A method for mechanical and electrical pipeline installation based on BIM+ three-dimensional laser assistance
By using BIM+3D laser-assisted methods, combining civil engineering construction drawings with 3D laser scanning, pipeline installation drawings were optimized, solving the problems of drawing defects and inconsistencies with civil engineering structures in electromechanical installation, and achieving efficient pipeline installation and resource conservation.
Patent Information
- Application Number
- CN202210826888.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-14
- Publication Date
- 2026-01-30
- Estimated Expiration
- 2042-07-14
AI Technical Summary
In electromechanical installation engineering, the existing technology has problems with design flaws in the engineering drawings for pipeline construction and inconsistencies between the civil structure and the drawings, resulting in rework and waste of resources.
The BIM+3D laser-assisted method is adopted. A BIM model is built based on the construction drawings of the civil structure. The calibration parameters are obtained by using a 3D laser scanner, the model is optimized, and the pipeline construction process is simulated to generate optimized pipeline construction drawings to assist in the installation of electromechanical pipelines.
It improved engineering efficiency, reduced rework and resource waste, and enhanced the efficiency and accuracy of model building.
Smart Images

Figure CN115203799B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of building engineering, and further relates to a method for mechanical and electrical pipeline installation based on BIM+three-dimensional laser. BACKGROUND
[0002] In the construction process of a building, mechanical and electrical installation engineering mainly includes intelligent building engineering, electrical engineering, ventilation and air conditioning engineering, water supply and drainage engineering, etc., including air pipe, self-spraying pipe, fire hydrant pipe, bridge, air conditioning water pipe, pressure drainage pipe, etc. At present, the construction of corresponding pipelines in mechanical and electrical installation engineering is based on two-dimensional drawings of design institutes, which has the following problems:
[0003] 1. There is a certain probability of design defects and loopholes in the engineering drawings of pipeline construction, which cannot be found in time, resulting in rework in subsequent pipeline construction and directly increasing the construction cost.
[0004] 2. The engineering drawings of pipeline construction are based on the engineering drawings of civil structure, but due to manual operation, technical conditions and other factors, there are many inconsistencies between the actual civil structure and the drawings of civil structure, which will directly affect the subsequent pipeline construction.
[0005] Therefore, the present application is proposed. SUMMARY
[0006] In view of the problem that the actual working condition is different from the working condition corresponding to the drawings in the pipeline construction process in the prior art, the present application provides a method for mechanical and electrical pipeline installation based on BIM+three-dimensional laser, which combines BIM technology and three-dimensional scanning technology to ensure the efficiency of model establishment, simulate the pipeline construction process based on the actual civil structure construction process, determine the influence of the actual civil structure on pipeline installation, and adjust according to the actual civil structure, greatly improving the engineering efficiency and reducing the problem of resource waste due to rework.
[0007] To achieve the above-mentioned application purposes, the present application provides the following technical solutions:
[0008] The present application relates to a method for mechanical and electrical pipeline installation based on BIM+three-dimensional laser, comprising the following steps:
[0009] Building a BIM model based on the construction drawings of civil structure;
[0010] Using a three-dimensional laser scanner to perform three-dimensional laser measurement on the civil structure to obtain calibration parameters of the civil structure;
[0011] The BIM model is optimized by combining the collected calibration parameters to obtain an optimized model of the civil structure;
[0012] Based on the optimization model and pipeline construction drawings, pipeline construction simulation is performed, and the pipeline construction drawings are optimized based on the simulation results.
[0013] The installation of electromechanical pipelines is assisted by the optimized pipeline construction drawings.
[0014] In this scheme, a BIM model is first constructed based on the original civil engineering construction drawings to form the building's civil engineering structure BIM. Then, a 3D laser scanner is used to scan the civil engineering structure to obtain its calibration parameters. Based on these calibration parameters and the BIM model constructed from the original civil engineering construction drawings, the model is optimized to match the actual condition of the completed civil engineering structure. Furthermore, based on the original pipeline installation drawings, pipeline installation simulation is performed in the optimized BIM model to simulate the installation process and its effects. Based on the installation process and effects, the pipeline installation drawings are further optimized to form an optimized version. The system provides pipeline construction drawings and facilitates pipeline construction based on these drawings, thereby aiding in the installation of electromechanical pipelines. The auxiliary installation scheme provided in this plan utilizes a BIM model built based on the original civil structure model. Optimization of the actual building's civil structure model effectively reduces the data processing volume during BIM model component assembly, significantly improving model construction efficiency. Furthermore, simulation of the optimized model directly simulates the pipeline construction process based on the actual civil structure construction, thus determining the impact of the actual civil structure on pipeline installation. Adjustments can be made according to the actual situation, greatly improving project efficiency and reducing resource waste due to rework.
