A power distribution wiring method, system, device and storage medium

Through the two-level planning method, user load information is automatically obtained and grouped, and transformers are set up to generate distribution wiring diagrams, which solves the problem of time-consuming and labor-consuming distribution line planning and achieves efficient and concise distribution network planning.

CN112580177BActive Publication Date: 2025-04-29STATE GRID HEILONGJIANG ELECTRIC POWER COMPANY +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202011560547.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-25
Publication Date
2025-04-29
Estimated Expiration
2040-12-25

AI Technical Summary

Technical Problem

Distribution line planning consumes time and manpower, and it is difficult for the existing technology to efficiently complete the planning of the distribution network.

Method used

Using a two-level planning method, firstly, by obtaining GIS geographic information, substation information and user load information, automatically group user loads and set up transformers to generate main and secondary veins connection diagrams, and then combine them into a distribution wiring diagram.

Benefits of technology

It realizes efficient planning of distribution lines, simplifies the design of wiring diagrams, reduces implementation difficulty and cost, and ensures the stability of power facilities and the reservation of future load capacity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112580177B_ABST
    Figure CN112580177B_ABST
Patent Text Reader

Abstract

The present application relates to a power distribution wiring method, system, device and storage medium, and the method includes the following steps: obtaining an atlas of GIS geographic information of the area to be planned; obtaining an atlas of substations in the area to be planned; obtaining an atlas of user loads in the area to be planned, and grouping the user loads according to the atlas of the user loads to obtain a number of user load groups; setting up a transformer for each user load group, and generating an atlas of the transformers in the area to be planned; planning to obtain a main vein connection diagram of the connection between the substation and the transformer according to the atlas of the substation, the atlas of GIS geographic information and the atlas of the transformer; planning to obtain a secondary vein connection diagram of the connection between the transformer and each user load in each user load group according to the atlas of GIS geographic information, the atlas of user loads and the atlas of transformers; combining the main vein connection diagram and the secondary vein connection diagram to obtain a power distribution wiring diagram. The present application has the effect of efficiently planning power distribution lines.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of power grid planning technology, and in particular to a power distribution wiring method, system, device and storage medium. Background Art

[0002] With the continuous growth of load, the improvement of power reliability requirements, the requirements of distribution automation, urban planning and environmental constraints, as well as the development and changes of society, politics, economy, industry and people's living standards, will have a profound impact on the development of distribution network. In addition, when planning the distribution network, the status of the planning area in economic development should also be considered, such as whether the planning area is an industrial development zone, commercial center, cash crop area, tourist area, agricultural development zone, science and technology center area, etc., as well as the requirements of the load development in the planning area for power supply reliability.

[0003] With respect to the above-mentioned related technologies, the inventors believe that distribution line planning is relatively time-consuming and consumes relatively much manpower and material resources. Summary of the invention

[0004] In order to improve the problem that power distribution line planning is relatively time-consuming and relatively consuming in terms of manpower and material resources, the present application provides a power distribution wiring method, system, device and storage medium.

[0005] In a first aspect, the present application provides a power distribution wiring method, which adopts the following technical solution:

[0006] A power distribution wiring method comprises the following steps:

[0007] Obtain a collection of GIS geographic information of the area to be planned;

[0008] Obtain an atlas of substations in the area to be planned;

[0009] Acquire a user load atlas of the area to be planned, and group the user loads according to the user load atlas to obtain a plurality of user load groups;

[0010] Set up a transformer for each user load group and generate a transformer atlas for the area to be planned;

[0011] According to the atlas of the substation, the atlas of GIS geographic information and the atlas of the transformer, a main connection diagram of the substation and the transformer is planned;

[0012] According to the atlas of the GIS geographic information, the atlas of the user loads and the atlas of the transformers, a sub-network connection diagram of the connection between the transformers and each user load in each user load group is planned;

[0013] The main vein connection diagram and the secondary vein connection diagram are combined to obtain the distribution wiring diagram.

