A Material Demand Forecasting Method for General Assembly Workshop

By establishing a time-to-completion prediction model that comprehensively considers worker information levels, the deficiencies in auxiliary material inventory and key parts distribution strategies in the material handling system in intelligent manufacturing are solved, and prediction accuracy and production efficiency are improved.

CN113496313BActive Publication Date: 2024-10-18NANJING UNIV OF AERONAUTICS & ASTRONAUTICS +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202110776812.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-07-09
Publication Date
2024-10-18
Estimated Expiration
2041-07-09

AI Technical Summary

Technical Problem

Existing technology In the field of intelligent manufacturing, the material handling system cannot ensure that the inventory of auxiliary materials is replenished before the minimum requirement, and the factors affecting the distribution strategy and completion time of critical parts are not considered enough, resulting in large prediction errors and low scenario adaptability.

Method used

By establishing a time-to-completion prediction model and comprehensively considering worker information, benchmark parts grade, auxiliary material grade and critical part grade, a material demand prediction method is proposed to provide the material handling system with predicted material handling tasks and the best delivery time period, and adopts improved The BP neural network optimized by the Dragonfly algorithm establishes a completion time-consuming prediction model.

Benefits of technology

It improves the prediction accuracy of the prediction model, ensures the timely distribution of auxiliary materials and key parts, avoids the problem of untimely material replenishment caused by heavy handling tasks and traffic congestion, and ensures the production efficiency of the production line.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113496313B_ABST
    Figure CN113496313B_ABST
Patent Text Reader

Abstract

The present invention is a material demand prediction method for an assembly workshop, which belongs to the field of intelligent manufacturing. When the auxiliary material demand prediction triggering conditions are met, first, it is determined whether it is a periodic start or an auxiliary material usage trigger, and the triggering station is set; then the corresponding key reference part of the triggering station and the current station where the key reference part is located are determined; finally, the number of auxiliary material distribution tasks and the optimal delivery time period to be generated by the triggering station are determined; when the important parts demand prediction triggering conditions are met, according to the important parts demand prediction method and the station completion time prediction algorithm, the optimal delivery time period of the important parts distribution tasks of the subsequent stations is determined and updated. This method comprehensively considers the worker information, the reference part level, the auxiliary material level and the important parts level, establishes a completion time prediction model, and proposes material demand prediction methods for auxiliary materials and important parts respectively, providing the material handling system with predicted material handling tasks and the optimal delivery time period, and providing the material handling system with scheduling buffer time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of intelligent manufacturing, and in particular to a method for predicting material demand in an assembly workshop. Background Art

[0002] Production assembly usually requires a variety of materials. For auxiliary materials with large usage and low unit price, a buffer area is often set up at the workstation for auxiliary material storage; for key and expensive parts with important structures, no workstation buffer area is set up, and the material handling system delivers the key and important parts to the required workstation in a timely manner according to the workstation requirements. Since the assembly execution at the workstation must meet the material completeness, how to ensure that the inventory of auxiliary materials in the buffer area is within the required inventory range and the key and important parts are delivered to the required workstation in the best time period has gradually become a major research hotspot in the field of intelligent manufacturing. In existing applications and research, the former is mainly implemented by the workstation sending a demand for auxiliary materials to the material system when the real-time inventory of auxiliary materials in the workstation buffer reaches a certain threshold, and the material handling system delivers a quota of auxiliary materials to the workstation buffer according to the demand for auxiliary materials. When the task volume in the material handling system is large and the traffic congestion is high, it is difficult to ensure that the auxiliary materials can be replenished before the auxiliary materials reach the minimum required inventory. The research directions of the latter mainly include material handling scheduling and completion time prediction. There are currently a large number of relevant literature on material handling scheduling, such as the Chinese invention patent application with publication number CN111653098A and patent name "Optimization Method for Traffic Sequence of Multi-Load Automated Guided Vehicles at Intersections", which studies the traffic control problem in scheduling. The latter is relatively less studied, and the existing research considers few dimensions of factors affecting completion time. For example, the article entitled "On-time Material Delivery Method for Digital Twin Workshop of Satellite Assembly" only considers the worker dimension. For scenarios where there are grade differences in materials, the method proposed in the article has a large prediction error and low scenario adaptability. In addition, in the prior art, a unified demand forecasting method is generally used for all materials based on the predicted completion time, without in-depth consideration of the differences in the distribution strategies of auxiliary materials and key parts, which makes it difficult to transform the method into practical applications. Summary of the invention

[0003] In order to solve the technical defects existing in the prior art, the present invention proposes a material demand forecasting method for the final assembly workshop. By comprehensively considering the worker information, reference part level, auxiliary material level and key part level, a completion time prediction model is established. Based on the completion time prediction model, material demand forecasting methods are proposed for auxiliary materials and key parts respectively, which provides the material handling system with predicted material handling tasks and the optimal delivery time period, and provides scheduling buffer time for the material handling system.

[0004] The present invention is achieved through the following technical solutions:

[0005] A method for predicting material demand in an assembly workshop comprises the following steps:

[0006] Step 1: Determine whether the auxiliary material demand forecast trigger condition or the critical component demand forecast trigger condition is met. If the auxiliary material demand forecast trigger condition is met, proceed to step 2. If the critical component demand forecast trigger condition is met, proceed to step 5. If neither is met, proceed to step 1.

[0007] Step 2: Determine whether it is a cycle trigger. If so, set all workstations as trigger workstations. If not, set the available quantity C of auxiliary materials to be lower than the minimum inventory quantity C. min The workstation is set as the trigger workstation;

[0008] Step 3: According to the key reference part determination method and the workstation completion time prediction algorithm, determine the key reference part corresponding to the triggering workstation and the workstation where the key reference part is currently located;

[0009] Step 4: According to the auxiliary material demand prediction method, the workstation completion time prediction algorithm, the corresponding key reference part of the triggering workstation and the workstation where the key reference part is currently located, determine the number of auxiliary material distribution tasks that need to be generated by the triggering workstation and the optimal delivery time period;

[0010] Step 5: According to the method for predicting the demand for important parts and the time-consuming prediction algorithm for completing the workstation, determine and update the optimal delivery time period for the important parts distribution tasks of subsequent workstations.

[0011] Furthermore, the auxiliary material demand forecast triggering conditions include cycle triggering and minimum inventory triggering.