[0015] Furthermore, the calibration parameters include floor spacing, floor slab parallelism, and floor slab inclination.
[0016] Furthermore, based on the optimized model and pipeline construction drawings, a pipeline construction simulation is performed, specifically including the following steps:
[0017] Based on the type of pre-built pipeline, pipeline priority is classified;
[0018] Based on pipeline priority, a pipeline construction simulation is performed, and pipeline collision detection is carried out during the construction process;
[0019] Based on the simulation results of pipeline construction, optimized pipeline construction drawings are generated.
[0020] Furthermore, pipeline construction simulation is performed according to pipeline priority. During the construction process, pipeline collision detection is conducted, specifically including:
[0021] Based on the preset locations in the original pipeline construction drawings, a pipeline construction simulation with the highest priority is performed on the optimized model.
[0022] Complete the pipeline construction simulation for the first priority, then proceed to the pipeline construction simulation for the second priority. After the construction is completed, perform collision detection.
[0023] After collision detection, a simulation of building a third-priority pipeline is performed.
[0024] Repeat the above construction and testing steps to complete the overall pipeline construction.
[0025] Furthermore, it also includes a pipeline space verification step, which, after all pipeline construction simulations are completed, specifically includes the following steps:
[0026] The location of the marked pipeline is determined, and the distance from the marked pipeline to the top surface of the floor is obtained, wherein the marked pipeline is the pipeline with the farthest distance from the top surface of the floor among all pipelines;
[0027] Determine the radius of the marked pipeline and obtain the maximum height of the overall pipeline construction model;
[0028] The maximum height obtained is compared with the maximum height in the preset pipeline construction drawings, and it is determined whether the optimized pipeline construction position will affect the floor height. If the maximum height obtained is less than or equal to the preset maximum height, the optimized pipeline construction drawings are exported; if the maximum height obtained is greater than the preset maximum height, the model is adjusted.
[0029] Furthermore, the model adjustment specifically includes the following steps:
[0030] Adjust the position of the marked pipeline so that the maximum height of the overall pipeline model corresponding to the marked pipeline is less than or equal to the preset maximum height;
[0031] Adjust the positions of the remaining pipelines according to the positions of the marked pipelines.
[0032] Furthermore, the position adjustment specifically includes the following steps:
[0033] Determine the priority of marked pipelines;
[0034] Pipelines with higher priority than the marked pipelines are adjusted in reverse order of priority.
[0035] Pipelines with priorities lower than the marked pipelines are adjusted in ascending order of priority.
[0036] Determine the distance between the farthest end of the adjusted pipeline model and the floor slab, and determine its relationship with the maximum height in the preset pipeline construction drawings; if it is less than or equal to the preset maximum height, export the optimized pipeline construction drawings; if the obtained maximum height is greater than the preset maximum height, repeat the model adjustment steps.
[0037] Furthermore, during the pipeline construction simulation, the installation position of each pipeline is adjusted to obtain the installation range of each pipeline, wherein the installation range is determined based on collision detection.
[0038] Furthermore, the installation of electromechanical pipelines is assisted by the optimized pipeline construction drawings, specifically including the following steps.
[0039] Based on the optimized pipeline construction drawings, and according to the priority of the pipelines, the pipelines are constructed in sequence.
[0040] The location of the pipelines was confirmed using a 3D laser scanner, and it was also confirmed that the pipelines under construction were within the corresponding installation range.
[0041] Furthermore, during the pipeline installation process, the location of the pipeline is confirmed using a 3D laser scanner, and collision checks are performed in the corresponding simulation results.