[0014] By adopting the above technical solution, the GIS geographic information, substation information and user load information of the area to be planned are automatically obtained, and the user loads are quickly grouped. Then, based on the user load group, a transformer is set in each user load group, and the distribution line between the transformer and the substation is planned to obtain the main vein connection diagram. The distribution line between the transformer and the user load in the user load group is planned to obtain the secondary vein connection diagram. The two-level planning is logically carried out to achieve the effect of efficient planning of the distribution line. In addition, through the setting of the two-level planning, the distribution wiring diagram is made more concise and clear, which is convenient for wiring implementation.

[0015] Preferably, the user loads are grouped according to the user load atlas, specifically including: grouping the user loads according to the distances between the user loads according to the user load atlas, and the average total load of each user load in each user load group is less than a preset calibrated total load.

[0016] By adopting the above technical solution, user loads are grouped according to the distance between user loads, further reducing the distance and difficulty of wiring, thus achieving the effect of saving costs and reducing the difficulty of implementation. In addition, the average total load of each user load group is limited, which can average the power pressure and protect the power facilities, while reserving load capacity space for the subsequent increase in the total power load in the future.

[0017] Preferably, establishing a transformer for each user load group specifically includes setting a transformer of corresponding capacity according to the total load of each user load group, and the total load of the user load group is 50%-70% of the rated capacity of the transformer of the load group.

[0018] By adopting the above technical solution, a transformer of corresponding capacity is set according to the total load of each user load group, so that the power facilities are matched with the power usage, providing guarantee for the stable transmission of power.

[0019] Preferably, the planning to obtain a main network connection diagram of the substation and the transformer specifically includes: marking the substation and the transformer as nodes, and generating the main network connection diagram by a minimum spanning tree algorithm.

[0020] By adopting the above technical solution, the line planning of the substation and the transformer of each user load group can be quickly realized through the minimum spanning tree algorithm, and the repeated laying of cables can be effectively avoided, the wiring length can be reduced, and the wiring cost can be saved.

[0021] Preferably, the planning to obtain a sub-network connection diagram of the transformers in each user load group and the user loads specifically includes: marking the transformers and user loads in the user load group as nodes, and generating a sub-network connection diagram by a minimum spanning tree algorithm

[0022] By adopting the above technical solution, the minimum spanning tree algorithm is used to quickly plan the lines of the transformers and user loads of each user load group, and the repeated laying of cables is effectively avoided, the wiring length is reduced, and the wiring cost is saved.

[0023] Preferably, the GIS geographic information includes: any one or more combinations of roads, bridges, tunnels, mountains, lakes, and rivers.

[0024] By adopting the above technical solution and using the atlas of GIS geographic information to realize distribution line planning, the line planning can be coordinated with actual needs and the manual workload can be reduced.

[0025] In a second aspect, the present application provides a power distribution wiring system, which adopts the following technical solution:

[0026] A power distribution wiring system, comprising:

[0027] An atlas acquisition module is used to obtain an atlas of GIS geographic information of the area to be planned, an atlas of substations in the area to be planned, and an atlas of user loads in the area to be planned;

[0028] A load grouping module, used for grouping the user loads according to the atlas of the user loads to obtain a plurality of user load groups;

[0029] A transformer planning module is used to plan and obtain a main connection diagram of the substation and the transformer according to the atlas of the substation, the atlas of GIS geographic information and the atlas of the transformer;

[0030] A line planning module is used to plan and obtain a sub-network connection diagram of the connection between the transformer and each user load in each user load group according to the atlas of the GIS geographic information, the atlas of the user load and the atlas of the transformer; and to plan and obtain a sub-network connection diagram of the connection between the transformer and each user load in each user load group according to the atlas of the GIS geographic information, the atlas of the user load and the atlas of the transformer;

[0031] The line combination module is used to combine the main vein connection diagram and the secondary vein connection diagram to obtain a distribution wiring diagram.

[0032] By adopting the above technical scheme, the GIS geographic information, substation information and user load information of the area to be planned are automatically obtained through the atlas acquisition module, and the user loads are quickly grouped. Then, based on the user load group, a transformer is set in each user load group, and the distribution line between the transformer and the substation is planned to obtain the main vein connection diagram, and the distribution line between the transformer and the user load in the user load group is planned to obtain the secondary vein connection diagram. The two-level planning is logically carried out to achieve the effect of efficient planning of the distribution line, and the two-level planning setting makes the distribution wiring diagram more concise and clear, which is convenient for wiring implementation.

