A full-process tracking and supervision system for engineering projects
By using orthogonal hierarchical analysis method to select the optimal audit indicators and predict time nodes in the full-process tracking and supervision system of the engineering project, the problem of insufficient time intervention points and time limit management in the existing technology is solved, and effective tracking of engineering projects is achieved Supervision and timeout warning improve audit quality and efficiency.
Patent Information
- Application Number
- CN202111494420.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2020-12-18
- Filing Date
- 2021-12-08
- Publication Date
- 2024-12-31
- Estimated Expiration
- 2041-12-08
AI Technical Summary
In the existing technology, the full process tracking and supervision of engineering projects lacks clear time intervention points and project maintenance time limit management, resulting in insufficient tracking and auditing results and timely warning and intervention.
Design a full-process tracking and supervision system for engineering projects, connect with the operation and maintenance station through the portal module, including project information module, audit management module and risk warning module, use orthogonal hierarchical analysis method to select the optimal audit indicators, predict time nodes, and Time-limited maintenance is carried out based on the nature of the project to achieve timeout warning.
The time intervention points for tracking audits were clarified, the cost control in the preliminary decision-making and bidding stages were improved, the project maintenance time limit was effectively managed, timely warning and intervention measures were provided, and the audit quality and efficiency were improved.
Smart Images

Figure CN114140090B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of project management, and more specifically, to a full-process tracking and supervision system for an engineering project. Background Art
[0002] The whole process tracking and supervision of engineering projects is an activity to audit and supervise the legality, authenticity and standardization of the whole process of construction project implementation, including pre-construction audit, construction audit and post-completion audit. Pre-construction audit, construction audit and post-completion audit run through the whole process of the project. From the perspective of audit consistency and completeness, the three parts complement each other and are indispensable.
[0003] In the existing technology, the whole process tracking audit of the project can be dynamically audited by time period and content, making the audit ideas clearer and relieving the pressure of processing a large amount of data in a short time. On the other hand, the tracking audit can analyze the related factors that affect each other in the previous and subsequent stages, and can dynamically supervise the operation of each stage of the whole life cycle. In the construction stage, after the tracking audit personnel sign and approve the measured records with the construction party, the supervision party, and the construction party at the construction site, the corresponding engineering data can be calculated immediately, avoiding the evasion and the long-term non-signing and large backlog of the previous drawbacks, compressing the long traditional audit cycle in advance and digesting it in the middle stage, so that the over-concentrated amount in the past can be dispersed as evenly as possible in the construction stage, thereby speeding up the settlement audit, increasing the audit intensity, and improving the economic benefits. The tracking audit is an audit and supervision of the technical and economic activities of the construction project from the preparation to the completion acceptance. It not only emphasizes the cost control in the construction stage, but also pays attention to the tracking audit of the early decision-making work, carries out in-depth tracking audit of design quality, and actively intervenes in the tracking audit of the bidding stage, so that the audit work develops in a diversified way. Prior art 1 (CN105279614A) "Process-based business audit system and method" parses and encapsulates business system data of different protocol types into standardized data in a unified format; according to the defined rule nodes, rule clusters, processes and indicators, the rule node matching, rule cluster matching, process matching and indicator analysis of the actual business system data after standardization are completed to determine whether the content to be audited meets the standards and to make timely warnings. In prior art 1, the process-based business audit system and method abstracts the entire business audit process, so that the audit analysis of business security can be realized through a unified and scalable method, greatly reducing the cost of business security audits. Prior art 2 (CN111461644A) "An audit information management and control platform" includes an audit portal module, which is used as the audit information operation access entrance of the audit information management and control platform; an audit management domain, which is used to manage the processes of various preset audit projects; and an audit operation domain, which includes multiple types of audit operation models, wherein the various types of audit operation models are associated with the audit management domain with the core management objects in the preset audit projects as nodes. Existing technology 3 can realize the intelligent control framework of audit project process, optimize and improve the online level of audit business, focus on finding more difficult audit problems more accurately and quickly, and improve audit efficiency and effectiveness. Represented by existing technologies 1 and 2, the systematic and unified tracking and supervision management of the entire project process is realized, which fundamentally improves the service quality of audit business.
