Emergency building precast strip foundation
Through the modularly designed emergency building prefabricated strip foundation, the problems of high construction costs and long cycles of emergency building are solved, and rapid and economical strip foundation assembly is achieved. The modular design improves construction efficiency and cost-effectiveness.
Patent Information
- Application Number
- CN202010894853.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-08-31
- Publication Date
- 2025-08-05
- Estimated Expiration
- 2040-08-31
AI Technical Summary
The construction cost of strip foundations of existing emergency buildings is high and the construction period is long. The traditional cast-in-place method leads to complicated on-site operation processes and many types of workers.
The prefabricated strip foundation of emergency buildings adopts a modular design, including the first base module, the second base module and the beam module, forms an integral structure through removable connection, and reserves holes for embedded connections and steel bars, and assembles prestressed steel bars on site to quickly form a strip foundation.
Reduce construction costs, shorten construction cycles, improve construction efficiency, and modules can be re-turned and used.
Smart Images

Figure CN111945765B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of construction engineering, and particularly relates to an emergency prefabricated strip foundation for a building. Background Art
[0002] The function of a building foundation is to bear the loads transmitted from the superstructure of the building and transmit them together with its own weight to the foundation; permanent buildings, temporary buildings with a long period of use, temporary buildings with important strategic significance, emergency buildings, etc. must all be built on a solid foundation and subgrade to ensure that the building has a high structural reliability, safety and comfort of use; among them, emergency buildings refer to flexible and adaptable shelters provided for people during social unrest or natural disasters. The number of floors should not be too many. In order to ensure the efficiency and safety of design, production and construction, they are generally 2-4 floors.
[0003] A strip foundation is a type of foundation in which the length is much longer than the width, with the length being greater than or equal to 10 times the width. Based on the superstructure, it is divided into wall-mounted strip foundations and column-mounted strip foundations. Due to its good applicability to low-rise and multi-story buildings, strip foundations have been widely used in emergency-type buildings. However, at this stage, strip foundations require designers to produce construction drawings based on design conditions and load requirements. Construction units then excavate foundation trenches on-site according to the drawings and cast them in situ. The main process includes construction drawing design, on-site measurement and layout, foundation trench excavation, formwork installation, steel bar tying, embedded parts embedding, concrete pouring, concrete curing and molding, and backfilling. The on-site work processes are complex, the workload is large, and many types of workers are involved. Therefore, using traditional cast-in-situ methods to set up strip foundations for emergency-type buildings will not only increase construction costs but also extend the construction period. Summary of the Invention
[0004] In order to overcome the above-mentioned shortcomings of the prior art, the purpose of the present invention is to provide a prefabricated strip foundation for emergency buildings, which can not only reduce the construction cost of emergency buildings, but also shorten the construction period of emergency buildings.
[0005] In order to achieve the purpose, the present invention adopts the following technical solutions:
[0006] A prefabricated strip foundation for an emergency building comprises a first base module, a second base module and several beam modules, wherein the first base module and the second base module are detachably connected to each other through the several beam modules, wherein the two ends of the several beam modules are detachably connected to the first base module and the second base module respectively, and the tops of the first base module and the second base module are pre-embedded with several connecting parts for connecting to the upper structure of the building; a plurality of first steel bar reserved channels are arranged in an arrangement in the bottom of the first base module, a plurality of second steel bar reserved channels are arranged in an arrangement in the bottom of the second base module, and a plurality of third steel bar reserved channels are arranged in an arrangement in the bottom of the several beam modules, wherein each of the third steel bar reserved channels is arranged in one-to-one correspondence with each of the first steel bar reserved channels and each of the second steel bar reserved channels.
[0007] Furthermore, the top of the first base module has a first support platform in a prism shape, and a plurality of the connecting members are pre-embedded on the top of the first support platform.
[0008] Furthermore, the top of the second base module has a second support platform in a prism shape, and a plurality of the connecting members are pre-embedded on the top of the second support platform.
