Assembled prefabricated wall panel and prefabricated beam
By using prefabricated reinforced concrete components and efficient connection methods in the prefabricated frame shear wall structure, the problems of unsolid connections and complex construction in the existing technology are solved, efficient and stable prefabricated structure construction is achieved, and construction efficiency and structural reliability are improved.
Patent Information
- Application Number
- CN202011406032.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-04
- Publication Date
- 2025-04-25
- Estimated Expiration
- 2040-12-04
AI Technical Summary
The existing prefabricated frame shear wall structures have problems such as unsolid connections, complex construction, and long construction periods during construction. Especially in high-rise buildings, the application of reinforced concrete has the problem of unreliable connections.
The structure of prefabricated prefabricated wall panels and prefabricated beams is adopted. Through prefabricated reinforced concrete columns, shear walls, main beams and other components, the installation support, limit grooves, bolt holes and other structural elements are used to achieve efficient connection between the main beams and the shear walls, and through the embedded spiral steel bars and the connection dark bars, the stability of the structure and the reliability of the connection are enhanced.
It has achieved high prefabricated level, high overall strength and stable structure, eliminated the thermal bridge inside the wall panel, improved the stiffness of the concrete shear wall, facilitated mass production and on-site assembly, shortened the construction cycle, improved the construction efficiency, and ensured the reliability of node connections.
Smart Images

Figure CN112376689B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an assembled concrete frame building, in particular to an assembled prefabricated wall panel and a prefabricated beam. Background Art
[0002] As we all know, the prefabrication of buildings has the advantages of improving project quality, shortening construction period, simplifying on-site construction process, reducing construction intensity, improving site environment, reducing pollution, and reducing wet operations. At the same time, prefabricated and assembled buildings can effectively save resources and energy, help to give full play to the performance of materials in achieving building energy conservation and structural stress, and reduce the demand for site and environmental conditions for on-site construction. Prefabricated assembled frame shear wall structure is one of the very important structural forms. In current projects, it is mainly reinforced concrete beam-column frame structure, and then the shear wall is cast in place. This type of shear wall fails to adopt prefabricated structure, and it is also necessary to tie steel bars, erect formwork, and pour concrete. The construction is complicated and the construction period is long. For multi-story structures, steel tube concrete has been increasingly used due to its good stress performance. However, if it is used in an assembled frame shear wall structure, its connection with the shear wall is an important link. How to connect the shear wall with the beam and column is also a concern of everyone. At present, sleeve grouting connection is used. This connection method is single and the construction quality is difficult to guarantee. The steel bars at the connection are spaced and connected, the connection is unreliable, and there is no thermal bridge between the insulation layer and the shear wall. Summary of the invention
[0003] The purpose of the present invention is to provide an assembled prefabricated wall panel and prefabricated beam, which has a high degree of assembly and can eliminate thermal bridges in the wall panel, while ensuring the rigidity of the concrete shear wall and realizing convenience for mass production and on-site assembly.
[0004] In order to solve the problems existing in the prior art, the technical solution adopted by the present invention is as follows:
[0005] A prefabricated prefabricated wall panel and prefabricated beam, mainly comprising columns, shear walls, prefabricated floor panels, thermal insulation wall panels, main beams, mounting caps, limiting grooves, bolt holes, bolts, connecting hidden bars and spiral steel bars; the columns and main beams are all prefabricated reinforced concrete components; the mounting caps are arranged at the connection between the upper side of the columns and the main beams; the limiting grooves are arranged in the middle of the mounting caps, and bolt holes are reserved on the left and right sides of the limiting grooves; the ends of the main beams are fixed to the mounting caps by bolts; a wall mounting groove is prefabricated at the upper end of the main beam, connecting steel bars are pre-embedded at the upper and lower ends of the main beam, and the connecting steel bars pre-embedded on the upper side are arranged in the wall mounting groove; connecting steel bars matching the positions of the connecting steel bars are pre-embedded at the connection position of the shear wall with the main beam; the main beam and the shear wall are connected at the contact point of the connecting steel bars of the two; spiral steel bars are pre-embedded at the edge of the plate at the connection end of the prefabricated floor panel and the main beam, and the spiral steel bars at the connection end of the prefabricated floor panel and the main beam are arranged in the mounting groove reserved on the beam on the main beam, and connecting hidden bars are pre-embedded inside the thermal insulation wall panel, and the thermal insulation wall panel is connected to the main beam through the connecting hidden bars.
