Energy-fed load test system
By designing an energy-feeding load testing system, using bidirectional converter and multi-speed matching technology, the problems of general use of generator test systems and grid pollution in the existing technology are solved, and efficient feedback and reuse of generator energy is achieved. , improves the flexibility and reliability of testing.
Patent Information
- Application Number
- CN202010299583.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-04-16
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2040-04-16
AI Technical Summary
The existing generator load testing system is not very general, and the generator power is strictly controlled to avoid grid pollution caused by backflow of electricity, which limits the scope of the test and affects practicality and marketing promotion.
Design a feed-type load testing system, using three-phase external terminals, transformers, four-quadrant converters and logic processing units, to realize the feedback and reuse of generator energy through bidirectional converters, and through load boxes and electrically controlled switches Control the load to ensure the system is stable and flexible.
It realizes efficient feedback and reuse of generator energy, enhances the generalization of the system, and avoids grid pollution through multi-speed matching and overvoltage protection, and improves the flexibility and reliability of testing.
Smart Images

Figure CN111458639B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a generator testing device, in particular to an energy-feed type load testing system. Background Art
[0002] The generator needs to be load tested. The traditional load testing method is to add a pure resistive load at the output end of the generator. This method cannot reuse the electric energy generated by the generator. Therefore, the prior art has developed the concept of using factory equipment to simulate the load, such as patent document 201710554979.0. It transforms the electric energy generated by the generator first and then converts it into current, and then sends it to the factory's internal power grid for use by the equipment, thereby achieving both generator load testing and generator power reuse.
[0003] However, the above solutions also have many shortcomings, such as:
[0004] (1) The test system can only be used for load testing and has the defect of not being widely applicable;
[0005] (2) When using the test system for load testing, the generator power must be strictly controlled to be lower than the load power of the equipment in the factory. Otherwise, there is a risk of electric energy flowing back into the industrial power grid through the factory's internal power grid, causing grid pollution. However, strict control of the generator power also limits the test range of the generator, which is not very practical and cannot be promoted in the market. Summary of the invention
[0006] The present invention is to improve or partially improve the deficiencies of the prior art and provide an energy-feeding load testing system.
[0007] To achieve the above object, the present invention is implemented through the following technical solutions:
[0008] Provided is an energy-feed load testing system, comprising:
[0009] Three-phase external terminals, used for external generator sets or electrical equipment;
[0010] A first transformer, a primary three-phase end of which is connected to a three-phase external terminal;
[0011] A converter cabinet, wherein both the grid side and the generator side are four-quadrant converters, wherein the three-phase AC side of the four-quadrant converter on the generator side is connected to the secondary three-phase terminal of the first transformer, the three-phase AC side of the four-quadrant converter on the grid side serves as the three-phase outgoing terminal of the converter cabinet, and the DC sides of the four-quadrant converter on the grid side and the four-quadrant converter on the generator side are connected;
[0012] A second transformer, whose primary three-phase terminal is connected to the three-phase outgoing terminal of the converter cabinet, and whose secondary three-phase terminal is used to connect to the external factory internal power grid;
[0013] The logic processing unit is used to drive the four-quadrant converter to operate.
[0014] In the above-mentioned energy-feed load test system, the four-quadrant converter on the grid side works in PWM rectification mode, which is mainly used to stabilize the DC side voltage and send the DC side energy to the factory internal grid or absorb energy from the factory internal grid and send it to the DC side; the four-quadrant converter on the generator side is mainly used to control the three-phase current to simulate resistive or inductive loads. When simulating the load, the energy of the generator is sent to the DC side. In the case of shore power application, it is used to invert the required AC voltage to power external ships.
[0015] The energy-fed load testing system of the present invention realizes bidirectional current conversion by setting both the grid side and the generator side in the converter cabinet as four-quadrant converters, and cooperates with the transformer-converter-converter architecture to feed back most of the electric energy generated by the generator set to the internal power grid of the factory for internal consumption, and can also be used as a mobile shore power supply device, thus having versatility.
[0016] Furthermore, in order to avoid excessive load causing the internal power grid of the factory to feed back power to the industrial power grid, the test system is also provided with a load box and a switch cabinet C electrically connected to the logic processing unit. The load box has multiple sets of power loads inside, and each set of power loads is provided with three high-power resistors. One end of the three resistors in each set of power loads is respectively connected to the three phase lines of the three-phase external terminals, and the other ends of the three resistors are commonly connected to the ground via the electric control switch of the switch cabinet C.
[0017] Furthermore, the resistance values of the pure resistive power loads are set to be different from each other so that they can be selected in different grades to achieve multi-grade matching.
