A method and device for interactive operation status information of electric power secondary equipment
Through message detection and processing between the power secondary monitoring system and the professional subsystem master station, real-time data synchronization and two-way interaction from the safety zone I to the safety zone II are realized, solving the problem of non-real-time and non-real-time data transmission in the existing technology. The problem of one-way transmission ensures unified transmission and real-time synchronization of data from multiple types of devices.
Patent Information
- Application Number
- CN202111192472.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-10-13
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing technology cannot realize real-time data transmission and synchronization from security zone I to security zone II, cannot guarantee real-time synchronization of data status of security control, protection, and automation equipment, and only achieves one-way data transmission and cannot achieve two-way data interaction.
By realizing real-time detection and processing of telemetry and remote signaling messages between the secondary monitoring system and the secondary professional subsystem master station, change messages are sent according to preset limits, and measurement values and remote signaling values are returned under specified parameters. , realizing two-way interaction and real-time synchronization of data.
It realizes real-time data synchronization from security zone I to security zone II, ensures the unified transmission of data status of security control, protection, and automation equipment, solves the problem that different types of data cannot be synchronized uniformly, and realizes two-way interaction of data.
Smart Images

Figure CN113972736B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method and a device for interacting with operating status information of electric power secondary equipment, belonging to the technical field of electric power equipment. Background Art
[0002] The secondary monitoring system mainly realizes real-time monitoring, comprehensive alarm, risk warning and global comprehensive analysis of the secondary system through unified modeling of secondary equipment, data collection and exchange, and real-time data processing. The service end of the secondary monitoring system is deployed in the safety zone II of the main station, and the collection end is a convergence server (edge node) deployed in the safety zone I, which is used to aggregate the operating status information of various secondary equipment in this safety zone, and obtain real-time data such as telemetry and telesignaling from the main station of the secondary professional subsystem (such as automation, security, security control, network security, etc.) through the message / service bus.
[0003] Since the real-time data transmission from safety zone I to safety zone II needs to pass through the forward isolation device, there is currently no mature technology to achieve the transmission and synchronization of real-time data from safety zone I to safety zone II and ensure the real-time status of the data. The detailed problem description is as follows:
[0004] First, current technology cannot guarantee the real-time data synchronization. The current transmission from Security Zone I to Security Zone II is basically minute-level transmission, while the secondary monitoring system needs to achieve data status synchronization in seconds.
[0005] Second, since the operating status of the original security, protection, and automation equipment did not define the same data status transmission protocol and standards, the original technology could not guarantee the real-time synchronization of the three major types of data, security, protection, and automation, from Security Zone I to Security Zone II.
[0006] Third, current technology is not only capable of one-way data transmission from Security Zone I to Security Zone II, but also cannot achieve two-way data interaction. This technology combines the reverse file transfer protocol from Security Zone II to Security Zone I to achieve two-way data interaction.
[0007] The operating status information of the secondary equipment in safety zone I needs to be synchronized to the server of the secondary monitoring system in safety zone II in a timely manner. According to the changing characteristics of the secondary equipment status data, the types of data interaction are divided into five types, namely: telemetry over-limit / update upload, telesignal change / update upload, read telesignal, read telemetry, call for full data and other functions. Summary of the invention
[0008] The purpose of the present invention is to overcome the deficiencies in the prior art and to provide a method and device for exchanging operating status information of secondary power equipment to solve the above problems.
[0009] To achieve the above object, the present invention is implemented by adopting the following technical solutions:
[0010] In a first aspect, the present invention provides a method for exchanging operating status information of electric secondary equipment, which is applied to a secondary professional subsystem master station, comprising:
[0011] According to the preset limit value, check whether there is any telemetry exceeding the limit. If there is any telemetry exceeding the limit, or the timed update, send the change telemetry message to the secondary monitoring system master station;
[0012] Check and determine whether the telesignal value has changed. When the telesignal value changes, or is updated regularly, send the telesignal message to the secondary monitoring system master station;
[0013] Among them, the secondary monitoring system master station is used to receive and process telemetry messages and telesignaling messages;
[0014] Receive the data value read request sent by the secondary monitoring system master station and return the measured value according to the specified parameters.