[0012] Furthermore, the minimum inventory quantity is triggered when the available quantity of auxiliary materials is lower than the minimum inventory quantity at a workstation.

[0013] Furthermore, the triggering condition for forecasting the demand for important parts is the appearance of a workstation for starting to execute the next assembly task.

[0014] Furthermore, the available amount of the auxiliary material is calculated as follows:

[0015] C=C r +c′*Δ (1)

[0016] In the formula, C r is the actual remaining amount of auxiliary materials in the auxiliary material buffer area of ​​the workstation, c′ is the number of auxiliary material delivery tasks to be delivered to the workstation, and Δ is the auxiliary material replenishment amount for a single delivery task.

[0017] Furthermore, the workstation completion time prediction algorithm is to input the assembly information required for prediction into the completion time prediction model of the corresponding workstation to obtain the predicted completion time of the workstation, the reference part b j On process line P i The rth station (r is a positive integer) the predicted completion time is:

[0018]

[0019] In the formula, For workstation Completion time prediction model; p, C B , C An , C Kl They are respectively the worker information of this assembly, the grade of the reference part, the grade of the nth auxiliary material and the grade of the lth key part; N is the number of auxiliary materials required for assembly at the workstation; L is the number of key parts required for assembly at the workstation.

[0020] Furthermore, the completion time prediction model is a BP neural network optimized by the improved dragonfly algorithm, and its establishment includes the following steps:

[0021] Step 3.1.1: Determine the total number of hidden layers U and the number of nodes n in the uth hidden layer of the BP neural network h,u , the number of nodes in the input layer I and the number of nodes in the output layer K.

[0022] Step 3.1.2: Determine the dragonfly population size DS and the maximum number of iterations t max and the dimension D of individual dragonflies.

[0023] Step 3.1.3: Generate the initial population of the dragonfly algorithm according to the population initialization method.

[0024] Step 3.1.4: Calculate the fitness value of the dragonfly individual. If there is a dragonfly individual whose fitness value is better than the food, update the food to the dragonfly individual. If there is a dragonfly individual whose fitness value is worse than the natural enemy, update the natural enemy to the dragonfly individual.

[0025] Step 3.1.5: Determine whether the maximum number of iterations has been reached. If so, proceed to step 3.1.8; if not, proceed to step 3.1.6.

[0026] Step 3.1.6: Update the neighborhood radius for each dragonfly according to the neighborhood radius update mechanism.

[0027] Step 3.1.7: Determine whether the food has not changed for G consecutive iterations. If so, generate a new population according to the population generation mechanism and proceed to step 3.1.4; if not, update the individual dragonfly position and step vector according to the definition of the basic dragonfly algorithm and proceed to step 3.1.4.

[0028] Step 3.1.8: Use the food corresponding solution as the initial weight and bias of the BP neural network, use the sample database to train the BP neural network, and establish a completion time prediction model.

[0029] Furthermore, the sample database is composed of multiple groups of sample data.

[0030] Furthermore, the sample data is composed of input data and output data, wherein the input data includes worker information, reference part grade, auxiliary material grade, and key part grade, and the output data is the actual completion time.

[0031] Furthermore, the dimension D of the dragonfly individual is the sum of the initial weights and the number of deviations required by the BP neural network, and its calculation method is as follows:

[0032]

[0033] Furthermore, the population initialization method is a Bernoulli chaos mapping population initialization method, which includes the following steps:

[0034] Step 3.1.3.1: According to the Bernoulli chaotic mapping formula, obtain a chaotic sequence [Z1, Z2, ..., Z D*DS ], the Bernoulli chaos mapping formula is as follows:

[0035]

[0036] Where λ is 0.4 and Z0 is a random number between (0, 1).

[0037] Step 3.1.3.2: Generate the initial dragonfly population based on the chaotic sequence. The calculation formula for the j-th dimension component of the i-th dragonfly individual in the initial population is as follows:

[0038]

[0039] Where, i = 1, 2, ..., D; lb j is the j-th dimension component of the lower limit matrix lb of the dragonfly individual; ub j is the j-th dimension component of the upper limit matrix ub of the dragonfly individual.

[0040] Step 3.1.3.3: Use random initialization method to generate initial step vector for dragonfly individuals in the initial population.

[0041] Furthermore, the fitness value of the dragonfly individual is calculated as follows:

[0042]

[0043] Where S is the number of sample data used to train the BP neural network; k = 1, 2..., K, s = 1, 2..., S; y s,k is the predicted output of the kth output layer node generated by the BP neural network corresponding to the dragonfly individual for the sth sample data; is the actual output of the kth output layer node of the BP neural network corresponding to the sth sample data.

[0044] Furthermore, the BP neural network corresponding to the dragonfly individual is a neural network obtained by training with a sample database using the dragonfly individual corresponding solution as the initial weight and bias of the BP neural network.

[0045] Furthermore, the neighborhood radius reward and punishment mechanism is a neighborhood radius reward and punishment mechanism, which updates the neighborhood radius of the dragonfly individual according to the fitness value of the dragonfly individual in the population. The update formula of the neighborhood radius of the ith dimension of the i-th dragonfly individual in the population is as follows:

[0046]

[0047] In the formula, E i is the fitness value of the i-th dragonfly individual in the population; E max is the maximum fitness value of all dragonfly individuals in the population; E min is the minimum fitness value of all dragonflies in the population; is the reward and punishment coefficient, which is 0.5; R j is the basic neighborhood radius of the jth dimension of the dragonfly individual, and the calculation formula is as follows:

[0048]

[0049] In the formula, iter is the current iteration number; t max is the maximum number of iterations.

[0050] Furthermore, the population generation mechanism is a composite mechanism of multi-level mutation and population initialization, comprising the following steps:

[0051] Step 3.1.7.1 Arrange the dragonfly individuals in the current population O in ascending order of fitness value, select dragonfly individuals in the set ratio, clone each dragonfly individual once, copy the step vector attribute of the corresponding dragonfly individual during cloning, and form a clone population A. Mutate each dragonfly individual in A five times with a probability of 0.1, keep the corresponding step vector unchanged, and arrange the dragonfly individuals after the mutation operation in ascending order of fitness value. The mutation operation is as follows:

[0052]

[0053]

[0054] In the formula, is the dragonfly individual p in the t-th generation population i The j-th dimension component of is the dragonfly individual p in the t-th generation population i is the j-dimensional component after the k-th mutation; a is a {-1, 1} random number; ρ is a Cauchy random variable that conforms to C(0, 1).

