Railway comprehensive inspection method

By fusing three-dimensional coordinates and panoramic image data, real-life point cloud detection of comprehensive railway inspection vehicles is realized, which solves the problems of complexity and high cost of the existing system, improves detection efficiency and accuracy, and adapts to the needs of railway inspection operations. increase.

CN114440767BActive Publication Date: 2024-10-25ZHUZHOU TIMES ELECTRONICS TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210094810.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-26
Publication Date
2024-10-25
Estimated Expiration
2042-01-26

AI Technical Summary

Technical Problem

The existing comprehensive railway inspection vehicle system is complex, the utilization rate of hardware equipment is low, the economic cost is high, and there are many operators, making it difficult to adapt to the growing demand for comprehensive railway inspection operations.

Method used

Use three-dimensional coordinate data, GNSS, IMU and DMI data for clock synchronization, generate point cloud data and panoramic images for fusion processing, realize real-life point cloud detection and analysis of railway infrastructure, reduce the number of detection equipment, and improve equipment integration and data compatibility sex.

Benefits of technology

It reduces system complexity and labor costs, improves detection efficiency and accuracy, enables multi-device data interconnection and disaster analysis, enriches detection functions, and reduces the work intensity of patrol workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114440767B_ABST
    Figure CN114440767B_ABST
Patent Text Reader

Abstract

The present invention discloses a railway comprehensive inspection method, comprising the following steps: S1) obtaining the three-dimensional coordinate data of the object to be measured, obtaining the GNSS, IMU and DMI data of the railway comprehensive inspection vehicle, and obtaining the panoramic image data; S2) providing clock synchronization for the three-dimensional coordinates, IMU, DMI and panoramic image data according to the timing of GNSS; S3) saving the three-dimensional coordinates, IMU, DMI and panoramic image data after clock synchronization in real time; S4) first using GNSS, IMU and DMI data fusion to solve POS data, then using POS data and laser radar data to jointly calculate point cloud data, and then fusing the point cloud data with the panoramic image data to obtain a real-time point cloud; S5) using the point cloud and panoramic image data as data sources to perform railway infrastructure detection and analysis. The present invention can solve the technical problems of high complexity, high labor cost and high data processing difficulty of the existing methods.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of railway engineering machinery, and in particular to a railway comprehensive inspection method for railway line maintenance. Background Art

[0002] With the rapid growth of my country's railway mileage, the tasks of railway inspection, railway infrastructure and its components are becoming more and more onerous. In the past, railway inspection and infrastructure inspection were completed by manual patrol or special equipment. Manual patrol has high requirements on the quality of workers, high work intensity, and missed inspections due to the easy distraction of people's attention. With the advancement of science and technology, the inspection of railway infrastructure and its components has gradually been upgraded to special inspection tools or operating vehicles. There are many types of railway infrastructure and its components, which directly leads to a large number of special inspection tools or systems. Each type of tool needs to be equipped with special technicians to operate, which is time-consuming and laborious for railway engineering departments. In recent years, railway comprehensive inspection vehicles have been gradually introduced to the railway market. Comprehensive inspection vehicles concentrate multiple inspection tools and inspection systems on the same inspection vehicle, and use one operating skylight to complete the inspection of multiple railway components.

[0003] The inspection items of the comprehensive inspection vehicle usually include the size and defect detection of rails, trackside facilities, and contact networks, which can be applied to engineering, electrical, and power supply departments. The existing comprehensive inspection vehicles are equipped with different inspection equipment for different inspection items, most of which are cameras. The technology used is the acquisition and processing of two-dimensional images, and includes a small amount of small-scale, close-range three-dimensional detection. Before the operation, all detection systems need to be turned on. During the operation, the system collects original photos (some systems will have real-time detection). After the operation is completed, the data is transferred to the ground processing system for storage and processing. This operation method requires a large number of personnel, a long time, high labor intensity, and low efficiency. Its inspection effect is directly related to the experience and sense of responsibility of the post-processing personnel. From the above operation method, it can be seen that the existing comprehensive inspection system has a complex configuration, low utilization rate of hardware equipment, and high economic cost. At the same time, due to the large number of system sets, more operators are required during the operation. At the same time, the existing comprehensive inspection system is mainly based on image processing, and the number of cameras configured ranges from millions of pixels to tens of millions of pixels, up to dozens. The amount of image data generated after one operation is huge, and offline processing is also difficult.

[0004] In the prior art, a Chinese invention application with publication number CN107472269A, which was applied by Baoji CRRC Times Engineering Machinery Co., Ltd. on September 15, 2017 and published on December 15, 2017, discloses a railway electric transmission comprehensive inspection vehicle, in which the vehicle body is mounted on the power bogie through the vehicle frame, and living facilities and maintenance and repair detection units are provided on the top and inside of the vehicle body, and electrical interfaces and external sockets are provided at the front and rear ends of the vehicle body for easy connection with external vehicles and electrical equipment. Power system I and power system II are provided at the bottom of the vehicle body, and power system I is connected to the power bogie and the driving control unit that controls the operation of the whole vehicle, and power system II is connected to the living facilities and maintenance and repair detection unit to realize the separate power supply mode of the whole vehicle operation and the living facilities and maintenance and repair detection unit. This invention uses power system I and power system II located at the bottom of the vehicle body to supply power to the vehicle's operation and living facilities and maintenance and repair inspection units respectively, thereby improving the safety performance of the vehicle's operation. It is a comprehensive inspection vehicle that integrates power supply, engineering, and electrical system inspection functions. The inspection vehicle has a speed of up to 160km / h, greatly improving work efficiency and meeting high-speed rail inspection needs.

[0005] In addition, a Chinese invention application with publication number CN103231719A, which was applied for by Baoji CSR Times Engineering Machinery Co., Ltd. on April 18, 2013 and published on February 3, 2016, discloses a dual-power railway track comprehensive inspection vehicle, including a vehicle body, a frame, a front power unit and a rear power unit. The vehicle body is arranged on the frame, and a main driver's cab and a deputy driver's cab are respectively provided at both ends of the vehicle body, an inspection room and an operating room are provided between the main driver's cab and the deputy driver's cab, a front power bogie and a rear power bogie are respectively provided on both sides of the lower end of the frame, the front power unit provides driving power to the front power bogie, and the rear power unit provides driving power to the rear power bogie, a diesel tank is provided between the front power unit and the rear power unit and the diesel tank is fixed to the lower end of the frame, and a plurality of inspection devices are installed on the frame. The invention is self-powered and can perform rapid dynamic scanning, intelligent status assessment and alarm on the status of surface structural components of high-speed railway tracks, rail contours and line limits. It can timely grasp the appearance status of high-speed railway engineering equipment, guide daily maintenance and repair, and ensure the safe and reliable operation of high-speed railways.

[0006] Although the application of comprehensive inspection vehicles has improved the efficiency of the use of working skylights, there are still the following obvious technical defects:

[0007] 1) The number of integrated inspection systems in the current comprehensive inspection vehicles produced by different manufacturers is not exactly the same, generally between 12 and 16 items, and the data compatibility between multiple inspection devices has become a problem. In addition, the inspection data obtained lacks intercommunication and interconnection, and equipment reuse has not been achieved;

[0008] 2) Since the single-item inspection equipment is simply installed in a centralized manner, the number of inspection equipment required is the same as the number of inspection points, resulting in a large number of inspection equipment; at the same time, each device needs to be equipped with a corresponding control system and post-processing system, which makes the operation of the comprehensive inspection vehicle complicated, and the data post-processing is difficult and the task is heavy;

[0009] 3) Since the number of detection equipment has not been reduced, the number of equipment operators has not been reduced, and the comprehensive inspection vehicle has many detection systems, the economic, personnel and use costs of the comprehensive inspection application are high, the operation process is complicated, and it cannot adapt to and meet the growing needs of railway comprehensive inspection operations. Summary of the invention

[0010] In view of this, the purpose of the present invention is to provide a railway comprehensive inspection method to solve the technical problems of the existing method, such as high system complexity, high labor cost, great difficulty in data processing, and inability to adapt to and meet the growing needs of railway comprehensive inspection operations.

[0011] In order to achieve the above-mentioned invention object, the present invention specifically provides a technical implementation scheme of a railway comprehensive inspection method, comprising the following steps:

[0012] S1) obtaining the three-dimensional coordinate data of the object to be measured, obtaining the GNSS, IMU and DMI data of the railway comprehensive inspection vehicle, and obtaining the panoramic image data;

[0013] S2) Provide clock synchronization for 3D coordinates, IMU, DMI and panoramic image data based on GNSS timing;

[0014] S3) Real-time storage of the three-dimensional coordinates, IMU, DMI and panoramic image data after clock synchronization;

[0015] S4) firstly, GNSS, IMU and DMI data are used to fuse and calculate POS data, then the POS data and the three-dimensional coordinate information of the measured object are used to jointly calculate the point cloud data, and then the point cloud data is fused with the panoramic image data to obtain the real-time point cloud;

[0016] S5) Use point cloud and panoramic image data as data sources to conduct railway infrastructure inspection and analysis.

[0017] Furthermore, point cloud and panoramic image raw data are collected during field work, and point cloud, POS track files and panoramic image data are generated during office work. The step S5) further includes the following track geometry parameter detection steps:

[0018] S601) segmenting the generated point cloud and dividing the POS trajectory file into file segments corresponding to the point cloud segments;

[0019] S602) reading in a segment of point cloud and separating it to obtain a ground point cloud;

[0020] S603) reading in the POS trajectory file corresponding to the segment of the point cloud;

[0021] S604) removing the point cloud centered on the POS track and whose distance exceeds the set range, and the remaining point cloud is the point cloud containing only the roadbed;

[0022] S605) In the ground point cloud, using elevation difference separation to obtain a point cloud of the rail part;

[0023] S606) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails;

[0024] S607) calculating the track centerline using the extracted left and right rail top surface vector lines to obtain the track centerline vector, where the vector node interval of the track centerline vector is a set distance;

[0025] S608) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages;

[0026] S609) performing fine processing on the coordinates of the track centerline;

[0027] S610) Output the calculated refined track centerline vector line for calculation of line geometry parameters.

[0028] Furthermore, the step S609) further includes:

[0029] S6091) Calculate the rail cross section passing through the track centerline vector node, and the thickness of the cross section does not exceed the set distance;

[0030] S6092) projecting the point cloud on the cross section relative to the cross section, and obtaining the two-dimensional coordinates of the rail cross section after projection;

[0031] S6093) accurately matching the cross sections of the left and right rails with the standard profiles of the rails respectively;

[0032] S6094) After matching, the top surface coordinates of the left and right rails are obtained, and the top surface coordinates of the original rails are updated using the top surface coordinates;

[0033] S6095) Calculate the precise orbit centerline coordinates, update the original orbit centerline vector node coordinates, and traverse and calculate all orbit centerline vector nodes that have been obtained.

[0034] Furthermore, point cloud and panoramic image raw data are collected during field work, and point cloud and panoramic image data are generated during office work. The step S5) further includes the following track limit and contour inspection steps:

[0035] S701) segmenting the generated point cloud;

[0036] S702) reading in a segment of point cloud and separating it to obtain a ground point cloud;

[0037] S703) In the ground point cloud, using elevation difference separation to obtain a point cloud of the rail part;

[0038] S704) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails;

[0039] S705) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline;

[0040] S706) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages;

[0041] S707) obtaining the cross section of the point cloud according to the set mileage interval value, and outputting all the cross section point clouds;

[0042] S708) performing limit calculation for each cross-section point cloud;

[0043] S709) Save and output the results of the limit calculation.

[0044] Furthermore, the step S708) further includes:

[0045] S7081) The intersection of the cross section and the center line of the track is taken as the coordinate origin, the x-axis is parallel to the top surface of the rail and points to the center line of the top surface of the right rail along the track direction, and the z-axis is perpendicular to the x-axis and upward to establish a limit reference coordinate system;

[0046] S7082) projecting the cross-sectional point cloud relative to the cross section to obtain the two-dimensional coordinates of the rail cross-sectional point cloud after projection;

[0047] S7083) converting the two-dimensional coordinates of the cross-section point cloud to a limit reference coordinate system;

[0048] S7084) generating a standard building boundary model in a boundary reference coordinate system;

[0049] S7085) Perform collision analysis by superimposing the cross-section point cloud with the standard building limit model and obtain the limit calculation result.