[0033] Preferably, the route planning module includes:

[0034] The minimum spanning tree unit is used to mark the substation and the transformer as nodes, and generate a main network connection diagram through the minimum spanning tree algorithm, mark the transformer and the user load in the user load group as nodes, and generate a secondary network connection diagram according to the minimum spanning tree algorithm;

[0035] The shortest path selection unit is used to measure the distance between the substation and the transformer on different routes, the distance between adjacent transformers on different routes, the distance between the transformer and the user load on different routes, and the distance between adjacent user loads on different routes, and compare and select the shortest path.

[0036] By adopting the above technical solution, the minimum spanning tree unit and the shortest path selection unit can be used to quickly plan the lines between the substation and the transformer of each user load group, and between the transformer of each user load group and the user load, and effectively avoid repeated laying of cables, reduce wiring length, and save wiring costs.

[0037] In a third aspect, the present application provides a power distribution wiring device, which adopts the following technical solution:

[0038] A power distribution wiring device comprises a memory and a processor, wherein the memory stores a computer program which can be loaded by the processor and execute any one of the above methods.

[0039] By adopting the above technical solution, the distribution line planning of the transformer and the substation is carried out to obtain the main network connection diagram, and the distribution line between the transformer and the user load in the user load group is planned to obtain the secondary network connection diagram. The two-level planning is carried out logically to achieve the effect of efficient planning of the distribution line. In addition, through the setting of the two-level planning, the distribution wiring diagram is made more concise and clear, which is convenient for wiring implementation.

[0040] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution:

[0041] A computer-readable storage medium includes a computer program that can be loaded by a processor and execute any of the above methods.

[0042] By adopting the above technical solution, the distribution line planning of the transformer and the substation is carried out to obtain the main network connection diagram, and the distribution line between the transformer and the user load in the user load group is planned to obtain the secondary network connection diagram. The two-level planning is carried out logically to achieve the effect of efficient planning of the distribution line. In addition, through the setting of the two-level planning, the distribution wiring diagram is made more concise and clear, which is convenient for wiring implementation.

[0043] In summary, the present application includes at least one of the following beneficial technical effects:

[0044] 1. Automatically obtain GIS geographic information, substation information and user load information of the area to be planned, and quickly group the user loads. Then, based on the user load group, set up transformers in each user load group, plan the distribution lines between the transformer and the substation to obtain the main network connection diagram, plan the distribution lines between the transformer and the user loads in the user load group to obtain the secondary network connection diagram, and logically carry out two-level planning to achieve the effect of efficient planning of distribution lines. In addition, through the setting of two-level planning, the distribution wiring diagram is more concise and clear, which is convenient for wiring implementation;

[0045] 2. User loads are grouped based on the distance between them, further reducing the distance and difficulty of wiring, thus saving costs and reducing implementation difficulty. The average total load of each user load group is limited, which can average out the power pressure and protect the power facilities. At the same time, it reserves load capacity space for the subsequent increase in the total power load in the future;

[0046] 3. Through the setting of the minimum spanning tree unit and the shortest path selection unit, the line planning of the substation and the transformer of each user load group, and the transformer of each user load group and the user load can be quickly realized, and the repeated laying of cables can be effectively avoided, the wiring length can be reduced, and the wiring cost can be saved. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] Figure 1 is a method block diagram of a power distribution wiring method in an embodiment of the present application;

[0048] Figure 2 is a system block diagram of a power distribution wiring system in an embodiment of the present application;

[0049] Figure 3 It is a system block diagram of the line planning module in the embodiment of the present application.

[0050] Explanation of the accompanying drawings: 1. Atlas acquisition module; 2. Load grouping module; 3. Transformer planning module; 4. Line planning module; 41. Minimum spanning tree unit; 42. Shortest path selection unit; 5. Line combination module. DETAILED DESCRIPTION

[0051] The following is combined with Figure 1-3 This application is described in further detail.

