By using a combination of base plate extension, sealant, waterproof carcass reinforcement and paint layer at the connection between the keel wall and the masonry wall, the problem of water seepage and cracking at the connection is solved, achieving higher waterproofing effect and construction Convenience increases the use area of the bathroom.
Patent Information
- Application Number
- CN202111119705.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-09-24
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-09-24
AI Technical Summary
The connection between the keel wall and the masonry wall is prone to cracking and water seepage. The existing technology mainly uses plastering to prevent these problems.
At the connection between the keel wall and the masonry wall, the extension section of the base plate is designed to be inserted into a groove and filled with sealant. Waterproof carcass reinforcing materials, steel wire mesh and paint layers are used at the connection for waterproofing treatment, and finally facing bricks are laid to enhance the waterproofing effect.
It effectively prevents water seepage and cracking at the connection, improves the overall waterproof performance, simplifies the construction process, and increases the use area of the bathroom.
Smart Images

Figure CN113718994B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building construction, and in particular to a keel wall and masonry wall connection structure and method. Background Art
[0002] In renovation projects, in order to reduce the load, the newly added walls of the bathroom often use keel walls in the form of a combination of keels and panels. When the bathroom area is limited, in order to increase the usable area of the bathroom and reduce the wall thickness, the partition wall often uses a thinner keel wall. The connection between the keel wall and the masonry wall is often prone to cracking and even water seepage. In the prior art, the connection between the keel wall and the masonry wall is often only treated with plastering. When the keel wall is hit or deformed, the connection often cracks. Summary of the invention
[0003] The invention provides a structure and method for connecting a keel wall and a masonry wall, which solves the technical problem of cracks and water seepage easily occurring at the connection between a partition wall and a masonry wall in the prior art.
[0004] In the first aspect, the present invention discloses a connection structure between a keel wall and a masonry wall, comprising: the keel wall comprises a keel frame fixed to the surface of the masonry wall and two base plates respectively attached and fixed to two side surfaces of the keel frame, at least one side of the two base plates extends out of the keel frame to form an extension section, and two grooves for inserting the extension sections are opened on the masonry wall, and both grooves are filled with sealant.
[0005] The connection structure of the keel wall and the masonry wall of the present invention is further improved in that a waterproof carcass reinforcement material is fixed at the intersection of the base plate and the side of the masonry wall that needs waterproofing, and a coating layer is coated on the surface of the waterproof carcass reinforcement material, the surface of the masonry wall and the surface of the base plate.
[0006] The connection structure of the keel wall and the masonry wall of the present invention is further improved in that a steel mesh is fixed on the surface of the masonry wall and the base plate on the side requiring waterproofing, the steel mesh is coated with mortar, and the surface of the mortar is coated with a coating layer.
[0007] The connection structure of the keel wall and the masonry wall of the present invention is further improved in that facing bricks are fixed on the surface of the coating layer.
[0008] In a second aspect, the present invention further provides a method for connecting a stud wall and a masonry wall, comprising the following steps:
[0009] A keel frame for fixing the keel wall on the masonry;
[0010] Two grooves are respectively provided on the masonry wall at positions corresponding to the installation positions of the two base plates;
[0011] Two base plates are respectively attached and fixed to the two side surfaces of the keel frame, and the two base plates are extended out of the keel frame to form an extension section;
[0012] Inserting the extension sections into the two grooves respectively;
[0013] Fill the two grooves with sealant.
[0014] The connection structure between the keel wall and the masonry wall of the present invention is further improved in that:
[0015] After filling the two grooves with sealant, a waterproof carcass reinforcement material is fixed at the intersection of the base plate and the side of the masonry wall that needs waterproofing;
[0016] A coating layer is applied to the waterproof carcass reinforcement material, the surface of the masonry wall and the surface of the base plate.
[0017] The connection structure between the keel wall and the masonry wall of the present invention is further improved in that:
[0018] After filling the two grooves with sealant, a steel mesh is fixed on the surface of the masonry wall and the base plate on the side to be waterproofed;
[0019] Applying mortar on the steel wire mesh;
[0020] A coating layer is applied on the surface of the mortar.
[0021] The connection structure of the keel wall and the masonry wall of the present invention is further improved in that, after the coating layer is constructed, the tiles are fixed on the surface of the coating layer.
