Substation operation ticket processing method, device, computer equipment and storage medium
Through automated specification review, component attribute review and power operation status review, the problem of low manual review accuracy is solved and the review accuracy and safety of substation operation tickets are improved.
Patent Information
- Application Number
- CN202010607780.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-30
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2040-06-30
AI Technical Summary
In the existing technology, the review of substation operation tickets relies on manual labor, resulting in low review accuracy and prone to unqualified substation operation tickets.
By obtaining substation operation tickets in electronic document format, automatic review of safety specifications is performed based on automatic review rules generated from power safety specification files, automatic review of component attributes is performed using the equipment component database, and power operation status is automatically reviewed based on historical substation operation tickets. , and automatically review safety measures based on the associated substation work ticket, triggering error adjustment or taking effect.
It improves the review accuracy of substation operation tickets, reduces the probability of unqualified tickets, and ensures that the tickets comply with power safety regulations and are correct.
Smart Images

Figure CN111861787B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of electrical safety technology, and in particular to a method, device, computer equipment and storage medium for processing a substation operation ticket. Background Art
[0002] Substations are places in power systems that transform voltage and current, receive and distribute electrical energy. Substations include many high-voltage electrical equipment, which need to be operated in a standardized manner based on the corresponding substation operation ticket to ensure safe operation. Substation operation tickets are an organizational written form of control basis designed for logical operations and orderly communication to change the operating status of electrical equipment and related factors. Substation operation tickets are an important basis for electrical equipment operation, maintenance, testing and power engineering construction, and are an important measure to ensure the safety of personnel, power grids and electrical equipment during power production. In order to ensure the standardization of substation operation tickets in substations, substation operation tickets need to be reviewed and processed.
[0003] At present, the review and processing of substation operation tickets completely relies on manual review. However, manual review of substation operation tickets often results in unqualified substation operation tickets, which leads to a low review accuracy of substation operation tickets. Summary of the invention
[0004] Based on this, it is necessary to provide a substation operation ticket processing method, device, computer equipment and storage medium that can improve the review accuracy of substation operation tickets in response to the above technical problems.
[0005] A method for processing a substation operation ticket, the method comprising:
[0006] Obtain the substation operation ticket in electronic document format;
[0007] According to the automatic review rules of the specifications generated based on the power safety specification file, the substation operation ticket is automatically reviewed for safety specifications;
[0008] Based on the equipment component database, automatically review the component attributes of the components associated with the substation operation ticket;
[0009] According to the historical substation operation ticket corresponding to the substation operation ticket, automatically review the power operation status of the substation operation ticket;
[0010] Automatically review the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket;
[0011] When at least one item fails the automatic review, a review error is triggered, and the substation operation ticket is adjusted based on the content of the review error;
[0012] When all automatic reviews are passed, the substation operation ticket is triggered to take effect.
[0013] In one embodiment, the automatic safety specification review of the substation operation ticket according to the automatic specification review rules generated based on the power safety specification file includes:
[0014] According to the automatic review rules of the specification generated based on the power safety specification file, searching for the first preset component name at the preset position of the substation operation ticket;
[0015] When the first preset component name is not found at the preset position of the substation operation ticket, it is determined that the automatic safety specification review of the substation operation ticket has failed;
[0016] When the first preset component name is found at the preset position of the substation operation ticket, it is determined whether the statement of the operation step corresponding to the first preset component name conforms to the preset grammatical rules; if so, it is determined that the automatic review of the safety specifications of the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety specifications of the substation operation ticket has failed.
[0017] In one embodiment, the automatic review of the attributes of the components associated with the substation operation ticket based on the equipment component database includes:
[0018] Extracting the attributes of the components associated with the power transformation operation ticket from the power transformation operation ticket;
[0019] Searching the equipment component database for properties of the component associated with the extracted substation operation ticket;
[0020] When the attributes of the components associated with the extracted substation operation ticket are found in the equipment component database, it is determined that the automatic review of the attributes of the components associated with the substation operation ticket has passed; otherwise, it is determined that the automatic review of the attributes of the components associated with the substation operation ticket has failed.
[0021] In one embodiment, the automatic review of the power operation status of the substation operation ticket according to the historical substation operation ticket corresponding to the substation operation ticket includes:
[0022] Extracting the names of the components associated with each other from the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket;
[0023] For the extracted identical component names, determining whether the corresponding power operation states are opposite;
[0024] When the power operation status is opposite, it is determined that the automatic review of the power operation status of the substation operation ticket has passed; otherwise, it is determined that the automatic review of the power operation status of the substation operation ticket has failed.
[0025] In one embodiment, the automatic review of the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket includes:
[0026] Extract the power operation states corresponding to the second preset component names respectively from the substation operation ticket and the substation work ticket associated with the substation operation ticket;
[0027] When the power operation states corresponding to the extracted second preset component names are consistent, it is determined that the automatic review of the safety measures for the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety measures for the substation operation ticket has failed.