[0009] Furthermore, a plurality of hooks are pre-embedded on the tops of the plurality of beam modules.
[0010] Furthermore, the first base module has a first connecting groove at one end close to the several beam modules, the second base module has a second connecting groove at the other end close to the several beam modules, and the two ends of the several beam modules have a third connecting groove and a fourth connecting groove respectively, wherein the first connecting groove and the third connecting groove are detachably matched, and the second connecting groove and the fourth connecting groove are detachably matched.
[0011] Furthermore, a first steel bar anchor plate is pre-embedded in one end of the first base module away from the several beam modules, and a plurality of first anchor holes are provided on the first steel bar anchor plate, wherein each of the first anchor holes is arranged in a one-to-one correspondence with each of the first steel bar reserved channels, and the corresponding first anchor holes are connected to the corresponding first steel bar reserved channels.
[0012] Furthermore, a second steel bar anchor plate is pre-embedded in one end of the second base module away from the several beam modules, and a plurality of second anchor holes are provided on the second steel bar anchor plate, wherein each second anchor hole is arranged in a one-to-one correspondence with each second steel bar reserved channel, and the corresponding second anchor hole is connected to the corresponding second steel bar reserved channel.
[0013] Furthermore, the aforementioned emergency building prefabricated strip foundation also includes a plurality of prestressed steel bars arranged in one-to-one correspondence with each of the first steel bar reserved channels, each of the second steel bar reserved channels, and each of the third steel bar reserved channels, wherein the corresponding prestressed steel bars are simultaneously passed through the corresponding first steel bar reserved channels, the second steel bar reserved channels, and the third steel bar reserved channels, and one end of the corresponding prestressed steel bar passes through the corresponding first anchor hole and is fixed to the first steel bar anchor plate, and the other end of the corresponding prestressed steel bar passes through the corresponding second anchor hole and is fixed to the second steel bar anchor plate.
[0014] Compared with the prior art, the present invention has the following beneficial effects:
[0015] The prefabricated strip foundation for emergency buildings proposed in the present invention adopts a modular design. By prefabricating the strip foundation suitable for emergency buildings into different component modules, during on-site construction, it is only necessary to assemble the various base modules and beam modules according to the construction requirements to quickly form a strip foundation of the required length. This is very convenient and quick. Moreover, the various component modules can be reused. Therefore, compared with the traditional method of setting up strip foundations for emergency buildings using a cast-in-place method, it can not only effectively reduce the construction cost of emergency buildings, but also effectively shorten the construction period of emergency buildings. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0017] Figure 1 This is a schematic diagram of the overall structure of an emergency building prefabricated strip foundation in one embodiment of the present invention;
[0018] Figure 2 Schematic diagram of the three-dimensional structure of the first base module in one embodiment of the present invention;
[0019] Figure 3 3 views of a first base module according to an embodiment of the present invention;
[0020] Figure 4 Schematic diagram of the three-dimensional structure of the beam module in one embodiment of the present invention;
[0021] Figure 5 3 views of a beam module according to an embodiment of the present invention;
[0022] Figure 6is a schematic diagram of the three-dimensional structure of the second base module in one embodiment of the present invention;
[0023] Figure 7 3-D view of the second base module in one embodiment of the present invention.
[0024] Description of reference numerals:
[0025] 1-first base module, 11-first steel bar reserved channel, 12-first support platform, 13-first connecting groove, 14-first steel bar anchor plate, 141-first anchor hole, 2-second base module, 21-second steel bar reserved channel, 22-second support platform, 23-second connecting groove, 24-second steel bar anchor plate, 3-beam module, 31-third steel bar reserved channel, 32-hook, 33-third connecting groove, 34-fourth connecting groove, 4-connecting piece. DETAILED DESCRIPTION
[0026] In order to be able to more clearly understand the above-mentioned objects, features and advantages of the present invention, the present invention is described in detail below with reference to the accompanying drawings and specific embodiments. It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other. In the following description, many specific details are set forth in order to fully understand the present invention. The embodiments described are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0027] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used in the specification of the present invention herein are only for the purpose of describing specific embodiments and are not intended to limit the present invention.