[0006] Furthermore, supporting columns are arranged on both sides of the upper end of the main beam body, and the supporting columns on both sides form a wall mounting groove. A beam mounting groove is reserved at the connection position of the main beam and the mounting base, and bolt holes are reserved on the main beam body corresponding to the beam mounting groove. A positioning block is arranged under the main beam body, and the size of the positioning block matches the limit groove.
[0007] Furthermore, the positioning block is placed in the limiting groove, the beam installation groove is arranged on the upper side of the installation base, and the bolts pass through the bolt holes reserved on the main beam and the installation base to fix the two together.
[0008] Furthermore, the connecting hidden reinforcement is composed of steel bar feet and fixed ring reinforcement; the steel bar feet are pre-buried in the insulation wall panel, the fixed ring reinforcement is exposed outside the insulation wall panel, and two rows of connecting hidden reinforcement are arranged at the main beam position.
[0009] Furthermore, the fixed ring reinforcement is sleeved on the connecting steel bars arranged on the upper and lower sides of the main beam, the spiral steel bars are placed inside the fixed ring reinforcement on the upper side of the main beam, and the connecting steel bars arranged on the upper and lower sides of the shear wall are placed on the fixed ring reinforcement.
[0010] Furthermore, the prefabricated floor slab is placed on the supporting columns on the upper side of the main beam body.
[0011] Furthermore, the thermal insulation wall panels are arranged outside the shear walls.
[0012] The advantages and beneficial effects of the present invention are:
[0013] The present invention discloses an assembled prefabricated wall panel and prefabricated beam, which has the following structure: a cap is installed on the upper side of the column for connecting with the main beam; a prefabricated beam installation groove is provided at the upper end of the main beam, and connecting steel bars are pre-embedded at the upper and lower ends of the main beam, and the upper connecting steel bars are pre-embedded in the beam installation groove, and the main beam and the shear wall are connected at the contact point of the connecting steel bars of the two; spiral steel bars are pre-embedded at the edge of the board at the connection end of the prefabricated floor slab and the main beam, and the spiral steel bars are arranged in the reserved beam installation groove on the main beam when the prefabricated floor slab is connected to the main beam, and the insulation wall panel is pre-embedded with internal connecting hidden bars, and the insulation wall panel is connected to the main beam through the connecting hidden bars. Therefore, the present invention has a high degree of assembly, high overall strength, and stable structure, and can also eliminate thermal bridges in the wall panel, and combines the concrete shear wall with the assembly process, which is convenient for mass production and on-site assembly while ensuring the rigidity of the concrete shear wall, thereby improving the on-site construction efficiency. It also effectively solves the problems of difficult assembly positioning and unreliable node connection in the assembled connection, thereby ensuring the reliability of the connection at the node. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a schematic diagram of the overall structure of an assembled prefabricated wall panel and prefabricated beam of the present invention;
[0015] Figure 2This is a schematic diagram of the connection between the column and the mounting base;
[0016] Figure 3 This is a schematic diagram of the connection between the column and the main beam;
[0017] Figure 4 This is a schematic diagram of the prefabricated floor structure;
[0018] Figure 5 This is the front view of the precast floor;
[0019] Figure 6 This is a schematic diagram of the main beam top structure;
[0020] Figure 7 This is a schematic diagram of the bottom structure of the main beam;
[0021] Figure 8 This is a schematic diagram of the structure for connecting hidden reinforcement;
[0022] Fig. 9 This is a schematic diagram for connecting concealed reinforcement and thermal insulation wall panels;
[0023] Fig.10 This is a schematic diagram of the connection between the prefabricated floor slab and the main beam;
[0024] Fig.11 This is a schematic diagram of the connection between the insulation wall panel and the main beam;
[0025] Fig.12 This is a schematic diagram of the connection between the shear wall and the main beam;
[0026] Fig.13 This is a schematic diagram of the connection between the prefabricated floor slab, thermal insulation wall panel and main beam;
[0027] Fig.14 for Fig.13 Detail of location A.