[0028] In one embodiment, before obtaining the substation operation ticket in electronic document format, the method further includes:
[0029] Obtain substation operation task information;
[0030] Determine the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed according to the transformation operation task information;
[0031] According to the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed, a transformation operation ticket in an electronic document format is generated according to a preset transformation operation ticket template.
[0032] A device for processing a substation operation ticket, comprising:
[0033] An acquisition module is used to acquire a substation operation ticket in an electronic document format;
[0034] The review module is used to automatically review the safety specifications of the substation operation ticket according to the automatic review rules of the specifications generated based on the power safety specification file; automatically review the properties of the components associated with the substation operation ticket based on the equipment component database; automatically review the power operation status of the substation operation ticket according to the historical substation operation tickets corresponding to the substation operation ticket; automatically review the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket; when at least one item fails the automatic review, trigger a review error, and trigger the adjustment of the substation operation ticket based on the content of the review error; when all automatic reviews pass, trigger the substation operation ticket to take effect.
[0035] In one embodiment, the device further comprises:
[0036] A generation module is used to obtain substation operation task information; determine the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed according to the substation operation task information; and generate a substation operation ticket in an electronic document format according to a preset substation operation ticket template based on the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed.
[0037] A computer device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the following steps are implemented:
[0038] Obtain the substation operation ticket in electronic document format;
[0039] According to the automatic review rules of the specifications generated based on the power safety specification file, the substation operation ticket is automatically reviewed for safety specifications;
[0040] Based on the equipment component database, automatically review the component attributes of the components associated with the substation operation ticket;
[0041] According to the historical substation operation ticket corresponding to the substation operation ticket, automatically review the power operation status of the substation operation ticket;
[0042] Automatically review the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket;
[0043] When at least one item fails the automatic review, a review error is triggered, and the substation operation ticket is adjusted based on the content of the review error;
[0044] When all automatic reviews are passed, the substation operation ticket is triggered to take effect.
[0045] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the following steps:
[0046] Obtain the substation operation ticket in electronic document format;
[0047] According to the automatic review rules of the specifications generated based on the power safety specification file, the substation operation ticket is automatically reviewed for safety specifications;
[0048] Based on the equipment component database, automatically review the component attributes of the components associated with the substation operation ticket;
[0049] According to the historical substation operation ticket corresponding to the substation operation ticket, automatically review the power operation status of the substation operation ticket;
[0050] Automatically review the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket;
[0051] When at least one item fails the automatic review, a review error is triggered, and the substation operation ticket is adjusted based on the content of the review error;
[0052] When all automatic reviews are passed, the substation operation ticket is triggered to take effect.
[0053] The above-mentioned substation operation ticket processing method, device, computer equipment and storage medium obtain the substation operation ticket in the electronic document format, and automatically review the safety specifications of the substation operation ticket according to the automatic review rules generated based on the power safety specification file to ensure that the substation operation ticket meets the requirements of the power safety specification file. Based on the equipment component database, the attributes of the components associated with the substation operation ticket are automatically reviewed to ensure that the attributes of the components associated with the substation operation ticket are correct. According to the historical substation operation ticket corresponding to the substation operation ticket, the power operation status of the substation operation ticket is automatically reviewed to ensure that the power operation status of the substation operation ticket is accurate. According to the substation work ticket associated with the substation operation ticket, the safety measures of the substation operation ticket are automatically reviewed to ensure that the substation operation ticket meets the requirements of the safety measures specification. When at least one item is not passed in the automatic review, the review error is triggered, and the substation operation ticket is adjusted based on the content of the review error. When all automatic reviews pass, the substation operation ticket is triggered to take effect. In this way, by automatically reviewing the safety specifications, component properties, power operation status and safety measures of substation operation tickets, the probability of unqualified substation operation tickets is reduced, thereby improving the review accuracy of substation operation tickets. BRIEF DESCRIPTION OF THE DRAWINGS
[0054] Figure 1 This is an application scenario diagram of a method for processing a substation operation ticket in an embodiment;
[0055] Figure 2 A schematic diagram of a process flow of a method for processing a substation operation ticket in one embodiment;
[0056] Figure 3 A schematic diagram of the review process of the operation terminology of the component "switch" in one embodiment;
[0057] Figure 4 A schematic diagram of the review process of the name of a component "screen cabinet" in one embodiment;
[0058] Figure 5 A schematic diagram of a process of reviewing a power supply operation ticket through a power outage operation ticket in one embodiment;
[0059] Figure 6A schematic diagram of a process of reviewing a substation operation ticket through a substation work ticket in one embodiment;
[0060] Figure 7 It is a structural block diagram of a substation operation ticket processing device in one embodiment;
[0061] Figure 8 It is a structural block diagram of a substation operation ticket processing device in another embodiment;
[0062] Fig. 9 FIG. 4 is a diagram showing the internal structure of a computer device in one embodiment. DETAILED DESCRIPTION
[0063] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0064] The method for processing substation operation tickets provided in this application can be applied to Figure 1 In the application environment shown. The application environment includes a terminal 102 and a server 104. The terminal 102 communicates with the server 104 through a network. The terminal 102 may specifically include a desktop terminal or a mobile terminal. The mobile terminal may specifically include at least one of a mobile phone, a tablet computer, and a laptop computer. The server 104 may be implemented as an independent server or a server cluster composed of multiple servers. Those skilled in the art will understand that Figure 1 The application environment shown in is only a part of the scenarios related to the present application solution and does not constitute a limitation on the application environment of the present application solution.