[0052] The present application embodiment discloses a power distribution wiring method. Figure 1 , a power distribution wiring method, comprising the following steps:

[0053] S1. Obtaining a collection of GIS geographic information of the area to be planned;

[0054] GIS geographic information includes: any one or more combinations of roads, bridges, tunnels, mountains, lakes, and rivers. In practice, distribution network lines cannot cross lakes and rivers at will, so the shapes and relative distances of roads, bridges, tunnels, mountains, lakes, and rivers and other geographic information should be marked in the area to be planned. Of course, some areas to be planned may not actually have any one or more of roads, bridges, tunnels, mountains, lakes, and rivers. In other words, GIS geographic information includes: any one or more combinations of roads, bridges, tunnels, mountains, lakes, and rivers. Using the atlas of GIS geographic information to implement distribution line planning can coordinate line planning with actual needs and reduce manual workload.

[0055] S2. Obtain an atlas of substations in the area to be planned;

[0056] S3, obtaining a user load atlas of the area to be planned, and grouping the user loads according to the user load atlas to obtain a plurality of user load groups;

[0057] The specific method of grouping user loads according to the atlas of user loads includes: grouping user loads according to the distance between user loads according to the atlas of user loads, and the average total load of each user load of each user load group is less than the preset calibrated total load. Grouping user loads based on the distance between user loads can further reduce the distance and difficulty of wiring, thereby achieving the effect of saving costs and reducing the difficulty of implementation. In addition, limiting the average total load of each user load group can average the power pressure and protect power facilities, while reserving load capacity space for subsequent increases in the total power load in the future.

[0058] S4. Set up a transformer for each user load group and generate a transformer atlas for the area to be planned;

[0059] Specifically, it includes: setting the transformer of corresponding capacity according to the total load of each user load group, and the total load of the user load group is 50%-70% of the rated capacity of the transformer of the load group, so that the power facilities match the power usage and provide guarantee for the stable transmission of power. At the same time, the total load of the user load group is 50%-70% of the rated capacity of the transformer of the load group, so that the transformer can not only ensure the stable transmission of power, but also improve the applicability of power equipment, and avoid the phenomenon of frequent replacement of transformers due to the increase of power load.

[0060] S5. According to the atlas of the substation, the atlas of GIS geographic information and the atlas of the transformer, a main connection diagram of the substation and the transformer is planned;

[0061] Specifically, the substation and transformer are marked as nodes, and the main network connection diagram is generated through the minimum spanning tree algorithm. The distance between the substation and the transformer and the distance between the adjacent transformers are calculated, and the shortest path is selected after comparison and summarized into the main network connection diagram. The minimum spanning tree algorithm is used to quickly plan the lines of the substation and the transformer of each user load group, and effectively avoid the repeated laying of cables, reduce the wiring length, and save wiring costs.

[0062] And the route is planned based on GIS geographic information. If the GIS geographic information includes one or more of roads, bridges, tunnels, mountains, lakes, and rivers, these GIS geographic information can be divided into objects that can be extended and objects that cannot be crossed. For example, in practice, it is possible to follow roads, bridges, tunnels, and rivers, bypass mountains and lakes, that is, to circle around the edges of mountains and lakes instead of crossing mountains and lakes. When the computer performs various possible plans, various plans can be compared to plan the main vein connection diagram.

[0063] S6. According to the atlas of GIS geographic information, the atlas of user loads and the atlas of transformers, a sub-network connection diagram of the connection between the transformers and each user load in each user load group is planned;

[0064] Specifically, the transformers and user loads in the user load group are marked as nodes, and a secondary network connection diagram is generated through the minimum spanning tree algorithm. The distances between the transformer and the user load on different routes and the distances between the adjacent user loads on different routes are calculated, and the shortest path is selected after comparison and summarized into the main network connection diagram. The minimum spanning tree algorithm is used to quickly plan the lines of the substation and the transformers of each user load group, and effectively avoid the repeated laying of cables, reduce the wiring length, and save wiring costs.

