A method for arranging a passage and structure in the inclined dome deck area of an LNG ship
By adjusting the opening size and structure in the inclined dome deck area of the LNG ship, combined with DNV specifications and finite element analysis, the problem of channel design not complying with regulations and insufficient structural strength was solved. The channel size met the requirements and the structural strength was improved, reducing costs. cost effect.
Patent Information
- Application Number
- CN202111479513.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-06
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-12-06
AI Technical Summary
In the design of LNG ships, the channel design in the inclined dome deck area is difficult to meet the requirements of SOLAS regulations, and the existing technology cannot guarantee the structural strength and economy when adjusting the opening position and fillet size, which poses safety risks especially for large ships. .
By determining the size and location of large openings in the inclined dome deck area of the LNG ship, moving the deck structure, adjusting the round size, and thickening and enlarging the ribs and panels, combined with DNV classification society specifications and finite element software analysis , ensure that the channel size meets the requirements and improve the structural strength.
It is possible to ensure the opening size and channel size requirements while enhancing the structural strength, avoiding structural instability, reducing the cost of reinforcing materials, and improving the overall stability and economy of the ship.
Smart Images

Figure CN114379701B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of ship design and manufacturing, and in particular relates to a channel and a structural arrangement method in an inclined dome deck area of an LNG ship. Background Art
[0002] In the design of LNG ships, the inclined dome deck area is relatively spacious and is usually used to arrange headers and passages. However, since this area is usually wide at the top and narrow at the bottom, special considerations are required when arranging the rib structure. It is necessary to consider both the rigid requirements for ensuring passage and the rationality of the structural layout. It is also necessary to take into account the requirements for structural weight to avoid wasting too much steel plates in the design and reducing the economy of the ship.
[0003] The openings in the inclined dome deck area are the locations of the manifolds and pedestrian passages, where the size of the passages must meet the requirements of the SOLAS regulations. Usually, the passages of newly designed ships do not meet the design requirements because this location is not taken into consideration, and this area usually needs to be reconsidered. Patent No. CN110667801A discloses a method for manufacturing a dome deck section of an LNG ship, and discloses a method for manufacturing a dome deck section of an LNG ship, which specifically includes the following steps: manufacturing a rib plate subassembly and a longitudinal subassembly; manufacturing a mid-assembly in the well deck; manufacturing a mid-assembly in the outer inclined top plate; manufacturing a mid-assembly in the main deck; manufacturing a mid-assembly in the inner inclined top plate; assembling the mid-assembly in the well deck, the mid-assembly in the outer inclined top plate, the mid-assembly in the main deck, and the mid-assembly in the inner inclined top plate into a dome deck section. The present invention shortens the dome construction period and improves construction efficiency.
[0004] The existing technology is to move the opening position downward to ensure the size of the channel in turn, but the inclined dome deck area is a structure that is wide at the top and narrow at the bottom. Moving the opening position downward cannot ensure that the opening size meets the requirements; the existing technology also uses changing the size of the opening fillet to increase the channel size. For large LNG ships, the stress at this position is relatively large, and the method of reducing the fillet size cannot ensure the safety of the opening structure. Summary of the invention
[0005] In order to overcome the above-mentioned deficiencies of the prior art, the present invention provides a channel and structural layout method for the inclined dome deck area of an LNG ship. The method of the present invention ensures the requirements of the opening size and the channel size while ensuring the structural strength at the opening to prevent structural instability in the inclined dome deck area.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is:
[0007] A method for arranging a passage and structure in an inclined dome deck area of an LNG ship, wherein the inclined dome deck of the LNG ship is a pentagonal structure, the upper part of the inclined dome deck of the LNG ship is a flat deck, the lower part of the inclined dome deck of the LNG ship is a main deck, the left side of the inclined dome deck of the LNG ship is an inclined deck, the upper right part of the inclined dome deck of the LNG ship is a longitudinal girder, the longitudinal girder is perpendicular to the flat deck, the lower right part of the inclined dome deck of the LNG ship is an inclined inner deck, the upper end of the inner deck is connected to the lower end of the longitudinal girder, and the lower end of the inner deck is connected to the main deck; a pentagonal opening is provided on the upper end face of the inclined dome deck of the LNG ship, and the method comprises the following steps:
[0008] The first step is to determine the size and position of the large opening: the end surface of the inclined dome deck is offset 650mm-700mm from the rib plate area, the end surface of the flat dome deck is offset 800mm-900mm from the rib plate area, the end surface of the longitudinal girder is offset 1200mm-1300mm from the rib plate area, and the end surface of the inner deck is offset 800mm-900mm from the rib plate area. The distance between the upper end surface and the lower end surface of the opening is 2600mm, so as to determine the size and position of the opening. The upper edges of the opening are connected by arc angles, and the arc radius is greater than 350mm.