[0015] Furthermore, the data value includes a telemetry value, a telesignaling value and a full data value.
[0016] Furthermore, the full data value includes all telemetry and telesignal frame data messages.
[0017] Furthermore, when the secondary monitoring system master station sends a request to read the telemetry value and the telesignaling value, the full path name of the measurement in Chinese is given in the parameter.
[0018] In a second aspect, the present invention provides a method for interacting with operating status information of a power secondary device, which is applied to a secondary monitoring system master station, comprising:
[0019] Receive and process telemetry messages and telesignaling messages sent by the secondary professional subsystem master station;
[0020] Send a request to read data value to the secondary professional subsystem master station;
[0021] Among them, the secondary professional subsystem master station is used to check whether there is any telemetry exceeding the limit according to the pre-set limit value. If there is any telemetry exceeding the limit, or it is updated regularly, it will send a telemetry change message to the secondary monitoring system master station; check and determine whether the telesignal value has changed. When the telesignal value changes, or it is updated regularly, it will send a telesignal message to the secondary monitoring system master station; receive the data value reading request sent by the secondary monitoring system master station, and return the measurement value according to the specified parameters.
[0022] Furthermore, the data value includes a telemetry value, a telesignaling value and a full data value.
[0023] Furthermore, the full data value includes all telemetry and telesignal frame data messages.
[0024] Furthermore, when the secondary monitoring system master station sends a request to read the telemetry value and the telesignaling value, the full path name of the measurement in Chinese is given in the parameter.
[0025] In a third aspect, the present invention provides a device for interacting with operating status information of electric secondary equipment, which is applied to a secondary professional subsystem master station, comprising:
[0026] The telemetry over-limit detection unit is used to check whether there is a telemetry over-limit according to the preset limit value. If there is a telemetry over-limit, or a regular update, a change telemetry message is sent to the secondary monitoring system master station;
[0027] The telesignal value checking unit checks and determines whether the telesignal value has changed. When the telesignal value has changed, or is updated regularly, a telesignal message is sent to the secondary monitoring system master station; wherein the secondary monitoring system master station is used to receive and process telemetering messages and telesignal messages;
[0028] The data value reading request receiving unit is used to receive the data value reading request sent by the secondary monitoring system master station and return the measured value according to the specified parameters.
[0029] In a fourth aspect, the present invention provides a device for interacting with operating status information of a power secondary device, which is applied to a master station of a secondary monitoring system, comprising:
[0030] The receiving unit receives and processes the telemetry messages and telesignaling messages sent by the master station of the secondary professional subsystem;
[0031] A data value request sending unit sends a data value reading request to a secondary professional subsystem master station;
[0032] Among them, the secondary professional subsystem master station is used to check whether there is any telemetry exceeding the limit according to the pre-set limit value. If there is any telemetry exceeding the limit, or it is updated regularly, it will send a telemetry change message to the secondary monitoring system master station; check and determine whether the telesignal value has changed. When the telesignal value changes, or it is updated regularly, it will send a telesignal message to the secondary monitoring system master station; receive the data value reading request sent by the secondary monitoring system master station, and return the measurement value according to the specified parameters.
[0033] Compared with the prior art, the present invention has the following beneficial effects:
[0034] The power secondary equipment operating status information interaction device provided by the present invention, firstly, realizes the real-time synchronization of the operating status of the secondary equipment from the safety zone I to the safety zone II; secondly, realizes the standardized protocol transmission of multiple types of secondary equipment such as security control, protection, and automation, and solves the problem that different types of data cannot be synchronized uniformly. Even if new types of secondary equipment are added, the method can still be used for transmission; thirdly, realizes two-way interaction from the safety zone I to the safety zone II, and realizes the real-time request and synchronization of changed data. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 This is a schematic diagram of a change telemetry triggering and sending process provided by an embodiment of the present invention;
[0036] Figure 2 This is a schematic diagram of a change remote signal triggering and sending process provided by an embodiment of the present invention;
[0037] Figure 3 is a schematic diagram of a process for reading telemetry values provided by an embodiment of the present invention;
[0038] Figure 4 It is a schematic diagram of a remote signal value reading process provided by an embodiment of the present invention;
[0039] Figure 5 It is a schematic diagram of a flow chart of reading all data values provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0040] The present invention will be further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.