[0065] The terminal 102 obtains the substation operation ticket in the electronic document format from the server 104. The terminal 102 automatically reviews the safety specifications of the substation operation ticket according to the automatic review rules of the specifications generated based on the power safety specification file. The terminal 102 automatically reviews the attributes of the components associated with the substation operation ticket based on the equipment component database. The terminal 102 automatically reviews the power operation status of the substation operation ticket according to the historical substation operation tickets corresponding to the substation operation ticket. The terminal 102 automatically reviews the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket. When at least one item is not passed in the automatic review, the terminal 102 triggers the review error and triggers the adjustment of the substation operation ticket based on the content of the review error. When all automatic reviews pass, the terminal 102 triggers the substation operation ticket to take effect.
[0066] In one embodiment, Figure 2 As shown, a method for processing a substation operation ticket is provided, and the method is applied to Figure 1The terminal 102 in the example is used as an example to illustrate, and the following steps are included:
[0067] S202, obtaining a substation operation ticket in an electronic document format.
[0068] Specifically, the terminal can generate the substation operation ticket in the electronic document format locally. Furthermore, the terminal can obtain the substation operation ticket in the electronic document format generated locally.
[0069] In one embodiment, the server stores the substation operation ticket in the electronic document format. The terminal can communicate with the server. Furthermore, the terminal can obtain the substation operation ticket in the electronic document format from the server.
[0070] S204, automatically reviewing the safety specifications of the substation operation ticket according to the automatic specification review rules generated based on the power safety specification file.
[0071] The power safety specification document is a document that specifies the operation requirements of the equipment in the substation. The automatic specification review rule is a rule that automatically performs a specification review on the substation operation ticket.
[0072] Specifically, the terminal can obtain the power safety specification file and generate the automatic specification review rules based on the power safety specification file. Furthermore, the terminal can automatically review the safety specifications of the substation operation ticket according to the automatic specification review rules generated based on the power safety specification file.
[0073] In one embodiment, the power safety specification file may include the "Power Safety Work Regulations of China Southern Power Grid Co., Ltd." The terminal may obtain the "Power Safety Work Regulations of China Southern Power Grid Co., Ltd." and perform safety specification automatic review on the operation terms, location terms, and operation principles of the substation operation ticket according to the specification automatic review rules generated based on the "Power Safety Work Regulations of China Southern Power Grid Co., Ltd.".
[0074] S206, based on the equipment component database, automatically review the attributes of the components associated with the substation operation ticket.
[0075] The equipment component database is a database storing information on equipment components related to equipment in the power system.
[0076] Specifically, the terminal can determine the relevant equipment component database and obtain the attributes of the components associated with the substation operation ticket. Furthermore, the terminal can automatically review the attributes of the components associated with the substation operation ticket based on the equipment component database.
[0077] In one embodiment, the components associated with the substation operation ticket may specifically include at least one of a pressure plate, a pressure plate meter, a panel cabinet, an air switch, and a handle, etc. The attributes of the components may specifically include at least one of a component name, a component number, a component position, and a component status, etc.
[0078] S208, automatically reviewing the power operation status of the substation operation ticket according to the historical substation operation ticket corresponding to the substation operation ticket.
[0079] The historical substation operation ticket is a substation operation ticket generated before the generation time of the substation operation ticket being processed this time.
[0080] Specifically, the terminal can obtain the historical substation operation ticket corresponding to the substation operation ticket. The terminal can respectively determine the component operation status corresponding to the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket, and compare the component operation status corresponding to the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket, so as to automatically review the power operation status of the substation operation ticket.
[0081] S210, automatically reviewing the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket.
[0082] Among them, the substation work ticket is a work ticket generated when repairing the equipment corresponding to the substation operation ticket.
[0083] Specifically, the terminal may generate a substation work ticket associated with the substation operation ticket. Further, the terminal may obtain the substation work ticket associated with the substation operation ticket. The terminal may automatically review the security measures of the substation operation ticket based on the substation work ticket associated with the substation operation ticket.
[0084] S212, when at least one item fails the automatic review, a review error is triggered, and the substation operation ticket is adjusted based on the content of the review error.
[0085] Specifically, the terminal can obtain the corresponding review results of the automatic review of safety specifications, automatic review of component attributes, automatic review of power operation status, and automatic review of safety measures. When at least one of the review results fails, the terminal can trigger a review error. The terminal can then trigger the adjustment of the substation operation ticket based on the content of the review error.