[0050] Furthermore, point cloud and panoramic image raw data are collected during field work, and point cloud, POS trajectory files and panoramic image data are generated during office work. The step S5) further includes the following contact network geometric parameter inspection steps:

[0051] S801) segmenting the generated point cloud and dividing the POS trajectory file into file segments corresponding to the point cloud segments;

[0052] S802) reading in a point cloud segment and reading in a POS trajectory file corresponding to the point cloud segment;

[0053] S803) removing the point cloud centered on the POS track and beyond the set range from the POS track, and the remaining point cloud is the point cloud Ce that only includes the roadbed and the point cloud above the roadbed;

[0054] S804) extracting the point cloud Cf-d of the ground part in the point cloud Ce, and taking out the point cloud Cf-d in the point cloud Ce to obtain the point cloud Cf-k of the aerial part;

[0055] S805) In the ground point cloud Cf-d, the point cloud of the rail part is obtained by using the elevation difference separation;

[0056] S806) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails;

[0057] S807) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline vector, where the vector node interval of the track centerline vector is a set distance;

[0058] S808) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages;

[0059] S809) in the aerial point cloud Cf-k, identifying and extracting the contact network line, and performing vector line fitting, the distance between the vector nodes is a set value;

[0060] S810) calculating geometric parameters of adjacent contact wires;

[0061] S811) Save and output the results of the contact network line geometric parameter calculation.

[0062] Furthermore, the step S810) further includes:

[0063] S8101) traverse all vector nodes of the center line of the top surface of the left rail in the railway rail;

[0064] S8102) calculating the direction vector of each vector node A and generating a normal plane perpendicular to the direction vector;

[0065] S8103) traverse the vector nodes of the center line of the top surface of the right rail, and find two vector nodes C and D located on both sides of the normal plane and adjacent to each other;

[0066] S8104) calculating the intersection point B of the normal plane and the line CD;

[0067] S8105) traversing the vector nodes of the contact network line to find two vector nodes E and F located on both sides of the normal plane and adjacent to each other;

[0068] S8106) calculating the intersection point G of the normal plane and the line EF;

[0069] S8107) Draw a perpendicular line through point G to line segment AB, with the foot of the perpendicular denoted as point H and the midpoint of line segment AB denoted as I;

[0070] S8108) The length of the line connecting HI is the contact line pull-out value at the corresponding mileage of point I;

[0071] S8109) The length of GH is the contact line height at the corresponding mileage of point I.

[0072] Furthermore, point cloud and panoramic image raw data are collected during field work, and point cloud and panoramic image data are generated during office work. The step S5) further includes the following line spacing inspection steps:

[0073] S901) segmenting the generated point cloud;

[0074] S902) reading in a segment of point cloud and separating it to obtain a ground point cloud;

[0075] S903) In the ground point cloud, using elevation difference separation to obtain a point cloud of the rail part;

[0076] S904) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails;

[0077] S905) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline;

[0078] S906) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages;

[0079] S907) calculating the line spacing between the center lines of two adjacent tracks;

[0080] S908) Save and output the result of line spacing calculation.

[0081] Furthermore, the step S907) further includes:

[0082] S9071) traverses all vector nodes of one of the track midlines,

[0083] S9072) calculating the direction vector of each vector node A, and generating a normal plane perpendicular to the direction vector;

[0084] S9073) traverse the vector nodes of the adjacent track midlines to find two adjacent vector nodes C and D located on both sides of the normal plane;

[0085] S9074) calculating the intersection point B of the normal plane and the line connecting the line segment CD;

[0086] S9075) calculating the horizontal distance of line segment AB, the horizontal distance of AB being the line spacing at the point;

[0087] S9076) Record the mileage of point A, and the mileage of A is recorded as the mileage value of the line spacing.

[0088] Furthermore, raw data is collected during field work, and point cloud, POS trajectory files and panoramic image data are generated during office work. The step S5) further includes the following ballast fullness inspection steps:

[0089] S1001) dividing the point cloud into point cloud segments;

[0090] S1002) simultaneously dividing the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments, and matching the POS trajectory file with the point cloud file;

[0091] S1003) Read in the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file;

[0092] S1004) Separating the ground point cloud and removing the aerial point cloud;

[0093] S1005) extracting point clouds within a set width range on both sides of the POS track line as the center line, and the extracted point cloud is a point cloud containing only the track bed part;

[0094] S1006) in the point cloud containing only the ballast part, using the elevation difference to separate and obtain the point cloud of the rail part;

[0095] S1007) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and the reliability of the rail top surface vector line extraction can be checked using the gauge range between the rails;

[0096] S1008) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline;

[0097] S1009) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages;

[0098] S1010) obtaining the cross section of the point cloud according to the set mileage interval value, and outputting all the cross section point clouds;

[0099] S1011) calculating the ballast fullness for each cross-section point cloud;

[0100] S1012) calculating the ballast fullness for each frame of point cloud for a continuous section of the line and accumulating the calculated ballast fullness to obtain the ballast fullness of the entire section of the line;

[0101] S1013) Save and output the results of ballast fullness calculation.

[0102] Furthermore, the step S1011) further includes:

[0103] S10111) projecting the point cloud in the cross section onto the cross section to form a two-dimensional point cloud C;

[0104] S10112) locating the rail in the cross section by calculating the intersection of the rail top surface vector line and the cross section;

[0105] S10113) locating the position of the ballast bed slope in the cross section by using the relative position relationship between the ballast bed slope and the rail;

[0106] S10114) establishing a standard coordinate system with the line connecting the midlines of the top surfaces of the left and right rails as the x-axis, the midpoint of the line as the coordinate origin, and the vertical line upward as the y-axis, and rotating and translating the two-dimensional point cloud C to the standard coordinate system;

[0107] S10115) generating a standard cross-section model of the roadbed in the standard coordinate system, calculating the area of ​​the figures sandwiched by the point cloud and the standard model one by one, the area above the standard model is excess ballast, and the area below the standard model is missing ballast, and the ballast fullness of the section can be obtained after the calculation is completed;

[0108] S10146) Save the calculation results of ballast fullness.

[0109] By implementing the technical solution of the railway comprehensive inspection method provided by the present invention, the following beneficial effects are achieved:

[0110] (1) The railway comprehensive inspection method of the present invention replaces the existing multiple systems on the comprehensive inspection vehicle with data collected by a single set of equipment, greatly improving the integration of the detection equipment. Both the complexity of the system and operation and the economic cost are far lower than the existing comprehensive inspection system;

[0111] (2) In the railway comprehensive inspection method of the present invention, the data collected by a single set of equipment can be used by multiple sets of subsequent application systems, which increases the compatibility of data between multiple detection devices, realizes the multiplexing of multiple devices and the interconnection of detection data, and reduces the complexity of application system development;

[0112] (3) The railway comprehensive inspection method of the present invention makes extensive use of point cloud data. Compared with the previous detection applications based on plane images, it can not only perform qualitative analysis, but also perform accurate quantitative analysis. It can not only realize a large number of infrastructure detection functions, but also realize disaster analysis and assessment, and has richer functions.

[0113] (4) The railway comprehensive inspection method of the present invention adopts three-dimensional real-scene inspection, has true color point cloud and panoramic images, and can perform accurate measurements. Compared with the previous image-based inspection, it is a huge improvement. At the same time, it provides a virtual inspection function, which greatly reduces the workload of patrol workers and greatly improves the accuracy and automation of patrol. BRIEF DESCRIPTION OF THE DRAWINGS

[0114] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the prior art descriptions. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other embodiments can be obtained based on these drawings without creative work.

[0115] Figure 1 It is a flowchart of the operation procedure of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0116] Figure 2 It is a schematic diagram of the installation structure of a specific embodiment of the railway comprehensive inspection system based on the method of the present invention on a comprehensive inspection vehicle;

[0117] Figure 3 It is a front view of the installation structure of a specific embodiment of the railway comprehensive inspection system based on the method of the present invention;

[0118] Figure 4 It is a side view of the installation structure of a specific embodiment of the railway comprehensive inspection system based on the method of the present invention;

[0119] Figure 5It is an axonometric diagram of the installation structure of a specific embodiment of the railway comprehensive inspection system on which the method of the present invention is based;

[0120] Figure 6 It is a system structure block diagram of a specific embodiment of the railway comprehensive inspection system based on the method of the present invention;

[0121] Figure 7 It is a working principle flow chart of a specific embodiment of the railway comprehensive inspection system based on the method of the present invention;

[0122] Figure 8 It is a schematic diagram of the slope geological disaster inspection process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0123] Fig. 9 It is a schematic diagram of a slope landslide disaster assessment process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0124] Fig.10 It is a schematic diagram of a line virtual inspection / additional ride process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0125] Fig.11 It is a schematic diagram of the inspection process of the sound and wind barrier of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0126] Fig.12 It is a schematic diagram of a utility pole verticality inspection process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0127] Fig.13 It is a schematic diagram of a track geometry parameter detection process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0128] Fig.14 It is a schematic diagram of a track clearance and profile inspection process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0129] Fig.15 It is a schematic diagram of the inspection process of the contact network geometric parameters of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0130] Fig.16 It is a schematic diagram of the line spacing inspection process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0131] Fig.17 It is a schematic diagram of the ballast fullness inspection process of a specific embodiment of the railway comprehensive inspection method of the present invention;

[0132] In the figure: 1-3D scanning system, 10-positioning system, 11-LiDAR, 12-panoramic camera, 13-GNSS equipment, 14-IMU equipment, 15-DMI equipment, 2-time-space synchronization system, 3-storage / control system, 4-inspection application system, 40-point cloud processing system, 41-integrated inspection system, 42-slope hazard inspection module, 43-slope hazard assessment module, 44-line virtual inspection / additional ride module, 45-track geometric parameter detection module, 46-track limit and contour Inspection module, 47-sound and wind barrier inspection module, 48-contact network geometric parameter inspection module, 49-line spacing inspection module, 410-ballast fullness inspection module, 411-telephone pole verticality inspection module, 100-railway comprehensive inspection vehicle, 101-vehicle body, 102-roof platform, 103-host cable, 104-control box, 105-encoder signal input, 106-power cord, 107-power supply, 108-air switch, 109-AC input, 110-network cable, 111-control terminal. DETAILED DESCRIPTION

[0133] For the purpose of reference and clarity, the technical terms, abbreviations or abbreviations used below are recorded as follows:

[0134] Point cloud data: Scanning data is recorded in the form of points, each point contains three-dimensional coordinates, and some may contain color information (RGB) or reflection intensity information (Intensity); In addition to geometric positions, some point cloud data also have color information. Color information is usually obtained by a camera to obtain a color image, and then the color information (RGB) of the pixel at the corresponding position is assigned to the corresponding point in the point cloud; Intensity information is obtained by the echo intensity collected by the laser scanner receiving device. This intensity information is usually related to the surface material, roughness, incident angle direction of the target, as well as the emission energy of the instrument and the laser wavelength;

[0135] Cloth algorithm: point cloud ground point filter (Cloth Simulation Filter, CSF) algorithm;

[0136] GNSS: Global Navigation Satellite System, the abbreviation of Global Navigation Satellite System;

[0137] IMU: Inertial Measurement Unit, short for inertial measurement unit;

[0138] DMI: Distance Measuring Instrument, short for distance measuring instrument;

[0139] POS: Position and Orientation System, the abbreviation of positioning and attitude system, is a high-precision position and attitude measurement system combined with IMU / GPS;

[0140] Internal work: A term used in surveying and mapping, referring to work done indoors;

[0141] Field work: A professional term in surveying and mapping, referring to work performed outdoors.

[0142] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0143] As attached Figure 1 To Attachment Fig.17 As shown, a specific embodiment of the railway comprehensive inspection method of the present invention is given, and the present invention is further described below in conjunction with the drawings and specific embodiments.

[0144] As attached Figure 1 As shown, an embodiment of the railway comprehensive inspection method of the present invention specifically includes the following steps:

[0145] S1) The attitude positioning system 10 obtains GNSS, IMU and DMI data of the railway comprehensive inspection vehicle, the laser radar 11 obtains the three-dimensional coordinate data of the measured object, and the panoramic camera 12 obtains panoramic image data (specifically, it can be a panoramic photo or panoramic image data);

[0146] S2) The spatiotemporal synchronization system 2 provides clock synchronization for three-dimensional coordinates, IMU, DMI and panoramic image data based on GNSS timing;

[0147] S3) The storage / control system 3 stores the three-dimensional coordinates, IMU, DMI and panoramic image data after clock synchronization in real time;

[0148] S4) The point cloud processing system 40 first uses GNSS, IMU and DMI data to fuse and solve the POS data, then uses the POS data and the lidar data to jointly calculate the point cloud data, and then fuses the point cloud data with the panoramic image data to obtain the real-time point cloud;

[0149] S5) The comprehensive inspection system 41 uses point cloud and panoramic image data as data sources to conduct railway inspection analysis and railway infrastructure detection analysis.

[0150] Among them, railway inspection analysis specifically includes inspection of geological disasters such as slope landslides (i.e. slope disaster inspection), slope (geological) disaster assessment, line virtual inspection / additional inspection, wind and sound barrier inspection, and overhead line pole verticality inspection. Railway infrastructure inspection analysis specifically includes track geometry parameter detection, track limit and profile inspection, overhead line geometry parameter inspection, line spacing inspection, and ballast fullness inspection. The following is a detailed introduction to each step.