[0009] The second step is to check the channel size: check whether the channel size in the opening position meets the size requirements. Taking the lower end surface of the opening as the reference, the height of the channel size is not less than 2000mm and the width is not less than 800mm;
[0010] The third step is to move the inclined dome deck: if the channel size in the opening meets the requirements, the channel and structure layout work in the inclined dome deck area is completed; if the channel size in the opening is less than 2000mm in height and less than 800mm in width, move the upper end surface of the inclined dome deck while ensuring that the position of the lower end surface of the inclined dome deck remains unchanged;
[0011] Step 4: Move the upper end point of the inclined dome deck toward the outer side of the hull, while keeping the lower end point of the inclined dome deck unchanged;
[0012] Step 5: Change the size of the chamfered corners: After the inclined dome deck is moved, change the radius of the chamfered corner on the right side of the lower end face of the opening, increase the opening size in the direction close to the inclined deck, and re-check whether the channel size of the large opening meets the requirements. If the channel size is unqualified, change the chamfered corner size again to increase the opening size to meet the channel size requirements;
[0013] Step 6: Thickening of ribs and panels: After the channel size meets the requirements, the panel of the opening is enlarged and the ribs on the end face where the opening is located are thickened;
[0014] In the seventh step, after the ribs are thickened and the panels are enlarged according to the structural stress, the passage and structure layout work in the inclined dome deck area of the LNG ship is completed.
[0015] The parallel offset dimensions of the inclined dome deck end face to the rib plate area, the parallel offset dimensions of the flat dome deck end face to the rib plate area, the parallel offset dimensions of the longitudinal girder end face to the rib plate area and the distance dimensions between the upper end face and the lower end face of the large opening in the first step are obtained according to the specifications of DNV classification society and the finite element software NAUTICUS HULL and GeniE analysis.
[0016] The dimension requirement of the passage in the second step above to be at least 2000*800mm is a hard requirement of SOLAS regulations.
[0017] While moving the upper end surface of the inclined dome deck of the LNG ship in the third step, the lower end point of the inclined dome deck of the LNG ship remains unchanged, so that the distance between the upper end point of the inclined deck and the center line of the hull is rounded to the middle.
[0018] The thickening of the ribs at various positions in the sixth step has different thickening sizes according to the stress distribution of the ribs. The end surface where the ribs are located is divided into three areas for thickening, specifically the thickness of the plate close to the inclined dome deck, the thickness of the plate close to the inner deck and the thickness of the plate close to the flat deck. The thickening size of the plate close to the inner deck is greater than the thickening size of the plate close to the flat deck, and the thickening size of the plate close to the flat deck is greater than the thickening size of the plate close to the inclined dome deck.
[0019] The panel enlargement in the sixth step is performed by using flat steel to enlarge the panel of the opening close to the inner deck, the panel close to the inclined dome deck and the panel at the lower end face of the opening. The section modulus of the panel at the lower end face of the opening is greater than the section modulus of the panel close to the inner deck, and the section modulus of the panel close to the inner deck is greater than the section modulus of the panel close to the inclined dome deck.
[0020] Based on the above scheme, the method of the present invention has achieved the following positive and beneficial effects through practice:
[0021] 1. The present invention moves the upper end point of the inclined dome deck while keeping the lower end point of the inclined dome deck unchanged, thereby increasing the size of the opening and the size of the passage while ensuring that the deck span remains unchanged, thereby improving the overall stability of the ship.
[0022] 2. The present invention performs structural reinforcement on the panel with openings and the ribs where the openings are located, and performs structural reinforcement of different sizes on different areas based on stress analysis. While ensuring the structural strength, the cost of using reinforcement materials is reduced, and excessive impact on subsequent structural design is avoided. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 The present invention is a flow chart of the opening and channel arrangement steps in a channel and structure arrangement method for an inclined dome deck area of an LNG ship.