[0086] In one embodiment, the terminal can automatically adjust the substation operation ticket based on the content of the review error report.
[0087] In one embodiment, the user can modify the substation operation ticket based on the content of the review error report. The terminal can obtain the substation operation ticket modified by the user and replace the substation operation ticket with the modified substation operation ticket.
[0088] S214: When all automatic reviews are passed, the substation operation ticket is triggered to take effect.
[0089] Specifically, when the automatic review of safety specifications, automatic review of component attributes, automatic review of power operation status and automatic review of safety measures are all passed, the terminal can trigger the substation operation ticket to take effect. It can be understood that the effective substation operation ticket can be used as a basis for users to operate substation equipment in the substation on site.
[0090] In the above-mentioned substation operation ticket processing method, by obtaining the substation operation ticket in the electronic document format, and according to the automatic review rules of the specifications generated based on the power safety specification file, the substation operation ticket is automatically reviewed for safety specifications to ensure that the substation operation ticket meets the requirements of the power safety specification file. Based on the equipment component database, the attributes of the components associated with the substation operation ticket are automatically reviewed to ensure that the attributes of the components associated with the substation operation ticket are correct. According to the historical substation operation ticket corresponding to the substation operation ticket, the power operation status of the substation operation ticket is automatically reviewed to ensure that the power operation status of the substation operation ticket is accurate. According to the substation work ticket associated with the substation operation ticket, the safety measures of the substation operation ticket are automatically reviewed to ensure that the substation operation ticket meets the requirements of the safety measures specification. When at least one item is not passed in the automatic review, the review error is triggered, and the substation operation ticket is adjusted based on the content of the review error. When all automatic reviews pass, the substation operation ticket is triggered to take effect. In this way, by automatically reviewing the safety specifications, component properties, power operation status and safety measures of substation operation tickets, the probability of unqualified substation operation tickets is reduced, thereby improving the review accuracy of substation operation tickets.
[0091] In one embodiment, step S204, that is, the step of automatically reviewing the safety specifications of the substation operation ticket according to the automatic review rules of the specifications generated based on the power safety specification file, specifically includes: searching for a first preset component name at a preset position of the substation operation ticket according to the automatic review rules of the specifications generated based on the power safety specification file; when the first preset component name is not found at the preset position of the substation operation ticket, determining that the automatic review of the safety specifications of the substation operation ticket has failed; when the first preset component name is found at the preset position of the substation operation ticket, determining whether the statement of the operation step corresponding to the first preset component name complies with the preset grammatical rules; if so, determining that the automatic review of the safety specifications of the substation operation ticket has passed; otherwise, determining that the automatic review of the safety specifications of the substation operation ticket has failed.
[0092] Among them, the first preset component name is the name of the preset component corresponding to the automatic review of the safety specifications of the substation operation ticket.
[0093] Specifically, the terminal may obtain the first preset component name, and search for the first preset component name at the preset position of the substation operation ticket according to the automatic review rule of the specification generated based on the power safety specification file. The terminal may monitor the search status of the first preset component name in real time. When the terminal detects that the first preset component name is not found at the preset position of the substation operation ticket, the terminal may directly determine that the automatic review of the safety specification of the substation operation ticket has not passed. When the terminal detects that the first preset component name is found at the preset position of the substation operation ticket, the terminal may obtain the corresponding preset grammatical rule. Furthermore, the terminal may determine whether the statement of the operation step corresponding to the first preset component name conforms to the preset grammatical rule. If the statement of the operation step corresponding to the first preset component name conforms to the preset grammatical rule, the terminal may determine that the automatic review of the safety specification of the substation operation ticket has passed. If the statement of the operation step corresponding to the first preset component name does not conform to the preset grammatical rule, the terminal may determine that the automatic review of the safety specification of the substation operation ticket has not passed.
[0094] In one embodiment, Figure 3 As shown, the terminal can determine whether the operation steps of the substation operation ticket include "switch" and whether it is the main item in the operation steps (relative to the corresponding sub-items, for example, the main item is step 1, and the corresponding sub-items are steps 1.1, 1.2 and 1.3, etc.). When the terminal determines that the operation steps of the substation operation ticket include "switch" and it is the main item in the operation steps, the terminal can continue to determine whether the operation steps in the substation operation ticket end with "switch" and do not start with "close" or "disconnect". When the terminal determines that the operation steps in the substation operation ticket end with "switch" and do not start with "close" or "disconnect", the terminal can trigger the generation of an error message "switch operation terminology error".
[0095] In the above embodiment, by determining whether the first preset component name can be found at the preset position of the substation operation ticket, and determining whether the statement of the operation step corresponding to the first preset component name conforms to the preset grammatical rules, a two-level review process is performed to further ensure the accuracy of the automatic review of the safety specifications of the substation operation ticket.
