Construction method of a curtain wall suspension structure
By combining prestressed cables and fixture structures to suspend the curtain wall, the problems of unstable suspension and inconvenient construction of the back-shaped ceramic tiles are solved, and safe and stable installation and cost-reducing effects are achieved.
Patent Information
- Application Number
- CN202210679405.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-16
- Publication Date
- 2025-07-25
- Estimated Expiration
- 2042-06-16
AI Technical Summary
In the prior art, when the back-shaped ceramic tiles are suspended on the main structure, they are inconvenient and unstable to be installed, and are easily damaged under external forces such as earthquakes, and cracks and gaps are easily caused during construction, which increases construction costs.
The combination of prestressed cable structure and fixture structure is adopted to connect the suspended curtain wall to avoid openings of the curtain wall, and a stable connection is achieved by using fixture single body and connecting components, and a buffer gasket is provided at the connection to enhance stability and cushioning effect.
It realizes safe and stable suspension of curtain walls, simplifies the installation process, improves construction efficiency, reduces construction costs, and reduces the risk of curtain wall damage under external forces.
Smart Images

Figure CN114961057B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of curtain wall construction, and more specifically, to a construction method for a curtain wall suspension structure. Background Art
[0002] In the prior art, when hanging the rectangular ceramic tiles in a loop shape, holes are often drilled on the rectangular ceramic tiles in a loop shape, and then the rectangular ceramic tiles in a loop shape are assembled in cooperation with the round steel columns installed on the main structure; this method is used to ensure that the round steel columns can bear the load of the rectangular ceramic tiles in a loop shape, and the round steel columns will be segmented, that is, the round steel columns will be fixed with keels to ensure their stability; during installation, the rectangular ceramic tiles in a loop shape can only be sleeved on the outside of the round steel columns through through holes from the top of the round steel columns; this makes the installation extremely inconvenient. Drilling holes in the rectangular ceramic tiles in a loop shape is very likely to cause damage during the hole drilling process. At the same time, the connection method of sleeve connection is not stable enough. Especially in earthquake-prone areas, the vibration effect generated by the earthquake is very likely to cause damage to the rectangular ceramic tiles in a loop shape. Summary of the Invention
[0003] The technical problem to be solved by the present invention is to provide a curtain wall suspension structure and a construction method, which have good safety and stability, convenient installation operation, effectively avoid problems such as cracking, breakage, poor gaps and flatness during the construction process, and greatly reduce the construction cost.
[0004] The solution adopted by the present invention to solve the technical problem is as follows:
[0005] On the one hand:
[0006] The present invention discloses a curtain wall suspension structure, including a prestressed cable structure with upper and lower ends respectively connected to the main structure, and a fixture structure sleeved outside the prestressed cable structure and connected to the curtain wall.
[0007] During use, first, according to the size of the whole version of the curtain wall to be installed, the total weight of the curtain wall, and the size of a single curtain wall unit, parameters such as the diameter and bearing capacity of the prestressed cable structure are determined, so that the prestressed cable structure can bear the weight of the curtain wall after installation; then the installation of the prestressed cable structure is carried out; after the installation of the prestressed cable is completed, the installation of the fixture structure and the curtain wall is carried out; adopting the above technical solution, compared with the prior art, there is no need to set additional support members, which simplifies the installation method; there is no need to drill holes in the curtain wall, and it can be connected to the prestressed cable through the fixture structure; the installation is more simple and convenient.
[0008] In some possible implementation manners, in order to effectively realize the connection between the fixture structure, the prestressed cable structure and the curtain wall;
[0009] The fixture structure includes two sets of fixture monomers with the same structure and symmetrically arranged along the prestressed cable structure, and connection components respectively connecting the fixture monomers and the curtain wall;
[0010] The two sets of fixture monomers are closed to each other to form a through hole sleeved on the outer side of the prestressed cable;
[0011] In some possible implementation manners, in order to effectively realize the connection between the connection component and the fixture monomer;
[0012] A vertical plate connected to the connection component is arranged at the top of the fixture monomer.