[0004] Based on the existing technologies 1 and 2, engineering construction projects generally go through investment decision-making, design, bidding, construction, completion settlement and other stages. If the tracking audit is involved in real-time tracking at different stages, the audit effect will be different. In the existing technology, there is no clear regulation on the time intervention point of the tracking audit. In theory, the earlier the audit is involved, the better. However, on the one hand, due to the lack of professional ability of auditors in evaluating whether the early decision is scientific, they cannot undertake this audit task. On the other hand, because the investors believe that the tracking audit is only to prevent the construction unit from overestimating and miscalculating during the construction stage, in the practice of tracking audit, most of them are involved in the tracking audit during the construction and completion settlement stages. Then the cost affected by the early decision-making, design and bidding stages cannot be controlled, and the effect of the tracking audit is not sufficient and obvious. For this reason, the existing technology 3 (CN111652458A) "A method for engineering audit based on blockchain technology" audits the project through the data layer to determine whether it is reasonable and effective; verifies the project through the data verification mechanism in the network layer; and calculates the time point of the project through the consensus layer to determine whether it meets the expected standard. Through blockchain technology, engineering documents can be audited. Since the blockchain system consists of a data layer, a network layer, a consensus layer, an incentive layer, a contract layer, and an application layer, the project can be audited. After that, professionals can check the process, management standards, and rules and regulations of the workpiece, so that the project can be audited comprehensively, the work efficiency can be improved, and the audit of the project is convenient. In addition, there is a lack of effective definition and unified management of the project maintenance time limit, so it is impossible to give timely warnings and intervention measures for the tracking and supervision of the entire process of the project. Therefore, the existing technology 4 (CN107833012A) "A management system for the time-limited completion of audit projects" proposes to use a database module and a system menu module to achieve scientific management of the time limit of project audit work through an auxiliary OA system. However, the existing technologies 3 and 4 are more concerned with the immutability of the time node control of the project tracking audit, requiring all parties in the project to strictly implement the working hours in a unified manner, so as to ensure the scientific management of the time limit of the project audit work; however, the control technology schemes of the various work time nodes involved in the entire process of the project are not elaborated in detail, and the handling measures for the overtime of the project audit work are not involved.
[0005] In addition, in the full-process tracking audit of engineering projects, more emphasis is placed on optimizing the management of the entire audit process from the five dimensions of audit nodes, audit objects, audit quality, audit efficiency, and audit work mode. However, in the existing technology, there is no relevant optimization research involved in the full-process tracking and supervision of engineering projects.
[0006] In summary, it is necessary to study a full-process tracking and supervision system for engineering projects to improve the work quality of full-process tracking and auditing of engineering projects. Summary of the invention
[0007] In order to solve the deficiencies in the prior art, the purpose of the present invention is to provide a full-process tracking and supervision system for engineering projects, which controls the time nodes of engineering projects submitted for audit based on audit indicators; carries out project time limit maintenance according to the nature of the project, and issues timeout warnings for audit projects based on the project time limit.
[0008] The present invention adopts the following technical solution.
[0009] A full-process tracking and supervision system for engineering projects includes a portal module. The system is connected to each operation and maintenance station through the portal module, and the configuration information of each engineering project in each operation and maintenance station is transmitted to the system through the portal module.
[0010] The system includes: project information module, audit management module, risk warning module;
[0011] In the project information module, the basic information of the project to be audited is entered; the project information module is used to maintain the completion deadline, audit submission deadline, and audit process deadline based on the basic information of the project to be audited;
[0012] The audit management module is used to select the optimal audit indicator from the audit indicator system based on the orthogonal hierarchical analysis method, and to control the time nodes of the engineering projects submitted for audit with the optimal audit indicator as the constraint and the optimal time prediction value of the entire audit process as the goal;
[0013] The risk warning module is used to determine whether the project submitted for audit has a timeout risk based on the various time nodes controlled by the audit management module and the various time limits maintained by the project information module; if there is a timeout risk, a timeout warning for the project is sent to the operation and maintenance station; among them, the timeout warning includes: completion timeout, audit submission timeout and audit process timeout.
[0014] Preferably, the starting point of the entire audit process is to map and associate the engineering project to be audited in the project information module with the electronic review form.
[0015] Preferably, basic information of the engineering project to be audited is entered in the project information module, including: project type and project nature;
[0016] The project information module maintains the completion deadline, audit submission deadline, and audit process deadline based on the project type;
[0017] Maintain the project's planned start time, actual start time, planned completion time, actual completion time, and audit submission time based on the nature of the project.
[0018] Preferably, the system further comprises: an audit time limit query module;
[0019] The audit time limit query module is used to query and display the processing time of each stage of the entire audit process for engineering projects that have been submitted for audit; among them, each stage includes the construction stage and the audit stage.