[0022] Compared with the prior art, the present invention has a positive and obvious effect. The present invention forms a whole with the masonry wall by making grooves on the masonry wall, inserting the base plate into the grooves, and performing waterproofing, thereby solving the technical problem of cracking and water seepage at the connection between the partition wall and the masonry wall in the prior art. The guide wall structure of the present invention is simple, the construction is convenient and quick, the wall is thin, and the use area of the bathroom is increased. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 This is a schematic diagram of the node structure of the connection structure between the keel wall and the masonry wall according to the first embodiment of the present invention.
[0024] Figure 2 for Figure 1 Enlarged view of point A in the middle.
[0025] Figure 3 This is a schematic diagram of the node structure of the connection structure between the keel wall and the masonry wall according to the second embodiment of the present invention. DETAILED DESCRIPTION
[0026] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0027] like Figure 1 , Figure 2 and Figure 3 As shown, the keel wall and masonry wall connection structure of the present invention, the keel wall includes a keel frame fixed to the surface of the masonry wall 4 and two base plates 3 respectively attached and fixed to the two side surfaces of the keel frame, at least one side of the two base plates 3 extends out of the keel frame to form an extension section, and the masonry wall 4 is provided with two grooves 5 for inserting the extension sections, and the two grooves 5 are filled with sealant 7.
[0028] The keel frame adopts horizontal keels 2 and vertical keels 1 fixed vertically and horizontally, and the keel frame is used to improve the strength of the keel wall. The base plate 3 is connected to the masonry wall 4 in an inserting manner, so that the path of water seepage becomes longer and curved, thereby having a certain waterproof effect, and the connection is further waterproofed with a waterproof layer, thereby further improving the waterproof effect. Base plates 3 are set on both sides of the keel frame, so as to seal the keel frame from being exposed for a long time and corroded and damaged, and further improve the waterproof and water-proof effect of the keel wall.
[0029] Preferably, Figure 3 As shown, a waterproof carcass reinforcement material 8 is fixed at the intersection of the base plate 3 and the side of the masonry wall 4 that needs waterproofing, and a coating layer 9 is coated on the surface of the waterproof carcass reinforcement material 8, the surface of the masonry wall 4 and the surface of the base plate 3.
[0030] In the first embodiment, the base plate 3 is made of a porcelain plate, and the waterproof carcass reinforcement material 8 has a higher bonding degree with the porcelain plate, and can fit tightly with the porcelain plate to improve the waterproof effect.
[0031] Preferably, Figure 2 As shown, a steel mesh 12 is fixed to the surface of the masonry wall 4 and the base plate 3 on the side that needs waterproofing, and a mortar 13 is coated on the steel mesh 12 , and a coating layer 9 is coated on the surface of the mortar 13 .
[0032] In the second embodiment, the base plate 3 is made of fiber cement board, and the waterproof effect is improved by combining the steel mesh 12 and the mortar 13. The fiber cement board, the steel mesh 12 and the mortar 13 are more tightly bonded.
[0033] Preferably, Figure 1 and Figure 3 As shown, tiles 11 are fixed on the surface of the coating layer 9 .
[0034] The facing bricks 11 have a certain waterproof effect and a decorative effect, and connect the masonry wall 4 and the keel wall into a whole.
[0035] The present invention also provides a method for connecting a keel wall and a masonry wall, comprising the following steps:
[0036] A keel frame for fixing the keel wall on the masonry;
[0037] Two grooves 5 are respectively provided on the masonry wall 4 at positions corresponding to the installation positions of the two base plates 3;
[0038] Two base plates 3 are respectively attached and fixed to the two side surfaces of the keel frame, and the two base plates 3 are extended out of the keel frame to form an extension section;
[0039] Insert the extension sections into the two grooves 5 respectively;
[0040] The two grooves 5 are filled with sealant 7 .
[0041] The keel frame is a combination of a vertical keel 1 and a horizontal keel 2. The top and bottom of the vertical keel 1 are respectively connected to the bottom of the upper floor and the concrete guide wall on the current floor. The horizontal keel 2 is welded and fixed to the vertical keel 1. Furthermore, a special adhesive 6 is used to bond the extension section to the groove 5, and the gap of the groove 5 is filled with a sealant 7 to seal it, so as to ensure that the extension section is tightly connected to the groove 5 to avoid water seepage and to prevent cracks at the connection between the masonry wall 4 and the keel wall when the keel wall is hit or deformed.