[0028] Reference Figure 1 、 Figure 2 、 Figure 4 and Figure 6An embodiment of the present invention provides an emergency prefabricated strip foundation for a building, comprising a first base module 1, a second base module 2, and a plurality of crossbeam modules 3. The first base module 1 and the second base module 2 are detachably connected to each other via the plurality of crossbeam modules 3. The ends of the plurality of crossbeam modules 3 are detachably connected to the first base module 1 and the second base module 2, respectively. The tops of the first base module 1 and the second base module 2 are pre-embedded with a plurality of connectors 4 for connecting to the building superstructure. The bottom of the first base module 1 is provided with a plurality of arranged first steel bar reserved channels, the bottom of the second base module 2 is provided with a plurality of arranged second steel bar reserved channels, and the bottoms of the plurality of crossbeam modules 3 are provided with a plurality of arranged third steel bar reserved channels, wherein each third steel bar reserved channel corresponds to each first steel bar reserved channel and each second steel bar reserved channel. The number of crossbeam modules 3 can be determined according to actual construction requirements. In some practical application scenarios, a strip foundation of a desired length can be obtained by changing the number of crossbeam modules 3. The structural form and pre-embedded number of the connectors 4 may be determined according to actual construction requirements. Optionally, the connectors 4 are anchor bolts. Schematically, four connectors 4 are pre-embedded on the top of the first base module 1 and the second base module 2 .
[0029] The construction process of the emergency prefabricated strip foundation of this embodiment is as follows:
[0030] During construction, according to the construction requirements, the required number of first base modules 1, second base modules 2 and beam modules 3 are transported to the construction site, and then the modules are connected end to end in sequence according to the assembly principle of "base modules at both ends and beam modules 3 in the middle". When connecting, the reserved steel bar channels of each module are aligned and obstacles in the channels are removed. After the assembly is completed, the size and the position and quantity of each embedded part (such as the position and quantity of the connector 4) are reviewed; after the review is correct, the pre-prepared prestressed steel bars are passed through each reserved steel bar channel and the existing anchors are used to fix the two ends of each prestressed steel bar, thereby completing the assembly of the strip foundation; the upper structure of the building can be quickly and reliably connected to the entire strip foundation through the connector 4 pre-embedded on the first base module 1 and the second base module 2.
[0031] The prefabricated strip foundation for emergency buildings in this embodiment is based on the design concept of standardization and modularization. By prefabricating strip foundations suitable for emergency buildings into different standardized modules, during on-site construction, it is only necessary to assemble the various base modules and beam modules 3 according to the construction requirements to quickly form a strip foundation of the required length. This is very convenient and fast. Moreover, the various component modules can be reused. Therefore, compared with the traditional method of setting up strip foundations for emergency buildings using a cast-in-place method, it can not only effectively reduce the construction cost of emergency buildings, but also effectively shorten the construction period of emergency buildings.
[0032] Further, refer to Figures 1 to 3 In a preferred embodiment, the top of the first base module 1 has a first prism-shaped support platform 12, and a plurality of connecting members 4 are pre-embedded on the top of the first support platform 12; the top of the second base module 2 has a second prism-shaped support platform 22, and a plurality of connecting members 4 are pre-embedded on the top of the second support platform 22.
[0033] In this embodiment, based on the above structural design, by setting a support platform with a narrow upper and wide lower prism shape on the top of the two base modules as the anchoring part of the connecting member 4, a good force transmission mechanism can be provided, so that the entire strip foundation can better withstand the load transmitted from the upper structure of the building.
[0034] Further, refer to Figure 1 、 Figure 4 and Figure 5 In order to facilitate the lifting of the beam modules 3 during production, transportation, and turnover, in a preferred embodiment, several hooks are embedded on the top of several beam modules 3. Schematically, two symmetrically arranged hooks are embedded on the top of each beam module 3.