[0055] Step 3.1.7.2: Based on the population initialization method, generate a new population B containing DS dragonfly individuals, and arrange the dragonfly individuals in B in ascending order according to their fitness values.

[0056] Step 3.1.7.3 Select the first 0.1DS dragonfly individuals from A and B as supplementary dragonflies, select the last 0.2DS dragonfly individuals in O and replace them with supplementary dragonflies to form a new population.

[0057] Furthermore, the set ratio is 50%.

[0058] Furthermore, the key reference component determination method comprises the following steps:

[0059] Step 3.2.1: Get the trigger station The available amount of auxiliary materials C and the process line P i and Current machining reference part b j exist Start processing time

[0060] Step 3.2.2: Determine the key reference part b j+x , the calculation formula of x is:

[0061]

[0062] In the formula, b is the workstation The consumption of auxiliary materials for a single processing, t0 is the current moment, The reference part b j Arrival at workstation moment, The reference part b j At the workstation The predicted completion time, C max is the maximum auxiliary material inventory in the auxiliary material buffer area of ​​the workstation, C min It is the minimum auxiliary material inventory in the auxiliary material buffer area of ​​the workstation.

[0063] Step 3.2.3: Initialize variables k←1, w←0, z←0, y←0.

[0064] Step 3.2.4: Determine the workstation Whether it exists, that is, whether rk is greater than 0, if so, z←1, go to step 3.2.5; if not, w←1, go to step 3.2.6.

[0065] Step 3.2.5: Get a workstation Current machining reference part b j′, compare j′ and j+x, if they are equal, y←1, output k, w, z, y, and the algorithm ends; if j′>j+x, y←2, output k, w, z, y, and the algorithm ends; if j′<j+x, k←k+1, go to step 3.2.4.

[0066] Step 3.2.6: Output k, w, z, y. When y = 0, obtain the key reference part b according to the production plan. j+x The planned production time t p , that is, b j+x The planned start time of the first process.

[0067] Furthermore, the auxiliary material demand forecasting method comprises the following steps:

[0068] Step 4.1: Determine whether the available amount of auxiliary material C at the triggering station is greater than C max -Δ, if yes, go to step 4.2; if no, go to step 4.3;

[0069] Step 4.2: Generate a supplementary material delivery task, end the call of this supplementary material demand forecasting method, and the starting time T of the optimal delivery time period of the supplementary material delivery task B With the deadline T E The calculation formulas are as follows:

[0070]

[0071] In the formula, t m,m+1 To remove the reference part from the workstation Transport to The handling time of the production line is 2000 hours; T is the production cycle of the production line; x is obtained by the key reference part determination method; t 0p As the reference time, the calculation formula is:

[0072]

[0073] Where y is obtained by the key reference part determination method.

[0074] Step 4.3: Determine whether the available amount C of the auxiliary material at the triggering station is greater than Cmin. If so, proceed to step 4.4; if not, proceed to step 4.5;

[0075] Step 4.4: Generate N task auxiliary material distribution tasks, ending the auxiliary material demand forecasting method call, N task The calculation formula is as follows:

[0076]

[0077] The starting time T of the optimal delivery time period for the qth auxiliary material distribution task generated BWith the deadline T E The calculation formulas are as follows:

[0078] T B =t0 (18)

[0079]

[0080] Where q = 1, 2, ... N task .

[0081] Step 4.5: Generate N′ task The starting time T of the best delivery time period B With the deadline T E All of them are auxiliary material distribution tasks of t0, ending the auxiliary material demand forecasting method call, N′ task The calculation formula is as follows:

[0082]

[0083] Furthermore, the method for predicting demand for important items includes the following steps:

[0084] Step 5.1: Calculate the current workstation Assembly reference part b j Arrive at the next workstation The calculation formula is as follows:

[0085]

[0086] Step 5.2: Calculate the workstation The best delivery time period for important and important items is calculated as follows:

[0087]

[0088] In the formula, Δt m The allowable error in the prediction time is determined according to the actual application requirements.

[0089] Compared with the prior art, the present invention has at least the following beneficial effects or advantages:

[0090] The present invention proposes a material demand forecasting method for an assembly workshop. By comprehensively considering worker information, reference part levels, auxiliary material levels and key parts levels, a completion time forecasting model is established, the model input consideration dimensions are improved, and the prediction accuracy of the forecasting model is enhanced. At the same time, based on the completion time forecasting model, material demand forecasting methods are proposed for auxiliary materials and key parts respectively, and the material handling system is provided with predicted material handling tasks and optimal delivery time periods, and scheduling buffer time is provided for the material handling system, so as to avoid untimely material replenishment due to large handling tasks and traffic congestion, and the situation where workstations wait for materials for production, thereby ensuring the production efficiency of the production line. BRIEF DESCRIPTION OF THE DRAWINGS

[0091] The present invention will be further described in detail below with reference to the accompanying drawings:

[0092] Figure 1 A flow chart of a method for predicting material demand in an assembly shop according to the present invention;

[0093] Figure 2 A flow chart of a BP neural network optimized by the improved dragonfly algorithm of the present invention;

[0094] Figure 3 It is an environmental model for a certain application scenario. DETAILED DESCRIPTION

[0095] The present invention will be described in detail below with reference to the accompanying drawings, but the present invention is not limited thereto. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0096] Since the present invention is a material demand forecasting method, the material handling tasks generated by it are tasks that will be generated in the future time period. The early release of tasks provides the material handling system with sufficient buffer time for task scheduling and traffic control. Therefore, the following assumptions are made:

[0097] 1. The assembly task is completed, and the worker moves out of the current workstation;

[0098] 2. When the reference part is delivered to the workstation, assembly can begin. That is, the moment the reference part arrives at the workstation is the moment when processing begins.

[0099] Figure 1 This is a flow chart of a method for predicting material demand in an assembly workshop according to the present invention. The method for predicting material demand in an assembly workshop specifically comprises the following steps:

[0100] A method for predicting material demand in an assembly workshop comprises the following steps:

[0101] Step 1: Determine whether the auxiliary material demand forecast trigger condition or the critical component demand forecast trigger condition is met. If the auxiliary material demand forecast trigger condition is met, proceed to step 2. If the critical component demand forecast trigger condition is met, proceed to step 5. If neither is met, proceed to step 1.