[0041] Example 1
[0042] This embodiment introduces a method for exchanging operating status information of electric secondary equipment, which is applied to a secondary professional subsystem master station, including:
[0043] According to the preset limit value, check whether there is any telemetry exceeding the limit. If there is any telemetry exceeding the limit, or the timed update, send the change telemetry message to the secondary monitoring system master station;
[0044] Check and determine whether the telesignal value has changed. When the telesignal value changes, or is updated regularly, send the telesignal message to the secondary monitoring system master station;
[0045] Among them, the secondary monitoring system master station is used to receive and process telemetry messages and telesignaling messages;
[0046] Receive the read data value request sent by the secondary monitoring system master station and return the measured value according to the specified parameters.
[0047] The application process of the method and device for exchanging operating status information of electric secondary equipment provided in this embodiment specifically involves the following steps:
[0048] Step 1: Telemetry limit crossing / update upload process
[0049] When the telemetry value exceeds the dead zone and the upper (upper) or lower (lower) limit, the telemetry data will be sent actively. The secondary professional subsystem master station should provide this function, and the secondary monitoring system master station should have the receiving and processing capabilities. Figure 1 As shown, the specific steps are as follows:
[0050] a) Check whether there is any telemetry exceeding the limit according to the set limit;
[0051] b) If there is a telemetry limit violation or a scheduled update, a change telemetry message is sent.
[0052] c) The receiving end receives and processes the message.
[0053] Step 2: Remote signal change / update upload process
[0054] When the telesignal value changes, the telesignal data will be sent automatically. The secondary professional subsystem master station should provide this function, and the secondary monitoring system master station should have the ability to receive and process. Figure 2 As shown, the specific steps are as follows:
[0055] a) Check and determine whether the remote signal value has changed;
[0056] b) When the telesignal value changes or is updated regularly, a change telesignal message is sent.
[0057] c) The receiving end receives and processes the message.
[0058] Step 3: Read telemetry value process
[0059] The client reads the specified measurement telemetry value of the server. This process is initiated by the secondary monitoring system master station. The process is as follows Figure 3 The specific steps are as follows:
[0060] a) The secondary monitoring system master station sends a request to read the telemetry value, and the full path name of the measurement in Chinese is given in the parameter;
[0061] b) The secondary professional subsystem master station receives the request and returns the measurement value according to the specified parameters.
[0062] c) The receiving end receives and processes the message.
[0063] Step 4: Read remote signal value process
[0064] The client reads the specified measurement telemetering value of the server. This process is initiated by the secondary monitoring system master station. The process is as follows Figure 4 The specific steps are as follows:
[0065] a) The secondary monitoring system master station sends a request to read the telesignal value, and the full path name of the measurement in Chinese is given in the parameter;
[0066] b) The secondary professional subsystem master station receives the request and returns the measurement value according to the specified parameters.
[0067] c) The receiving end receives and processes the message.
[0068] Step 5: Read all data values
[0069] The client reads all data values of the server in units of devices (IED) or components (LD). This process is initiated by the secondary monitoring system master station. Figure 5 The specific steps are as follows:
[0070] a) The secondary monitoring system master station sends a request to obtain full data when the system is initialized or during system operation;
[0071] b) The secondary professional subsystem master station receives the request and returns the full telemetry and full telesignaling frame data messages in sequence according to the specified parameters (IED or LD Chinese full path name); the end frame identification parameter is set to 1 in the last frame message, and the identification is 0 for other frames.