[0028] In the figure: column 1, shear wall 2, prefabricated floor slab 3, thermal insulation wall panel 4, main beam 5, mounting base 6, limit groove 7, bolt hole 8, bolt 9, connecting hidden reinforcement 10, spiral reinforcement 11;
[0029] Supporting column 5-1, wall installation groove 5-2, beam installation groove 5-3, connecting steel bar 5-4, positioning block 5-5; steel bar foot 10-1, fixed ring reinforcement 10-2. DETAILED DESCRIPTION
[0030] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] like Figure 1 As shown, the present invention is an assembled prefabricated wall panel and prefabricated beam, which mainly includes a column 1, a shear wall 2, a prefabricated floor slab 3, an insulation wall panel 4, a main beam 5, a mounting base 6, a limit groove 7, a bolt hole 8, a bolt 9, a connecting hidden reinforcement 10 and a spiral reinforcement 11; the column 1 and the main beam 5 are both prefabricated reinforced concrete components. Figure 2 As shown, a mounting platform 6 is arranged at the connection between the upper side of the column 1 and the main beam 5; a limiting groove 7 is arranged in the middle of the mounting platform 6, and bolt holes 8 are reserved on the left and right sides of the limiting groove 7. Figure 3 As shown, the ends of the main beam 5 are fixed to the mounting platform 6 by bolts 9; the upper end of the main beam 5 is prefabricated with a wall mounting groove 5-2, the upper and lower ends of the main beam are pre-embedded with connecting steel bars 5-4, and the upper pre-embedded connecting steel bars 5-4 are arranged in the wall mounting groove 5-2; the shear wall 2 is pre-embedded with connecting steel bars matching the positions of the connecting steel bars 5-4 at the connection position with the main beam 5; the main beam 5 and the shear wall 2 are connected at the contact point of the connecting steel bars of the two. Figure 4 , 5 As shown in 12, 13 and 14, the spiral reinforcement 11 is embedded in the edge of the plate at the connection end between the precast floor slab 3 and the main beam 5, and the spiral reinforcement 11 at the connection between the precast floor slab 3 and the main beam 5 is arranged in the installation groove reserved on the main beam, and the insulation wall panel 4 is embedded with the connecting hidden reinforcement 10, and the insulation wall panel 4 is connected to the main beam 5 through the connecting hidden reinforcement 10. The insulation wall panel 4 is arranged outside the shear wall 2.
[0032] like Figure 6 , 7 As shown, supporting columns 5-1 are arranged on both sides of the upper end of the main beam 5, and the supporting columns 5-1 on both sides form a wall mounting groove 5-2. A beam mounting groove 5-3 is reserved at the connection position between the main beam 5 and the mounting base 6. Bolt holes 8 are reserved on the main beam body corresponding to the beam mounting groove 5-3. A positioning block 5-5 is arranged under the main beam body, and the size of the positioning block 5-5 matches the limit groove 7.
[0033] The positioning block 5 - 5 is placed in the limiting groove 7 , the beam installation groove 5 - 3 is arranged on the upper side of the installation base 6 , and the bolts 9 pass through the bolt holes 8 reserved on the main beam 5 and the installation base 6 to fix the two together.
[0034] like Figure 8 , 9 As shown, the connecting hidden reinforcement 10 is composed of a steel bar foot 10 - 1 and a fixed ring reinforcement 10 - 2; the steel bar foot 10 - 1 is pre-buried in the insulation wall panel 4, and the fixed ring reinforcement 10 - 2 is exposed outside the insulation wall panel 4, and two rows of connecting hidden reinforcement 10 are arranged at the position of the main beam 5.
[0035] like Fig.11As shown, the fixed ring reinforcement 10-2 is mounted on the connecting reinforcement 5-4 arranged on the upper and lower sides of the main beam, the spiral reinforcement 11 is placed inside the fixed ring reinforcement 10-2 on the upper side of the main beam, and the connecting reinforcements arranged on the upper and lower sides of the shear wall 2 are placed on the fixed ring reinforcement 10-2.