[0018] Furthermore, the power loads are all set to be pure resistive power loads to ensure that the reactive power in the system will not change when they are loaded.
[0019] Furthermore, in order to realize independent shutdown control of the transformers, the primary three-phase terminals and the secondary three-phase terminals of the first transformer and the second transformer are both connected in series with an electronically controlled switch electrically connected to the logic processing unit.
[0020] Furthermore, in order to increase the transformer capacity of the system and match multiple converter cabinets, the first transformer and the second transformer are formed by connecting multiple identical transformers in parallel.
[0021] Furthermore, in order to improve the system's current conversion capacity, the converter cabinet has multiple ones that are connected in parallel with each other. Each converter cabinet has multiple four-quadrant converters on the grid side and the generator side. The four-quadrant converters on the grid side are connected in parallel with each other, and the four-quadrant converters on the generator side are connected in parallel with each other.
[0022] Furthermore, in order to ensure the stable operation of the converter, a switch tube and an impulse grounding resistor Rch are arranged on the DC side where the four-quadrant converter on the grid side and the four-quadrant converter on the generator side are connected. The two ends of the branch formed by the switch tube in series with the impulse grounding resistor Rch are respectively bridged across the positive and negative bus bars on the DC side to achieve overvoltage protection.
[0023] Furthermore, all control circuits and signal acquisition circuits in the converter cabinet are connected by round copper plugs and terminal blocks to avoid tip discharge.
[0024] Furthermore, it also includes a plurality of voltage sensors and current sensors for collecting the internal grid voltage of the factory, the output current of the converter cabinet and the DC side voltage of the four-quadrant converter and providing them to the logic processing unit.
[0025] Furthermore, in order to facilitate mobility, the first transformer, the converter cabinet, and the second transformer are integrated in a movable container.
[0026] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented according to the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are listed below. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:
[0028] Figure 1 A system block diagram of the energy-feed load testing system of the present invention is shown;
[0029] Figure 2 shows the circuit diagram inside the system converter cabinet;
[0030] Figure 3 The schematic diagram shows the state of the energy-feed load testing system of the present invention when used as a mobile shore power supply device. DETAILED DESCRIPTION
[0031] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.
[0032] This embodiment aims to meet the following objectives:
[0033] 1. Meet the basic load test of normal marine generators. The voltage of marine generators is AC400V, 50Hz;
[0034] 2. To feed back most of the electric energy generated by the generator set to the internal power grid of the factory for internal consumption;
[0035] 3. Meet the reliability requirements during use and eliminate problems such as low insulation after the use of dry-type load boxes;
[0036] 4. Used as a mobile shore power supply device.
[0037] To this end, the energy-feed load test system of this embodiment is mainly composed of the following parts, including a 400V / 690V box-type transformer, a system converter cabinet, a 690V / 10KV box-type transformer, a 3MW load box, and a host computer as a logic processing unit. The 400V / 690V box-type transformer, the system converter cabinet, the 690V / 10KV box-type transformer and the matching switch cabinet are installed in a movable container, which is convenient for realizing a mobile shore power supply.
[0038] See Figure 1 , the front end of the system is a 400V / 690V box-type transformer installed in a movable container, with an overall capacity of 6MVA, which is used to boost the AC400V output of the generators G1 and G2 to AC690V to meet the rated working voltage range of the converter. Among them, the 400V / 690V box-type transformer is composed of two parallel 3150KVA dry-type transformers T1 and T2 and a switch cabinet A (to simplify the diagram, the switch cabinets in this embodiment are not shown). After the transformers T1 and T2 are connected in parallel, their primary three-phase ends (A, B, and C phases) are connected to the three-phase external terminals for external generator sets or electrical equipment through three of the electric control switches of the switch cabinet A, and the secondary three-phase ends are connected to the three-phase incoming line terminals of the system converter cabinet through the other three electric control switches of the switch cabinet A.
[0039] The system converter cabinet consists of two parallel converters A1 and A2. Figure 2 The converters A1 and A2 are divided into two electrical cabinets, where A1 is the master control cabinet and A2 is the slave control cabinet. The internal electrical and mechanical structures of the master control cabinet and the slave control cabinet are exactly the same. They can be divided into power modules, control modules, heat dissipation modules and movable cabinets with rollers.
[0040] The main body of the power module is a three-bridge-arm four-quadrant converter, of which the grid side and the generator side are each composed of three four-quadrant converters in parallel. The three-phase AC side of the four-quadrant converter on the generator side is connected to the secondary three-phase end of the 400V / 690V box-type transformer, and the three-phase AC side of the four-quadrant converter on the grid side serves as the three-phase outgoing terminal of the system converter cabinet. The DC sides of the four-quadrant converter on the grid side and the four-quadrant converter on the generator side are connected to achieve bidirectional conversion.