[0151] 1) Inspection of geological disasters such as slope landslides

[0152] Railway slopes are prone to geological disasters such as landslides from time to time due to rain erosion or other factors. The occurrence of such geological disasters has a great impact on railway operations, causing railway interruptions at the least and casualties at the worst. Therefore, inspections and early warnings of geological disasters such as railway slope landslides are very important. The railway comprehensive inspection system uses a three-dimensional (mobile) scanning system 1 to regularly scan the slope areas along the railway. Each point cloud obtained is managed in a unified manner. Since the point clouds obtained in multiple periods have the same mileage and coordinate system, the point clouds can be compared in detail. The location and amount of slope changes can be found through the comparison results of the point clouds, and landslides can be warned based on this. As shown in the attached figure, Figure 8 The specific implementation steps are as follows:

[0153] S100) In order to achieve a better positioning effect when comparing point clouds, before performing three-dimensional scanning of the slope, a number of laser marker targets (referred to as marker targets, targets) with very stable positions are set on the railway slope that needs to be inspected. The adjacent laser marker targets are arranged in a "Z" shape, and the horizontal distance between every two laser marker targets is about 100 meters, and the vertical distance is ≥10 meters; during field operations, the original data of sensors such as the laser radar 11, the panoramic camera 12, the GNSS device 13, the IMU device 14 and the DMI device 15 are collected; during indoor operations, point clouds and panoramic image data (i.e., panoramic photos, panoramic images) are generated; the laser marker targets are accurately extracted from the scanned point clouds, and the extracted laser marker targets are given unique names. The laser marker targets at the same position in the point clouds obtained by scanning at different times should be named the same;

[0154] S101) obtaining the current point cloud, and then reading in the previous point cloud to be compared;

[0155] S102) using the mileage and coordinates of the laser marking target to roughly overlay and display the two phases of point clouds;

[0156] S103) using the previous laser marking target coordinates and the current laser marking target coordinates to calculate accurate point cloud superposition parameters, i.e., seven parameters for point cloud coordinate conversion;

[0157] S104) using accurate point cloud overlay parameters to perform coordinate conversion on the current coordinates, and after the conversion, perform accurate point cloud overlay comparison;

[0158] S105) After superposition, the coordinate difference of the point cloud at the same position in the two phases of point cloud is calculated, that is, the change amount. The specific steps are as follows:

[0159] S1051) firstly grid the current point cloud into grids of about 10cm*10cm;

[0160] S1052) traverse each grid in the current point cloud, assuming that the first point cloud grid to be processed is C;

[0161] S1053) performing plane fitting on the point cloud C to obtain a plane P, and obtaining the center coordinate O of the point cloud grid C;

[0162] S1054) Calculate the normal line of the plane P passing through the point O to obtain the normal line L;

[0163] S1055) finding the intersection point J of the normal line L and the previous point cloud, and calculating the distance of the line segment OJ, which is the change amount of the same position in the two point clouds;

[0164] S1056) Repeat the above steps for each grid in the grid to obtain the change amount of each grid point cloud before and after;

[0165] S106) Check the result of the change amount, retrieve the current and previous panoramic image data for the area with large coordinate difference, and manually confirm whether the slope change has indeed occurred;

[0166] S107) saving the coordinate difference of the point cloud superposition comparison;

[0167] S108) reading in the previous point cloud to compare the coordinate difference, drawing a coordinate difference change curve, and detecting whether the coordinate difference has a tendency to gradually increase;

[0168] S109) issuing an early warning or alarm for the area where the coordinate difference gradually increases.

[0169] 2) Assessment of disasters such as slope landslides

[0170] Railway slopes are prone to geological disasters such as landslides during the rainy season. When a geological disaster such as a landslide occurs, it is necessary to assess the size of the disaster as soon as possible to provide a basis for disaster handling. After an emergency occurs, the three-dimensional scanning system 1 can be used to quickly scan the line again, and compared with the previous data, the earth and stone of the landslide can be immediately determined, the size of the disaster can be assessed, and accurate quantitative data can be provided for emergency handling. In addition, the three-dimensional point cloud and panoramic images obtained by scanning can be used as a base map for disaster handling, providing strong map support for disaster handling. As shown in the attached figure Fig. 9The specific implementation steps are as follows:

[0171] S200) In order to achieve a better positioning effect during point cloud comparison, before performing three-dimensional slope scanning, several laser marker targets with very stable positions are set on the railway slope to be inspected, and adjacent targets are arranged in a "Z" shape, with a horizontal distance of about 100 meters and a vertical distance of ≥10 meters between every two marker targets; during field operations, the original sensor data of point clouds and panoramic photos are collected; during indoor operations, point clouds and panoramic photos are generated; laser marker targets are extracted from the scanned point clouds, and the extracted laser marker targets are given unique names, and laser marker targets at the same position in point clouds of different periods are named the same;

[0172] S201) obtaining the current point cloud, and then reading in the previous point cloud to be compared;

[0173] S202) using the mileage and coordinates of the laser marking target to perform a rough overlay display of the two phases of point clouds;

[0174] S203) calculating accurate point cloud superposition parameters using the previous laser marking target coordinates and the current laser marking target coordinates;

[0175] S204) using accurate superposition parameters to perform coordinate transformation on the current coordinates, and after the transformation, perform accurate point cloud superposition comparison;

[0176] S205) After superposition, the coordinate difference of the point clouds at the same position in the two phases of point clouds is calculated, and the difference of the elevation coordinate z is compared in particular;

[0177] S206) using the coordinate difference between the two point clouds, calculating the volume of the part contained in the two point clouds, which is the earth and stone of the landslide;

[0178] S207) Statistically calculating the area of ​​the landslide portion;

[0179] S208) Retrieving the panoramic image data scanned in the previous period, checking the actual topography of the disaster site, and intercepting and saving the three-dimensional point cloud according to the mileage;

[0180] S209) simultaneously locates the mileage where the emergency occurs, and uses the three-dimensional point cloud and panoramic image of the location as the base map for emergency processing, providing the latest and most realistic map reference for emergency processing.

[0181] 3) Virtual inspection / additional inspection of routes

[0182] For railway inspection, the common practice in the industry is to conduct regular manual inspections of the railway. The quality of manual inspections depends on the workers' work attitude and professional skills. When experienced inspectors inspect, the quality and efficiency of the inspections are guaranteed. However, if the professional quality of the inspectors is not high, there will be problems such as low quality, low efficiency, and high missed inspection rate. In addition, the work intensity of manual inspections is very high and the working methods are very backward.

[0183] The 3D scanning system 1 can obtain high-precision point cloud and panoramic photo data within a 50-meter range of the railway. The point cloud and image after fitting are very suitable for operators to watch, and they also have the characteristics of being able to measure. Therefore, they are very suitable for virtual line inspections, which can greatly reduce the workload of field work. At the same time, there is a demand for regular additions in various railway bureaus. The 3D point cloud and panoramic images generated by the 3D scanning system 1 are very detailed. The fitted point cloud and panoramic photos can be displayed in virtual reality VR after virtual reality processing, simulating the perspective of the locomotive driver for virtual additions. As shown in the attached Fig.10 The specific implementation steps are as follows:

[0184] S300) Collect the original data of each sensor in the field, and generate point cloud, panoramic image and POS trajectory files in the office;

[0185] S301) using the calibrated panoramic image to assign true color values ​​to the grayscale point cloud to generate a true color point cloud (using true color point clouds for railway inspection / virtual ride-on can increase the sense of presence);

[0186] S302) Since the point cloud is massive, in order to inspect the smoothness of browsing the point cloud, the point cloud needs to be segmented. According to the general performance of the current processor, it is best to segment the point cloud into point cloud segments of 1GB-3GB in size;

[0187] S303) synchronously dividing the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments;

[0188] S304) reading in the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file;

[0189] S305) The default viewpoint of the integrated inspection system interface is located at the starting point of the POS trajectory file, and the field of view direction is consistent with the POS trajectory file. After the user clicks Start, point cloud roaming can be performed in a variety of ways (automatic roaming or free roaming can be used) to achieve the visual effect of virtual inspection / additional ride;

[0190] Among them, automatic roaming: after the user sets the roaming direction (direction: from large mileage to small mileage or from small mileage to large mileage), the system automatically moves forward at a certain speed to browse the point cloud according to the set direction. The speed of automatic roaming is adjustable; free roaming: there are two types of free roaming: (1) full free roaming, the roaming direction and speed are all determined by the user through the keyboard and mouse. During full free roaming, the viewpoint and field of view are not related to the POS trajectory file, and the viewpoint and field of view are determined by the user; (2) step roaming, which is similar to automatic roaming, but during step roaming, the inspection system does not automatically move the point cloud. Instead, the user browses forward or backward through the direction control button. Each time the direction control button is clicked, the point cloud moves a certain distance;

[0191] S306) During the point cloud roaming process, the user can change the field of view direction and pause the point cloud movement at any time;

[0192] S307) After pausing the movement of the point cloud, the user can carefully view a specific component by zooming in and out, and can call up a panoramic photo corresponding to the point cloud to view the image information of the component;

[0193] S308) If a component has a defect or fault, the integrated inspection system outputs the defect information by creating a defect report; when creating the defect report, the information that must be saved includes: the mileage of the defective component, POS track coordinates, corresponding point cloud information, corresponding impact information, and the type and level of the fault / missing item;

[0194] S309) After the inspection of one section of point cloud is completed, the point cloud of the next section is automatically read in, and the above steps S301) to S308) are repeated for inspection until the line inspection is completed.

[0195] 4) Noise and wind barrier inspection

[0196] In downtown areas, residential areas, and areas with strong winds such as bridges or Gobi Desert, sound / wind barriers are installed on both sides of the railway line. These barriers play a key role in reducing noise, especially reducing noise damage in nearby residential areas. In areas with strong winds, sound / wind barriers also play a key role in protecting railways and operational safety. As the operating time increases, these barriers will be damaged due to various reasons, so regular inspections are required to detect damage and the severity of the damage. The sound / wind barrier damage information obtained from the detection can be used to guide maintenance personnel to repair and replace damaged sound barrier guardrails.

[0197] The three-dimensional point cloud data and panoramic image data of the acquisition line are collected by the three-dimensional scanning system 1, which can be used for the inspection of the sound / wind barrier. Based on the geometric characteristics of the sound / wind barrier, a corresponding algorithm can be designed to extract the sound / wind barrier information from the collected three-dimensional point cloud data. By comparing the multi-period point cloud data, the point cloud data of the sound / wind barrier area can be extracted and analyzed to detect whether the sound / wind barrier is damaged, the damage situation, and the shape and area of ​​the damage. Fig.11 The specific implementation steps are as follows:

[0198] S400) In order to achieve a better positioning effect during point cloud comparison, before performing three-dimensional scanning of the railway line, it is necessary to set a number of laser marker targets with very stable positions on the railway barrier to be inspected. The adjacent targets are arranged in a "Z" shape, and the horizontal distance between every two marker targets is about 100 meters. The vertical layout principle is adopted: that is, the high-position marker target is located at the top of the barrier, and the low-position marker target is located at the bottom of the barrier; when working in the field, the original sensor data of the point cloud and panoramic photos are collected; when working in the office, the point cloud, POS trajectory file and panoramic photos are generated;

[0199] S401) Since the point cloud is massive, in order to ensure the smoothness of the inspection calculation, it is recommended to first manually intercept the point cloud of the road section containing only the barrier. If the length of the road section is still long, the point cloud needs to be segmented. According to the general performance of the current processor, it is best to divide the point cloud into point cloud segments of 1GB-3GB in size;

[0200] S402) synchronously dividing the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments, and matching the POS trajectory file with the point cloud file;

[0201] S403) reading in the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file;

[0202] S404) using a cloth algorithm to separate and obtain ground point clouds, and removing the point clouds in the air;

[0203] S405) Since the inspection is performed on the barrier, the point cloud obtained in step S404) needs to be segmented to separate the point cloud of the barrier part: since the inertial navigation device is fixedly installed during field operation data collection, the relative position relationship between the inertial navigation device and the roadbed is relatively stable, so the POS trajectory file can be used to segment and extract the roadbed, and the point cloud of the barrier part is a point cloud in the vertical direction, and the normal of this part of the point cloud is perpendicular to the POS trajectory;

[0204] S406) extracting the point cloud within the width range of 2.5-3.5 meters on both sides of the POS trajectory line as the center line (the point cloud of the barrier part is included in this part of the point cloud), which is C, performing height filtering on the point cloud C, removing the point cloud with an elevation coordinate value Z less than 0.7 meters, and obtaining the remaining point cloud C', then calculating the point cloud normal of C', removing the point cloud that is not perpendicular to the POS trajectory line, and finally the remaining is the point cloud CP containing only the barrier part;

[0205] S407) extracting laser marker targets from the point cloud CP, and giving the extracted laser marker targets unique names, and laser marker targets at the same position in point clouds of different periods have the same name;

[0206] S408) reading in the previous point cloud to be compared;

[0207] S409) using the mileage and coordinates of the laser marking target to perform a rough overlay display of the two phases of point clouds;

[0208] S410) calculating accurate point cloud overlay parameters using previous laser marking target coordinates and current laser marking target coordinates;

[0209] S411) using accurate superposition parameters to perform coordinate transformation on the current coordinates, and after the transformation, perform accurate point cloud superposition comparison;

[0210] S412) After superposition, traverse the current point cloud and count the number of point clouds within a radius of 2 cm for each point cloud. For point clouds whose number in the previous point cloud is not 0 but in the current point cloud is 0, it is considered that the barrier in the current point cloud has been damaged;

[0211] S413) Statistically calculating the area of ​​the damaged part;

[0212] S414) The panoramic image and three-dimensional point cloud of the damaged mileage are saved to facilitate manual confirmation by the staff afterwards.