[0020] Preferably, in the audit management module, the audit indicator system includes: audit nodes, audit objects, audit quality, audit efficiency and audit work mode.
[0021] Preferably, the audit management module includes a review form management unit;
[0022] The audit form management unit is used to associate the engineering projects submitted for audit with the electronic audit form set; it is also used to construct k factors {A (1) ,A (2) ,…A (i) …,A (k)}, the i-th factor A (i) Represents the importance of the i-th audit indicator in the audit process of the project submitted for audit, i = 1, 2, ..., k; among them, the i-th factor A (i) Include i level factors; then use each factor and its level factor and range to calculate the i-th factor A (i) revised factors Sort by large to small, and extract the indicator ranked first as the optimal audit indicator.
[0023] Preferably, for the i-th factor A (i) Make revisions to satisfy the following relationship:
[0024]
[0025] In the formula,
[0026] is the revised factor, which represents the importance of the i-th audit indicator in the audit process of the project submitted for audit when considering the influence of other audit indicators in the audit process of the project submitted for audit. i=1,2,…,k,
[0027] A is the influence effect matrix constructed by the level factors of each factor, in which the elements in the influence effect matrix are normalized.
[0028] C is the influence weight matrix constructed by the extreme values of each factor.
[0029] Preferably, the influence effect matrix A satisfies the following relationship:
[0030]
[0031] Where M(i) is the i-th factor A (i) n i The normalized value of the sum of the level factors satisfies the following relationship:
[0032]
[0033] In the formula, is the i-th factor A (i) is the j-th level factor of , and nom(·) is the normalization function.
[0034] Preferably, the influence weight matrix C satisfies the following relationship:
[0035]
[0036] In the formula, R i is the i-th factor A (i) Very bad.
[0037] Preferably, the time forecast value of the entire audit process includes: a project start time forecast value, a completion time forecast value, an audit submission time forecast value, and an audit end time forecast value.
[0038] Preferably, under the constraint of the optimal audit index, the approval order management unit evaluates the purity of the predicted value output by the time prediction model of the entire audit process based on the data purity analysis method, and takes the predicted value with the highest purity as the optimal time prediction value of the entire audit process; wherein, the purity of the predicted value uses the standard deviation of the predicted value sample as the reverse indicator, satisfying the following relationship:
[0039] purf(s)=-sV
[0040] Where purf(s) is the purity of the predicted value, s is the predicted value, and V is the standard deviation of the predicted value sample.
[0041] Preferably, the time prediction model for the entire audit process includes: a time prediction model based on SVM, a time prediction model based on decision tree, and a time prediction model based on clustering.
[0042] Preferably, the optimal time prediction value of the entire audit process is used to set each time node, including: project start time node, completion time node, audit submission time node and audit end time node.
[0043] Preferably, the risk warning module extracts the time node from the audit management module, extracts the corresponding time limit from the project information module, and compares the time node with the time limit. If the time node exceeds the time limit, it is determined that the project submitted for audit has a timeout risk, and a timeout warning for the project is sent to the operation and maintenance station; conversely, if the time node does not exceed the time limit, it is determined that the project submitted for audit has no timeout risk.
[0044] The beneficial effects of the present invention are as follows:
[0045] 1) It has clear time intervention points for follow-up audits, and can intervene in different stages for real-time tracking, so that post-audits can be developed into process control and pre-audit guidance, especially in the early decision-making, design and bidding stages, which can effectively control costs and improve the effect of follow-up audits;
[0046] 2) Effectively define and uniformly manage the project maintenance time limit, and provide timely warnings and intervention measures for the tracking and supervision of the entire project process;
[0047] 3) Based on the orthogonal hierarchical analysis method, the optimal audit indicator is selected from the audit indicator system, which not only considers the direct and individual impact of each audit indicator in the project, but also considers the indirect and comprehensive impact of other indicators on the project, so that the selected optimal audit indicator takes into account the overall situation. For example, the system proposed in the present invention not only emphasizes the audit quality, but also considers the impact of the audit object on the audit quality, and introduces the comprehensive impact of audit efficiency and audit work mode on audit quality. It also fully considers the guarantee of high-quality audit quality under the premise of meeting the audit nodes, and fully reflects the management's ability to improve quality and efficiency;
[0048] 4) With the optimal audit indicator as a constraint and the optimal time prediction value of the entire audit process as the goal, the time nodes of the engineering projects submitted for audit are controlled. The goal of the prediction value evaluation is to be close to the true value. The obtained prediction value is used as a time node, which can be used to control the whole process tracking and supervision in the most practical management method for the project, which is the foundation of improving management quality and efficiency;
[0049] 5) Realize the function of sending timeout warnings to the operation and maintenance station, improve the information exchange between management systems, and ensure the smooth implementation of full-process tracking and supervision of engineering projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] Figure 1 It is a structural diagram of the whole process tracking and supervision system of the engineering project of the present invention;
[0051] The reference numerals are described as follows:
[0052] 1- Portal module; 2- Project information module; 3- Audit management module; 4- Risk warning module; 5- Operation and maintenance station;
[0053] Figure 2 It is a diagram of a time limit maintenance interface in a project information module in a system in one embodiment of the present invention;
[0054] Figure 3 This is an interface diagram of a risk warning module in a system in one embodiment of the present invention. DETAILED DESCRIPTION
[0055] The present application is further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present application.