[0042] Preferably, Figure 1 and Figure 2 As shown, after the sealant 7 is filled in the two grooves 5, a waterproof carcass reinforcement material 8 is fixed at the intersection of the base plate 3 and the side of the masonry wall 4 that needs waterproofing;
[0043] A coating layer 9 is coated on the waterproof carcass reinforcement material 8 , the surface of the masonry wall 4 and the surface of the base plate 3 .
[0044] A waterproof carcass reinforcement material 8 is fixed at the inner corner where the keel wall and the masonry wall 4 meet, and the waterproof carcass reinforcement material 8 is made to fit tightly against the surface of the base plate 3 and the masonry wall 4, and then a coating layer 9 is applied on the outside of the masonry wall 4 and the base plate 3, and the coating layer 9 is a waterproof coating.
[0045] Preferably, Figure 3 As shown, after the sealant 7 is filled in the two grooves 5, a steel mesh 12 is fixed on the surface of the masonry wall 4 and the base plate 3 on the side that needs waterproofing;
[0046] Applying mortar 13 on the steel wire mesh 12;
[0047] A coating layer 9 is coated on the surface of the mortar 13 .
[0048] When the base plate 3 is made of fiber cement board, a steel mesh 12 is set outside the base plate 3 and the masonry wall 4, and then mortar 13 is applied on the wall surface and the steel mesh 12, and waterproof material is applied outside the mortar 13. The adhesion between the fiber cement board and the mortar 13 is higher, so that the masonry wall 4 and the base plate 3 are connected as a whole, which is conducive to the subsequent setting of the waterproof layer.
[0049] Preferably, after the coating layer 9 is constructed, tiles 11 are fixed on the surface of the coating layer 9 .
[0050] The outer surface of the coating layer 9 is bonded to the bricks 11 on the masonry wall and the keel wall base plate 3 by the adhesive 10, so as to further improve the waterproof performance.
[0051] The present invention forms a whole with the keel wall and the masonry wall 4 by slotting the masonry wall 4, inserting the base plate 3 into the slot, and performing waterproof treatment, thereby solving the technical problem of cracking and water seepage at the connection between the partition wall and the masonry wall 4 in the prior art. The guide wall structure of the present invention is simple, the construction is convenient and fast, the wall is thin, and the use area of the bathroom is increased.
[0052] The above is only a preferred embodiment of the present invention, and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technician familiar with this profession can make some changes or modifications to equivalent embodiments of equivalent changes using the technical contents disclosed above without departing from the scope of the technical solution of the present invention. However, any simple modification, equivalent change and modification made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still fall within the scope of the technical solution of the present invention.
Claims
1. A keel wall and masonry wall connection structure, characterized in that: The keel wall includes a keel frame fixed on the surface of the masonry wall and two base plates respectively attached and fixed on both sides of the keel frame, at least one side of the two base plates extends out of the keel frame to form an extension section, and two grooves for inserting the extension sections are opened on the masonry wall, and both grooves are filled with sealant; a waterproof carcass reinforcement material is fixed at the intersection of the base plate and the side of the masonry wall that needs waterproofing, and a coating layer is coated on the surface of the waterproof carcass reinforcement material, the surface of the masonry wall and the surface of the base plate; a steel mesh is fixed on the surface of the masonry wall and the side of the base plate that needs waterproofing, and mortar is coated on the steel mesh, and a coating layer is coated on the surface of the mortar; facing bricks are fixed on the surface of the coating layer.
2. A method for connecting a keel wall and a masonry wall, characterized in that: The steps include: Fix the keel frame of the keel wall on the masonry wall; Two grooves are respectively provided on the masonry wall at positions corresponding to the installation positions of the two base plates; Two base plates are respectively attached and fixed to the two side surfaces of the keel frame, and the two base plates are extended out of the keel frame to form an extension section; Inserting the extension sections into the two grooves respectively; Filling the two grooves with sealant; After the two grooves are filled with sealant, a waterproof carcass reinforcement material is fixed at the intersection of the base plate and the side of the masonry wall that needs waterproofing; a coating layer is applied to the surface of the waterproof carcass reinforcement material, the masonry wall and the base plate; After the two grooves are filled with sealant, a steel mesh is fixed on the surface of the masonry wall and the surface of the base plate on the side to be waterproofed; mortar is applied on the steel mesh; and a coating layer is applied on the surface of the mortar; After the coating layer is constructed, tiles are fixed on the surface of the coating layer.
Citation Information
Patent Citations
Keel wall and masonry wall connecting structure
CN216920808U