[0096] In one embodiment, step S206, that is, the step of automatically reviewing the attributes of the components associated with the substation operation ticket based on the equipment component database, specifically includes: extracting the attributes of the components associated with the substation operation ticket from the substation operation ticket; searching the extracted attributes of the components associated with the substation operation ticket in the equipment component database; when the attributes of the components associated with the extracted substation operation ticket are found in the equipment component database, determining that the automatic review of the attributes of the components associated with the substation operation ticket has passed; otherwise, determining that the automatic review of the attributes of the components associated with the substation operation ticket has failed.
[0097] Specifically, the substation operation ticket may include the attributes of the components associated with the substation operation ticket. The terminal may extract the attributes of the components associated with the substation operation ticket from the substation operation ticket. The terminal may determine the corresponding equipment component database, and search for the attributes of the components associated with the extracted substation operation ticket in the equipment component database. The terminal may monitor the search status of the attributes of the components associated with the substation operation ticket in real time. When the terminal detects that the attributes of the components associated with the extracted substation operation ticket are found in the equipment component database, the terminal may directly determine that the automatic component attribute review of the attributes of the components associated with the substation operation ticket has passed. When the terminal detects that the attributes of the components associated with the extracted substation operation ticket are not found in the equipment component database, the terminal may determine that the automatic component attribute review of the attributes of the components associated with the substation operation ticket has failed.
[0098] In one embodiment, Figure 4 As shown, the terminal can determine whether the statement of the operation step in the substation operation ticket is "in *** cabinet". When the terminal determines that the statement of the operation step in the substation operation ticket is "in *** cabinet", the terminal can extract the name of the cabinet and search for the name of the cabinet in the database corresponding to the ledger. When the name of the cabinet is not found in the database corresponding to the ledger, the terminal can generate an error message "wrong cabinet name".
[0099] In the above embodiment, by determining whether the attributes of the components associated with the extracted substation operation ticket can be found in the equipment component database, the attributes of the components associated with the substation operation ticket are automatically reviewed. In this way, the accuracy of the automatic review of the attributes of the components on the substation operation ticket is further guaranteed.
[0100] In one embodiment, step S208, that is, the step of automatically reviewing the power operation status of the substation operation ticket according to the historical substation operation ticket corresponding to the substation operation ticket, specifically includes: extracting the component names associated with each other in the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket; for the extracted identical component names, judging whether the corresponding power operation states are opposite; when the power operation states are opposite, determining that the automatic review of the power operation status of the substation operation ticket has passed; otherwise, determining that the automatic review of the power operation status of the substation operation ticket has failed.
[0101] Specifically, the substation operation ticket is associated with a component name, and the historical substation operation ticket corresponding to the substation operation ticket is also associated with a corresponding component name. The terminal can extract the component names associated with each other from the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket. Each component name can correspond to its own power operation status. For the extracted identical component names, the terminal can determine whether the corresponding power operation states are opposite. The terminal can monitor the judgment of the power operation state in real time. When the terminal detects that the power operation states corresponding to the same component names are opposite, the terminal can determine that the automatic review of the power operation state of the substation operation ticket has passed. When the terminal detects that the power operation states corresponding to the same component names are the same, the terminal can determine that the automatic review of the power operation state of the substation operation ticket has failed.
[0102] In one embodiment, Figure 5 As shown, the substation operation ticket may include a power supply operation ticket and a power outage operation ticket. The terminal may determine whether the operation steps of the power supply operation ticket end with "switch" and start with "close". When the terminal determines that the operation steps of the power supply operation ticket end with "switch" and start with "close", the terminal may extract the name of the switch and determine whether the operation steps of the power outage operation ticket end with "switch" and start with "disconnect", and the switch names are consistent. When the terminal determines that any of the conditions of ending with "switch", starting with "disconnect" and having the same switch name in the operation steps of the power outage operation ticket does not meet the requirements, the terminal may generate an error message "unclosed loop".
[0103] In the above embodiment, the power operation status of the substation operation ticket is automatically reviewed by judging whether the power operation status corresponding to the same component name in the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket is opposite. In this way, the accuracy of the automatic review of the power operation status of the substation operation ticket is further guaranteed.
[0104] In one embodiment, step S210, that is, the step of automatically reviewing the safety measures of the substation operation ticket based on the substation work ticket associated with the substation operation ticket, specifically includes: extracting the power operation states corresponding to the second preset component names from the substation operation ticket and the substation work ticket associated with the substation operation ticket; when the power operation states corresponding to the extracted second preset component names are consistent, it is determined that the automatic review of the safety measures of the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety measures of the substation operation ticket has failed.
[0105] Among them, the second preset component name is the preset component name corresponding to the automatic review of safety measures for the substation operation ticket.