[0056] like Figure 1 A full-process tracking and supervision system for engineering projects includes a portal module 1. The system is connected to each operation and maintenance station 5 through the portal module 1, and the configuration information of each engineering project in each operation and maintenance station is transmitted to the system through the portal module 1.
[0057] The configuration information of each engineering project in each operation and maintenance station includes: the corresponding project specialists, email addresses and sending frequencies of each operation and maintenance station; after the maintenance is complete, after the audit department issues the electronic review form to each operation and maintenance station, the project specialists of each operation and maintenance station can receive the review form processing email in their mailbox.
[0058] The system includes: project information module 2, audit management module 3, risk warning module 4;
[0059] In the project information module 2, the basic information of the engineering project to be audited is entered; the project information module is used to maintain the completion deadline, audit submission deadline, and audit process deadline based on the basic information of the engineering project to be audited.
[0060] Preferably, basic information of the engineering project to be audited is entered into the project information module, including: project type and project nature.
[0061] Project information modules, such as Figure 2 , based on the project type, maintain the completion deadline, audit submission deadline, and audit process deadline for subsequent early warning. Figure 2 In the interface shown, the fields for each time limit are editable.
[0062] Maintain the project's planned start time, actual start time, planned completion time, actual completion time, and audit submission time based on the nature of the project.
[0063] The list of basic project information contains a list of all projects of the Audit Department. Users can check whether the project information is correct and complete according to the query conditions on the page.
[0064] Audit management module 3 is used to select the optimal audit indicator from the audit indicator system based on the orthogonal hierarchical analysis method, and to control the time nodes of the engineering projects submitted for audit with the optimal audit indicator as the constraint and the optimal time prediction value of the entire audit process as the goal;
[0065] The risk warning module 4 is used to determine whether the project submitted for audit has a timeout risk according to the various time nodes controlled by the audit management module and the various time limits maintained by the project information module; if there is a timeout risk, a timeout warning for the project is sent to the operation and maintenance station; Figure 3 ,Timeout warnings include: completion timeout, audit submission timeout and audit process timeout.
[0066] Preferably, the starting point of the whole audit process is to map and associate the engineering project to be audited in the project information module with the electronic verification form. After the electronic verification form is added, the basic information of the engineering project to be audited is stored in the electronic verification form, and each electronic verification form corresponds to a unique number.
[0067] The end point of the entire audit process is the final issuance of a paper-stamped audit report by the audit department.
[0068] Preferably, the system also includes: an audit time limit query module.
[0069] The audit time limit query module is used to query and display the processing time of each stage of the entire audit process for engineering projects that have been submitted for audit; among them, each stage includes the construction stage and the audit stage.
[0070] Preferably, in the audit management module, the audit indicator system includes: audit nodes, audit objects, audit quality, audit efficiency and audit work mode.
[0071] Preferably, the audit management module includes a review form management unit.
[0072] The audit form management unit is used to associate the engineering projects submitted for audit with the electronic audit form set; it is also used to construct k factors {A (1) ,A (2) ,…A (i) …,A (k)}, the i-th factor A (i) Represents the importance of the i-th audit indicator in the audit process of the project submitted for audit, i = 1, 2, ..., k; among them, the i-th factor A (i) Include i level factors; then use each factor and its level factor and range to calculate the i-th factor A (i) revised factors Sort by large to small, and extract the indicator ranked first as the optimal audit indicator.
[0073] Preferably, for the i-th factor A (i) Make revisions to satisfy the following relationship:
[0074]
[0075] In the formula,
[0076] is the revised factor, which represents the importance of the i-th audit indicator in the audit process of the project submitted for audit when considering the influence of other audit indicators in the audit process of the project submitted for audit. i=1,2,…,k,
[0077] A is the impact effect matrix constructed by the level factors of each factor, in which the elements in the impact effect matrix are normalized.