[0024] Figure 2 The present invention is a schematic diagram of openings in an inclined dome deck area of a LNG ship in a method for arranging a passage and structure in the inclined dome deck area.
[0025] Figure 3 It is a schematic diagram of an opening scheme in a channel and a structural arrangement method for an inclined dome deck area of an LNG ship according to the present invention.
[0026] Figure 4 It is a schematic diagram of an unreasonable opening scheme in a channel and structural arrangement method in an inclined dome deck area of an LNG ship according to the present invention.
[0027] Figure 5 It is a schematic diagram of opening reinforcement in a channel and structure arrangement method of an inclined dome deck area of an LNG ship according to the present invention. DETAILED DESCRIPTION
[0028] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is described below by the specific examples shown in the accompanying drawings. However, it should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.
[0029] like Figure 1 As shown, a specific implementation method of a channel and structure layout method in an inclined dome deck area of a LNG ship of the present invention is as follows.
[0030] The present invention relates to a channel and structure arrangement method for the inclined dome deck area of an LNG ship, such as Figure 2 As shown, the inclined dome deck of the LNG ship is a pentagonal structure, the upper part of the inclined dome deck of the LNG ship is a flat deck, the lower part of the inclined dome deck of the LNG ship is the main deck, the left side of the inclined dome deck of the LNG ship is an inclined deck, the upper right side of the inclined dome deck of the LNG ship is a longitudinal girder, the longitudinal girder is perpendicular to the flat deck, the lower right side of the inclined dome deck of the LNG ship is an inclined inner deck, the upper end of the inner deck is connected to the lower end of the longitudinal girder, and the lower end of the inner deck is connected to the main deck; there is a pentagonal opening on the upper end face of the inclined dome deck of the LNG ship.
[0031] A method for arranging a passage and structure in an inclined dome deck area of an LNG ship, the method comprising the following steps:
[0032] The first step is to determine the size and position of the large opening: from the end face of the inclined dome deck 3 to the rib plate 8 area, it is offset by 650mm-700mm in parallel, from the end face of the flat dome deck 2 to the rib plate 8 area, it is offset by 800mm-900mm in parallel, from the end face of the longitudinal girder 9 to the rib plate 8 area, it is offset by 1200mm-1300mm in parallel, from the end face of the inner deck 1 to the rib plate 8 area, it is offset by 800mm-900mm in parallel, the distance between the upper end face and the lower end face of the opening 5 is 2600mm, so as to determine the size and position of the opening 5, the upper edges of the opening 5 are connected by chamfer 6, the radius of the chamfer 6 is greater than 350mm, and the size diagrams of the positions of the opening 5 are as follows: Figure 2 As shown, the edges of the opening 5 are connected by rounded corners 6 to improve the structural strength of the inclined dome deck area;
[0033] The second step is to check the channel size: check whether the size of the channel 10 in the opening 5 position meets the size requirements. Taking the lower end surface of the opening 5 as the reference, the height of the channel 10 is not less than 2000mm and the width is not less than 800mm;
[0034] The third step is to move the inclined dome deck: if the size of the passage 10 in the opening 5 meets the requirements, the passage 10 and the structural arrangement work in the inclined dome deck area are completed; if the height of the passage 10 in the opening 5 is less than 2000mm and the width is less than 800mm, the upper end surface of the inclined dome deck 3 is moved while ensuring that the position of the lower end surface of the inclined dome deck 3 remains unchanged. The area between the inclined dome deck 3 and the inner deck 1 is an empty tank set to protect the liquid cargo tank, and there is no liquid tank inside, so the inclined dome deck 3 can be moved;
[0035] The fourth step is to move the upper end point of the inclined dome deck 3 toward the outside of the hull, while the position of the lower end point of the inclined dome deck 3 remains unchanged, such as Figure 4 As shown, when the upper and lower ends of the inclined dome 3 deck are moved at the same time, the length of the inclined dome deck 3 will increase, and the weight of the inclined dome deck 3 will also increase, resulting in an increase in the deadweight of the ship and a reduction in the economic benefits of the ship;
[0036] Step 5, change the size of the rounded corners: after the inclined dome deck 3 is moved, change the radius size of the right side of the lower end face of the opening 5, increase the size of the opening 5 in the direction close to the inclined dome deck 3, and re-check whether the size of the channel 10 of the opening 5 meets the requirements. If the size of the channel 10 is unqualified, change the size of the rounded corner 6 again to increase the size of the opening 5 to meet the size requirements of the channel 10. Reduce the radius size of the right side of the lower end face of the opening 5 to increase the effective area of the channel 10 in the opening 5, so that the size of the channel 10 meets the requirements;
[0037] Step 6: Thickening the ribs and enlarging the panel: After the size of the channel 10 meets the requirements, enlarge the panel 7 of the opening 5 and thicken the ribs 8 on the end face where the opening 5 is located;
[0038] Step 7: After the ribs 8 are thickened and the panels 7 are enlarged according to the structural stress, the channel 10 and the structural arrangement work in the inclined dome deck area of the LNG ship are completed.