[0072] c) The receiving end receives and processes the message.
[0073] Example 2
[0074] This embodiment provides a method for exchanging operating status information of a power secondary device, which is applied to a secondary monitoring system master station, and includes:
[0075] Receive and process telemetry messages and telesignaling messages sent by the secondary professional subsystem master station;
[0076] Send a request to read data value to the secondary professional subsystem master station;
[0077] Among them, the secondary professional subsystem master station is used to check whether there is any telemetry exceeding the limit according to the pre-set limit value. If there is any telemetry exceeding the limit, or it is updated regularly, it will send a telemetry change message to the secondary monitoring system master station; check and determine whether the telesignal value has changed. When the telesignal value changes, or it is updated regularly, it will send a telesignal message to the secondary monitoring system master station; receive the data value reading request sent by the secondary monitoring system master station, and return the measurement value according to the specified parameters.
[0078] Furthermore, the data value includes a telemetry value, a telesignaling value and a full data value.
[0079] Furthermore, the full data value includes all telemetry and telesignal frame data messages.
[0080] Furthermore, when the secondary monitoring system master station sends a request to read the telemetry value and the telesignaling value, the full path name of the measurement in Chinese is given in the parameter.
[0081] Example 3
[0082] This embodiment provides a device for interacting with operating status information of electric secondary equipment, which is applied to a secondary professional subsystem master station, including:
[0083] The telemetry over-limit detection unit is used to check whether there is a telemetry over-limit according to the preset limit value. If there is a telemetry over-limit, or a regular update, a change telemetry message is sent to the secondary monitoring system master station;
[0084] The telesignal value checking unit checks and determines whether the telesignal value has changed. When the telesignal value has changed, or is updated regularly, a telesignal message is sent to the secondary monitoring system master station; wherein the secondary monitoring system master station is used to receive and process telemetering messages and telesignal messages;
[0085] The data value reading request receiving unit is used to receive the data value reading request sent by the secondary monitoring system master station and return the measured value according to the specified parameters.
[0086] Example 4
[0087] This embodiment provides a device for interacting with operating status information of a power secondary device, which is applied to a master station of a secondary monitoring system, and includes:
[0088] The receiving unit receives and processes the telemetry messages and telesignaling messages sent by the master station of the secondary professional subsystem;
[0089] A data value request sending unit sends a data value reading request to a secondary professional subsystem master station;
[0090] Among them, the secondary professional subsystem master station is used to check whether there is any telemetry exceeding the limit according to the pre-set limit value. If there is any telemetry exceeding the limit, or it is updated regularly, it will send a telemetry change message to the secondary monitoring system master station; check and determine whether the telesignal value has changed. When the telesignal value changes, or it is updated regularly, it will send a telesignal message to the secondary monitoring system master station; receive the data value reading request sent by the secondary monitoring system master station, and return the measurement value according to the specified parameters.
[0091] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for interactive operation status information of power secondary equipment, applied to the master station of the secondary professional subsystem, characterized in that: include: According to the preset limit value, check whether there is any telemetry exceeding the limit. If there is any telemetry exceeding the limit, or the timed update, send the change telemetry message to the secondary monitoring system master station; Check and determine whether the telesignal value has changed. When the telesignal value changes, or is updated regularly, send the telesignal message to the secondary monitoring system master station; Among them, the secondary monitoring system master station is used to receive and process telemetry messages and telesignaling messages; Receive the data value reading request sent by the secondary monitoring system master station and return the measured value according to the specified parameters; The data values include telemetry values, telesignaling values and full data values; The full data value includes all telemetry and telesignal frame data messages; When the secondary monitoring system master sends a request to read telemetry and telesignaling values, the full path name of the measurement in Chinese is given in the parameter; The method specifically comprises the following steps: Step 1: Telemetry limit crossing / update upload process, the specific steps are as follows: The secondary professional subsystem master station checks whether there is a telemetry limit violation based on the set limit value; If there is a telemetry over-limit or scheduled update, the secondary professional subsystem master sends a telemetry message of the change; The secondary monitoring system master station receives and processes the message; Step 2: Remote signal change / update upload process, the specific steps are as follows: The master station of the secondary professional subsystem checks and determines whether the telesignal value has changed; When the telesignal value changes, or is updated regularly, the secondary professional subsystem master station sends a change telesignal message; The secondary monitoring system master station receives and processes the message; Step 3: Read telemetry value process. The specific steps are as follows: The secondary monitoring system master sends a request to read the telemetry value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 4: Read remote signal value process. The specific steps are as follows: The secondary monitoring system master station sends a request to read the telesignal value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 5: Read all data values. The specific steps are as follows: The secondary monitoring system master station sends a request to obtain full data when the system is initialized or during system operation; The secondary professional subsystem master station receives the request and returns the full telemetry and full telesignaling data messages in sequence according to the full path name in Chinese of IED or LD; the end frame identification parameter is set to 1 in the last frame message, and the identification is set to 0 in other frames; The receiving end receives and processes the message.