[0102] The material demand forecasting method for a general assembly workshop proposed in the present invention involves the demand forecasting of two types of materials, auxiliary materials and key parts. Since the distribution strategies of the above two types of materials are different, different trigger conditions for material demand forecasting are adopted, namely auxiliary material demand forecasting trigger conditions and key parts demand forecasting trigger conditions. Among them, the auxiliary material demand forecasting trigger conditions are divided into periodic triggering and minimum inventory triggering. The former is to make an auxiliary material demand forecast for all workstations at regular intervals, and the latter is to make an auxiliary material demand forecast for the workstation when the available amount of auxiliary materials is lower than the minimum inventory. The trigger condition for the forecast of key parts demand is the appearance of a workstation that starts to execute the next assembly task, that is, the appearance of a workstation that starts to execute a new task.

[0103] In the implementation case of the present invention, the available amount of auxiliary materials is not the actual remaining amount of auxiliary materials in the auxiliary material buffer area of ​​the workstation, but the sum of the actual remaining amount of auxiliary materials and the amount of auxiliary materials to be delivered, and the calculation formula is as follows:

[0104] C=C r +c′*Δ (1)

[0105] In the formula, C r is the actual remaining amount of auxiliary materials in the auxiliary material buffer area of ​​the workstation, c′ is the number of auxiliary material delivery tasks to be delivered to the workstation, and Δ is the auxiliary material replenishment amount for a single delivery task.

[0106] Step 2: Determine whether it is a cycle trigger. If so, set all workstations as trigger workstations, and set the workstation where the auxiliary material available quantity C is lower than the minimum inventory quantity Cmin as the trigger workstation;

[0107] Since the periodic trigger is to make a forecast of auxiliary material demand for all workstations, if the auxiliary material demand forecast trigger condition is a periodic trigger, all workstations are set as trigger workstations. If the auxiliary material demand forecast trigger condition is not a periodic trigger, that is, the auxiliary material demand forecast trigger condition is a minimum inventory trigger, then the auxiliary material available quantity is lower than the minimum inventory C min The workstation is set as a trigger workstation. Usually, the minimum inventory is the minimum required amount of the auxiliary material buffer area set to ensure the normal assembly of the workstation. If the available amount of auxiliary materials is lower than the minimum inventory, it is likely to affect the execution of subsequent assembly tasks of the workstation. Therefore, it is necessary to immediately predict the auxiliary material demand of the workstation and replenish the auxiliary materials. The setting of the trigger workstation is used to clarify which workstations need to perform material demand prediction.

[0108] Step 3: According to the key reference part determination method and the workstation completion time prediction algorithm, determine the key reference part corresponding to the triggering workstation and the workstation where the key reference part is currently located;

[0109] When it is determined that there is a triggering workstation with auxiliary material demand forecast, the corresponding key reference part of the triggering workstation and its current workstation are determined according to the key reference part determination method and the workstation completion time prediction algorithm.

[0110] The workstation completion time prediction algorithm is used to provide the completion prediction time of the assembly task of the workstation, and provides the required completion prediction time for the calculation in the key reference part determination method, auxiliary material demand prediction method and key part demand prediction method. The key reference part determination method is used to determine the auxiliary material available margin that makes the triggering workstation reach C max -Δ or Cmin, where Cmax is the maximum inventory of the auxiliary material buffer area at the workstation, C max -Δ and Cmin correspond respectively to the auxiliary material buffer area of ​​the triggering station being able to accept one auxiliary material task replenishment and the auxiliary material available surplus having reached the minimum limit.

[0111] The method for determining key reference parts will be described in detail later.

[0112] In this implementation case, the station completion time prediction algorithm is to input the assembly information required for prediction into the completion time prediction model of the corresponding station, obtain the completion prediction time of the assembly task at the station, and the reference part b j On process line P i The rth station (r is a positive integer) the predicted completion time is:

[0113]

[0114] In the formula, For workstation Completion time prediction model; p, C B , C An , C Kl They are the worker information of this assembly, the grade of the reference part, the grade of the nth auxiliary material and the grade of the lth key part, which are the assembly information required for the completion time prediction; N is the number of auxiliary materials required for the assembly of the workstation; L is the number of key parts required for the assembly of the workstation. The worker information p has a total of Species value, among which For workstation Number of available workers, For workstation The number of workers required for a single processing and assembly, the value of the worker information p input into the completion time prediction model is determined by the worker schedule. For example, if the workstation is a two-person collaborative workstation, the number of available workers in the workstation is 3, and the corresponding workers are A, B, and C, respectively. Therefore, there are 3 values ​​for worker information p, and the worker information p is encoded as {1, 2, 3}, corresponding to A and B, A and C, and B and C, respectively. When the completion time of a certain reference part at the workstation needs to be predicted, the corresponding worker combination of the reference part at the workstation in the worker schedule is queried. If it is A and C, the worker information p input into the completion time prediction model this time is 2. The coding method of the benchmark part grade, auxiliary material grade and key part grade is the same as the worker information. When predicting the completion time of a workstation, the corresponding benchmark part may be the current processing benchmark part of the workstation or the future processing benchmark part. The grades of the benchmark part, auxiliary material and key part of the former are known, while the grades of the benchmark part, auxiliary material and key part of the latter are known, and the grades of auxiliary material and key part are unknown. At this time, the proportion of auxiliary materials and key parts of each grade in the BOM list of the day can be used, and the roulette wheel can be used to determine the grades of auxiliary materials and key parts as the corresponding input information for the completion time prediction.

[0115] The completion time prediction model can use BP neural network, BP neural network optimized based on bionic algorithm, grayscale theory prediction model, etc. In this implementation case, the completion time prediction model uses the BP neural network optimized by the improved dragonfly algorithm. The essence of the BP neural network optimized by the improved dragonfly algorithm is to use the initial weights and biases of the BP neural network as dragonfly individuals, and iterate the improved dragonfly algorithm. When the algorithm meets the iteration stop condition, the food of the dragonfly algorithm, that is, the historical optimal dragonfly individual of the dragonfly algorithm, is output as the initial weight and bias of the BP neural network. Compared with the basic BP neural network, the BP neural network optimized by the improved dragonfly algorithm can reduce the possibility of the neural network falling into the local optimal trap during training and increase the probability that the output neural network is optimal.

[0116] The BP neural network optimized by the improved dragonfly algorithm will be described in detail later.