[0213] 5) Inspection of verticality of electric poles

[0214] The utility poles are the main bearing bodies of the contact network cables, and whether the utility poles are tilted has a significant impact on the power supply of the railway. The utility poles that have been in use for a long time are at risk of tilting or even falling down due to the pulling of the contact network cables. Especially in the Yunnan-Guizhou Plateau and Guangdong-Guangxi regions, due to geological disasters, heavy rains, and typhoons, the probability of this failure occurring is higher than in other areas. Therefore, it is very necessary to regularly check the verticality of the utility poles. After collecting the holographic point cloud around the railway, the railway comprehensive inspection system can perform point cloud segmentation to obtain the point cloud of the utility pole part, obtain the point cloud center of the utility pole part, and perform straight line fitting to obtain the vector equation of the center of the contact network utility pole, and then obtain the verticality of the utility pole. As shown in the attached figure Fig.12The specific implementation steps are as follows:

[0215] S500) When working in the field, collecting the original data of the sensor of the point cloud and the panoramic photo; when working in the office, generating the point cloud, POS trajectory file and the panoramic photo;

[0216] S501) Since the point cloud is massive, in order to ensure the smoothness of inspection calculation, it is best to divide the point cloud into point cloud segments of 1GB-3GB in size according to the general performance of current processors;

[0217] S502) synchronously dividing the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments, and matching the POS trajectory file with the point cloud file;

[0218] S503) Read in the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file;

[0219] S504) Since the electric poles are located on both sides of the railway and the distance from the center line of the track (the center line of the left and right rails along the track) is between 3.5 meters and 6 meters, the redundant point cloud can be deleted by using the POS track to reduce the amount of calculation, and the remaining point cloud is recorded as C;

[0220] S505) First, all the electric poles are found. The method of finding is as follows:

[0221] S5051) finding a cross section of the point cloud at the start of the POS trajectory, the height of the cross section being the same as the POS trajectory, and the cross section being horizontal;

[0222] S5052) obtaining the intersection of the cross section and the point cloud C. Since the height of the POS track is located between the overhead wire and the rail, the cross section will inevitably intersect with the nearby electric poles;

[0223] S5053) calculating the diameter or size of the point cloud at each intersection respectively, and calculating the distance between the centers of the point clouds at two adjacent intersections;

[0224] S5054) Since the diameter of the electric pole is a fixed value, and the distance between the electric poles is also relatively fixed, these two conditions can be used to eliminate some interference items;

[0225] S5055) After eliminating the interference items, the remaining point cloud is considered to be the electric pole, and the obtained electric pole is recorded as D (recording the x, y coordinates of the center of the electric pole);

[0226] S5056) Due to the ups and downs of the railway, the cross section at the starting point of the POS track may not be able to find all the electric poles, so starting from the starting point of the POS track, a cross section is obtained every 200 meters (the calculation process of each cross section repeats steps S5052) to S5055), and the obtained electric poles are merged into D;

[0227] S5057) cyclically calculating to obtain all electric poles D;

[0228] S506) Perform the following operations for each electric pole in D:

[0229] S5061) Take out a telephone pole Di(xi,yi) from D;

[0230] S5062) extracting a point cloud C-Di with Di(xi, yi) as the center and a radius of about 1 meter from the point cloud C, and calculating the maximum value zmax and the minimum value zmin of the elevation coordinates zi of all points in C-Di;

[0231] S5063) between the maximum value zmax and the minimum value zmin, a horizontal cross section is set every 100 mm, the intersection surface between the cross section and C-Di is obtained, and the center oi of the intersection surface point cloud is obtained;

[0232] S5064) after obtaining the centers of the intersection surfaces of all cross sections and C-Di, fitting all the center points into a straight line and obtaining the slope of the straight line;

[0233] S5065) Record the position and slope of the electric pole.

[0234] S507) Save and output the calculation results.

[0235] 6) Track geometry parameter detection

[0236] The smoothness of the track directly reflects the stability of the train to passengers. The better the smoothness, the smoother the train runs. After a long period of operation, the railway will generally undergo linear changes and deviations. It is necessary to obtain the deviation through regular track geometry parameter measurements and then make linear corrections. The smoothness of the track is generally measured by track geometry parameters, including the track gauge, superelevation, horizontal deviation and vertical deviation of the line.

[0237] The 3D scanning system 1 obtains a 3D point cloud model of the line environment, and on this basis, high-precision rail extraction is performed. After obtaining the rail coordinates, the rail centerline coordinates can be obtained, and the line plane and elevation measurement and track line shape measurement can be performed. Fig.13 The specific implementation steps are as follows:

[0238] S600) During field work, the original data of the sensors of the point cloud and the panoramic photo are collected; during office work, the point cloud, POS trajectory files and the panoramic photo are produced;

[0239] S601) Segmenting the generated point cloud. Since the point cloud is very large, in order to reduce the burden on the point cloud processing system 40, it is best to segment the original point cloud into point cloud segments of 1000 meters each, and at the same time segment the POS trajectory file into file segments corresponding to the point cloud segments;

[0240] S602) reading in a point cloud, first using a cloth algorithm to separate and obtain a ground point cloud;

[0241] S603) reading in the POS trajectory file corresponding to the segment of the point cloud;

[0242] S604) removing the point cloud centered on the POS track and more than 2 meters away from the POS track, and the remaining point cloud is the point cloud containing only the roadbed;

[0243] S605) In the ground point cloud, since the elevation of the rail is higher than that of the ballast, the point cloud of the rail part can be separated by using the elevation difference;

[0244] S606) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and the reliability of the extraction of the rail top surface vector line (i.e., the center line of the rail top surface along the rail direction) can be checked using the rail gauge range of 1435±3mm between the rails;

[0245] S607) using the extracted left and right rail top surface vector lines to calculate the track centerline, and obtain the track centerline vector, the vector node interval of the centerline vector is 20cm;

[0246] S608) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the starting point and the end point mileage;

[0247] S609) Since the measurement of track geometry parameters has a very high requirement for accuracy, it is also necessary to perform fine processing on the track centerline coordinates. The specific processing steps are as follows:

[0248] Traverse the obtained track centerline vector nodes and perform the following operations on each of them:

[0249] S6091) Calculate the rail cross section passing through the track centerline vector node, the thickness of the cross section shall not exceed 15 cm;

[0250] S6092) projecting the point cloud on the cross section relative to the cross section, and obtaining the two-dimensional coordinates of the rail cross section after projection;

[0251] S6093) accurately matching the cross sections of the left and right rails with the standard profiles of the rails respectively;

[0252] S6094) After matching, the top surface coordinates of the left and right rails are obtained, and the top surface coordinates of the original rails are updated using the top surface coordinates;

[0253] S6095) Calculate the precise orbit centerline coordinates and update the original orbit centerline vector node coordinates;

[0254] S610) Output the calculated refined track centerline vector line for calculation of line geometry parameters.

[0255] 7) Track limit and profile inspection

[0256] The three-dimensional point cloud data of the track is collected by scanning with the three-dimensional scanning system 1. First, the point cloud is divided into segments along the direction of the rail. Then, the point cloud of the rail area is extracted from each tunnel point cloud. The reference coordinate system for tunnel limit analysis is established through the point cloud of the rail to obtain high-precision cross-sectional data of the track. Finally, it is determined whether there is foreign matter intrusion according to the limit regulations of the railway track. Fig.14 The specific implementation steps are as follows:

[0257] S700) During field work, the original data of the sensor of the point cloud and the panoramic photo are collected; during office work, the point cloud and the panoramic photo are generated;

[0258] S701) segmenting the generated point cloud. Since the point cloud is very large, in order to reduce the burden on the point cloud processing system, it is best to segment the original point cloud into segments of 1000 meters each;

[0259] S702) reading in a segment of point cloud, firstly using a cloth algorithm to separate and obtain a ground point cloud;

[0260] S703) In the ground point cloud, since the elevation of the rail is higher than that of the ballast, the point cloud of the rail part can be separated by using the elevation difference;

[0261] S704) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and the reliability of the rail top surface vector line extraction can be checked using the rail gauge range of 1435±3mm;

[0262] S705) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline;

[0263] S706) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the starting point and the end point mileage;

[0264] S707) obtaining the cross section of the point cloud according to the set mileage interval value, and outputting all the cross section point clouds;

[0265] S708) For each cross-section point cloud, perform the following operations:

[0266] S7081) The intersection of the cross section and the center line of the track is taken as the coordinate origin, the x-axis is parallel to the top surface of the rail and points to the center line of the top surface of the right rail along the track direction, and the z-axis is perpendicular to the x-axis and upward to establish a limit reference coordinate system;

[0267] S7082) projecting the cross-sectional point cloud relative to the cross section to obtain the two-dimensional coordinates of the rail cross-sectional point cloud after projection;

[0268] S7083) converting the two-dimensional coordinates of the cross-section point cloud to a limit reference coordinate system;

[0269] S7084) generating a standard building boundary model in a boundary reference coordinate system;

[0270] S7085) performing a superimposed collision analysis on the cross-section point cloud and the standard building limit model to obtain a limit calculation result;

[0271] S709) Save and output the results of the limit calculation.

[0272] 8) Inspection of contact network geometric parameters

[0273] The contact network geometric parameters characterize the relative position relationship between the contact network conductor and the centerline of the railway track. The lateral distance between the contact network conductor and the centerline of the railway track is called the pull-out value, and the longitudinal distance between the contact network conductor and the centerline of the railway track is called the conductor height. In order to ensure the normal current collection of the pantograph, the contact network geometric parameters need to be in a reasonable range. If the contact network geometric parameters exceed the normal range, the pantograph may be detached, causing a train operation safety accident. Therefore, the contact network geometric parameters are data that must be measured regularly.

[0274] The point cloud of the railway line is collected by scanning with the three-dimensional scanning system 1, and then the cross-section is processed. The rails and contact wires are extracted from the cross-section, and finally the relative position relationship between the contact wire and the center line of the track is calculated to obtain the contact network geometric parameters. Fig.15 The specific implementation steps are as follows:

[0275] S800) During field work, the original data of the sensors of point cloud and panoramic photos are collected; during office work, point cloud, POS trajectory files and panoramic photos are generated;

[0276] S801) Segmenting the generated point cloud. Since the point cloud is very large, in order to reduce the burden on the point cloud processing system 40, it is best to segment the original point cloud into segments of 1000 meters each, and at the same time segment the POS trajectory file into file segments corresponding to the point cloud;

[0277] S802) reading in a point cloud segment and reading in a POS trajectory file corresponding to the point cloud segment;

[0278] S803) removing the point cloud centered on the POS track and more than 2 meters away from the POS track, and the remaining point cloud is the point cloud Ce that only includes the roadbed and the point cloud above the roadbed;

[0279] S804) extracting the point cloud Cf-d of the ground part in the point cloud Ce by using the cloth algorithm, and taking out the point cloud Cf-d from the point cloud Ce to obtain the point cloud Cf-k of the aerial part;

[0280] S805) In the ground point cloud Cf-d, since the elevation of the rail is higher than that of the ballast, the point cloud of the rail part can be separated by using the elevation difference;

[0281] S806) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and the reliability of the rail top surface vector line extraction can be checked using the rail gauge range of 1435±3mm;

[0282] S807) using the extracted left and right rail top surface vector lines to calculate the track centerline, and obtain the track centerline vector, the vector node interval of the track centerline vector is 20cm;

[0283] S808) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the starting point and the end point mileage;

[0284] S809) In the aerial point cloud Cf-k, since only the point cloud above the roadbed is limited, there are fewer interference point clouds, including only the point cloud of the contact wire and the load-bearing cable, and the point cloud of the basic network support device at the pole; for the accuracy of contact wire extraction, it is best to use the manual mouse click method to specify the contact wire to be identified, provide a seed point cloud for contact wire extraction, and then use the regional growth algorithm (that is, merge pixels with similar properties together, specify a seed point as the starting point of growth for each region, and then compare the pixel points in the area around the seed point with the seed point, merge points with similar properties and continue to grow outward until no pixels that meet the conditions are included, so that the growth of a region is completed) to identify and extract the contact wire, and perform vector line fitting, and the distance between vector nodes is 20cm;

[0285] S810) Calculate the geometric parameters of adjacent contact wires, the specific steps are as follows:

[0286] S8101) traverse all vector nodes of the center line of the top surface of the left rail in the railway rail;

[0287] S8102) calculating the direction vector of each vector node (denoted as point A) and generating a normal plane F perpendicular to the direction vector;

[0288] S8103) traverse the vector nodes of the center line of the top surface of the right rail, and find two adjacent vector nodes (denoted as C and D) on both sides of the normal plane F;

[0289] S8104) calculating the intersection point of the normal plane F and the line connecting CD (recorded as point B);

[0290] S8105) traverse the vector nodes of the contact network line to find two adjacent vector nodes (denoted as E and F) located on both sides of the normal plane F;

[0291] S8106) calculating the intersection point of the normal plane F and the line connecting EF (denoted as point G);

[0292] S8107) Draw a perpendicular line through point G to line segment AB, with the foot of the perpendicular denoted as point H and the midpoint of line segment AB denoted as I;

[0293] S8108) The length of the line connecting HI is the contact line pull-out value at the corresponding mileage of point I;

[0294] S8109) The length of GH is the contact line height at the corresponding mileage of point I;

[0295] S811) Save and output the results of contact line geometric parameter calculation.