[0106] Specifically, there is a second preset component name in the substation operation ticket and the substation work ticket associated with the substation operation ticket. The second preset component names in the substation operation ticket and the substation work ticket associated with the substation operation ticket correspond to their respective power operation states. The terminal can extract the power operation states corresponding to the second preset component names from the substation operation ticket and the substation work ticket associated with the substation operation ticket. The terminal can compare the power operation states corresponding to the second preset component names in the substation operation ticket and the substation work ticket associated with the substation operation ticket. When the power operation states corresponding to the second preset component names in the substation operation ticket and the substation work ticket associated with the substation operation ticket are consistent, the terminal can determine that the automatic review of the safety measures for the substation operation ticket has passed. When the power operation states corresponding to the second preset component names in the substation operation ticket and the substation work ticket associated with the substation operation ticket are inconsistent, the terminal can determine that the automatic review of the safety measures for the substation operation ticket has not passed.
[0107] In one embodiment, Figure 6 As shown, the terminal can determine whether the safety measures specified in the substation work ticket corresponding to the substation operation ticket require disconnecting the "switch". When the terminal determines that the safety measures specified in the substation work ticket require disconnecting the "switch", the terminal can extract the name of the switch and determine whether the operation steps of the substation operation ticket end with "switch" and start with "disconnect", and the switch names are consistent. When the terminal determines that any of the conditions that the operation steps of the power outage operation ticket end with "switch", start with "disconnect", and the switch names are consistent do not meet the requirements, the terminal can generate an error message "Safety measures not met".
[0108] In the above embodiment, the safety measures of the substation operation ticket are automatically reviewed by judging whether the power operation states corresponding to the second preset component names in the substation operation ticket and the substation work ticket associated with the substation operation ticket are consistent. In this way, the accuracy of the automatic review of the safety measures of the substation operation ticket is further guaranteed.
[0109] In one embodiment, before obtaining the substation operation ticket in an electronic document format, the substation operation ticket processing method also includes: obtaining substation operation task information; determining the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed according to the substation operation task information; generating the substation operation ticket in an electronic document format according to a preset substation operation ticket template based on the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed.
[0110] The substation operation task information is information corresponding to the substation operation task corresponding to the actual substation business demand.
[0111] Specifically, the terminal can obtain the substation operation task information and the preset substation operation ticket template. The substation operation task information may include the device to be substationed and the name of the component to be operated corresponding to the device to be substationed. The terminal can determine the device to be substationed and the name of the component to be operated corresponding to the device to be substationed according to the substation operation task information. Then, according to the determined device to be substationed and the name of the component to be operated corresponding to the device to be substationed, the substation operation ticket in the electronic document format is generated according to the obtained preset substation operation ticket template.
[0112] In the above embodiment, the substation operation ticket in electronic document format is generated by using the equipment to be substation determined by the substation operation task information and the names of the components to be operated corresponding to the equipment to be substation, as well as a preset substation operation ticket template. This can shorten the generation time of the substation operation ticket and thus improve the generation efficiency of the substation operation ticket.
[0113] It should be understood that although Figure 2 The steps are shown in order, but they are not necessarily executed in order. Unless otherwise specified in this document, there is no strict order restriction for the execution of these steps, and these steps can be executed in other orders. Figure 2 At least part of the steps may include multiple sub-steps or multiple stages. These sub-steps or stages are not necessarily executed at the same time, but can be executed at different times. The execution order of these sub-steps or stages is not necessarily sequential, but can be executed in turn or alternately with other steps or at least part of the sub-steps or stages of other steps.
[0114] In one embodiment, Figure 7 As shown, a substation operation ticket processing device 700 is provided, comprising: an acquisition module 701 and a review module 702, wherein:
[0115] The acquisition module 701 is used to acquire the substation operation ticket in the electronic document format.
[0116] Review module 702 is used to automatically review the safety specifications of the substation operation ticket according to the automatic review rules of the specifications generated based on the power safety specification file; automatically review the attributes of the components associated with the substation operation ticket based on the equipment component database; automatically review the power operation status of the substation operation ticket according to the historical substation operation tickets corresponding to the substation operation ticket; automatically review the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket; when at least one item fails the automatic review, a review error is triggered, and the substation operation ticket is adjusted based on the content of the review error; when all automatic reviews pass, the substation operation ticket is triggered to take effect.
[0117] In one embodiment, the review module 702 is also used to search for a first preset component name at a preset position of the substation operation ticket according to the automatic review rules of the specifications generated based on the power safety specification file; when the first preset component name is not found at the preset position of the substation operation ticket, it is determined that the automatic review of the safety specifications for the substation operation ticket has failed; when the first preset component name is found at the preset position of the substation operation ticket, it is determined whether the statement of the operation step corresponding to the first preset component name complies with the preset grammatical rules; if so, it is determined that the automatic review of the safety specifications for the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety specifications for the substation operation ticket has failed.