[0117] Step 4: According to the auxiliary material demand prediction method, the workstation completion time prediction algorithm, the corresponding key reference part of the triggering workstation and the workstation where the key reference part is currently located, determine the number of auxiliary material distribution tasks that need to be generated by the triggering workstation and the optimal delivery time period;

[0118] The workstation completion time prediction algorithm is used to obtain the completion prediction time required for auxiliary material prediction. Based on the obtained completion prediction time data, the auxiliary material demand prediction method is used to determine the number of auxiliary material delivery tasks that need to be generated by the triggering workstation and the optimal delivery time period for each auxiliary material delivery task.

[0119] The auxiliary material demand forecasting method will be described in detail later.

[0120] Step 5: According to the method for predicting the demand for important parts and the time-consuming prediction algorithm for completing the workstation, determine and update the optimal delivery time period for the important parts distribution tasks of subsequent workstations.

[0121] The station completion time prediction algorithm is used to obtain the completion prediction time required for the prediction of the demand for key parts. Based on the obtained completion prediction time data, the key parts demand prediction method is used to determine and update the optimal delivery time period for the subsequent station's key parts distribution tasks. For example, when the benchmark part b j arrive Figure 3 Station S P1,1 When the benchmark part b is obtained according to the forecasting method of the demand for key parts j Arrive at the subsequent workstation S P1,2 , S P1,3 , S P1,4 , S P1,5 The predicted time of the workstation S can be determined based on the obtained predicted time. P1,2 , S P1,3 , S P1,4 , S P1,5 For reference part b j The best delivery time for the supporting key parts is when the reference part b j Arrive at the next station S P1,2 When the benchmark part b is j Arrive at the subsequent workstation S P1,3 , S P1,4 , S P1,5 The predicted time is updated, and the workstation S is updated according to the obtained predicted time P1,3 , S P1,4 , S P1,5 For reference part b j The best delivery time period for supporting important parts. By adding the obtained important parts distribution tasks with the best delivery time period attribute to the task library of the material handling system, the material handling system can plan the paths and assign tasks for these important parts distribution tasks in advance. Since the above tasks are prediction tasks, the impact of path congestion on the punctuality of task delivery can be reduced. When the material handling system has fewer tasks, the transport cart can be arranged to prepare for transportation in advance. Through the forecast of demand for important parts, sufficient scheduling buffer time can be provided for the material handling system.

[0122] The method for predicting demand for key parts will be described in detail later.

[0123] Figure 2 The flowchart of the BP neural network optimized by the improved dragonfly algorithm of the present invention is as follows:

[0124] Step 3.1.1: Determine the total number of hidden layers U and the number of nodes n in the uth hidden layer of the BP neural network h,u , the number of nodes in the input layer I and the number of nodes in the output layer K.

[0125] The BP neural network consists of 1 input layer, 1 custom hidden layer, and 1 output layer. When establishing a completion time prediction model, it is necessary to first determine the total number of hidden layers U, the number of nodes in the uth layer of the hidden layer n h,u , the number of nodes in the input layer I and the number of nodes in the output layer K. Preferably, the total number of hidden layers U is 1, and the number of nodes in the hidden layer n h,1 =10, the number of nodes I in the input layer is equal to the number of dimensions of the assembly information required for the station to predict the completion time, that is, the number of variables in formula (2). Different stations have different values ​​of the number of nodes I in the input layer due to the different types of auxiliary materials and key parts required. For example, Figure 3 As shown, it includes sub-assembly line P1, sub-assembly line P2, sub-assembly line P3, final assembly line P4, and workstation S P4,1 , S P4,2 , S P4,3 . Requires 1 auxiliary material, 1 key component, station S P4,1 Requires 2 kinds of auxiliary materials, 2 kinds of key parts, workstation S P4,1 The number of nodes I in the input layer of the neural network in the completion time prediction model is 4 and 6 respectively. Since the completion time prediction model only outputs the completion time, the number of nodes K in the output layer of the BP neural network is 1.

[0126] Step 3.1.2: Determine the dragonfly population size DS, the maximum number of iterations tmax and the dimension D of dragonfly individuals.

[0127] The dragonfly population size DS is the number of dragonflies in the dragonfly population. The dimension D of the dragonfly individual, that is, the number of components of the corresponding solution that constitutes the dragonfly individual, is equal to the sum of the initial weights and biases of the BP neural network. The calculation method is as follows:

[0128]

[0129] For workstations For example, the dimension D of a dragonfly individual is 65.

[0130] Step 3.1.3: Generate the initial population of the dragonfly algorithm according to the population initialization method.

[0131] According to the population initialization method, the initial population for iterative calculation of the dragonfly algorithm is generated.

[0132] In this implementation case, the population initialization method is a Bernoulli chaos mapping population initialization method, which includes the following steps:

[0133] Step 3.1.3.1: According to the Bernoulli chaotic mapping formula, obtain a chaotic sequence [Z1, Z2, ..., Z D*DS ], the Bernoulli chaos mapping formula is as follows:

[0134]

[0135] Where λ is 0.4 and Z0 is a random number between (0, 1).

[0136] Step 3.1.3.2: Generate the initial dragonfly population based on the chaotic sequence. The calculation formula for the j-th dimension component of the i-th dragonfly individual in the initial population is as follows:

[0137]

[0138] Where, i = 1, 2, ..., D; lb j is the j-th dimension component of the lower limit matrix lb of the dragonfly individual; ub j is the j-th dimension component of the upper limit matrix ub of the dragonfly individual.

[0139] Step 3.1.3.3: Use random initialization method to generate initial step vector for dragonfly individuals in the initial population.

[0140] Step 3.1.4: Calculate the fitness value of the dragonfly individual. If there is a dragonfly individual whose fitness value is better than the food, update the food to the dragonfly individual. If there is a dragonfly individual whose fitness value is worse than the natural enemy, update the natural enemy to the dragonfly individual.