[0013] In some possible implementation manners, in order to effectively realize the connection between the connection component and the vertical plate;
[0014] An installation chamber is formed by the cooperation between the vertical plates on the two sets of fixture monomers and the top of the fixture monomers;
[0015] The connection component includes a plug-in part inserted into the vertical plate and located on the side of the vertical plate away from the fixture monomer, and a connecting piece connecting the plug-in part and the side of the curtain wall close to the fixture monomer;
[0016] One side of the connecting piece away from the plug-in part abuts against the fixture monomer.
[0017] In some possible implementation manners, in order to prevent the plug-in part from sliding after installation;
[0018] Threaded holes are arranged on the vertical plate along the axial direction of the prestressed cable, and the plug-in part is screwed to the vertical plate.
[0019] In some possible implementation manners, in order to facilitate the hard contact between the connection component and the fixture monomer and between the connection component and the curtain wall, and cause damage to the curtain wall under the action of earthquake or other external forces;
[0020] Buffer gaskets are respectively arranged between the vertical plate and the plug-in part, and between the connecting piece and the curtain wall; two buffer gaskets in the same group of plug-in parts cooperate to install the slot of the type groove and the vertical plate.
[0021] In some possible implementation manners, in order to ensure the installation of the buffer gasket;
[0022] A T-shaped groove is arranged at the part of the plug-in part close to the vertical plate, and its small end is open; the buffer gasket includes a connecting part installed in the T-shaped groove and a buffer part connected to the connecting part and abutting against the vertical plate.
[0023] In some possible implementation manners, in order to realize the connection between the curtain wall and the fixture structure;
[0024] The curtain wall includes Structure 1 connected to the side of the fixture structure closer to the interior and Structure 2 connected to the side of the fixture structure farther from the interior. Structure 1 and Structure 2 cooperate with each other to form a fixed cavity that is sleeved on the outside of the fixture structure.
[0025] In some possible implementation manners,
[0026] The prestressed cable structure includes two sets of symmetrically arranged cable heads, a cable body arranged vertically and connected to the two sets of cable heads at both ends respectively, and connecting plates respectively connected to the two sets of cable heads and fixed on the main structure.
[0027] On the other hand:
[0028] The present invention also discloses a construction method for a curtain wall suspension structure, which specifically includes the following steps:
[0029] Step S1: Installation of the prestressed cable structure;
[0030] Step S2: Installation of the fixture unit; specifically referring to:
[0031] The fixture unit is sleeved on the outside of the prestressed cable structure, and two sets of fixture units arranged symmetrically vertically are connected by tie bolts;
[0032] Step S3: Installation of the curtain wall; specifically including the following steps:
[0033] Step S31: Connect the connection components to Structure 1 and Structure 2 respectively;
[0034] Step 32: Install the buffer gasket in the T-shaped groove of the insertion part;
[0035] Step S33: Insert the insertion part into the vertical plate and fix the insertion part to the vertical plate with screws; the installation is completed.
[0036] Compared with the prior art, the beneficial effects of the present invention:
[0037] The present invention effectively realizes the suspension of the curtain wall by the cooperation of the prestressed cable structure and the fixture structure; compared with the prior art that uses the sleeve of the round steel column and the curtain wall to fix the curtain wall, the installation structure of the present invention is more firm and the installation is more convenient, without the need to open extra curtain wall interfaces; using the fixture structure to fix the curtain wall can effectively avoid the damage of the curtain wall caused by external forces (such as earthquakes), increasing the stability;
[0038] When installing the curtain wall in the present invention, it can be carried out simultaneously on a large area, and its working efficiency will be greatly improved compared with the prior art;
[0039] The present invention has a simple structure and strong practicability. Description of the Drawings
[0040] Figure 1 is the structural schematic diagram of the present invention;
[0041] Figure 2 is the schematic diagram of the connection relationship among the curtain wall, the fixture structure and the prestressed cable structure in the present invention;
[0042] Figure 3 is the schematic diagram of the connection relationship between two groups of fixture monomers in the present invention;
[0043] Figure 4 is the structural schematic diagram of the connection component in the present invention;
[0044] Figure 5 is the structural schematic diagram of the curtain wall in the present invention;
[0045] Wherein: 1, main structure; 2, connecting plate; 3, prestressed cable structure; 4, fixture structure; 41, fixture monomer; 410, through hole; 411, installation cavity; 412, vertical plate; 4121, threaded hole; 413, tie bolt; 42, connection component; 421, insertion part; 4211, T-shaped groove; 422, connecting piece; 43, buffer gasket; 10, structure one; 20, structure two; 30, fixed cavity. Specific embodiments
[0046] In the present invention, unless otherwise clearly defined and limited, terms such as "installation", "connection", "connection", "fixation" and the like shall be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or integrated; it can be directly connected, or indirectly connected through an intermediate medium, and it can be the internal communication of two elements or the interaction relationship between two elements. The "first", "second" and similar terms mentioned in this application do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, terms such as "one" or "a" do not indicate a quantity limitation, but indicate that there is at least one. In the implementation of this application, "and / or" describes the association relationship of associated objects, indicating that three relationships can exist. For example, A and / or B can represent: A exists alone, A and B exist simultaneously, and B exists alone. In the description of the embodiments of this application, unless otherwise stated, the meaning of "a plurality" is two or more. For example, a plurality of positioning columns means two or more positioning columns. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific situations.