2. A method for interactive operation status information of power secondary equipment, applied to the master station of the secondary monitoring system, characterized in that: include: Receive and process telemetry messages and telesignaling messages sent by the secondary professional subsystem master station; Send a request to read data value to the secondary professional subsystem master station; Among them, the secondary professional subsystem master station is used to check whether there is a telemetry limit violation according to the preset limit value. If there is a telemetry limit violation, or it is updated regularly, it sends a telemetry change message to the secondary monitoring system master station; check and determine whether the telemetering value has changed. When the telemetering value changes, or it is updated regularly, it sends a telemetering message to the secondary monitoring system master station; receive the read data value request sent by the secondary monitoring system master station, and return the measured value according to the specified parameters; The data values include telemetry values, telesignaling values and full data values; The full data value includes all telemetry and telesignal frame data messages; When the secondary monitoring system master sends a request to read telemetry and telesignaling values, the full path name of the measurement in Chinese is given in the parameter; The method specifically comprises the following steps: Step 1: Telemetry limit crossing / update upload process, the specific steps are as follows: The secondary professional subsystem master station checks whether there is a telemetry limit violation based on the set limit value; If there is a telemetry over-limit or scheduled update, the secondary professional subsystem master sends a telemetry message of the change; The secondary monitoring system master station receives and processes the message; Step 2: Remote signal change / update upload process, the specific steps are as follows: The master station of the secondary professional subsystem checks and determines whether the telesignal value has changed; When the telesignal value changes, or is updated regularly, the secondary professional subsystem master station sends a change telesignal message; The secondary monitoring system master station receives and processes the message; Step 3: Read telemetry value process. The specific steps are as follows: The secondary monitoring system master sends a request to read the telemetry value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 4: Read remote signal value process. The specific steps are as follows: The secondary monitoring system master station sends a request to read the telesignal value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 5: Read all data values. The specific steps are as follows: The secondary monitoring system master station sends a request to obtain full data when the system is initialized or during system operation; The secondary professional subsystem master station receives the request and returns the full telemetry and full telesignaling data messages in sequence according to the full path name in Chinese of IED or LD; the end frame identification parameter is set to 1 in the last frame message, and the identification is set to 0 in other frames; The receiving end receives and processes the message.