[0042] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0043] This invention relates to a method for installing electromechanical pipelines based on BIM and 3D laser-assisted installation. First, a BIM model is constructed based on the original civil engineering construction drawings, forming a BIM of the building's civil engineering structure. Then, a 3D laser scanner is used to scan the civil engineering structure to obtain its calibration parameters. Based on these calibration parameters and the BIM model constructed from the original civil engineering construction drawings, the model is optimized to match the actual condition of the completed civil engineering structure. Furthermore, based on the original pipeline installation drawings, pipeline installation is simulated in the optimized BIM model, simulating the installation process and its effects. Based on the installation process and effects, the pipeline installation is then... The construction drawings are optimized to form optimized pipeline construction drawings, and pipelines are constructed based on these drawings, thereby assisting in the installation of electromechanical pipelines. The auxiliary installation scheme provided in this plan uses a BIM model built based on the original civil structure model. Optimizing the civil structure model based on the actual building effectively reduces the data processing volume of the BIM model component process, greatly improving model construction efficiency. Furthermore, by simulating the optimized model, the pipeline construction process during the actual civil structure construction can be directly simulated, thus determining the impact of the actual civil structure on pipeline installation and allowing for adjustments based on actual conditions. This significantly improves project efficiency and reduces resource waste caused by rework. Attached Figure Description
[0044] The accompanying drawings are provided to further illustrate the invention and form part of the specification. They are used together with the embodiments of the invention to explain the invention and do not constitute a limitation thereof.
[0045] Figure 1 A flowchart of a method for installing electromechanical pipelines based on BIM and 3D laser-assisted installation provided in an embodiment of the present invention;
[0046] Figure 2 This is a flowchart illustrating the pipeline construction simulation provided in an embodiment of the present invention;
[0047] Figure 3 This is a flowchart of the pipeline installation process provided in an embodiment of the present invention. Detailed Implementation
[0048] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0049] In the following description, numerous specific details are set forth in order to provide a thorough understanding of the invention. However, it will be apparent to those skilled in the art that these specific details are not necessary to practice the invention. In other instances, well-known structures, circuits, materials, or methods have not been specifically described in order to avoid obscuring the invention.
[0050] Throughout this specification, references to "an embodiment," "an example," or "an example" mean that a particular feature, structure, or characteristic described in connection with that embodiment or example is included in at least one embodiment of the invention. Therefore, the phrases "an embodiment," "an example," "an example," or "an example" appearing in various places throughout the specification do not necessarily refer to the same embodiment or example. Furthermore, specific features, structures, or characteristics can be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. Moreover, those skilled in the art will understand that the illustrations provided herein are for illustrative purposes and are not necessarily drawn to scale. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.
[0051] In the description of this invention, it should be understood that the terms "front", "rear", "left", "right", "up", "down", "vertical", "horizontal", "high", "low", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limiting the scope of protection of this invention.
[0052] Example
[0053] like Figure 1 As shown, this embodiment of the invention relates to a method for installing electromechanical pipelines based on BIM and 3D laser-assisted installation, comprising the following steps:
[0054] Building BIM model based on construction drawings of civil engineering structure;
[0055] A 3D laser scanner is used to perform 3D laser measurement on the civil engineering structure to obtain the calibration parameters of the civil engineering structure.
[0056] The BIM model is optimized by combining the collected calibration parameters to obtain an optimized model of the civil structure;
[0057] Based on the optimization model and pipeline construction drawings, pipeline construction simulation is performed, and the pipeline construction drawings are optimized based on the simulation results.
[0058] The installation of electromechanical pipelines is assisted by the optimized pipeline construction drawings.
[0059] As those skilled in the art should know, in engineering construction, construction is usually carried out based on corresponding engineering drawings. Conventional engineering drawings are two-dimensional drawings. Construction workers build corresponding three-dimensional building structures based on two-dimensional drawings. However, in the construction process, there are certain engineering errors under the premise of meeting the structural strength of the building. It is precisely because of the occurrence of engineering errors that they will directly affect the subsequent pipeline installation.