[0036] like Fig.10 As shown, the prefabricated floor slab 3 is placed on the supporting column 5 - 1 on the upper side of the main beam 5 .
Claims
1. An assembled prefabricated wall panel and prefabricated beam, characterized in that: The invention mainly comprises a column (1), a shear wall (2), a prefabricated floor slab (3), an insulation wall panel (4), a main beam (5), an installation pedestal (6), a limit groove (7), a bolt hole (8), a bolt (9), a connecting hidden reinforcement (10) and a spiral reinforcement (11); the column (1) and the main beam (5) are both prefabricated reinforced concrete components; the installation pedestal (6) is arranged at the connection between the upper side of the column (1) and the main beam (5); the limit groove (7) is arranged in the middle of the installation pedestal (6), and the limit groove (7) is prefabricated on both sides. Bolt holes (8) are left; the end of the main beam (5) is fixed to the mounting base (6) by bolts (9); a wall mounting groove (5-2) is prefabricated at the upper end of the main beam (5); connecting steel bars (5-4) are pre-embedded at the upper and lower ends of the main beam, and the upper pre-embedded connecting steel bars (5-4) are arranged in the wall mounting groove (5-2); connecting steel bars matching the position of the connecting steel bars (5-4) are pre-embedded at the shear wall (2) at the connection position with the main beam (5); the main beam (5) and the shear wall (2) are connected at the contact point of the connecting steel bars of the two. A spiral steel bar (11) is pre-buried at the edge of the plate at the connection end between the prefabricated floor slab (3) and the main beam (5); the spiral steel bar (11) at the connection between the prefabricated floor slab (3) and the main beam (5) is arranged in a reserved beam installation groove on the main beam; a connecting hidden steel bar (10) is pre-buried inside the thermal insulation wall panel (4); and the thermal insulation wall panel (4) is connected to the main beam (5) via the connecting hidden steel bar (10).
2. The assembled prefabricated wall panel and prefabricated beam according to claim 1, characterized in that: Supporting columns (5-1) are arranged on both sides of the upper end of the main beam (5), and the supporting columns (5-1) on both sides enclose a wall installation groove (5-2). A beam installation groove (5-3) is reserved at the connection position between the main beam (5) and the installation base (6), and bolt holes (8) are reserved on the main beam body corresponding to the beam installation groove (5-3). A positioning block (5-5) is arranged under the main beam body, and the size of the positioning block (5-5) matches the limit groove (7).
3. The assembled prefabricated wall panel and prefabricated beam according to claim 2, characterized in that: The positioning block (5-5) is placed in the limiting groove (7), the beam installation groove (5-3) is arranged on the upper side of the installation base (6), and the bolts (9) pass through the bolt holes (8) reserved on the main beam (5) and the installation base (6) to fix the two together.
4. The assembled prefabricated wall panel and prefabricated beam according to claim 1, characterized in that: The connecting hidden reinforcement (10) is composed of a steel bar foot (10-1) and a fixed ring reinforcement (10-2); the steel bar foot (10-1) is pre-buried in the thermal insulation wall panel (4), the fixed ring reinforcement (10-2) is exposed outside the thermal insulation wall panel (4), and two rows of connecting hidden reinforcement (10) are arranged at the position of the main beam (5).
5. The assembled prefabricated wall panel and prefabricated beam according to claim 4, characterized in that: The fixed ring reinforcement (10-2) is sheathed on the connecting reinforcement (5-4) arranged on the upper and lower sides of the main beam, the spiral reinforcement (11) is placed inside the fixed ring reinforcement (10-2) on the upper side of the main beam, and the connecting reinforcement arranged on the upper and lower sides of the shear wall (2) is placed on the fixed ring reinforcement (10-2).
6. The assembled prefabricated wall panel and prefabricated beam according to claim 1, characterized in that: The prefabricated floor slab (3) is placed on the supporting columns (5-1) on the upper side of the main body of the main beam (5).
7. The assembled prefabricated wall panel and prefabricated beam according to claim 1, characterized in that: The thermal insulation wall panel (4) is arranged outside the shear wall (2).
Citation Information
Patent Citations
Fabricated prefabricated wallboard and prefabricated beam
CN213979281U