[0078] C is the influence weight matrix constructed by the extreme values of each factor.
[0079] Preferably, the influence effect matrix A satisfies the following relationship:
[0080]
[0081] Where M (i) is the i-th factor A (i) n i The normalized value of the sum of the level factors satisfies the following relationship:
[0082]
[0083] In the formula, is the i-th factor A (i) is the j-th level factor of , and nom(·) is the normalization function.
[0084] Preferably, the influence weight matrix C satisfies the following relationship:
[0085]
[0086] In the formula, R i is the i-th factor A (i) Very bad.
[0087] Preferably, the time forecast value of the entire audit process includes: a project start time forecast value, a completion time forecast value, an audit submission time forecast value, and an audit end time forecast value.
[0088] Preferably, under the constraint of the optimal audit index, the approval order management unit evaluates the purity of the predicted value output by the time prediction model of the entire audit process based on the data purity analysis method, and takes the predicted value with the highest purity as the optimal time prediction value of the entire audit process; wherein, the purity of the predicted value uses the standard deviation of the predicted value sample as the reverse indicator, satisfying the following relationship:
[0089] purf(s)=-sV
[0090] Where purf(s) is the purity of the predicted value, s is the predicted value, and V is the standard deviation of the predicted value sample.
[0091] Preferably, the time prediction model for the entire audit process includes: a time prediction model based on SVM, a time prediction model based on decision tree, and a time prediction model based on clustering.
[0092] Preferably, the optimal time prediction value of the entire audit process is used to set each time node, including: project start time node, completion time node, audit submission time node and audit end time node.
[0093] Preferably, the risk warning module extracts the time node from the audit management module, extracts the corresponding time limit from the project information module, and compares the time node with the time limit. If the time node exceeds the time limit, it is determined that the project submitted for audit has a timeout risk, and a timeout warning for the project is sent to the operation and maintenance station; conversely, if the time node does not exceed the time limit, it is determined that the project submitted for audit has no timeout risk.
[0094] The system can also export and save all audit project warning information as a data table file.
[0095] The beneficial effects of the present invention are as follows:
[0096] 1) It has clear time intervention points for follow-up audits, and can intervene in different stages for real-time tracking, so that post-audits can be developed into process control and pre-audit guidance, especially in the early decision-making, design and bidding stages, which can effectively control costs and improve the effect of follow-up audits;
[0097] 2) Effectively define and uniformly manage the project maintenance time limit, and provide timely warnings and intervention measures for the tracking and supervision of the entire project process;
[0098] 3) Based on the orthogonal hierarchical analysis method, the optimal audit indicator is selected from the audit indicator system, which not only considers the direct and individual impact of each audit indicator in the project, but also considers the indirect and comprehensive impact of other indicators on the project, so that the selected optimal audit indicator takes into account the overall situation. For example, the system proposed in the present invention not only emphasizes the audit quality, but also considers the impact of the audit object on the audit quality, and introduces the comprehensive impact of audit efficiency and audit work mode on audit quality. It also fully considers the guarantee of high-quality audit quality under the premise of meeting the audit nodes, and fully reflects the management's ability to improve quality and efficiency;
[0099] 4) With the optimal audit indicator as a constraint and the optimal time prediction value of the entire audit process as the goal, the time nodes of the engineering projects submitted for audit are controlled. The goal of the prediction value evaluation is to be close to the true value. The obtained prediction value is used as a time node, which can be used to control the whole process tracking and supervision in the most practical management method for the project, which is the foundation of improving management quality and efficiency;
[0100] 5) Realize the function of sending timeout warnings to the operation and maintenance station, improve the information exchange between management systems, and ensure the smooth implementation of full-process tracking and supervision of engineering projects.
[0101] The applicant of the present invention has made a detailed explanation and description of the implementation examples of the present invention in conjunction with the drawings in the specification. However, those skilled in the art should understand that the above implementation examples are only preferred implementation schemes of the present invention, and the detailed description is only to help readers better understand the spirit of the present invention, but not to limit the scope of protection of the present invention. On the contrary, any improvements or modifications based on the inventive spirit of the present invention should fall within the scope of protection of the present invention.