[0060] In this scheme, a BIM model is first constructed based on the original civil engineering construction drawings to form the building's civil engineering structure BIM. Then, a 3D laser scanner is used to scan the civil engineering structure to obtain its calibration parameters. Based on these calibration parameters and the BIM model constructed from the original civil engineering construction drawings, the model is optimized to match the actual condition of the completed civil engineering structure. Furthermore, based on the original pipeline installation drawings, pipeline installation simulation is performed in the optimized BIM model to simulate the installation process and its effects. Based on the installation process and effects, the pipeline installation drawings are further optimized to form an optimized version. The system provides pipeline construction drawings and facilitates pipeline construction based on these drawings, thereby aiding in the installation of electromechanical pipelines. The auxiliary installation scheme provided in this plan utilizes a BIM model built based on the original civil structure model. Optimization of the actual building's civil structure model effectively reduces the data processing volume during BIM model component assembly, significantly improving model construction efficiency. Furthermore, simulation of the optimized model directly simulates the pipeline construction process based on the actual civil structure construction, thus determining the impact of the actual civil structure on pipeline installation. Adjustments can be made according to the actual situation, greatly improving project efficiency and reducing resource waste due to rework.
[0061] In some embodiments, the calibration parameters include floor spacing, floor slab parallelism, and floor slab inclination.
[0062] It should be noted that the main purpose of collecting calibration parameters is to adjust the original BIM model so that it corresponds to the actual civil engineering structure. It should be noted that those skilled in the art should know that the model of the actual civil engineering structure can be directly constructed by using 3D laser scanning to obtain point cloud data. However, in this solution, by pre-constructing the original BIM model and then adjusting the model, the amount of computer processing and processing time are greatly reduced, and the model construction efficiency is improved.
[0063] Furthermore, as those skilled in the art should know, during the design process of civil engineering structures, three-dimensional structural simulations are usually performed, and corresponding construction drawings are generated after multiple adjustments. In this solution, the pre-built structural model can be directly used and converted into the corresponding BIM model, thereby saving production costs and improving production efficiency.
[0064] In some embodiments, pipeline construction simulation is performed based on the optimization model and pipeline construction drawings, specifically including the following steps:
[0065] Based on the type of pre-built pipeline, pipeline priority is classified;
[0066] Based on pipeline priority, a pipeline construction simulation is performed, and pipeline collision detection is carried out during the construction process;
[0067] Based on the simulation results of pipeline construction, optimized pipeline construction drawings are generated.
[0068] Among them, electromechanical pipelines include, but are not limited to, heating and ventilation ducts, smoke exhaust ducts, power and weak current cable trays, water supply and drainage pipes, fire sprinkler pipes, air conditioning water pipes, etc. As those skilled in the art should know, when constructing the corresponding electromechanical pipelines, they are usually constructed in a certain order. Specifically, the construction order of the corresponding pipelines is the priority of the corresponding pipelines, and the first one constructed has the highest priority.
[0069] like Figure 2 As shown, in some embodiments, pipeline construction simulation is performed according to pipeline priority. During the construction process, pipeline collision detection is performed, specifically including:
[0070] Based on the preset locations in the original pipeline construction drawings, a pipeline construction simulation with the highest priority is performed on the optimized model.
[0071] Complete the pipeline construction simulation for the first priority, then proceed to the pipeline construction simulation for the second priority. After the construction is completed, perform collision detection.
[0072] After collision detection, a simulation of building a third-priority pipeline is performed.
[0073] Repeat the above construction and testing steps to complete the overall pipeline construction.
[0074] The process involves simulating pipeline construction according to pipeline priority and conducting collision checks between pipelines during the construction process to determine whether the pipeline installation location meets the requirements. It should be noted that during the pipeline collision check, it is necessary to determine whether the newly constructed pipeline is in conflict with all existing pipelines.
[0075] During collision checks, if adjustments to existing pipelines are required, a new collision check must be performed on the adjusted pipelines.
[0076] In some embodiments, a pipeline space verification step is further included, wherein the pipeline space verification step is performed after all pipeline construction simulations are completed, and specifically includes the following steps:
[0077] The location of the marked pipeline is determined, and the distance from the marked pipeline to the top surface of the floor is obtained, wherein the marked pipeline is the pipeline with the farthest distance from the top surface of the floor among all pipelines;
[0078] Determine the radius of the marked pipeline and obtain the maximum height of the overall pipeline construction model;
[0079] The maximum height obtained is compared with the maximum height in the preset pipeline construction drawings, and it is determined whether the optimized pipeline construction position will affect the floor height. If the maximum height obtained is less than or equal to the preset maximum height, the optimized pipeline construction drawings are exported; if the maximum height obtained is greater than the preset maximum height, the model is adjusted.