[0065] S7. Combine the main vein connection diagram and the secondary vein connection diagram to obtain the distribution wiring diagram. Automatically obtain the GIS geographic information, substation information and user load information of the area to be planned, and quickly group the user loads. Then, based on the user load group, set a transformer in each user load group, plan the distribution line between the transformer and the substation to obtain the main vein connection diagram, plan the distribution line between the transformer and the user load in the user load group to obtain the secondary vein connection diagram, and logically carry out two-level planning to achieve the effect of efficient planning of distribution lines. Through the setting of two-level planning, the distribution wiring diagram is more concise and clear, which is convenient for wiring implementation.

[0066] The present application also discloses a power distribution wiring system. Figure 2 , a power distribution wiring system comprising:

[0067] Atlas acquisition module 1, used to obtain an atlas of GIS geographic information of the area to be planned, an atlas of substations in the area to be planned, and an atlas of user loads in the area to be planned;

[0068] A load grouping module 2, used for grouping user loads according to the user load atlas to obtain a plurality of user load groups;

[0069] The transformer planning module 3 is used to plan and obtain the main connection diagram of the substation and the transformer according to the atlas of the substation, the atlas of the GIS geographic information and the atlas of the transformer;

[0070] The line planning module 4 is used to plan and obtain the sub-network connection diagram of the transformers in each user load group and the connections between each user load according to the atlas of GIS geographic information, the atlas of user loads and the atlas of transformers; and to plan and obtain the sub-network connection diagram of the transformers in each user load group and the connections between each user load according to the atlas of GIS geographic information, the atlas of user loads and the atlas of transformers;

[0071] The line combination module 5 is used to combine the main vein connection diagram and the secondary vein connection diagram to obtain a distribution wiring diagram.

[0072] The atlas acquisition module 1 automatically obtains the GIS geographic information, substation information and user load information of the area to be planned, and quickly groups the user loads. Then, based on the user load group, a transformer is set in each user load group, and the distribution line between the transformer and the substation is planned to obtain the main network connection diagram. The distribution line between the transformer and the user load in the user load group is planned to obtain the secondary network connection diagram. The two-level planning is logically carried out to achieve the effect of efficient planning of the distribution line. The two-level planning setting makes the distribution wiring diagram more concise and clear, which is convenient for wiring implementation.

[0073] Reference Figure 3 , the route planning module 4 includes:

[0074] The minimum spanning tree unit 41 is used to mark the substation and the transformer as nodes, and generate a primary network connection diagram through a minimum spanning tree algorithm, mark the transformer and the user load in the user load group as nodes, and generate a secondary network connection diagram according to the minimum spanning tree algorithm;

[0075] The shortest path selection unit 42 is used to measure the distances between the substation and the transformer on different routes, the distances between adjacent transformers on different routes, the distances between the transformer and the user load on different routes, and the distances between adjacent user loads on different routes, and compare and select the shortest path.

[0076] The minimum spanning tree unit 41 and the shortest path selection unit 42 can be used to quickly plan the lines between the substation and the transformer of each user load group, and between the transformer of each user load group and the user load, and effectively avoid repeated laying of cables, reduce wiring length, and save wiring costs.

[0077] An embodiment of the present application further discloses a power distribution wiring device, including a memory and a processor, wherein the memory stores a computer program that can be loaded by the processor and execute the above method.

[0078] The embodiment of the present application also discloses a computer-readable storage medium, which stores a computer program that can be loaded by a processor and executed as in the above method. The computer-readable storage medium includes, for example: a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, and other media that can store program codes.

[0079] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the scope of protection of the invention. Obviously, the described embodiments are only some embodiments of the present invention, rather than all embodiments. Based on these embodiments, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in this field can still combine, add, delete or make other adjustments to the features in the various embodiments of the present invention according to the circumstances without conflict, without making creative work, so as to obtain different other technical solutions that do not deviate from the concept of the present invention in essence, and these technical solutions also belong to the scope of protection of the present invention.

