) is provided inside the crossbeam (9), and a guide rail (10) is slidably connected in the guide rail (10). The guide block (11) comprises a first suspension rod (12), the first suspension rod (12) is fixedly connected to the guide block (11), a cavity is formed at the lower end of the first suspension rod (12), and a second suspension rod (15) is inserted into the cavity, a rotating rod (16) is rotatably connected to an inner wall of one side of the cavity, and the rotating rod (16) passes through the side wall of the first suspension rod (12), a worm wheel (17) is fixedly sleeved on the side wall of the rotating rod (16), and a vertical worm (18) is rotatably connected to the inner wall of the upper end of the cavity, and a screw (19) is fixedly connected to the lower end of the worm (18). The upper side wall of the second suspension rod (15) is provided with a threaded hole (20) matching the screw rod (19); the lower end of the second suspension rod (15) is fixedly connected with a mounting seat (21), and a glue injection positioning box (22) is sleeved on the outer side of the mounting seat (21); the side walls on both sides of the mounting seat (21) are fixedly connected with connecting rods (24), and the connecting rods (24) are fixedly connected with the glue injection positioning box (22); when the rotating rod (16) is rotated, the rotating rod (16) drives the worm wheel (17) to mesh with the worm (18), and the worm (18) drives the screw rod (19) to mesh with the threaded hole (20), due to The first suspension rod (12) and the second suspension rod (15) are both square columns, so the axial rotation of the second suspension rod (15) is restricted, so that the second suspension rod (15) can move up and down only when the screw rod (19) is engaged with the threaded hole (20). In addition, when the second suspension rod (15) moves downward, the glue injection positioning box (22) and the chip (26) are in contact with the chip base (4) at the same time, and the glue injection positioning box (22) surrounds the chip (26). At this time, glue is injected into the glue injection positioning box (22), and the glue surrounds the chip (26) in the middle. After the glue is cured, the chip (26) can be effectively prevented from deviating. S3, moving the sliding mechanism again so that the adsorption device moves to the top of the positioning device, and the sliding mechanism moves until it is fixed by the fixing device, and then adjusting the telescopic device again so that the adsorption device places the chip (26) into the positioning device; S4, after the chip (26) is placed in place, glue injection begins, and after the glue is cured, the adsorption device is closed, and the telescopic device is adjusted back to the original position for the next operation.
2. The chip production error control method based on the Internet of Things according to claim 1, characterized in that: The adsorption device in the S2 method includes a vacuum generator (27), the vacuum generator (27) is fixedly connected to the first suspension rod (12), and the vacuum generator (27) is connected to a suction cup (25) via a hose (28), and the suction cup (25) is fixedly connected to the lower end of the mounting seat (21).
3. The chip production error control method based on the Internet of Things according to claim 2 is characterized in that: The conveying device in the S2 method comprises a conveying belt (23), wherein the conveying belt (23) is fixedly connected to the upper surface of the base (1), and the conveying belt (23) is arranged on one side of the positioning seat (2).
4. The chip production error control method based on the Internet of Things according to claim 3 is characterized in that: The fixing device in the S3 method comprises a magnet block (13), wherein the magnet block (13) is fixedly connected to the side wall of the crossbeam (9), and the side wall of the first suspension rod (12) is fixedly connected to an iron block (14) matching the magnet block (13).
5. The chip production error control method based on the Internet of Things according to claim 4 is characterized in that: Both inner walls of the cavity are provided with sliding grooves (29), and both side walls of the second suspension rod (15) are rotatably connected to pulleys (30) that are slidably connected to the sliding grooves (29).
6. The chip production error control method based on the Internet of Things according to claim 4 is characterized in that: A handle (32) is fixedly connected to a side wall of the first suspension rod (12).
7. The chip production error control method based on the Internet of Things according to claim 4 is characterized in that: One end of the rotating rod (16) located outside the cavity is fixedly connected to a crank (31).