[0296] 9) Line spacing inspection

[0297] The line spacing represents the horizontal distance between the center lines of two adjacent lines and is a key indicator for determining whether a railway line can operate safely. If the line spacing is too small, it may affect the operation of locomotives on both lines. This indicator generally needs to be measured after the railway line is overhauled and the track is adjusted.

[0298] The 3D point cloud data of the line is collected by scanning with the 3D scanning system 1. First, the point cloud is divided into segments along the direction of the rails. Then, the point cloud of the rail area is extracted from each tunnel point cloud. The rail top surface vector line is obtained using the rail point cloud. The track centerline can be calculated based on the vector lines of the left and right rails. When there are multiple tracks in the point cloud, multiple track centerlines can be obtained. Fig.16 The specific implementation steps are as follows:

[0299] S900) During field work, the original data of the sensors of the point cloud and the panoramic photo are collected; during office work, the point cloud and the panoramic photo are generated;

[0300] S901) Segmenting the generated point cloud. Since the point cloud is very large, in order to reduce the burden on the point cloud processing system, it is best to segment the original point cloud into segments of 1000 meters each;

[0301] S902) reading in a point cloud, first using a cloth algorithm to separate and obtain a ground point cloud;

[0302] S903) In the ground point cloud, since the elevation of the rail is higher than that of the ballast, the point cloud of the rail part can be separated by using the elevation difference; at the same time, in order to increase the stability of the detection, the position of the rail can be clearly determined by clicking the rail point cloud with a mouse, and then the rail point cloud can be extracted by using the region growing algorithm;

[0303] S904) fitting and extracting the rail top surface using the point cloud of the separated rail part to obtain the left and right rail top surface vector lines, and the reliability of the rail top surface vector line extraction can be checked using the rail gauge range of 1435±3mm;

[0304] S905) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline;

[0305] S906) assigning a mileage value to the track centerline, and unifying the track centerline mileage with the railway maintenance mileage by setting the start and end mileages;

[0306] S907) Calculate the distance between the center lines of two adjacent tracks:

[0307] S9071) traverses all vector nodes of one of the track midlines,

[0308] S9072) Calculate the direction vector of each vector point (denoted as point A) and generate a normal plane perpendicular to the direction vector.

[0309] S9073) traverses the vector points of the adjacent track midlines, and finds two adjacent vector nodes (denoted as C and D) located on both sides of the normal plane.

[0310] S9074) calculating the intersection point of the normal plane and the line connecting line segment CD (recorded as point B);

[0311] S9075) calculating the horizontal distance of line segment AB, the horizontal distance of AB being the line spacing at the point;

[0312] S9076) Record the mileage of point A, and the mileage of A is recorded as the mileage value of the line spacing.

[0313] S908) Save and output the result of line spacing calculation.

[0314] 10) Ballast fullness inspection

[0315] The ballast bed is an important part of the track and the foundation of the track frame. The main function of the ballast bed is to support the sleepers, evenly transfer the huge pressure on the top of the sleepers to the roadbed, fix the position of the sleepers, prevent the sleepers from moving longitudinally or laterally, and greatly reduce the deformation of the roadbed while also alleviating the impact of the locomotive wheels on the rails. However, after a long period of locomotive operation and rail lifting and shifting, the ballast bed will have irregular shapes, incomplete ballast and other defects. Therefore, it is necessary to regularly inspect the shape of the ballast bed to detect defects in time. One of the most important inspection indicators of the ballast bed is the fullness of the ballast. The angle of the ballast bed slope is often used to determine the fullness of the ballast. The standard slope of the ballast bed is 1:1.5.

[0316] The railway comprehensive inspection system can quickly and accurately detect and analyze the roadbed based on the acquisition of the panoramic three-dimensional point cloud of the line. First, the point cloud section of the railway line is intercepted to obtain high-precision section data of the roadbed, and then the point cloud of the roadbed part is identified and separated. The angle of the roadbed slope can be obtained through linear fitting to determine whether there is a lack of ballast, etc. Fig.17 The specific implementation steps are as follows:

[0317] S1000) When working in the field, collect the original data of the sensor; when working in the office, generate data such as point cloud, panoramic image and POS trajectory file;

[0318] S1001) Since the point cloud is massive, in order to ensure the smoothness of inspection calculation, the point cloud needs to be segmented. According to the general performance of current processors, it is best to segment the point cloud into point cloud segments of 1GB-3GB in size;

[0319] S1002) synchronously dividing the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments, and matching the POS trajectory file with the point cloud file;

[0320] S1003) reading in the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file segment;

[0321] S1004) using a cloth algorithm to separate and obtain ground point clouds, and removing the point clouds in the air;

[0322] S1005) extracting a point cloud within a range of 2.5 meters in width on both sides of the POS track line as the center line, and the extracted point cloud is a point cloud containing only the track bed part;

[0323] Since the inspection is done on the roadbed, the point cloud needs to be segmented first to separate the point cloud of the roadbed part: since the inertial navigation device is fixedly installed during field operation data collection, the relative position relationship between the inertial navigation device and the roadbed is relatively fixed, so the POS trajectory file can be used to segment and extract the roadbed;

[0324] S1006) In the point cloud obtained in step S1008), since the elevation of the rail is higher than that of the ballast, the point cloud of the rail part can be obtained by using the elevation difference separation;

[0325] S1007) fitting and extracting the rail top surface using the point cloud of the separated rail part to obtain the left and right rail top surface vector lines, and the reliability of the rail top surface vector line extraction can be checked using the rail gauge range of 1435±3mm between the rails;

[0326] S1008) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline;

[0327] S1009) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the starting point and the end point mileage;

[0328] S1010) obtaining the cross section of the point cloud according to the set mileage interval value, and outputting all the cross section point clouds;

[0329] S1011) For each cross-section point cloud, perform the following operations:

[0330] S10111) Since the cross section has a certain thickness (usually between 10 cm and 30 cm), the point cloud in the cross section is first projected onto the cross section to form a two-dimensional point cloud C;

[0331] S10112) Locating the rail in the cross section: the rail can be located by calculating the intersection of the vector line of the top surface of the rail and the cross section;

[0332] S10113) Using the relative position relationship between the ballast bed slope and the rail, the position of the ballast bed slope is located in the cross section. According to the standard of the ballast bed cross section, it can be obtained that: 850mm further outward from the outer rail is the high point of the ballast bed slope, and 850mm+400mm further out is the low point of the ballast bed slope;

[0333] S10114) establishing a standard coordinate system with the line connecting the midpoints of the top surfaces of the left and right rails as the x-axis, the midpoint of the line as the coordinate origin, and the vertical line upward as the y-axis, and rotating and translating the two-dimensional point cloud C to the standard coordinate system;

[0334] S10115) generating a standard cross-section model of the roadbed in the standard coordinate system, calculating the area of ​​the figures sandwiched by the point cloud and the standard model one by one, the area above the standard model is excess ballast, and the area below the standard model is missing ballast, and the ballast fullness of the section can be obtained after the calculation is completed;

[0335] S10116) saving the calculation result of ballast fullness;

[0336] S1012) applying the above steps S10111) to S10116) to calculate and accumulate for each frame of point cloud on a continuous section of the line, so as to obtain the ballast fullness of the entire railway line;

[0337] S1013) Save and output the results of ballast fullness calculation.

[0338] As attached Figure 2 To Attachment Figure 5 As shown, a railway comprehensive inspection system based on the method of the present invention is specifically installed on a railway comprehensive inspection vehicle 100, and the three-dimensional scanning system 1 is installed on the body 101 of the railway comprehensive inspection vehicle 100 as an important device. The specific embodiment of the present invention will provide a railway comprehensive inspection system based on the three-dimensional (mobile) scanning system 1, using the three-dimensional (mobile) scanning system 1 as a data acquisition sensor, and performing subsequent railway infrastructure inspection work based on the rich data obtained by the three-dimensional scanning system 1. It can replace most of the detection systems in the existing railway comprehensive inspection vehicles, and provide some detection or other functions that the original detection system does not have, thereby improving the operating efficiency of the comprehensive inspection system, reducing the system complexity, and greatly saving labor costs. Among them, the three-dimensional (mobile) scanning system 1 integrates a high-precision laser radar 11, a high-resolution panoramic camera 12, a GNSS device 13, an inertial navigation device (i.e., an IMU device 14) and a mileage encoder (i.e., a DMI device 15), which can completely replace the detection equipment of the traditional railway comprehensive inspection vehicle. The three-dimensional scanning system 1 can be used alone to collect data once to collect complete railway track three-dimensional point cloud data, panoramic image data, mileage data, GNSS data and inertial navigation data. The point cloud processing system 40 manages the collected data, automatically analyzes and detects defects, and conducts manual verification.

[0339] As attached Figure 6As shown, an embodiment of a railway comprehensive inspection system based on the method of the present invention specifically includes: a three-dimensional scanning system 1, a time-space synchronization system 2, a storage / control system 3 and an inspection application system 4, wherein the three-dimensional scanning system 1 includes a posture positioning system 10, a laser radar 11 and a panoramic camera 12, and the inspection application system 4 includes a point cloud processing system 40 and a comprehensive inspection analysis system 41. The posture positioning system 10 obtains the GNSS, IMU and DMI data of the railway comprehensive inspection vehicle, the laser radar 11 obtains the three-dimensional coordinate data of the object to be measured, and the panoramic camera 12 obtains the panoramic image data. The time-space synchronization system 2 provides clock synchronization for the three-dimensional coordinates, IMU, DMI and panoramic image data according to the GNSS timing. The storage / control system 3 saves the three-dimensional coordinates, IMU, DMI and panoramic image data after clock synchronization in real time. The point cloud processing system 40 first uses the GNSS, IMU and DMI data to fuse and solve the POS data, then uses the POS data and the laser radar data to jointly calculate the point cloud data, and then fuses the point cloud data with the panoramic image data to obtain the real-time point cloud. The comprehensive inspection and analysis system 41 uses point cloud and panoramic image data as data sources to perform railway inspection and analysis and railway infrastructure detection and analysis. Figure 7 The functions of each device in the railway comprehensive inspection system are introduced in detail below.

[0340] The hardware of the entire railway comprehensive inspection system is mainly divided into three parts: the three-dimensional (mobile) scanning system 1 outside the vehicle, the storage / control system 2 inside the vehicle, the point cloud processing system 40 on the ground and the comprehensive inspection analysis system 41. The ground comprehensive inspection analysis system 41 uses the data obtained by the three-dimensional scanning system 1 as input and is equipped with different detection (software) function modules for different detection points. Among them, the three-dimensional (mobile) scanning system 1 integrates two laser scanners (i.e., laser radar 11), a panoramic camera 12, a GNSS device 13, a high-precision IMU device 14, a DMI device 15 and other electrical equipment.

[0341] Laser radar 11: It is a sensor used to obtain the local three-dimensional coordinates of the surface of the scanned object at high speed. It can rotate 360° for laser scanning and obtain high-precision three-dimensional coordinates with the laser radar phase center as the coordinate origin at a speed of 1 million points per second. In this embodiment, the Z+F9012 laser radar can be used. The point frequency of this radar reaches 1.016 million points / second, the rotation speed reaches 200 revolutions / second, the ranging range reaches 190 meters, and the ranging accuracy is less than 2mm. It is the laser radar with the highest ranging accuracy under the same point frequency conditions at this stage. Since railway detection has high requirements for various data indicators, in this embodiment, two Z+F9012 laser radars can also be carried at the same time, and the laser planes are crossed at 90° to achieve a higher point cloud density while reducing the occlusion of cylindrical objects.