Claims

1. A power distribution wiring method, characterized in that: The following steps are involved: Obtaining an atlas of GIS geographic information of the area to be planned, wherein the GIS geographic information includes any one or more combinations of roads, bridges, tunnels, mountains, lakes, and rivers; Obtain an atlas of substations in the area to be planned; Acquire a user load atlas of the area to be planned, and group the user loads according to the user load atlas to obtain a plurality of user load groups; Set up a transformer for each user load group and generate a transformer atlas for the area to be planned; According to the atlas of the substation, the atlas of GIS geographic information and the atlas of the transformer, a main connection diagram of the substation and the transformer is planned; According to the atlas of the GIS geographic information, the atlas of the user loads and the atlas of the transformers, a sub-network connection diagram of the connection between the transformers and each user load in each user load group is planned; Combining the main vein connection diagram and the secondary vein connection diagram to obtain a power distribution wiring diagram; The user loads are grouped according to the atlas of the user loads, specifically comprising: grouping the user loads according to the distances between the user loads according to the atlas of the user loads, and the average total load of each user load in each user load group is less than a preset calibrated total load; The planning to obtain the main vein connection diagram of the substation and the transformer specifically includes: marking the substation and the transformer as nodes, generating the main vein connection diagram by using the minimum spanning tree algorithm, and calculating the distances between the substation and the transformer on different routes, and the distances between the adjacent transformers on different routes, and selecting the shortest path after comparison to summarize into the main vein connection diagram; The planning to obtain a sub-network connection diagram of the connection between the transformer and each user load in each user load group specifically includes: marking the transformers and user loads in the user load group as nodes, generating a sub-network connection diagram through a minimum spanning tree algorithm, and calculating the distances between the transformer and the user loads on different routes and the distances between the adjacent user loads on different routes, and selecting the shortest path after comparison to summarize into the sub-network connection diagram.

2. A power distribution wiring method according to claim 1, characterized in that: The transformer is set up for each user load group, which specifically includes setting a transformer of corresponding capacity according to the total load of each user load group, and the total load of the user load group is 50%-70% of the rated capacity of the transformer of the load group.

3. A power distribution wiring system, characterized in that: include: An atlas acquisition module (1) is used to acquire an atlas of GIS geographic information of the area to be planned, an atlas of substations in the area to be planned, and an atlas of user loads in the area to be planned, wherein the GIS geographic information includes any one or more combinations of roads, bridges, tunnels, mountains, lakes, and rivers; A load grouping module (2), used for grouping the user loads according to the user load atlas to obtain a plurality of user load groups; A transformer planning module (3) is used to plan and obtain a main connection diagram of the substation and the transformer according to the atlas of the substation, the atlas of GIS geographic information and the atlas of the transformer; A line planning module (4) is used to plan and obtain a sub-network connection diagram of the connection between the transformer and each user load in each user load group based on the atlas of the GIS geographic information, the atlas of the user load and the atlas of the transformer; A line combination module (5) is used to combine the main vein connection diagram and the secondary vein connection diagram to obtain a power distribution wiring diagram; The user loads are grouped according to the atlas of the user loads, specifically comprising: grouping the user loads according to the distances between the user loads according to the atlas of the user loads, and the average total load of each user load in each user load group is less than a preset calibrated total load; The planning to obtain the main vein connection diagram of the substation and the transformer specifically includes: marking the substation and the transformer as nodes, generating the main vein connection diagram by using the minimum spanning tree algorithm, and calculating the distances between the substation and the transformer on different routes, and the distances between the adjacent transformers on different routes, and selecting the shortest path after comparison to summarize into the main vein connection diagram; The planning to obtain a sub-network connection diagram of the connection between the transformer and each user load in each user load group specifically includes: marking the transformers and user loads in the user load group as nodes, generating a sub-network connection diagram through a minimum spanning tree algorithm, and calculating the distances between the transformer and the user loads on different routes and the distances between the adjacent user loads on different routes, and selecting the shortest path after comparison to summarize into the sub-network connection diagram.

4. A power distribution wiring device, characterized in that: The method comprises a memory and a processor, wherein the memory stores a computer program which can be loaded by the processor and executes the method according to any one of claims 1 to 2.

5. A computer-readable storage medium, characterized in that: A computer program is stored which can be loaded by a processor and execute the method as claimed in any one of claims 1 to 2.

Citation Information