[0141] In the dragonfly algorithm, food corresponds to the optimal solution in the historical iteration of the dragonfly population, and natural enemies correspond to the worst solution. The quality of individual dragonflies is determined by their fitness values. When a dragonfly individual with a fitness value better than that of food appears in the dragonfly population, the food is updated to the dragonfly individual. When a dragonfly individual with a fitness value worse than that of natural enemies appears in the dragonfly population, the natural enemy is updated to the dragonfly individual. Since the dragonfly algorithm in the BP neural network optimized by the improved dragonfly algorithm is used to provide high-quality initial weights and biases for the BP neural network, the fitness value of the dragonfly individual is the mean square error of the predicted output of the BP neural network corresponding to the dragonfly individual. The calculation formula for the fitness value of the dragonfly individual is:

[0142]

[0143] Where S is the number of sample data used to train the BP neural network; k = 1, 2..., K, s = 1, 2..., S; y s,k is the predicted output of the kth output layer node generated by the BP neural network corresponding to the dragonfly individual for the sth sample data; is the actual output of the kth output layer node of the BP neural network corresponding to the sth sample data. The BP neural network corresponding to the dragonfly individual mentioned above is a neural network obtained by training the sample database using the corresponding solution of the dragonfly individual as the initial weight and bias of the BP neural network. The sample database mentioned above consists of multiple groups of sample data, each of which consists of input data and output data, where the input data includes worker information, reference part grade, auxiliary material grade, and key part grade, and the output data is the actual completion time.

[0144] Step 3.1.5: Determine whether the maximum number of iterations has been reached. If so, proceed to step 3.1.8; if not, proceed to step 3.1.6.

[0145] Determine whether the improved dragonfly algorithm has reached the maximum number of iterations. If so, proceed to step 3.1.8 and output the food corresponding solution as the initial weight and bias of the BP neural network. If not, proceed to step 3.1.6 and update the neighborhood radius for the dragonfly individual.

[0146] Step 3.1.6: Update the neighborhood radius for each dragonfly according to the neighborhood radius update mechanism.

[0147] In the dragonfly algorithm, the neighborhood radius determines the number of adjacent individuals of a dragonfly individual, which affects the position and step vector of the next step of the dragonfly individual. The improved dragonfly algorithm optimizes the BP neural network and introduces a neighborhood radius reward and punishment mechanism when calculating the neighborhood radius of the dragonfly individual.

[0148] The neighborhood radius reward and punishment mechanism is to update the neighborhood radius of dragonflies according to their fitness values ​​in the population. The update formula of the neighborhood radius of the jth dimension of the i-th dragonfly in the population is as follows:

[0149]

[0150] In the formula, E i is the fitness value of the i-th dragonfly individual in the population; E max is the maximum fitness value of all dragonfly individuals in the population; E min is the minimum fitness value of all dragonflies in the population; is the reward and punishment coefficient, which is 0.5; R j is the basic neighborhood radius of the jth dimension of the dragonfly individual, and the calculation formula is as follows:

[0151]

[0152] In the formula, iter is the current iteration number; t max is the maximum number of iterations.

[0153] Step 3.1.7: Determine whether the food has not changed for G consecutive iterations. If so, generate a new population according to the population generation mechanism and proceed to step 3.1.4; if not, update the individual dragonfly position and step vector according to the definition of the basic dragonfly algorithm and proceed to step 3.1.4.

[0154] Determine whether the food has not changed for G consecutive iterations. If so, it means that the population has fallen into a local optimal trap with a certain probability. Therefore, according to the population generation mechanism, a new population is generated to replace the original population to enter the next iteration and enter step 3.1.4. If not, update the algorithm parameters required for updating the position and step vector of the dragonfly individual in the population, calculate the five behavioral components of the dragonfly individual, update the position and step vector of the dragonfly individual, form the next generation population, and enter step 3.1.4.

[0155] In this implementation case, the population generation mechanism adopts a multi-level mutation and population initialization composite mechanism, which includes the following steps:

[0156] Step 3.1.7.1 Arrange the dragonfly individuals in the current population O in ascending order of fitness value, select dragonfly individuals in the set ratio, clone each dragonfly individual once, copy the step vector attribute of the corresponding dragonfly individual during cloning, and form a clone population A. Mutate each dragonfly individual in A five times with a probability of 0.1, keep the corresponding step vector unchanged, and arrange the dragonfly individuals after the mutation operation in ascending order of fitness value. The mutation operation is as follows:

[0157]

[0158] In the formula, is the dragonfly individual p in the t-th generation population i The j-th dimension component of is the dragonfly individual p in the t-th generation population i is the j-dimensional component after the k-th mutation; a is a {-1, 1} random number; ρ is a Cauchy random variable that conforms to C(0, 1).

[0159] In this implementation case, the ratio is set to 50% so that the population size of the clone population A is consistent with the current population O.

[0160] Step 3.1.7.2: Based on the population initialization method, generate a new population B containing DS dragonfly individuals, and arrange the dragonfly individuals in B in ascending order according to their fitness values.

[0161] Step 3.1.7.3 Select the first 0.1DS dragonfly individuals from A and B as supplementary dragonflies, select the last 0.2DS dragonfly individuals in O and replace them with supplementary dragonflies to form a new population.

[0162] Step 3.1.8: Use the food corresponding solution as the initial weight and bias of the BP neural network, use the sample database to train the BP neural network, and establish a completion time prediction model.

[0163] The method for determining key reference parts includes the following steps:

[0164] Step 3.2.1: Get the trigger station The available amount of auxiliary materials C and the process line P i and Current machining reference part b j exist Start processing time

[0165] Step 3.2.2: Determine the key reference part b j+x , the calculation formula of x is:

[0166]

[0167] In the formula, b is the workstation The consumption of auxiliary materials for a single processing, t0 is the current moment, The reference part b j Arrival at workstation moment, The reference part b j At the workstation The predicted completion time, C max is the maximum auxiliary material inventory in the auxiliary material buffer area of ​​the workstation, C min It is the minimum auxiliary material inventory in the auxiliary material buffer area of ​​the workstation.

[0168] It should be noted that the calculation formulas for x for the start time prediction and end time prediction of the optimal delivery time period for auxiliary material distribution tasks are different.

[0169] Step 3.2.3: Initialize variables k←1, w←0, z←0, y←0.

[0170] Step 3.2.4: Determine the workstation Whether it exists, that is, whether rk is greater than 0, if so, z←1, go to step 3.2.5; if not, w←1, go to step 3.2.6.

[0171] Step 3.2.5: Get a workstation Current machining reference part b j′ , compare j′ and j+x, if they are equal, y←1, output k, w, z, y, and the algorithm ends; if j′>j+x, y←2, output k, w, z, y, and the algorithm ends; if j′<j+x, k←k+1, go to step 3.2.4.

[0172] Step 3.2.6: Output k, w, z, y. When y = 0, obtain the key reference part b according to the production plan. j+x The planned production time t p , that is, b j+x The planned start time of the first process.