3. A device for interactive operation status information of power secondary equipment, applied to the master station of secondary professional subsystem, characterized in that: include: The telemetry over-limit detection unit is used to check whether there is a telemetry over-limit according to the preset limit value. If there is a telemetry over-limit, or a regular update, a change telemetry message is sent to the secondary monitoring system master station; The telesignal value checking unit checks and determines whether the telesignal value has changed. When the telesignal value has changed, or is updated regularly, a telesignal message is sent to the secondary monitoring system master station; wherein the secondary monitoring system master station is used to receive and process telemetering messages and telesignal messages; The data value reading request receiving unit is used to receive the data value reading request sent by the secondary monitoring system master station, and return the measurement value according to the specified parameters, wherein the data value includes the telemetry value, the telesignaling value and the full data value; the full data value includes the full telemetry and full telesignaling frame data messages; when the secondary monitoring system master station sends the telemetry value and telesignaling value reading request, the measurement Chinese full path name is given in the parameter; When the device is running, the following steps are performed: Step 1: Telemetry limit crossing / update upload process, the specific steps are as follows: The secondary professional subsystem master station checks whether there is a telemetry limit violation based on the set limit value; If there is a telemetry over-limit or scheduled update, the secondary professional subsystem master sends a telemetry message of the change; The secondary monitoring system master station receives and processes the message; Step 2: Remote signal change / update upload process, the specific steps are as follows: The master station of the secondary professional subsystem checks and determines whether the telesignal value has changed; When the telesignal value changes, or is updated regularly, the secondary professional subsystem master station sends a change telesignal message; The secondary monitoring system master station receives and processes the message; Step 3: Read telemetry value process. The specific steps are as follows: The secondary monitoring system master sends a request to read the telemetry value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 4: Read remote signal value process. The specific steps are as follows: The secondary monitoring system master station sends a request to read the telesignal value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 5: Read all data values. The specific steps are as follows: The secondary monitoring system master station sends a request to obtain full data when the system is initialized or during system operation; The secondary professional subsystem master station receives the request and returns the full telemetry and full telesignaling data messages in sequence according to the full path name in Chinese of IED or LD; the end frame identification parameter is set to 1 in the last frame message, and the identification is set to 0 in other frames; The receiving end receives and processes the message.
4. A device for interacting with the operating status information of secondary power equipment, applied to the master station of the secondary monitoring system, characterized in that: include: The receiving unit receives and processes the telemetry messages and telesignaling messages sent by the master station of the secondary professional subsystem; A data value request sending unit sends a data value reading request to a secondary professional subsystem master station; Among them, the secondary professional subsystem master station is used to check whether there is a telemetry limit violation according to the preset limit value. If there is a telemetry limit violation, or it is updated regularly, it sends a telemetry change message to the secondary monitoring system master station; check and determine whether the telemetering value has changed. When the telemetering value changes, or it is updated regularly, it sends a telemetering message to the secondary monitoring system master station; receive the read data value request sent by the secondary monitoring system master station, and return the measured value according to the specified parameters; The data values include telemetry values, telesignaling values and full data values; The full data value includes all telemetry and telesignal frame data messages; When the secondary monitoring system master sends a request to read telemetry and telesignaling values, the full path name of the measurement in Chinese is given in the parameter; When the device is running, the following steps are performed: Step 1: Telemetry limit crossing / update upload process, the specific steps are as follows: The secondary professional subsystem master station checks whether there is a telemetry limit violation based on the set limit value; If there is a telemetry over-limit or scheduled update, the secondary professional subsystem master sends a telemetry message of the change; The secondary monitoring system master station receives and processes the message; Step 2: Remote signal change / update upload process, the specific steps are as follows: The master station of the secondary professional subsystem checks and determines whether the telesignal value has changed; When the telesignal value changes, or is updated regularly, the secondary professional subsystem master station sends a change telesignal message; The secondary monitoring system master station receives and processes the message; Step 3: Read telemetry value process. The specific steps are as follows: The secondary monitoring system master sends a request to read the telemetry value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 4: Read remote signal value process. The specific steps are as follows: The secondary monitoring system master station sends a request to read the telesignal value, and the full path name of the measurement in Chinese is given in the parameter; The secondary professional subsystem master receives the request and returns the measured value according to the specified parameters; The receiving end receives and processes the message; Step 5: Read all data values. The specific steps are as follows: The secondary monitoring system master station sends a request to obtain full data when the system is initialized or during system operation; The secondary professional subsystem master station receives the request and returns the full telemetry and full telesignaling data messages in sequence according to the full path name in Chinese of IED or LD; the end frame identification parameter is set to 1 in the last frame message, and the identification is set to 0 in other frames; The receiving end receives and processes the message.