[0041] Furthermore, in order to achieve grid-side filtering, an LCL filter is connected in series on the three-phase AC side of the four-quadrant converter on the grid side; in order to achieve independent controllable shutdown, circuit breakers K1 and Q1 are connected in series on the three-phase AC sides of the four-quadrant converter on the generator side and the four-quadrant converter on the grid side, and the circuit breakers K1 and Q1 are connected to the control module to achieve shutdown control; in order to limit the short-circuit current of the capacitor in the four-quadrant converter at the moment of power-on, so as to protect the components on the system converter cabinet from being damaged by the instantaneous short-circuit current of the capacitor, a circuit breaker K1 and Q1 are connected in series on the four-quadrant converter on the grid side and the generator side. A conventional pre-charging circuit is arranged on the DC side where the four-quadrant converter on the motor side is connected. To achieve overvoltage protection, an overvoltage protection circuit is arranged on the DC side where the four-quadrant converter on the grid side and the four-quadrant converter on the generator side are connected. The overvoltage protection circuit is formed by a switch tube connected in series with an impulse grounding resistor Rch, and its two ends are respectively bridged across the positive and negative bus bars on the DC side. A voltage detector SV1 is also bridged across the positive and negative bus bars for collecting the voltage on the DC side for the control module, so that the control module can turn on the switch tube in the event of overvoltage and thereby connect the impulse grounding resistor Rch.
[0042] The control module includes three digital controllers (DCU), of which two are allocated to the main control cabinet, namely the grid-side DCU and the generator-side DCU, and one is allocated to the slave control cabinet, namely the grid-side DCU. The grid-side DCU of the main control cabinet controls the grid-side four-quadrant converter of the main control cabinet, and the grid-side DCU of the slave control cabinet controls the grid-side four-quadrant converter of the slave control cabinet. The generator-side grid-side four-quadrant converters of the main control cabinet and the slave control cabinet are all controlled by the generator-side DCU of the main control cabinet.
[0043] The control module also includes multiple voltage sensors and current sensors. The control module collects the factory internal grid voltage, the output current of the system converter cabinet and the DC side voltage of the four-quadrant converter through the voltage sensors and current sensors, and controls the constancy of the DC side voltage, thereby controlling the equivalent energy-fed load of the generator under normal power generation conditions, and transmitting the generated energy to the factory internal power grid. In the shore power supply mode, the grid energy is controlled to pass through the grid-side converter, and the output voltage is inverted by the original generator-side converter to supply power to the moored ships.
[0044] Furthermore, since it works in a high current environment, all control circuits and signal acquisition circuits in the system converter cabinet are connected using round copper plug terminal blocks to avoid tip discharge, while communication uses communication interfaces such as optical fiber and Profibus to ensure reliable communication signals.
[0045] The heat dissipation module adopts water cooling. Its specific structure and cabinet structure can refer to the existing settings and will not be repeated here.
[0046] See Figure 1 The three-phase outgoing line of the system converter cabinet is connected to a 690V / 10KV box-type transformer installed in a movable container, with an overall capacity of 6MVA, which is used to boost the AC690V output of the system converter cabinet to AC10KV. The 690V / 10KV box-type transformer also consists of two parallel 3150KVA dry-type transformers T3 and T4 and a switch cabinet B. After the transformers T3 and T4 are connected in parallel, their primary three-phase ends are connected to the three-phase outgoing line of the system converter cabinet through three of the electric control switches of the switch cabinet B. The secondary three-phase ends of the transformers T3 and T4 after being connected in parallel are connected to the internal power grid of the factory through another three electric control switches of the switch cabinet B.
[0047] The 3MW load box consists of an AC400V-3MW dry-type load box and a switch cabinet C. There are multiple sets of pure resistive power loads inside the dry-type load box. The resistance values of each set of pure resistive power loads are different. Each set of pure resistive power loads is composed of three high-power resistors. One end of the three resistors in each set of pure resistive power loads is respectively connected to the three phase lines of the three-phase external terminals, and the other ends of the three resistors are connected to the ground through three of the electric control switches of the switch cabinet C.
[0048] The host computer is the control center of the entire system. It is connected to the control modules in the switch cabinets A, B, C and the system converter cabinet respectively. It reads the electrical parameters of the instruments in each switch cabinet, loads and unloads the system converter cabinet, and supplies power to the electrical equipment (load 1, load 2, etc.) in the factory through the factory's internal power grid.