[0039] The parallel offset dimension of the inclined dome deck 3 end face to the rib plate 8 area, the parallel offset dimension of the flat dome deck 2 end face to the rib plate 8 area, the parallel offset dimension of the longitudinal girder 9 end face to the rib plate 8 area, the distance dimension between the upper end face and the lower end face of the opening 5, and the parallel offset dimension of the inner deck 1 end face to the rib plate 8 area in the first step are obtained according to the specifications of DNV classification society and the analysis of finite element software NAUTICUS HULL and GeniE; these are conventional calculations and will not be repeated here.
[0040] The dimension requirement of the passage 10 in the second step above being at least 2000*800 mm is a rigid requirement of SOLAS regulations.
[0041] While moving the upper end surface of the inclined dome deck 3 of the LNG ship in the third step, the position of the lower end point of the inclined dome deck 3 of the LNG ship remains unchanged, so that the distance from the upper end point of the inclined dome deck 3 to the center line of the hull is rounded to an integer. The distance from the middle distance 11 is the main data of the hull, and rounding the distance from the middle distance 11 is convenient for subsequent calculations of the ship.
[0042] In the sixth step, the ribs 8 are thickened at different locations according to the stress distribution of the ribs 8. The end surface of the ribs 8 is divided into three areas for thickening, specifically, the plate thickness f near the inclined dome deck 3, the plate thickness c near the inner deck 1, and the plate thickness b near the flat deck. The thickening size of the plate thickness c near the inner deck 1 is greater than the thickening size of the plate thickness b near the flat deck, and the thickening size of the plate thickness b near the flat deck is greater than the thickening size of the plate thickness f near the inclined dome deck 3. The thickening of the ribs 8 at different areas is as follows: Figure 5 As shown, the rib plate 8 is thickened according to the stress magnitude at different positions, thereby increasing the strength of the rib plate 8 and reducing the cost.
[0043] The panel 7 in the sixth step is enlarged by using flat steel to enlarge the panel d close to the inner deck 1, the panel g close to the inclined dome deck 3 and the panel e at the lower end surface of the opening 5. The section modulus of the panel e at the lower end surface of the opening 5 is greater than the section modulus of the panel d close to the inner deck 1, and the section modulus of the panel d close to the inner deck 1 is greater than the section modulus of the panel g close to the inclined dome deck 3.
[0044] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.