Claims
1. A full-process tracking and supervision system for engineering projects, the system includes a portal module, the system is connected to each operation and maintenance station through the portal module, and the configuration information of each engineering project in each operation and maintenance station is transmitted to the system through the portal module; characterized in that: The system includes: project information module, audit management module, risk warning module, and audit time limit query module; In the project information module, the basic information of the project to be audited is entered; the project information module is used to maintain the completion deadline, audit submission deadline, and audit process deadline based on the basic information of the project to be audited; The audit management module is used to select the optimal audit indicator from the audit indicator system based on the orthogonal hierarchical analysis method, and control the time nodes of the engineering projects submitted for audit with the optimal audit indicator as the constraint and the optimal time prediction value of the whole audit process as the goal; the starting point of the whole audit process is to map and associate the engineering projects to be audited in the project information module with the electronic approval form; the audit indicator system includes: audit nodes, audit objects, audit quality, audit efficiency and audit work mode; the time prediction value of the whole audit process includes: project start time prediction value, completion time prediction value, audit submission time prediction value and audit end time prediction value; The audit management module includes an audit form management unit, which is used to associate the engineering project submitted for audit with the electronic audit form set; it is also used to construct k factors {A (1) , A (2) , …A (i) …, A (k) }, the i-th factor A (i) Represents the importance of the i-th audit indicator in the audit process of the project submitted for audit, i = 1, 2, ..., k; among them, the i-th factor A (i) Include i level factors; then use each factor and its level factor and range to calculate the i-th factor A (i) revised factors Sort by order from largest to smallest, and extract the indicator ranked first as the optimal audit indicator; Under the constraint of the optimal audit index, the approval order management unit evaluates the purity of the predicted value output by the time prediction model of the entire audit process based on the data purity analysis method, and takes the predicted value with the highest purity as the optimal time prediction value of the entire audit process; among them, the purity of the predicted value uses the standard deviation of the predicted value sample as the reverse indicator, which satisfies the following relationship: purf(s)=-sV Where purf(s) is the purity of the predicted value, s is the predicted value, and V is the standard deviation of the predicted value sample; Among them, the time prediction models of the whole audit process include: time prediction model based on SVM, time prediction model based on decision tree, and time prediction model based on clustering; the optimal time prediction value of the whole audit process is used to set each time node, including: project start time node, completion time node, audit submission time node, and audit end time node; The risk warning module is used to determine whether the project submitted for audit has a timeout risk based on the various time nodes controlled by the audit management module and the various time limits maintained by the project information module; if there is a timeout risk, a timeout warning for the project is sent to the operation and maintenance station; among them, the timeout warning includes: completion timeout, audit submission timeout and audit process timeout; The audit time limit query module is used to query and display the processing time of each stage of the entire audit process for engineering projects that have been submitted for audit; among them, each stage includes the construction stage and the audit stage.
2. The whole process tracking and supervision system of the engineering project according to claim 1 is characterized in that: Enter the basic information of the project to be audited in the project information module, including: project type and project nature; The project information module maintains the completion deadline, audit submission deadline, and audit process deadline based on the project type; Maintain the project's planned start time, actual start time, planned completion time, actual completion time, and audit submission time based on the nature of the project.
3. The whole process tracking and supervision system of the engineering project according to claim 1 is characterized in that: For the i-th factor A (i) Make revisions to satisfy the following relationship: In the formula, is a revised factor, which represents the importance of the i-th audit indicator in the audit process of the project submitted for audit when considering the influence of other audit indicators in the audit process of the project submitted for audit. i=1, 2, …, k, A is the impact effect matrix constructed by the level factors of each factor, in which the elements in the impact effect matrix are normalized. C is the influence weight matrix constructed by the extreme values of each factor.
4. The whole process tracking and supervision system of the engineering project according to claim 3 is characterized in that: The impact effect matrix A satisfies the following relationship: Where M (i) is the i-th factor A (i) n i The normalized value of the sum of the level factors satisfies the following relationship: In the formula, is the i-th factor A (i) is the j-th level factor of , and nom(·) is the normalization function.
5. The whole process tracking and supervision system of engineering projects according to claim 3 is characterized in that: The influence weight matrix C satisfies the following relationship: In the formula, R i is the i-th factor A (i) Very bad.
6. The whole process tracking and supervision system of engineering projects according to claim 1 is characterized in that: The risk warning module extracts the time node from the audit management module, extracts the corresponding time limit from the project information module, and compares the time node with the time limit. If the time node exceeds the time limit, it is determined that the project submitted for audit has a timeout risk, and a timeout warning for the project is sent to the operation and maintenance station; On the contrary, if the time node does not exceed the deadline, it is determined that there is no risk of overtime for the project submitted for audit.