[0035] Further, refer to Figure 1 、 Figure 2 、 Figure 4 and Figure 6In an exemplary embodiment, the first base module 1 has a first connecting groove 13 at one end close to the several beam modules 3, the second base module 2 has a second connecting groove 23 at the other end close to the several beam modules 3, and the two ends of the several beam modules 3 have a third connecting groove 33 and a fourth connecting groove 34 respectively, wherein the first connecting groove 13 and the third connecting groove 33 are detachably matched, and the second connecting groove 23 and the fourth connecting groove 34 are detachably matched. It should be noted here that the structural forms of the first connecting tongue and groove 13, the second connecting tongue and groove 23, the third connecting tongue and groove 33 and the fourth connecting tongue and groove 34 can be flexibly set according to actual construction requirements. Diagrammatically, the first connecting tongue and groove 13 and the fourth connecting tongue and groove 34 are both in the shape of a step with "convex on top and concave on bottom", and the second connecting tongue and groove 23 and the third connecting tongue and groove 33 are both in the shape of a step with "concave on top and convex on bottom"; of course, in some other embodiments, the first connecting tongue and groove 13 and the fourth connecting tongue and groove 34 can also be designed as a protrusion in the shape of an "I" or a "X", and correspondingly, the second connecting tongue and groove 23 and the third connecting tongue and groove 33 can be designed as a groove in the shape of an "I" or a "X", and so on. As long as the detachable cooperation between the first base module 1 and the beam module 3, between the second base module 2 and the beam module 3, and between the beam modules 3 and the beam modules 3 can be achieved, this embodiment does not make any specific restrictions on this.
[0036] In this embodiment, based on the above structural design, two adjacent modules can engage with each other through corresponding connecting tongues and grooves to achieve rapid assembly, which is beneficial to improving construction efficiency.
[0037] Further, refer to Figures 1 to 3 In a preferred embodiment, a first steel bar anchor plate 14 is pre-embedded in one end of the first base module 1 away from the plurality of beam modules 3, and a plurality of first anchor holes 141 are provided on the first steel bar anchor plate 14, wherein each first anchor hole 141 is arranged in a one-to-one correspondence with each first steel bar reserved channel 11, and the corresponding first anchor hole 141 is connected to the corresponding first steel bar reserved channel 11.
[0038] In this embodiment, based on the above structural design, by arranging the first steel bar anchor plate 14 in the first base module 1 as one of the anchoring ends of the prestressed steel bars after the strip foundation is assembled, the influence of local pressure on the first base module 1 can be reduced, so that the entire strip foundation can better withstand the load from the upper structure of the building.
[0039] Further, refer to Figure 1 、 Figure 6 and Figure 7In a preferred embodiment, a second steel bar anchor plate 24 is embedded in one end of the second base module 2 away from the plurality of beam modules 3, and a plurality of second anchor holes (not shown in the figure) are provided on the second steel bar anchor plate 24, wherein each second anchor hole is arranged in a one-to-one correspondence with each second steel bar reserved channel 21, and the corresponding second anchor hole is connected to the corresponding second steel bar reserved channel 21.
[0040] In this embodiment, based on the above structural design, by arranging a second steel bar anchor plate 24 in the second base module 2 as another anchoring end of the prestressed steel bar after the strip foundation is assembled, the influence of local pressure on the second base module 2 can be reduced, so that the entire strip foundation can better withstand the load from the upper structure of the building.
[0041] Further, refer to Figures 1 to 7 The above-mentioned emergency building prefabricated strip foundation also includes a plurality of prestressed steel bars (not shown in the figure) arranged in one-to-one correspondence with each first steel bar reserved channel 11, each second steel bar reserved channel 21, and each third steel bar reserved channel 31, wherein the corresponding prestressed steel bars are simultaneously passed through the corresponding first steel bar reserved channel 11, the second steel bar reserved channel 21, and the third steel bar reserved channel 31, and one end of the corresponding prestressed steel bar passes through the corresponding first anchor hole 141 and is fixed to the first steel bar anchor plate 14 (such as fixed by an anchor), and the other end of the corresponding prestressed steel bar passes through the corresponding second anchor hole and is fixed to the second steel bar anchor plate 24 (such as fixed by an anchor).