[0047] The present invention will be described in detail below.
[0048] As Figures 1-5 shown: On the one hand:
[0049] The present invention discloses a curtain wall suspension structure, which includes a prestressed cable structure with its upper and lower ends respectively connected to the main structure 1, and a fixture structure 4 sleeved outside the prestressed cable structure and connected to the curtain wall.
[0050] The fixture structure 4 is mainly used for suspending, supporting and fixing the curtain wall.
[0051] During use, first, according to the size of the entire curtain wall to be installed, the total weight of the curtain wall, and the size of a single curtain wall unit, parameters such as the diameter and bearing capacity of the prestressed cable structure are determined, so that the prestressed cable structure can bear the weight of the curtain wall after installation; then the installation of the prestressed cable structure is carried out; after the installation of the prestressed cable is completed, the installation of the fixture structure 4 and the curtain wall is carried out; adopting the above technical solution, compared with the prior art, there is no need to set additional support members, which simplifies the installation method; there is no need to perform hole-opening treatment on the curtain wall, and it can be connected to the prestressed cable through the fixture structure 4; the installation is more simple and convenient.
[0052] In some possible implementation manners, in order to effectively realize the connection between the fixture structure 4, the prestressed cable structure and the curtain wall;
[0053] The fixture structure 4 includes two sets of fixture monomers 41 with the same structure and symmetrically arranged along the prestressed cable structure, and connection components 42 respectively connected to the fixture monomers 41 and the curtain wall;
[0054] The two sets of fixture monomers 41 are closed to form a through hole 410 sleeved outside the prestressed cable;
[0055] The two sets of fixture monomers 41 are connected by tie bolts 413 and form a through hole 410 on the side close to each other. The through hole 410 is in interference fit with the prestressed cable structure 3 to achieve connection and fixation; it is ensured that the fixture body formed by the two sets of fixture monomers 41 will not move vertically;
[0056] In some possible implementation manners, in order to effectively realize the connection between the connection component 42 and the fixture monomer 41;
[0057] A vertical plate 412 connected to the connection component 42 is provided at the top of the fixture monomer 41.
[0058] In some possible implementation manners, in order to effectively realize the connection between the connection component 42 and the vertical plate 412;
[0059] The vertical plates 412 on the two sets of fixture monomers 41 cooperate with the top of the fixture monomer 41 to form an installation chamber 411;
[0060] The connection component 42 includes a plug-in portion 421 that is inserted into the vertical plate 412 and is located on the side of the vertical plate 412 away from the fixture unit 41, and a connecting member 422 that connects the plug-in portion 421 and the curtain wall on the side close to the fixture unit 41;
[0061] One side of the connecting member 422 away from the plug-in portion 421 abuts against the fixture unit 41.
[0062] In some possible implementation manners, in order to prevent the plug-in portion 421 from sliding after installation;
[0063] The vertical plate 412 is provided with threaded holes 4121 along the axial direction of the prestressed cable, and the plug-in portion 421 is screwed to the vertical plate 412.