[0173] By calling the key reference part determination method, the values ​​of variables k, w, z, and y are obtained. z is used to determine whether the triggering station is the first station of the assembly line. z = 0 indicates the triggering station The first station of the assembly line, z = 1 indicates the triggering station It is not the first station of the assembly line. y is used to determine the key reference part b j+x The location of y = 0 represents the key reference part b j+x It has not yet entered the assembly line and is in the production scheduling state; y=1 indicates that the key reference part b j+x At work Assembly; y = 2 represents the key reference part b j+x Already at work Completed assembly but not yet reached the workstation w is used to judge the key reference part b j+x Whether it is in the production scheduling state, w=0 means the key reference part b j+x Has entered the assembly line; w=1 indicates the key reference part b j+x In production scheduling status.

[0174] The auxiliary material demand forecasting method comprises the following steps:

[0175] Step 4.1: Determine whether the available amount of auxiliary material C at the triggering station is greater than C max -Δ, if yes, go to step 4.2; if no, go to step 4.3;

[0176] Step 4.2: Generate a supplementary material delivery task, end the call of this supplementary material demand forecasting method, and the starting time T of the optimal delivery time period of the supplementary material delivery task B With the deadline T E The calculation formulas are as follows:

[0177]

[0178] In the formula, t m,m+1 To remove the reference part from the workstation Transport to The handling time of the production line is 2000 hours; T is the production cycle of the production line; x is obtained by the key reference part determination method; t 0p As the reference time, the calculation formula is:

[0179]

[0180] Where y is obtained by the key reference part determination method.

[0181] Step 4.3: Determine whether the available amount of auxiliary material C at the triggering station is greater than C min If yes, go to step 4.4; if no, go to step 4.5;

[0182] Step 4.4: Generate N task auxiliary material distribution tasks, ending the auxiliary material demand forecasting method call, N task The calculation formula is as follows:

[0183]

[0184] The starting time T of the optimal delivery time period for the qth auxiliary material distribution task generated B With the deadline T E The calculation formulas are as follows:

[0185] T B =t0 (18)

[0186]

[0187] Where q = 1, 2, ... N task .

[0188] Step 4.5: Generate N′ task The starting time T of the best delivery time period B With the deadline T E All of them are auxiliary material distribution tasks of t0, ending the auxiliary material demand forecasting method call, N′ task The calculation formula is as follows:

[0189]

[0190] The method for forecasting demand for key parts includes the following steps:

[0191] Step 5.1: Calculate the current workstation Assembly reference part b j Arrive at the next workstation The calculation formula is as follows:

[0192]

[0193] Step 5.2: Calculate the workstation The best delivery time period for important and important items is calculated as follows:

[0194]

[0195] In the formula, Δtm The allowable error in the prediction time is determined according to the actual application requirements.

[0196] The above description is only a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several improvements without departing from the principle of the present invention, and these improvements should also be regarded as within the protection scope of the present invention.

Claims

1. A method for predicting material demand in an assembly workshop, characterized in that: The following steps are involved: Step 1: Determine whether the auxiliary material demand forecast trigger condition or the critical component demand forecast trigger condition is met. If the auxiliary material demand forecast trigger condition is met, proceed to step 2. If the critical component demand forecast trigger condition is met, proceed to step 5. If neither is met, proceed to step 1. Step 2: Determine whether it is a cycle trigger. If so, set all workstations as trigger workstations. If not, set the available quantity C of auxiliary materials to be lower than the minimum inventory quantity C. min The workstation is set as the trigger workstation; Step 3: According to the key reference part determination method and the workstation completion time consumption prediction algorithm, determine the key reference part corresponding to the triggering workstation and the workstation where the key reference part is currently located; the workstation completion time consumption prediction algorithm is specifically as follows: Reference piece b j On process line P i The rth station S Pi,r The estimated time to completion is: t bj,Pi,r =f Pi,r (p,C B ,C A1 ,...,C A n,...,C AN ,C K1 ,...,C KL ,...,C KL ) (2) In the formula, For workstation Completion time prediction model, p, C B , C An , C Kt They are the worker information of this assembly, the grade of the reference part, the grade of the nth auxiliary material and the grade of the lth key part, N is the number of auxiliary materials required for assembly at the workstation, and L is the number of key parts required for assembly at the workstation; The completion time prediction model is a BP neural network optimized by an improved dragonfly algorithm, and its establishment includes the following steps: Step 3.1.1: Determine the total number of hidden layers U and the number of nodes n in the uth hidden layer of the BP neural network h,u , the number of nodes in the input layer I and the number of nodes in the output layer K; Step 3.1.2: Determine the dragonfly population size DS and the maximum number of iterations t max and the dimension D of individual dragonflies; Step 3.1.3: Generate the initial population of the dragonfly algorithm according to the population initialization method; Step 3.1.4: Calculate the fitness value of the dragonfly individual. If there is a dragonfly individual whose fitness value is better than the food, update the food to the dragonfly individual. If there is a dragonfly individual whose fitness value is worse than the natural enemy, update the natural enemy to the dragonfly individual. Step 3.1.5: Determine whether the maximum number of iterations has been reached. If so, proceed to step 3.1.

8. If not, proceed to step 3.1.

6. Step 3.1.6: Update the neighborhood radius for the dragonfly individual according to the neighborhood radius update mechanism; Step 3.1.7: Determine whether the food has not changed for G consecutive iterations. If so, generate a new population according to the population generation mechanism and proceed to step 3.1.

4. If not, update the individual dragonfly position and step vector according to the basic dragonfly algorithm definition and proceed to step 3.1.

4. Step 3.1.8: Use the food corresponding solution as the initial weight and bias of the BP neural network, use the sample database to train the BP neural network, and establish a completion time prediction model, where the sample database consists of multiple groups of sample data, each group of sample data consists of input data and output data, where the input data includes worker information, reference part grade, auxiliary material grade, and key part grade, and the output data is the actual completion time; Step 4: According to the auxiliary material demand prediction method, the workstation completion time prediction algorithm, the corresponding key reference part of the triggering workstation and the workstation where the key reference part is currently located, determine the number of auxiliary material distribution tasks that need to be generated by the triggering workstation and the optimal delivery time period; Step 5: According to the method for predicting the demand for important parts and the time-consuming prediction algorithm for completing the workstation, determine and update the optimal delivery time period for the important parts distribution tasks of subsequent workstations.