[0118] In one embodiment, the review module 702 is also used to extract the attributes of the components associated with the substation operation ticket in the substation operation ticket; search for the attributes of the components associated with the extracted substation operation ticket in the equipment component database; when the attributes of the components associated with the extracted substation operation ticket are found in the equipment component database, it is determined that the automatic review of the attributes of the components associated with the substation operation ticket has passed; otherwise, it is determined that the automatic review of the attributes of the components associated with the substation operation ticket has failed.
[0119] In one embodiment, the review module 702 is also used to extract the component names associated with each other in the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket; for the extracted identical component names, determine whether the corresponding power operation states are opposite; when the power operation states are opposite, determine that the automatic review of the power operation state of the substation operation ticket has passed; otherwise, determine that the automatic review of the power operation state of the substation operation ticket has failed.
[0120] In one embodiment, the review module 702 is also used to extract the power operation states corresponding to the second preset component names from the substation operation ticket and the substation work ticket associated with the substation operation ticket; when the power operation states corresponding to the extracted second preset component names are consistent, it is determined that the automatic review of the safety measures for the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety measures for the substation operation ticket has failed.
[0121] refer to Figure 8 In one embodiment, the substation operation ticket processing device 700 further includes: a generation module 703, wherein:
[0122] Generation module 703 is used to obtain substation operation task information; determine the equipment to be substationed and the names of the components to be operated corresponding to the equipment to be substation according to the substation operation task information; generate a substation operation ticket in an electronic document format according to a preset substation operation ticket template based on the equipment to be substationed and the names of the components to be operated corresponding to the equipment to be substation.
[0123] The above-mentioned substation operation ticket processing device obtains the substation operation ticket in the electronic document format, and automatically reviews the safety specifications of the substation operation ticket according to the automatic review rules generated based on the power safety specification file, so as to ensure that the substation operation ticket meets the requirements of the power safety specification file. Based on the equipment component database, the attributes of the components associated with the substation operation ticket are automatically reviewed to ensure that the attributes of the components associated with the substation operation ticket are correct. According to the historical substation operation ticket corresponding to the substation operation ticket, the power operation status of the substation operation ticket is automatically reviewed to ensure that the power operation status of the substation operation ticket is accurate. According to the substation work ticket associated with the substation operation ticket, the safety measures of the substation operation ticket are automatically reviewed to ensure that the substation operation ticket meets the requirements of the safety measures specification. When at least one item is not passed in the automatic review, the review error is triggered, and the substation operation ticket is adjusted based on the content of the review error. When all automatic reviews pass, the substation operation ticket is triggered to take effect. In this way, by automatically reviewing the safety specifications, component properties, power operation status and safety measures of substation operation tickets, the probability of unqualified substation operation tickets is reduced, thereby improving the review accuracy of substation operation tickets.
[0124] The specific definition of the substation operation ticket processing device can be found in the definition of the substation operation ticket processing method above, which will not be repeated here. Each module in the above-mentioned substation operation ticket processing device can be implemented in whole or in part by software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0125] In one embodiment, a computer device is provided, which may be the above-mentioned Figure 1 The internal structure diagram of the terminal 102 in FIG. Fig. 9As shown. The computer device includes a processor, a memory, a network interface, a display screen and an input device connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The network interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, a method for processing a substation operation ticket is implemented. The display screen of the computer device can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covering the display screen, or a key, trackball or touchpad set on the computer device housing, or an external keyboard, touchpad or mouse, etc.
[0126] Those skilled in the art will understand that Fig. 9 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.
[0127] In one embodiment, a computer device is provided, including a memory and a processor, wherein the memory stores a computer program, and when the computer program is executed by the processor, the processor executes the steps of the above-mentioned method for processing a substation operation ticket. The steps of the method for processing a substation operation ticket here may be the steps of the method for processing a substation operation ticket in each of the above-mentioned embodiments.
[0128] In one embodiment, a computer-readable storage medium is provided, which stores a computer program. When the computer program is executed by a processor, the processor executes the steps of the above-mentioned method for processing a substation operation ticket. The steps of the method for processing a substation operation ticket here can be the steps of the method for processing a substation operation ticket in each of the above-mentioned embodiments.
[0129] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application can include non-volatile and / or volatile memory. Non-volatile memory can include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory can include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
[0130] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0131] The above-mentioned embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent of the present application shall be subject to the attached claims.
Claims
1. A method for processing a substation operation ticket, characterized in that: The method comprises: Obtain the substation operation ticket in electronic document format; According to the automatic review rules of the specifications generated based on the power safety specification file, the substation operation ticket is automatically reviewed for safety specifications; Based on the equipment component database, automatically review the component attributes of the components associated with the substation operation ticket; According to the historical substation operation ticket corresponding to the substation operation ticket, the power operation status of the substation operation ticket is automatically reviewed, including: Extracting the names of the components associated with each other from the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket; For the extracted identical component names, determining whether the corresponding power operation states are opposite; When the power operation state is opposite, it is determined that the automatic review of the power operation state of the substation operation ticket has passed; otherwise, it is determined that the automatic review of the power operation state of the substation operation ticket has failed; Automatically review the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket; When at least one item fails the automatic review, a review error is triggered, and the substation operation ticket is adjusted based on the content of the review error; When all automatic reviews are passed, the substation operation ticket is triggered to take effect.