[0064] After the plug-in portion 421 is inserted into the vertical plate 412, the plug-in portion 421 and the vertical plate 412 are fixed by the cooperation of bolts and the threaded holes 4121, so as to prevent displacement between the two during use and prevent sliding;
[0065] In some possible implementation manners, in order to facilitate hard contact between the connection component 42 and the fixture unit 41, and between the connection component 42 and the curtain wall, and cause damage to the curtain wall under the action of an earthquake or other external forces;
[0066] Buffer gaskets 43 are respectively arranged between the vertical plate 412 and the plug-in portion 421, and between the connecting member 422 and the curtain wall; two buffer gaskets 43 in the same group of plug-in portions 421 cooperate with the vertical plate 412 to install the slots of the profile groove.
[0067] The buffer gasket 43 can, on the one hand, prevent slipping and avoid noise and stress caused by rigid contact; on the other hand, prevent electrochemical reactions from occurring between different metals and causing corrosion.
[0068] The vertical plate 412 is located in the slot and abuts against the two buffer gaskets 43. The buffer gasket 43 is made of an elastic material such as rubber or silica gel, which can effectively buffer under the action of external forces and avoid extrusion deformation of the connection component 42 and the fixture unit 41, thereby causing damage to the curtain wall.
[0069] In some possible implementation manners, in order to ensure the installation of the buffer gasket 43;
[0070] The plug-in portion 421 is provided with a T-shaped groove 4211 near the vertical plate 412, and its small end is open; the buffer gasket 43 includes a connecting portion installed in the T-shaped groove 4211 and a buffer portion connected to the connecting portion and abutting against the vertical plate 412.
[0071] The T-shaped groove 4211 is a through groove, which avoids the installation of the buffer gasket 43 and is arranged in the horizontal direction.
[0072] The insertion part 421 is provided with an opening groove, the opening of the opening groove faces downward and is inserted into the vertical plate 412; T-shaped grooves 4211 are arranged on both sides of the opening groove, the small ends of the T-shaped grooves 4211 are open, and the openings are arranged close to one side of the vertical plate 412, and the connecting part is installed in the T-shaped groove 4211; and it passes through the opening of the T-shaped groove 4211 and is connected to the buffer part; the buffer part will effectively ensure that under the action of external forces, such as during an earthquake, it can effectively prevent the insertion part 421 and the vertical plate 412 from shaking and deforming due to mutual extrusion, thereby causing damage to the curtain wall.
[0073] Preferably, T-shaped grooves 4211 are also arranged on the side of the connecting piece 422 close to the fixture unit 41, and buffer gaskets 43 are installed.
[0074] Furthermore, the connecting piece 422 and the curtain wall are connected by bolts.
[0075] In some possible implementation manners, in order to realize the connection between the curtain wall and the fixture structure 4;
[0076] The curtain wall includes a structure one 10 connected to the side of the fixture structure 4 close to the indoor side and a structure two 20 connected to the side of the fixture structure 4 far from the indoor side. The structure one 10 and the structure two 20 cooperate with each other to form a fixing cavity 30 sleeved on the outside of the fixture structure 4.
[0077] In the present invention, as Figure 5 shown, the curtain wall is divided into two pieces, and the connection with the prestressed cable structure 3 is realized through the connection of the connection components 42 respectively connected to two groups of symmetrically arranged fixture units 41.
[0078] The main purpose of setting the structure one 10 is that when the position of the main structure 1 corresponding to the curtain wall is glass, it will greatly increase its aesthetic degree. When the position of the main structure 1 corresponding to the curtain wall is a wall, the structure one 10 can be not set, and it can be mainly configured according to the on-site construction.
[0079] Preferably, there are two groups of fixing cavities 30, and the fixture structure 4 is installed in the fixing cavities 30; two groups of fixture bodies will be arranged in each fixing cavity 30; this will ensure the firmness of the installation.
[0080] Of course, the fixing cavities 30 can also be three groups, four groups or more groups; the fixture bodies in each fixing cavity 30 can also be multiple groups, and it can be mainly selected according to the on-site construction needs.
[0081] In some possible implementation manners,
[0082] The prestressed cable structure 3 includes two groups of symmetrically arranged cable heads, a cable body arranged vertically and connected to the two groups of cable heads at both ends, and connecting plates 2 respectively connected to the two groups of cable heads and fixed on the main structure 1.