2. The material demand forecasting method for an assembly shop according to claim 1, characterized in that: The auxiliary material demand forecast triggering conditions include cycle triggering and minimum inventory triggering, wherein the minimum inventory triggering is the workstation where the auxiliary material available quantity is lower than the minimum inventory quantity. The auxiliary material available quantity calculation formula is as follows: C=C r +c'*Δ (1) In the formula, C r is the actual remaining amount of auxiliary materials in the auxiliary material buffer area of ​​the workstation, c′ is the number of auxiliary material delivery tasks to be delivered to the workstation, and Δ is the auxiliary material replenishment amount for a single delivery task; The key reference part is to make the available margin C of the auxiliary material at the triggering station reach C max -Δ or C min The reference part, where C max It is the maximum inventory quantity of the auxiliary material buffer area of ​​the workstation.

3. A method for predicting material demand in an assembly shop according to claim 1, characterized in that: The neighborhood radius update mechanism is a neighborhood radius reward and punishment mechanism, which updates the neighborhood radius of dragonflies according to the fitness values ​​of dragonflies in the population. The neighborhood radius update formula of the j-th dimension of the i-th dragonfly in the population is as follows: In the formula, E i is the fitness value of the i-th dragonfly in the population, E max is the maximum fitness value of all dragonflies in the population, E min is the minimum fitness value of all dragonflies in the population, is the reward and punishment coefficient, R j is the basic neighborhood radius of the jth dimension of the dragonfly individual, and the calculation formula is as follows: In the formula, iter is the current iteration number, t max is the maximum number of iterations.

4. A method for predicting material demand in an assembly shop according to claim 3, characterized in that: The population generation mechanism is a composite mechanism of multi-level mutation and population initialization, including the following steps: Step 3.1.7.1 Arrange the dragonfly individuals in the current population O in ascending order of fitness value, select dragonfly individuals in the set ratio, clone each dragonfly individual once, copy the step vector attribute of the corresponding dragonfly individual during cloning, and form a clone population A. Mutate each dragonfly individual in A several times with a set probability, keep the corresponding step vector unchanged, and arrange the dragonfly individuals after the mutation operation in ascending order of fitness value. The mutation operation is as follows: In the formula, is the dragonfly individual p in the tth generation population i The j-th dimension component of is the dragonfly individual p in the tth generation population i The j-th dimension component after the k-th mutation of , a is a {-1, 1} random number; ρ is a Cauchy random variable that conforms to C(0, 1); Step 3.1.7.2 Based on the population initialization method, generate a new population B containing DS dragonflies, and arrange the dragonflies in B in ascending order according to fitness value; Step 3.1.7.3 Select the first 0.1DS dragonflies from A and B as supplementary dragonflies, select the last 0.2DS dragonflies from O and replace them with the supplementary dragonflies to form a new population.

5. The method for predicting material demand in an assembly shop according to claim 2, characterized in that: The key reference part determination method comprises the following steps: Step 3.2.1: Get the trigger station The available amount of auxiliary materials C and the process line P i and Current machining reference part b j exist Start processing time Step 3.2.2: Determine the key reference part b j+x , the calculation formula of x is: In the formula, Δ is the auxiliary material replenishment for a single delivery task, and b is the workstation The consumption of auxiliary materials for a single processing, t0 is the current moment, The reference piece b j Arrival at workstation moment, The reference piece b j At the workstation The predicted completion time, C max is the maximum auxiliary material inventory in the auxiliary material buffer area of ​​the workstation, C min The minimum auxiliary material inventory in the auxiliary material buffer area of ​​the workstation; Step 3.2.3: Initialize variables k←1, w←0, z←0, y←0; Step 3.2.4: Determine the workstation Whether it exists, that is, whether rk is greater than 0, if so, z←1, go to step 3.2.5, if not, w←1, go to step 3.2.6; Step 3.2.5: Obtain the work station Current machining reference part b j′ , compare j′ with j + x, if they are equal, y ← 1, output k, w, z, y, and the algorithm ends; if j′ > j + x, y ← 2, output k, w, z, y, and the algorithm ends; if j′ < j + x, k ← k + 1, and proceed to Step 3.2.4; Step 3.2.6: Output k, w, z, y. When y = 0, obtain the key reference part b according to the production plan. j+x The planned production time t p , that is, b j+x The planned start time of the first process.

6. A method for predicting material demand in an assembly shop according to claim 5, characterized in that: The auxiliary material demand forecasting method comprises the following steps: Step 4.1: Determine whether the available amount of auxiliary material C at the triggering station is greater than C max -Δ, if yes, go to step 4.2, if no, go to step 4.3; Step 4.2: Generate a supplementary material delivery task, end the call of this supplementary material demand forecasting method, and the starting time T of the optimal delivery time period of the supplementary material delivery task B With the deadline T E The calculation formulas are as follows: In the formula, t m,m+1 To remove the reference part from the work station Transport to The handling time is T, the production cycle of the production line, x is obtained by the key reference part determination method, t 0p As the reference time, the calculation formula is: In the formula, y is obtained by the key reference part determination method; Step 4.3: Determine whether the available amount of auxiliary material C at the triggering station is greater than C min If yes, go to step 4.4; if no, go to step 4.5; Step 4.4: Generate N task auxiliary material distribution tasks, ending the auxiliary material demand forecasting method call, N task The calculation formula is as follows: The starting time T of the optimal delivery time period for the qth auxiliary material distribution task generated B With the deadline T E The calculation formulas are as follows: T B =t0 (18) Where q = 1, 2, ... N task ; Step 4.5: Generate N′ task The starting time T of the best delivery time period B With the deadline T E All of them are auxiliary material distribution tasks of t0, ending the auxiliary material demand forecasting method call, N′ task The calculation formula is as follows:

7. The method for predicting material demand in an assembly shop according to claim 5, characterized in that: The method for predicting demand for critical parts comprises the following steps: Step 5.1: Calculate the current workstation Assembly reference part b j Arrive at the next workstation The calculation formula is as follows: Step 5.2: Calculate the workstation The best delivery time period for important and important items is calculated as follows: In the formula, Δt m The allowable error in the prediction time is determined according to the actual application requirements.

Citation Information

Patent Citations

  • Method for optimizing passing sequence of intersections of multi-carrying-capacity automatic guided vehicles

    CN111653098A

  • Material management system based on cloud computing

    CN112053082A