Claims
1. A method for arranging a passage and structure in the inclined dome deck area of an LNG ship, wherein the inclined dome deck of the LNG ship is a pentagonal structure, the upper part of the inclined dome deck of the LNG ship is a flat deck, the lower part of the inclined dome deck of the LNG ship is a main deck, the left side of the inclined dome deck of the LNG ship is an inclined deck, the upper right part of the inclined dome deck of the LNG ship is a longitudinal girder, the longitudinal girder is perpendicular to the flat deck, the lower right part of the inclined dome deck of the LNG ship is an inclined inner deck, the upper end of the inner deck is connected to the lower end of the longitudinal girder, and the lower end of the inner deck is connected to the main deck; the upper end face of the inclined dome deck of the LNG ship has a pentagonal opening, characterized in that: The method comprises the following steps: The first step is to determine the size and position of the large opening: the end surface of the inclined dome deck (3) is parallelly offset to the rib plate (8) area by 650mm-700mm, the end surface of the flat dome deck (2) is parallelly offset to the rib plate (8) area by 800mm-900mm, the end surface of the longitudinal girder (9) is parallelly offset to the rib plate (8) area by 1200mm-1300mm, and the end surface of the inner deck (1) is parallelly offset to the rib plate (8) area by 800mm-900mm. The distance between the upper end surface and the lower end surface of the opening (5) is 2600mm, thereby determining the size and position of the opening (5). The upper edges of the opening (5) are connected by chamfers (6), and the radius of the chamfers (6) is greater than 350mm. The second step is to check the channel size: check whether the channel (10) at the opening (5) meets the size requirements. Taking the lower end surface of the opening (5) as a reference, the height of the channel (10) is not less than 2000 mm and the width is not less than 800 mm. The third step is to move the inclined dome deck: if the size of the passage (10) in the opening (5) meets the requirements, the passage (10) and structure arrangement work in the inclined dome deck area is completed; if the height of the passage (10) in the opening (5) is less than 2000 mm and the width is less than 800 mm, the upper end surface of the inclined dome deck (3) is moved while ensuring that the position of the lower end surface of the inclined dome deck remains unchanged; while moving the upper end surface of the inclined dome deck (3) of the LNG ship, the position of the lower end point of the inclined dome deck (3) of the LNG ship remains unchanged, so that the upper end point of the inclined dome deck (3) is rounded to the middle distance (11) from the center line of the hull; Step 4: Move the upper end point of the inclined dome deck (3) toward the outer side of the hull, while keeping the lower end point of the inclined dome deck (3) unchanged; Step 5, changing the size of the rounded corners: after the inclined dome deck area is moved, the radius of the rounded corners on the right side of the lower end surface of the opening (5) is changed, the size of the opening (5) is increased in the direction close to the inclined dome deck (3), and the size of the passage (10) in the opening (5) is re-checked to see whether it meets the requirements. If the size of the passage (10) is unqualified, the size of the rounded corners (6) is changed again, and the size of the opening (5) is increased to meet the size requirements of the passage (10); Step 6, rib thickening and panel enlargement: after the size of the channel (10) meets the requirements, the panel (7) of the opening (5) is enlarged and the rib (8) at the end face where the opening (5) is located is thickened; the thickening of the rib (8) at each position is carried out with different thickening sizes according to the stress distribution of the rib (8), and the end face where the rib (8) is located is divided into three areas for thickening, specifically, the plate thickness (f) close to the inclined dome deck (3), the plate thickness (c) close to the inner deck (1) and the plate thickness (b) close to the flat deck, and the plate thickness (c) close to the inner deck (1) is thickened larger than the plate thickness (b) close to the flat deck. ) thickening dimension, the thickening dimension of the plate thickness (b) close to the flat deck is greater than the thickening dimension of the plate thickness (f) close to the inclined dome deck (3); the panel (7) is enlarged, and flat steel is used to enlarge the panel (d) close to the inner deck (1), the panel (g) close to the inclined dome deck (3) and the panel (e) at the lower end face of the opening (5), the section modulus of the panel (e) at the lower end face of the opening (5) is greater than the section modulus of the panel (d) close to the inner deck (1), and the section modulus of the panel (d) close to the inner deck (1) is greater than the section modulus of the panel (g) close to the inclined dome deck (3); In the seventh step, after the ribs are thickened and the panels (7) are enlarged according to the structural stress, the passage (10) and structural arrangement work of the inclined dome deck area of the LNG ship is completed.
2. According to claim 1, a method for arranging passages and structures in the inclined dome deck area of a LNG ship is characterized in that: The parallel offset dimension of the end face of the inclined dome deck (3) to the rib plate (8), the parallel offset dimension of the end face of the flat dome deck (2) to the rib plate (8), the parallel offset dimension of the end face where the longitudinal girder (9) is located to the rib plate (8) and the distance dimension between the upper end face and the lower end face of the opening (5) in the first step are obtained according to the specifications of the DNV classification society and the analysis of the finite element software NAUTIUSHULL and GeniE.
3. The method for arranging passages and structures in the inclined dome deck area of a LNG ship according to claim 1, characterized in that: The dimension requirement of the passage (10) in the second step to be at least 2000*800 mm is a rigid requirement of SOLAS regulations.
Citation Information
Patent Citations
Manufacturing method of dome deck panel of LNG (liquefied natural gas) ship
CN110667801A
Method of producing and installing Side Passage Way in ship and Structure thereof
KR1020060127583A