[0042] In this embodiment, based on the above structural design, prestressed steel bars and combined steel bar anchor plates (i.e., the combination of the first steel bar anchor plate 14 and the second steel bar anchor plate 24) are used to combine the various modules into an organic whole to obtain a strip foundation that meets the use requirements.
[0043] It should be noted that other contents of the emergency prefabricated strip foundation disclosed in the present invention can be found in the prior art and will not be described in detail here.
[0044] The above are merely preferred embodiments of the present invention and do not constitute any form of limitation to the present invention. Therefore, any modifications, equivalent changes, and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. An emergency prefabricated strip foundation, characterized in that: The utility model comprises a first base module, a second base module and a plurality of beam modules, wherein the first base module and the second base module are detachably connected to each other through the plurality of beam modules, wherein the two ends of the plurality of beam modules are detachably connected to the first base module and the second base module respectively, and the tops of the first base module and the second base module are pre-embedded with a plurality of connectors for connecting to the upper structure of the building; a plurality of first steel bar reserved channels arranged in an array are provided in the bottom of the first base module, a plurality of second steel bar reserved channels arranged in an array are provided in the bottom of the second base module, and a plurality of third steel bar reserved channels arranged in an array are provided in the bottom of the plurality of beam modules, wherein each of the third steel bar reserved channels is respectively arranged in a one-to-one correspondence with each of the first steel bar reserved channels and each of the second steel bar reserved channels; The top of the first base module has a first support platform in the shape of a prism, and a plurality of the connecting members are pre-embedded on the top of the first support platform; The top of the second base module has a second support platform in the shape of a prism, and a plurality of the connecting members are pre-embedded on the top of the second support platform; The first base module has a first connecting groove at one end close to the plurality of beam modules, the second base module has a second connecting groove at the other end close to the plurality of beam modules, and the plurality of beam modules have a third connecting groove and a fourth connecting groove at both ends, wherein the first connecting groove is detachably engaged with the third connecting groove, and the second connecting groove is detachably engaged with the fourth connecting groove; A first steel bar anchor plate is pre-embedded in one end of the first base module away from the plurality of crossbeam modules, and a plurality of first anchor holes are provided on the first steel bar anchor plate, wherein each of the first anchor holes is arranged in a one-to-one correspondence with each of the first steel bar reserved channels, and corresponding first anchor holes are connected to corresponding first steel bar reserved channels; A second steel bar anchor plate is pre-embedded in one end of the second base module away from the plurality of crossbeam modules, and a plurality of second anchor holes are provided on the second steel bar anchor plate, wherein each second anchor hole is arranged in a one-to-one correspondence with each second steel bar reserved channel, and corresponding second anchor holes are connected to corresponding second steel bar reserved channels; It also includes a plurality of prestressed steel bars arranged in one-to-one correspondence with each of the first steel bar reserved holes, each of the second steel bar reserved holes, and each of the third steel bar reserved holes, wherein the corresponding prestressed steel bars are simultaneously passed through the corresponding first steel bar reserved holes, the second steel bar reserved holes, and the third steel bar reserved holes, and one end of the corresponding prestressed steel bar passes through the corresponding first anchor hole and is fixed to the first steel bar anchor plate, and the other end of the corresponding prestressed steel bar passes through the corresponding second anchor hole and is fixed to the second steel bar anchor plate.
2. The emergency prefabricated strip foundation according to claim 1, characterized in that: A plurality of hooks are pre-embedded on the tops of the plurality of beam modules.
Citation Information
Patent Citations
Emergency building prefabricated strip foundation
CN212506355U