[0342] Panoramic camera 12: collects panoramic photos at a fixed frequency, and can specifically use a ladybug5Plus camera. The panoramic photos output by this camera have a resolution of 30 million pixels and a frame rate of up to 5 frames per second.

[0343] The attitude positioning system 10 further includes a GNSS device 13, an IMU device 14 (i.e., an inertial navigation device) and a DMI device 15 (i.e., a mileage encoder). Among them, the GNSS device 13 is a global navigation satellite system, which obtains absolute geodetic coordinate information and accurate clock information at a frequency of 20 Hz, and is used to provide the system with real-time geodetic coordinate data and an accurate timing clock source. The IMU device 14 is an inertial navigation unit, which calculates the three-axis acceleration and posture data of the device at a frequency of 200 Hz, and is used to provide the system with real-time posture data. It is used in conjunction with the GNSS to form a positioning and attitude system, and provides the system with real-time position and posture data. The DMI device 15 is a mileage encoder, which is installed on the rotating shaft of the wheelset and is used to provide mileage information.

[0344] The above sensors are installed on the railway comprehensive inspection vehicle 100 according to the designed rigid body structure, that is, high-precision three-dimensional geometric information and image texture information within 50 meters of the center line of the railway line can be synchronously collected as the vehicle body 101 moves forward. The GNSS device 13, the IMU device 14 and the DMI device 15 together constitute the positioning and attitude determination system 10 of the railway comprehensive inspection system. The IE (Inertial Explorer) post-processing software is used to jointly solve the three navigation data to obtain the corresponding posture and position. With the assistance of these three positioning and attitude determination sensors, the laser scanner (i.e., laser radar 11) enables the system to obtain absolute three-dimensional geometric information, while the panoramic camera 12 can collect image texture information. By fusing the acquired laser scanner data with the panoramic image data, three-dimensional point cloud data including color information can be obtained.

[0345] Space-time synchronization system 2: It is used to receive GNSS timing and can stamp all the above sensor data with a unified high-precision time stamp in real time, providing a high-precision clock synchronization basis for subsequent internal data processing.

[0346] Storage / control system 3: This system contains multiple sensors with very large data volumes, so it is equipped with a special storage system to save the original data of each sensor after clock synchronization in real time. At the same time, the system can also control the operation of the entire railway comprehensive inspection system.

[0347] Point cloud processing system 40: This system uses the original data in the storage / control system 3 as input, and after internal processing, outputs an overall three-dimensional point cloud based on geodetic coordinates to achieve the matching of panoramic images (photos) and point clouds. The three-dimensional point cloud contains high-precision absolute coordinate information and relative coordinate information, and uses the reflection intensity of the laser point to generate a grayscale image, and uses a panoramic camera to generate a true color image. Therefore, the data obtained by the three-dimensional mobile measurement system (i.e., the three-dimensional scanning system 1) not only contains accurate dimensional data, but also rich image data, which can be used for comprehensive railway inspection.

[0348] The point cloud processing system 40 first uses GNSS, IMU and DMI data fusion to solve POS data, and then uses POS data and LiDAR data to jointly calculate point cloud data. After obtaining POS data, the pose data is calculated for each panoramic photo. After obtaining the pose information of the panoramic photo, the panoramic photo can be combined with the point cloud for joint use.

[0349] In a specific embodiment of the present invention, the data output by the laser radar 11 and the panoramic camera 12 per unit time is very large, so the real-time collected data is first stored in the storage / control system 3 in the vehicle, and then transferred offline to the comprehensive inspection (processing) system 41 on the ground side through a mobile hard disk or other means for unified processing. Among them, the three-dimensional point cloud contains high-precision absolute coordinate information and relative coordinate information, and at the same time, a grayscale image is generated using the reflection intensity of the laser point, and a true color image is generated using the panoramic camera 12. Therefore, the data acquired by the three-dimensional mobile measurement system (i.e., the three-dimensional scanning system 1) not only contains accurate dimensional data, but also rich image data, which can be used to realize a variety of railway line comprehensive inspection functions. The specific functional items are shown in the attached figure. Figure 6 shown.

[0350] The three-dimensional scanning system 1 includes a posture positioning system 10, a laser radar 11 and a panoramic camera 12, and the posture positioning system 10 further includes a GNSS device 13, an IMU device 14 and a DMI device 15. In order to ensure the unobstructed laser radar and the image acquisition performance of the panoramic camera, the laser radar 11, the panoramic camera 12, the GNSS device 13 and the IMU device 14 of the three-dimensional scanning system 1 are installed on the roof platform 102 at the head or tail of the railway comprehensive inspection vehicle body 101, and the mileage encoder (i.e., the DMI device 15) is installed on the wheel axle. The interior of the vehicle body 101 is provided with a control box 104 (in which a storage / control system 3 is installed), a power supply 107, a control terminal 111, etc. The three-dimensional scanning system 1 is connected to the control box 104 through a host cable 103, and the control box 104 is connected to the control terminal 111 through a network cable 110. The encoder signal input 105 is connected to the control box 104 , and the AC input 109 is input into the power supply 107 (specifically, a UPS uninterruptible power supply can be used) through the air switch 108 and then supplies power to the control box 104 through the power line 106 .

[0351] The operation process of using the system described in the specific embodiment of the present invention to perform comprehensive inspection of railway lines is divided into field raw data collection and indoor data processing. The specific process is shown in the attached figure. Figure 7 As shown. The system first collects the original data of sensors such as GNSS, IMU, laser scanner, panoramic camera, DMI, etc. through field operations, saves the data and performs simple data verification. During the internal operations, the original data collected in the field is transferred to the point cloud processing system 40 on the ground side through mobile hard disk transfer or network and other means to generate three-dimensional point clouds and panoramic images. The internal data platform first uses GNSS, IMU and DMI data fusion to solve the POS data, and then uses POS data and lidar data to jointly calculate the point cloud data. The point cloud data is fused with panoramic photos to obtain a true color real-life scenic spot cloud. Finally, the comprehensive inspection and analysis system 41 uses point clouds and panoramic photos as data sources to perform various railway inspection analyses and infrastructure detection analyses.

[0352] The comprehensive inspection and analysis system 41 includes a slope hazard inspection module 42. A number of laser marker targets are set on the railway slopes that need to be inspected. The three-dimensional scanning system 1 collects raw data during field operations, and the point cloud processing system 40 generates point cloud and panoramic image data during indoor operations. Figure 8 As shown, the slope disaster inspection module 42 performs accurate extraction of laser marker targets from the scanned point cloud data, and sets a unique number or name for the extracted laser marker targets. The laser marker targets at the same position in the point clouds obtained by scanning in different periods have the same number or name. The current point cloud is obtained, and then the previous point cloud to be compared is read in. The mileage and coordinates of the laser marker targets are used to roughly superimpose and display the two point clouds, and the accurate point cloud superposition parameters are calculated using the previous laser marker target coordinates and the current laser marker target coordinates. The current coordinates are converted using the accurate point cloud superposition parameters, and after the conversion, accurate point cloud superposition and comparison are performed. After superposition, the coordinate difference of the same position in the two point clouds is calculated. Check the result of the change, and retrieve the current and previous panoramic images for areas with large coordinate differences to manually confirm whether a slope change has occurred. Save the coordinate difference of the point cloud superposition comparison, read in the previous point cloud comparison coordinate difference, draw a coordinate difference change curve, detect whether the coordinate difference has a trend of gradually enlarging, and issue an early warning or alarm for areas where the coordinate difference shows a gradually enlarging trend. Among them, the slope hazard inspection module 42 meshes the current point cloud, performs plane fitting on the first processed point cloud grid C, obtains the plane P, and obtains the center coordinate O of the point cloud grid C. Then the normal of the plane P passing through point O is obtained to obtain the normal line L, the intersection point J of the normal line L and the previous point cloud is obtained, and the distance of the line segment OJ is calculated, which is the change amount of the same position in the two point clouds. Each grid in the current point cloud is traversed, and the change amount of each grid point cloud before and after is calculated, so as to obtain the coordinate difference of the same position in the two point clouds.

[0353] The comprehensive inspection and analysis system 41 includes a slope hazard assessment module 43. Several laser marker targets are set on the railway slopes that need to be inspected. The three-dimensional scanning system 1 collects raw data during field operations, and the point cloud processing system 40 generates point clouds and panoramic image data during indoor operations. The slope hazard assessment module 43 extracts laser marker targets from the scanned point cloud data, and sets a unique number or name for the extracted laser marker targets. The laser marker targets at the same position in the point clouds of different periods have the same number or name. The current point cloud is obtained, and then the previous point cloud to be compared is read in. The mileage and coordinates of the laser marker targets are used to perform a rough superposition display of the two point clouds, and the previous laser marker target coordinates and the current laser marker target coordinates are used to calculate the precise point cloud superposition parameters. The current coordinates are converted using the precise superposition parameters, and after the conversion, precise point cloud superposition comparison is performed. After superposition, the point cloud coordinate difference at the same position in the two point clouds is calculated, and the difference in the elevation coordinate z is compared in particular. The volume of the part contained in the two point clouds is calculated by using the coordinate difference of the two point clouds, which is the earth and stone of the landslide, and the area of ​​the landslide part is calculated. The panoramic image data of the previous scan is retrieved to view the actual topography of the disaster point, and the three-dimensional point cloud is intercepted and saved according to the mileage. At the same time, the mileage where the emergency occurred is located, and the three-dimensional point cloud and panoramic image at this location are used as the base map for emergency treatment, providing a map reference for emergency treatment.

[0354] The comprehensive inspection and analysis system 41 includes a line virtual inspection / addition module 44. The three-dimensional scanning system 1 collects raw data during field operations, and the point cloud processing system 40 generates point clouds, panoramic images, and POS track files during office operations. The line virtual inspection / addition module 44 uses the calibrated panoramic image to assign true color values ​​to the grayscale point cloud, generates true color point clouds, divides the true color point clouds into point cloud segments, and divides the POS track files into POS track file segments corresponding to the point cloud segments. Read in the point cloud segments and corresponding POS track files of the mileage to be inspected. The default viewpoint of the line virtual inspection / addition module 44 display interface is located at the starting point of the POS track file, and the field of view direction is consistent with the POS track file. After the user clicks Start, the point cloud can be roamed in a variety of ways to achieve the visual effect of virtual inspection / addition. During the point cloud roaming process, the user can change the field of view direction and pause the point cloud movement at any time. After pausing the point cloud movement, the user can view specific components by zooming in and out the panoramic image corresponding to the point cloud to view the image information of the component. If a component has a defect or fault, the line virtual inspection / addition module 44 outputs the defect information by creating a defect report. When the inspection of a section of point cloud is completed, the next section of point cloud is automatically read in for inspection until the line inspection is completed.

[0355] The comprehensive inspection and analysis system 41 includes an acoustic and wind barrier inspection module 47. Several laser marker targets are set on the railway barriers that need to be inspected. The three-dimensional scanning system 1 collects raw data during field operations. The point cloud processing system 40 generates point clouds, POS trajectory files and panoramic image data during indoor operations. The acoustic and wind barrier inspection module 47 manually intercepts the point cloud of the section that only contains the barrier. If the section is long, the point cloud is divided into point cloud segments, and the POS trajectory file is divided into POS trajectory file segments corresponding to the point cloud segments, and the POS trajectory file is matched with the point cloud. The point cloud segments of the mileage to be inspected and the corresponding POS trajectory files are read in, the point cloud of the aerial part is separated to obtain the ground point cloud, and the ground point cloud is segmented to separate the point cloud of the barrier part. Extract the point cloud C with the POS trajectory line as the center line and the set width range on both sides, perform height filtering on the point cloud C, remove the point cloud with the elevation coordinate z value less than the set value, and obtain the remaining point cloud C', then calculate the point cloud normal of C', remove the point cloud that is not perpendicular to the POS trajectory line in the point cloud, and finally the remaining is the point cloud CP containing only the barrier part. Extract the laser mark target from the point cloud CP, and set a unique number or name for the extracted laser mark target. The laser mark targets at the same position in the point clouds of different periods have the same number or name. Read in the previous point cloud to be compared, use the mileage and coordinates of the laser mark target to roughly overlay and display the two periods of point clouds, and use the previous laser mark target coordinates and the current laser mark target coordinates to calculate the precise point cloud overlay parameters. Use accurate overlay parameters to transform the current coordinates, perform accurate point cloud overlay comparison after transformation, traverse the current point cloud after overlay, and count the number of point clouds within the set radius for each point cloud. For point clouds whose number in the previous point cloud is not 0 but in the current point cloud is 0, it is considered that the barrier in the current point cloud has been damaged. Calculate the area of ​​the damaged part, save the current scanned panoramic image and 3D point cloud at the damaged mileage, so that the staff can confirm it manually afterwards.