[0083] The cable body is a prior art, and its structure will be described in detail here; before installation, it can be directly purchased according to the on-site construction needs;
[0084] On the other hand:
[0085] The present invention also discloses a construction method for a curtain wall suspension structure, which specifically includes the following steps:
[0086] Step S1: Install the prestressed cable structure 3;
[0087] According to the size of the entire curtain wall, the size and weight of a single curtain wall structure, calculate the diameter and bearing capacity of the required prestressed cable structure, and obtain the layout spacing of the prestressed cable structure; after obtaining the above parameters, install the prestressed cable structure 3 on site;
[0088] Step S2: Install the fixture unit 41; specifically:
[0089] Put the fixture unit 41 on the outside of the prestressed cable structure 3, and two groups of fixture units 41 arranged symmetrically along the vertical direction are connected by the tension bolts 413;
[0090] Connect and fix the two groups of fixture units 41 to the prestressed cable structure through the tension bolts 413;
[0091] Step S3: Install the curtain wall; specifically includes the following steps:
[0092] Step S31: Connect the connection components 42 to the structure one 10 and the structure two 20 respectively; of course, when the structure one 10 is not needed, the connection components 42 do not need to be installed on the structure one 10;
[0093] Step 32: Install the buffer gasket 43 in the T-shaped groove 4211 of the insertion part 421;
[0094] Step S33: Insert the insertion part 421 into the vertical plate 412, and fix the insertion part 421 to the vertical plate 412 with screws; the installation is completed.
[0095] The present invention is not limited to the foregoing specific embodiments. The present invention extends to any new feature or any new combination disclosed in this specification, as well as any new method or process step or any new combination disclosed.
Claims
1. A construction method of a curtain wall suspension structure, characterized in that, The described curtain wall suspension structure includes a prestressed cable structure with its upper and lower ends respectively connected to the main structure, and a fixture structure sleeved outside the prestressed cable structure and connected to the curtain wall; the fixture structure includes two sets of fixture monomers with the same structure and symmetrically arranged along the prestressed cable structure, and a connection component respectively connected to the fixture monomers and the curtain wall; The two sets of fixture monomers are closed to each other to form a through hole sleeved outside the prestressed cable; a vertical plate connected to the connection component is arranged at the top of the fixture monomer; an installation chamber is formed by the cooperation between the vertical plates on the two sets of fixture monomers and the top of the fixture monomers; The connection component includes a plug-in part inserted into the vertical plate and located on the side of the vertical plate away from the fixture monomer, and a connecting piece connecting the plug-in part and the side of the curtain wall close to the fixture monomer; One side of the connecting piece away from the plug-in part abuts against the fixture monomer; a threaded hole is arranged on the vertical plate along the axial direction of the prestressed cable, and the plug-in part is screwed to the vertical plate; buffer gaskets are respectively arranged between the vertical plate and the plug-in part, and between the connecting piece and the curtain wall; two buffer gaskets in the same set of plug-in parts cooperate with the vertical plate to install the slot of the groove; a T-shaped groove is arranged on the plug-in part close to the vertical plate, and its small end is open; the buffer gasket includes a connecting part installed in the T-shaped groove and a buffer part connected to the connecting part and abutting against the vertical plate; the curtain wall includes a structure one connected to the side of the fixture structure close to the interior, and a structure two connected to the side of the fixture structure away from the interior, and the structure one and the structure two cooperate with each other to form a fixed chamber sleeved outside the fixture structure; the prestressed cable structure includes two sets of symmetrically arranged cable heads, a cable body arranged vertically and connected to the two sets of cable heads at both ends respectively, and connecting plates respectively connected to the two sets of cable heads and fixed on the main structure; Specifically, it includes the following steps: Step S1: Installation of the prestressed cable structure; Step S2: Installation of the fixture monomer; specifically referring to: The fixture monomer is sleeved outside the prestressed cable structure, and the two sets of fixture monomers arranged symmetrically along the vertical direction are connected by tie bolts; Step S3: Installation of the curtain wall; specifically including the following steps: Step S31: Connect the connection components to the structure one and the structure two respectively; Step 32: Install the buffer gasket in the T-shaped groove of the plug-in part; Step S33: Insert the plug-in part into the vertical plate and fix the plug-in part to the vertical plate with screws; the installation is completed.