[0049] The energy-feed load testing system of this embodiment can be used as a load, and can also be used as a mobile shore power supply device.
[0050] When used as a load, Figure 1 As shown, the engines G1 and G2 are connected to the three-phase external terminals, and the positive output of the control system converter cabinet is controlled to supply power to the internal power grid of the factory.
[0051] In this mode, please note that:
[0052] (1) The load power and power factor of the factory internal power grid can be adjusted through the control system converter cabinet. The specific adjustment method refers to the method of adjusting the power factor and power value of the converter in the prior art, which will not be described in detail here;
[0053] (2) When the host computer detects that the load demand of the factory's internal power grid is lower than the load test demand, the host computer automatically calculates the difference between the load demand of the factory's internal power grid and the load test demand, and then controls the 3MW load box to selectively access the load through the switch cabinet C, thereby consuming the difference and achieving a compensatory effect to avoid excessive load causing the factory's internal power grid to send power back to the industrial power grid.
[0054] When no load test is performed, the test system can be used as a mobile shore power supply device. Figure 3 As shown, the control system converter cabinet reversely outputs AC440V, 60Hz shore power and transmits power to the outside through the three-phase external terminals.
[0055] Similarly, in this mode, when the power factor of the factory's internal power grid is low, power factor compensation can be achieved by controlling the converter.
[0056] It should be stated that the content and specific implementation methods of the present invention are intended to demonstrate the practical application of the technical solution provided by the present invention and should not be interpreted as limiting the scope of protection of the present invention. Those skilled in the art may make various modifications, equivalent substitutions, or improvements inspired by the spirit and principles of the present invention. However, these changes or modifications are within the scope of protection of the application to be approved.
Claims
1. Energy-feed load test system, characterized in that: include: Three-phase external terminals, used for external generator sets or electrical equipment; A first transformer, a primary three-phase end of which is connected to a three-phase external terminal; A converter cabinet, wherein both the grid side and the generator side are four-quadrant converters, wherein the three-phase AC side of the four-quadrant converter on the generator side is connected to the secondary three-phase terminal of the first transformer, the three-phase AC side of the four-quadrant converter on the grid side serves as the three-phase outgoing terminal of the converter cabinet, and the DC sides of the four-quadrant converter on the grid side and the four-quadrant converter on the generator side are connected; A second transformer, whose primary three-phase terminal is connected to the three-phase outgoing terminal of the converter cabinet, and whose secondary three-phase terminal is used to connect to the external factory internal power grid; A logic processing unit, which is used to drive the four-quadrant converter to work; It also includes a load box and a switch cabinet C electrically connected to the logic processing unit, wherein the load box has multiple sets of power loads inside, each set of power loads is provided with three high-power resistors, one end of the three resistors in each set of power loads is respectively connected to the three phase lines of the three-phase external terminal, and the other ends of the three resistors are commonly connected to the ground via the electric control switch of the switch cabinet C; The first transformer and the second transformer are formed by connecting a plurality of identical transformers in parallel.
2. The energy-feed load testing system according to claim 1, characterized in that: The resistance values of each set of pure resistive power loads are different from each other; and / or the power loads are all pure resistive power loads.
3. The energy-feed load testing system according to claim 1, characterized in that: The primary three-phase end and the secondary three-phase end of the first transformer and the second transformer are both connected in series with an electric control switch electrically connected to the logic processing unit.
4. The energy-fed load testing system according to claim 1, characterized in that: The converter cabinet has multiple four-quadrant converters which are connected in parallel with each other. The grid side and the generator side of each converter cabinet have multiple four-quadrant converters. The four-quadrant converters on the grid side are connected in parallel with each other, and the four-quadrant converters on the generator side are connected in parallel with each other.
5. The energy-fed load testing system according to claim 4, characterized in that: A switch tube and an impulse grounding resistor Rch are arranged on the DC side where the four-quadrant converter on the grid side and the four-quadrant converter on the generator side are connected. The two ends of the branch formed by the switch tube in series with the impulse grounding resistor Rch are respectively bridged over the positive and negative busbars on the DC side.
6. The energy-fed load testing system according to claim 4, characterized in that: All control circuits and signal acquisition circuits in the converter cabinet are connected by circular copper plugs and terminal blocks.
7. The energy-feed load testing system according to claim 1, characterized in that: It also includes a plurality of voltage sensors and current sensors for collecting the voltage of the internal power grid of the factory, the output current of the converter cabinet and the DC side voltage of the four-quadrant converter and providing them to the logic processing unit.
8. The energy-feed load testing system according to claim 1, characterized in that: The first transformer, the converter cabinet and the second transformer are integrated in a movable container.