[0356] The comprehensive inspection and analysis system 41 includes an overhead line pole verticality inspection module 411. After collecting the holographic point cloud around the railway, the overhead line pole verticality inspection module 411 performs point cloud segmentation to obtain the point cloud of the pole part, obtains the point cloud center of the pole part, and performs straight line fitting to obtain the vector equation of the center of the overhead line pole, and obtains the verticality of the pole. The three-dimensional scanning system 1 performs raw data acquisition during field operations, and the point cloud processing system 40 generates point clouds, POS trajectory files and panoramic image data during indoor operations. The overhead line pole verticality inspection module 411 divides the point cloud into point cloud segments, and divides the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments, and matches the POS trajectory file with the point cloud file. Read in the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file, use the POS trajectory to delete the redundant point cloud, and the remaining point cloud is C. All poles are found, and the position and slope of each pole are calculated, and the calculation results are saved and output. Among them, the overhead line pole verticality inspection module 411 obtains a cross section of the point cloud at the starting point of the POS track. The height of the cross section is the same as the POS track and the cross section is horizontal, and the intersection of the cross section and the point cloud C is obtained. The diameter or size of the point cloud at each intersection is calculated respectively, and the distance between the centers of the point clouds at two adjacent intersections is calculated. The diameter of the pole is a fixed value, and the distance between the poles is also a fixed value to eliminate interference items, and the remaining point cloud is the pole. The pole is recorded as D, and the coordinates of the center of the pole are x, y. Starting from the starting point of the POS track, a cross section is obtained every set distance, and the obtained poles are merged into D, and all poles D are calculated cyclically. The overhead line pole verticality inspection module 411 takes out a pole Di (xi, yi) in D, extracts the point cloud C-Di with Di (xi, yi) as the center and within the set radius in the point cloud C, and calculates the maximum value zmax and minimum value zmin of the elevation coordinates zi of all points in the point cloud C-Di. Between the maximum value zmax and the minimum value zmin, a horizontal cross section is set at a set distance, the intersection surface of the cross section and the point cloud C-Di is obtained, and the center coordinate oi of the intersection surface point cloud is obtained. After obtaining the center of the intersection surface of all cross sections and the point cloud C-Di, all center points are fitted into a straight line, and the slope of the straight line is obtained, and the position and slope of the pole are recorded.

[0357] The comprehensive inspection and analysis system 41 includes a track geometry parameter detection module 45. The three-dimensional scanning system 1 collects point cloud and panoramic image raw data during field operations, and the point cloud processing system 40 generates point cloud, POS track files and panoramic image data during office operations. Fig.13As shown, the track geometry parameter detection module 45 segments the generated point cloud and divides the POS track file into file segments corresponding to the point cloud segments. A segment of point cloud is read in, and the ground point cloud is separated. The POS track file corresponding to the segment of point cloud is read in, and the point cloud with the POS track as the center and the distance exceeding the set range is removed. The remaining point cloud is the point cloud containing only the roadbed. In the ground point cloud, the point cloud of the rail part is separated by elevation difference, and the point cloud of the separated rail part is used to fit and extract the top surface of the rail to obtain the left and right two rail top surface vector lines (i.e., the center line of the rail top surface along the track direction), and the gauge range between the rails is used to check the credibility of the extraction of the rail top surface vector line. The vector lines of the extracted left and right rails are used to calculate the track centerline to obtain the track centerline vector. The vector nodes of the centerline vector are spaced at a set distance to assign a mileage value to the track centerline. The mileage of the track centerline is unified with the railway maintenance mileage by setting the starting and end mileages. The coordinates of the centerline of the track are refined, and the refined centerline vector line of the track is output for the calculation of the line geometry parameters. Among them, the track geometry parameter detection module 45 calculates the cross section of the rail passing through the centerline vector node of the track, and the thickness of the cross section does not exceed the set distance. The point cloud on the cross section is projected relative to the cross section, and the two-dimensional coordinates of the cross section of the rail are obtained after projection. The cross sections of the left and right rails are accurately matched with the standard profile of the rail respectively. After matching, the top surface coordinates of the left and right rails are obtained, and the top surface coordinates of the original rail are updated using the top surface coordinates. Calculate the precise centerline coordinates of the track, update the original centerline vector node coordinates of the track, traverse and calculate all the centerline vector nodes that have been obtained, and complete the refinement of the coordinates of the centerline of the track.

[0358] The comprehensive inspection and analysis system 41 includes a track limit and contour inspection module 46. The three-dimensional scanning system 1 collects point cloud and panoramic image raw data during field operations, and the point cloud processing system 40 generates point cloud and panoramic image data during office operations. Fig.14As shown, the track limit and profile inspection module 46 segments the generated point cloud, reads in a segment of the point cloud, separates it to obtain the ground point cloud, and in the ground point cloud, uses the elevation difference to separate the point cloud of the rail part. The separated point cloud of the rail part is used to fit and extract the rail top surface, and the left and right rail top surface vector lines are obtained, and the reliability of the rail top surface vector line extraction is checked using the gauge range between the rails. The track centerline is calculated using the extracted left and right rail top surface vector lines, and the track centerline is obtained. The mileage value is assigned to the track centerline, and the mileage of the track centerline is unified with the railway maintenance mileage by setting the starting and end mileages. The cross section of the point cloud is obtained according to the set mileage interval value, and all cross-section point clouds are output. The limit calculation is performed for each cross-section point cloud, and the result of the limit calculation is saved and output. Among them, the track limit and profile inspection module 46 takes the intersection of the cross section and the track centerline as the coordinate origin, the x-axis is parallel to the top surface of the rail and points to the centerline of the top surface of the right rail along the track direction, and the z-axis is perpendicular to the x-axis and upward to establish a limit reference coordinate system. The cross-section point cloud is projected relative to the cross section, and the two-dimensional coordinates of the rail cross-section point cloud are obtained after projection. The two-dimensional coordinates of the cross-section point cloud are converted to the limit reference coordinate system and a standard building limit model is generated in the coordinate system. The cross-section point cloud and the standard building limit model are superimposed for collision analysis, and the limit calculation results are obtained and saved.

[0359] The comprehensive inspection and analysis system 41 includes a contact network geometric parameter inspection module 48, a 3D scanning system 1 collects point cloud and panoramic image raw data during field operations, and a point cloud processing system 40 generates point cloud, POS trajectory files and panoramic image data during office operations. Fig.15As shown, the contact network geometric parameter inspection module 48 segments the generated point cloud and divides the POS trajectory file into file segments corresponding to the point cloud segments. Read in a point cloud segment and the POS trajectory file corresponding to the point cloud segment, remove the point cloud centered on the POS trajectory and the distance from the POS trajectory beyond the set range, and the remaining point cloud is the point cloud Ce that only contains the roadbed and the roadbed above. Extract the point cloud Cf-d of the ground part in the point cloud Ce, take out the point cloud Cf-d from the point cloud Ce to obtain the point cloud Cf-k of the aerial part, and use the elevation difference to separate the point cloud of the rail part in the ground point cloud Cf-d. Use the separated point cloud of the rail part to fit and extract the rail top surface, and obtain the left and right rail top surface vector lines, and use the gauge range between the rails to check the credibility of the rail top surface vector line extraction. Use the extracted left and right rail top surface vector lines to calculate the track centerline, and obtain the track centerline vector, and the vector node interval of the centerline vector is the set distance. Assign a mileage value to the center line of the track, and unify the mileage of the center line of the track with the railway maintenance mileage by setting the starting and ending mileages. Identify and extract the contact network line in the aerial point cloud Cf-k, and perform vector line fitting, with the distance between vector nodes being the set value. Calculate the geometric parameters of adjacent contact network lines, save and output the geometric parameters of the contact network lines. Among them, the contact network geometric parameter inspection module 48 traverses all the vector nodes on the center line of the top surface of the left rail in the railway rail, calculates the direction vector of each vector node A, and generates a normal plane F perpendicular to the direction vector. Traverse the vector nodes of the center line of the top surface of the right rail, find two vector nodes C and D located on both sides of the normal plane F and adjacent to each other, and calculate the intersection B of the line connecting the normal plane F and CD. Traverse the vector nodes of the contact network line, find two vector nodes E and F located on both sides of the normal plane F and adjacent to each other, and calculate the intersection G of the line connecting the normal plane F and EF. Draw a perpendicular line to line segment AB through point G, with the foot of the perpendicular denoted as point H and the midpoint of line segment AB denoted as I. The length of the line HI is the contact line pull-out value at the mileage corresponding to point I, and the length of GH is the contact line conductance value at the mileage corresponding to point I, thereby obtaining the geometric parameters of adjacent contact network lines.

[0360] The comprehensive inspection and analysis system 41 includes a line spacing inspection module 49. The three-dimensional scanning system 1 collects point cloud and panoramic image raw data during field operations, and the point cloud processing system 40 generates point cloud and panoramic image data during indoor operations. The line spacing inspection module 49 segments the generated point cloud, reads in a segment of point cloud, separates it to obtain the ground point cloud, and uses the elevation difference to separate the point cloud of the rail part. The point cloud of the separated rail part is used to fit and extract the rail top surface, and the left and right rail top surface vector lines are obtained. The gauge range between the rails is used to check the reliability of the rail top surface vector line extraction. The extracted left and right rail top surface vector lines are used to calculate the track centerline, and the track centerline is obtained. The mileage value is assigned to the track centerline, and the mileage of the track centerline is unified with the railway maintenance mileage by setting the starting point and end point mileage. The line spacing between the centerlines of two adjacent tracks is calculated, and the line spacing is saved and output. The line spacing inspection module 49 traverses all vector nodes in the center line of one track, calculates the direction vector of each vector node A, and generates a normal plane perpendicular to the direction vector. The vector nodes of the center lines of adjacent tracks are traversed, and two vector nodes C and D located on both sides of the normal plane and adjacent to each other are found, and the intersection point B of the normal plane and the line connecting CD is calculated. The horizontal distance of AB is calculated, and the horizontal distance of AB is the line spacing at this point, and the mileage of point A is recorded, and the mileage of A is recorded as the mileage value of the line spacing.

[0361] The comprehensive inspection and analysis system 41 includes a ballast fullness inspection module 410. The three-dimensional scanning system 1 collects raw data during field operations, and the point cloud processing system 40 generates point clouds, POS trajectory files, and panoramic image data during office operations. Fig.17As shown, the ballast fullness inspection module 410 divides the point cloud into point cloud segments, divides the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments, and matches the POS trajectory file with the point cloud file. Read the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file, separate the ground point cloud, remove the point cloud in the air, extract the point cloud within the set width range on both sides with the POS trajectory line as the center line, and the extracted point cloud is the point cloud containing only the roadbed part. In the point cloud containing only the roadbed part, the point cloud of the rail part is separated by elevation difference, and the point cloud of the separated rail part is used to fit and extract the top surface of the rail to obtain the left and right two rail top surface vector lines, and the gauge range between the rails can be used to check the credibility of the extraction of the rail top surface vector line. The center line of the track is calculated using the extracted left and right two rail top surface vector lines to obtain the center line of the track, and the mileage value is assigned to the center line of the track. The mileage of the center line of the track is unified with the railway maintenance mileage by setting the starting point and end point mileage. The cross section of the point cloud is obtained according to the set mileage interval value, and all the cross-sectional point clouds are output. The ballast fullness is calculated for each cross-sectional point cloud. The ballast fullness is calculated for each frame of point cloud in a continuous section of line and then accumulated to obtain the ballast fullness of the entire section of the line, and the result of the limit calculation is saved and output. Among them, the ballast fullness inspection module 410 projects the point cloud in the cross section to the cross section to make it a two-dimensional point cloud C. The rail is located in the cross section by calculating the intersection of the vector line on the top surface of the rail and the cross section, and the relative position relationship between the roadbed slope and the rail is used to locate the position of the roadbed slope in the cross section. A standard coordinate system is established with the line connecting the center lines of the top surfaces of the left and right rails as the x-axis, the midpoint of the line as the coordinate origin, and the vertical line upward as the y-axis, and the two-dimensional point cloud C is rotated and translated to the standard coordinate system. Generate a standard cross-section model of the track bed in the standard coordinate system, and calculate the area of ​​the figures enclosed by the point cloud and the standard model one by one. The area above the standard model is excess ballast, and the area below is missing ballast. After the calculation is completed, the ballast fullness of the section can be obtained.

[0362] The railway comprehensive inspection system described in the specific embodiment of the present invention uses a three-dimensional scanning system 1 to scan and obtain a high-precision holographic point cloud and a high-resolution panoramic image within a range of 50 meters from the railway centerline. After the panoramic image and the point cloud are accurately matched, a true-color holographic point cloud can be obtained. Then, on the basis of the obtained point cloud and panoramic image, railway-related inspection work is carried out, which can replace most of the detection system functions in the existing railway comprehensive inspection vehicle and provide some detection or other functions that the original detection system does not have. Due to the high integration performance of the system, the extremely rich data collected, and the high accuracy of the point cloud, more railway infrastructure detection functions and railway asset management, census and other functions can be realized. Compared with previous equipment, the complexity of the system is greatly reduced, the operating efficiency of the comprehensive inspection system is improved, labor costs are saved, and economic practicality is improved.