2. The method according to claim 1, characterized in that: The automatic safety specification review of the substation operation ticket according to the automatic specification review rules generated based on the power safety specification file includes: According to the automatic review rules of the specification generated based on the power safety specification file, searching for the first preset component name at the preset position of the substation operation ticket; When the first preset component name is not found at the preset position of the substation operation ticket, it is determined that the automatic safety specification review of the substation operation ticket has failed; When the first preset component name is found at the preset position of the substation operation ticket, it is determined whether the statement of the operation step corresponding to the first preset component name conforms to the preset grammatical rules; if so, it is determined that the automatic review of the safety specifications of the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety specifications of the substation operation ticket has failed.
3. The method according to claim 1, characterized in that: The automatic review of the attributes of the components associated with the substation operation ticket based on the equipment component database includes: Extracting the attributes of the components associated with the power transformation operation ticket from the power transformation operation ticket; Searching the equipment component database for properties of the component associated with the extracted substation operation ticket; When the attributes of the components associated with the extracted substation operation ticket are found in the equipment component database, it is determined that the automatic review of the attributes of the components associated with the substation operation ticket has passed; otherwise, it is determined that the automatic review of the attributes of the components associated with the substation operation ticket has failed.
4. The method according to claim 1, characterized in that The automatic review of the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket includes: Extract the power operation states corresponding to the second preset component names respectively from the substation operation ticket and the substation work ticket associated with the substation operation ticket; When the power operation states corresponding to the extracted second preset component names are consistent, it is determined that the automatic review of the safety measures for the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety measures for the substation operation ticket has failed.
5. The method according to any one of claims 1 to 4, characterized in that Before obtaining the substation operation ticket in electronic document format, the method further includes: Obtain substation operation task information; Determine the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed according to the transformation operation task information; According to the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed, a transformation operation ticket in an electronic document format is generated according to a preset transformation operation ticket template.
6. A substation operation ticket processing device, characterized in that: The device comprises: An acquisition module is used to acquire a substation operation ticket in an electronic document format; A review module is used to automatically review the safety specifications of the substation operation ticket according to the automatic review rules of the specifications generated based on the power safety specification file; automatically review the properties of the components associated with the substation operation ticket based on the equipment component database; automatically review the power operation status of the substation operation ticket according to the historical substation operation ticket corresponding to the substation operation ticket, including: extracting the names of the components associated with each other from the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket; judging whether the power operation statuses corresponding to the extracted identical component names are opposite; when the power operation statuses are opposite, judging that the automatic review of the power operation status of the substation operation ticket has passed; otherwise, judging that the automatic review of the power operation status of the substation operation ticket has failed; automatically reviewing the safety measures of the substation operation ticket according to the substation work ticket associated with the substation operation ticket; when at least one item fails in the automatic review, triggering a review error, and triggering the adjustment of the substation operation ticket based on the content of the review error; when all automatic reviews pass, triggering the substation operation ticket to take effect; Among them, the review module is also used to extract the component names associated with each other in the substation operation ticket and the historical substation operation ticket corresponding to the substation operation ticket; for the extracted identical component names, determine whether the corresponding power operation states are opposite; when the power operation states are opposite, determine that the automatic review of the power operation state of the substation operation ticket has passed; otherwise, determine that the automatic review of the power operation state of the substation operation ticket has failed.
7. The device according to claim 6, characterized in that The review module is also used to: According to the automatic review rules of the specifications generated based on the power safety specification file, the first preset component name is searched at the preset position of the substation operation ticket; when the first preset component name is not found at the preset position of the substation operation ticket, it is determined that the automatic review of the safety specifications for the substation operation ticket has failed; when the first preset component name is found at the preset position of the substation operation ticket, it is determined whether the statement of the operation step corresponding to the first preset component name complies with the preset grammatical rules; if so, it is determined that the automatic review of the safety specifications for the substation operation ticket has passed; otherwise, it is determined that the automatic review of the safety specifications for the substation operation ticket has failed.
8. The device according to claim 7, characterized in that The device also includes: A generation module is used to obtain substation operation task information; determine the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed according to the substation operation task information; and generate a substation operation ticket in an electronic document format according to a preset substation operation ticket template based on the equipment to be transformed and the names of the components to be operated corresponding to the equipment to be transformed.
9. A computer device comprising a memory, a processor and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 5 are implemented.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 5 are implemented.
Citation Information
Patent Citations
Electronic mobile operation order system
CN104036348A
Power grid maintenance application ticket comprehensive inspection method
CN106202541A
Electrical operation ticket verification method
CN107767122A
Method and device for checking switching operation by associating historical ticket
CN108879661A
Logic checking method for transformer station sequential control operation
CN109633319A