[0363] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, segment or portion of code that includes one or more executable instructions for implementing the steps of a specific logical function or process, and the scope of the preferred embodiments of the present invention includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by those skilled in the art to which the embodiments of the present invention belong.

[0364] A person of ordinary skill in the art can understand that all or part of the steps carried out in the above-mentioned embodiment method can be completed by instructing related hardware through a program, and the program can be stored in a computer-readable medium. When the program is executed, it includes one of the steps of the method embodiment or a combination thereof.

[0365] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0366] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course by hardware, but in many cases the former is a better implementation method.

[0367] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the conditions under which this application can be implemented. Therefore, they have no substantive technical significance. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical content disclosed in this application without affecting the effects and purposes that can be achieved by this application.

[0368] By implementing the technical solution of the railway comprehensive inspection method described in the specific embodiment of the present invention, the following technical effects can be produced:

[0369] (1) The railway comprehensive inspection method described in the specific embodiment of the present invention replaces the existing multiple systems on the comprehensive inspection vehicle with data collected by a single set of equipment, greatly improving the integration of the detection equipment. Both the complexity of the system and operation and the economic cost are far lower than the existing comprehensive inspection system;

[0370] (2) In the railway comprehensive inspection method described in the specific embodiment of the present invention, the data collected by a single set of equipment can be used by multiple sets of subsequent application systems, thereby increasing the compatibility of data between multiple detection devices, realizing the multiplexing of multiple devices and the interconnection of detection data, and reducing the complexity of application system development;

[0371] (3) The railway comprehensive inspection method described in the specific embodiment of the present invention makes extensive use of point cloud data. Compared with the previous detection application based on plane images, it can not only perform qualitative analysis, but also perform accurate quantitative analysis. It can not only realize a large number of infrastructure detection functions, but also realize disaster analysis and assessment, and has richer functions.

[0372] (4) The railway comprehensive inspection method described in the specific embodiment of the present invention adopts three-dimensional real-scene inspection, has true color point cloud and panoramic image, and can perform accurate measurement. Compared with the previous image-based inspection, it is a huge improvement. At the same time, it provides a virtual inspection function, which greatly reduces the workload of patrol workers and greatly improves the accuracy and automation of patrol.

[0373] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0374] The above is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as above in the preferred embodiment, it is not used to limit the present invention. Any technician familiar with the art can make many possible changes and modifications to the technical solution of the present invention by using the methods and technical contents disclosed above without departing from the spirit and technical solution of the present invention, or modify it into an equivalent embodiment of equivalent changes. Therefore, any simple modification, equivalent replacement, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the scope of protection of the technical solution of the present invention.

Claims

1. A railway comprehensive inspection method, It is characterized in that The following steps are involved: S1) obtaining the three-dimensional coordinate data of the object to be measured, obtaining the GNSS, IMU and DMI data of the railway comprehensive inspection vehicle, and obtaining the panoramic image data; S2) Provide clock synchronization for 3D coordinates, IMU, DMI and panoramic image data based on GNSS timing; S3) Real-time storage of the three-dimensional coordinates, IMU, DMI and panoramic image data after clock synchronization; S4) firstly, GNSS, IMU and DMI data are used to fuse and calculate POS data, then the POS data and the three-dimensional coordinate information of the measured object are used to jointly calculate the point cloud data, and then the point cloud data is fused with the panoramic image data to obtain the real-time point cloud; S5) Using point cloud and panoramic image data as data sources, conduct railway infrastructure inspection and analysis; During field work, point cloud and panoramic image raw data are collected, and during office work, point cloud, POS track file and panoramic image data are generated; the step S5) further includes the following track geometry parameter detection step: S601) segmenting the generated point cloud and dividing the POS trajectory file into file segments corresponding to the point cloud segments; S602) reading in a segment of point cloud and separating it to obtain a ground point cloud; S603) reading in the POS trajectory file corresponding to the segment of the point cloud; S604) removing the point cloud centered on the POS track and whose distance exceeds the set range, and the remaining point cloud is the point cloud containing only the roadbed; S605) In the ground point cloud, using elevation difference separation to obtain a point cloud of the rail part; S606) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails; S607) calculating the track centerline using the extracted left and right rail top surface vector lines to obtain the track centerline vector, where the vector node interval of the track centerline vector is a set distance; S608) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages; S609) performing fine processing on the coordinates of the track centerline; S610) Output the calculated refined track centerline vector line for calculation of line geometry parameters.

2. The railway comprehensive inspection method according to claim 1, It is characterized in that The step S609) further comprises: S6091) Calculate the rail cross section passing through the track centerline vector node, and the thickness of the cross section does not exceed the set distance; S6092) projecting the point cloud on the cross section relative to the cross section, and obtaining the two-dimensional coordinates of the rail cross section after projection; S6093) accurately matching the cross sections of the left and right rails with the standard profiles of the rails respectively; S6094) After matching, the top surface coordinates of the left and right rails are obtained, and the top surface coordinates of the original rails are updated using the top surface coordinates; S6095) Calculate the precise orbit centerline coordinates, update the original orbit centerline vector node coordinates, and traverse and calculate all orbit centerline vector nodes that have been obtained.

3. The railway comprehensive inspection method according to claim 1 or 2, It is characterized in that During field work, point cloud and panoramic image raw data are collected, and during office work, point cloud and panoramic image data are generated; the step S5) further includes the following track limit and contour inspection steps: S701) segmenting the generated point cloud; S702) reading in a segment of point cloud and separating it to obtain a ground point cloud; S703) In the ground point cloud, using elevation difference separation to obtain a point cloud of the rail part; S704) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails; S705) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline; S706) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages; S707) obtaining the cross section of the point cloud according to the set mileage interval value, and outputting all the cross section point clouds; S708) performing limit calculation for each cross-section point cloud; S709) Save and output the results of the limit calculation.

4. The railway comprehensive inspection method according to claim 3, It is characterized in that The step S708) further comprises: S7081) The intersection of the cross section and the center line of the track is taken as the coordinate origin, the x-axis is parallel to the top surface of the rail and points to the center line of the top surface of the right rail along the track direction, and the z-axis is perpendicular to the x-axis and upward to establish a limit reference coordinate system; S7082) projecting the cross-sectional point cloud relative to the cross section to obtain the two-dimensional coordinates of the rail cross-sectional point cloud after projection; S7083) converting the two-dimensional coordinates of the cross-section point cloud to a limit reference coordinate system; S7084) generating a standard building boundary model in a boundary reference coordinate system; S7085) Perform collision analysis by superimposing the cross-section point cloud with the standard building limit model and obtain the limit calculation result.

5. The railway comprehensive inspection method according to claim 1, 2 or 4, It is characterized in that During field work, point cloud and panoramic image raw data are collected, and during office work, point cloud, POS trajectory files and panoramic image data are generated; the step S5) further includes the following contact network geometric parameter inspection steps: S801) segmenting the generated point cloud and dividing the POS trajectory file into file segments corresponding to the point cloud segments; S802) reading in a point cloud segment and a POS trajectory file corresponding to the point cloud segment; S803) removing the point cloud centered on the POS track and beyond the set range from the POS track, and the remaining point cloud is the point cloud Ce that only includes the roadbed and the point cloud above the roadbed; S804) extracting the point cloud Cf-d of the ground part in the point cloud Ce, and taking out the point cloud Cf-d in the point cloud Ce to obtain the point cloud Cf-k of the aerial part; S805) In the ground point cloud Cf-d, the point cloud of the rail part is obtained by using the elevation difference separation; S806) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails; S807) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline vector, where the vector node interval of the track centerline vector is a set distance; S808) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages; S809) in the aerial point cloud Cf-k, identifying and extracting the contact network line, and performing vector line fitting, the distance between the vector nodes is a set value; S810) calculating geometric parameters of adjacent contact wires; S811) Save and output the results of the contact network line geometric parameter calculation.

6. The railway comprehensive inspection method according to claim 5, It is characterized in that The step S810) further comprises: S8101) traverse all vector nodes of the center line of the top surface of the left rail in the railway rail; S8102) calculating the direction vector of each vector node A and generating a normal plane perpendicular to the direction vector; S8103) traverse the vector nodes of the center line of the top surface of the right rail, and find two vector nodes C and D located on both sides of the normal plane and adjacent to each other; S8104) calculating the intersection point B of the normal plane and the line CD; S8105) traversing the vector nodes of the contact network line to find two vector nodes E and F located on both sides of the normal plane and adjacent to each other; S8106) calculating the intersection point G of the normal plane and the line EF; S8107) Draw a perpendicular line through point G to line segment AB, with the foot of the perpendicular denoted as point H and the midpoint of line segment AB denoted as I; S8108) The length of the line connecting HI is the contact line pull-out value at the corresponding mileage of point I; S8109) The length of GH is the contact line height at the corresponding mileage of point I.

7. The railway comprehensive inspection method according to claim 1, 2, 4 or 6, It is characterized in that During field work, point cloud and panoramic image raw data are collected, and during office work, point cloud and panoramic image data are generated; the step S5) further includes the following line spacing inspection steps: S901) segmenting the generated point cloud; S902) reading in a segment of point cloud and separating it to obtain a ground point cloud; S903) In the ground point cloud, using elevation difference separation to obtain a point cloud of the rail part; S904) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and checking the reliability of the rail top surface vector line extraction using the gauge range between the rails; S905) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline; S906) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages; S907) calculating the line spacing between the center lines of two adjacent tracks; S908) Save and output the result of line spacing calculation.

8. The railway comprehensive inspection method according to claim 7, It is characterized in that The step S907) further comprises: S9071) traverses all vector nodes of one of the track midlines, S9072) calculating the direction vector of each vector node A, and generating a normal plane perpendicular to the direction vector; S9073) traverse the vector nodes of the adjacent track midlines to find two adjacent vector nodes C and D located on both sides of the normal plane; S9074) calculating the intersection point B of the normal plane and the line connecting the line segment CD; S9075) calculating the horizontal distance of line segment AB, the horizontal distance of AB being the line spacing at the point; S9076) Record the mileage of point A, and the mileage of A is recorded as the mileage value of the line spacing.

9. The railway comprehensive inspection method according to claim 1, 2, 4, 6 or 8, It is characterized in that During field work, raw data collection is performed, and during office work, point cloud, POS trajectory file and panoramic image data are generated; the step S5) further includes the following ballast fullness inspection steps: S1001) dividing the point cloud into point cloud segments; S1002) simultaneously dividing the POS trajectory file into POS trajectory file segments corresponding to the point cloud segments, and matching the POS trajectory file with the point cloud file; S1003) Read in the point cloud segment of the mileage to be inspected and the corresponding POS trajectory file; S1004) Separating the ground point cloud and removing the aerial point cloud; S1005) extracting point clouds within a set width range on both sides of the POS track line as the center line, and the extracted point cloud is a point cloud containing only the track bed part; S1006) in the point cloud containing only the ballast part, using the elevation difference to separate and obtain the point cloud of the rail part; S1007) fitting and extracting the rail top surface using the separated point cloud of the rail part to obtain the left and right rail top surface vector lines, and the reliability of the rail top surface vector line extraction can be checked using the gauge range between the rails; S1008) calculating the track centerline using the extracted left and right rail top surface vector lines, and obtaining the track centerline; S1009) assigning a mileage value to the center line of the track, and unifying the mileage of the center line of the track with the railway maintenance mileage by setting the start and end mileages; S1010) obtaining the cross section of the point cloud according to the set mileage interval value, and outputting all the cross section point clouds; S1011) calculating the ballast fullness for each cross-section point cloud; S1012) calculating the ballast fullness for each frame of point cloud for a continuous section of the line and accumulating the calculated ballast fullness to obtain the ballast fullness of the entire section of the line; S1013) Save and output the results of ballast fullness calculation.

10. The railway comprehensive inspection method according to claim 9, It is characterized in that The step S1011) further comprises: S10111) projecting the point cloud in the cross section onto the cross section to form a two-dimensional point cloud C; S10112) locating the rail in the cross section by calculating the intersection of the rail top surface vector line and the cross section; S10113) locating the position of the ballast bed slope in the cross section by using the relative position relationship between the ballast bed slope and the rail; S10114) establishing a standard coordinate system with the line connecting the midlines of the top surfaces of the left and right rails as the x-axis, the midpoint of the line as the coordinate origin, and the vertical line upward as the y-axis, and rotating and translating the two-dimensional point cloud C to the standard coordinate system; S10115) generating a standard cross-section model of the roadbed in the standard coordinate system, calculating the area of ​​the figures sandwiched by the point cloud and the standard model one by one, the area above the standard model is excess ballast, and the area below the standard model is missing ballast, and the ballast fullness of the section can be obtained after the calculation is completed; S10146) Save the calculation results of ballast fullness.