[0080] It should be noted that verifying the size of the space can reduce the impact of pipeline installation on the floor height and avoid affecting the usable space due to adjustments to the pipeline structure.
[0081] The distance from the marked pipeline to the top surface of the floor refers to the distance from the axis of the marked pipeline to the top surface of the floor.
[0082] The location of the marked pipeline is the pipeline closest to the floor level in the entire pipeline system. By obtaining the height and the radius of the marked pipeline, the closest position of the entire pipeline structure to the ground is determined, thereby determining the range of the installation space of the entire pipeline structure. By comparison, it is determined whether there is any impact.
[0083] In some embodiments, the model adjustment specifically includes the following steps:
[0084] Adjust the position of the marked pipeline so that the maximum height of the overall pipeline model corresponding to the marked pipeline is less than or equal to the preset maximum height;
[0085] Adjust the positions of the remaining pipelines according to the positions of the marked pipelines.
[0086] Furthermore, the position adjustment specifically includes the following steps:
[0087] Determine the priority of marked pipelines;
[0088] Pipelines with higher priority than the marked pipelines are adjusted in reverse order of priority.
[0089] Pipelines with priorities lower than the marked pipelines are adjusted in ascending order of priority.
[0090] Determine the distance between the farthest end of the adjusted pipeline model and the floor slab, and determine its relationship with the maximum height in the preset pipeline construction drawings; if it is less than or equal to the preset maximum height, export the optimized pipeline construction drawings; if the obtained maximum height is greater than the preset maximum height, repeat the model adjustment steps.
[0091] Specifically, as those skilled in the art should know, after the marked pipelines are identified, the priority of the corresponding marked pipelines can be directly obtained, and the pipeline adjustment sequence can be divided according to the specific priority.
[0092] The specific adjustment order starts with the priority of the marked pipes. For pipes with higher priority than the marked pipes, the position of each pipe is adjusted in reverse order to meet the collision detection requirements. For pipes with lower priority than the marked pipes, the same adjustment is made. This will not be elaborated again.
[0093] In some embodiments, during pipeline construction simulation, the installation position of each pipeline is adjusted to obtain the installation range of each pipeline, wherein the installation range is determined based on collision detection.
[0094] As should be known to those skilled in the art, for pipelines, a rectangular coordinate system can be established on a plane perpendicular to the axis, with the axis of the marked pipeline or any pipeline as the origin. By determining the relative positional relationship between the pipelines, the range can be determined, where the range includes the range in the X-axis direction and the Y-axis direction in the corresponding rectangular coordinate system.
[0095] like Figure 3 As shown, in some embodiments, the installation of electromechanical pipelines is assisted by optimized pipeline construction drawings, specifically including the following steps:
[0096] Based on the optimized pipeline construction drawings, and according to the priority of the pipelines, the pipelines are constructed in sequence.
[0097] The location of the pipelines was confirmed using a 3D laser scanner, and it was also confirmed that the pipelines under construction were within the corresponding installation range.
[0098] Furthermore, during the pipeline installation process, the location of the pipeline is confirmed using a 3D laser scanner, and collision checks are performed in the corresponding simulation results.
[0099] In this solution, the location of the pipelines to be constructed is determined again by using a 3D laser scanner, which can further guide the installation process. Furthermore, collision checks can be performed by importing the optimized model. As should be known by those skilled in the art, after importing the corresponding pipeline parameters into the optimized model, simulations can also be performed based on the structural model to guide the construction process.
[0100] The above are preferred embodiments of the present invention. Those skilled in the art can make changes and modifications to the above embodiments. Therefore, the present invention is not limited to the specific embodiments described above. Any obvious improvements, substitutions or modifications made by those skilled in the art based on the present invention are within the protection scope of the present invention.
Claims
1. A method for BIM+ three-dimensional laser-assisted electromechanical piping installation, characterized by, The method comprises the following steps: constructing a BIM model based on construction drawings of a civil structure; performing three-dimensional laser measurement on the civil structure by using a three-dimensional laser scanner to obtain calibration parameters of the civil structure; optimizing the BIM model in combination with the collected calibration parameters to obtain an optimized model of the civil structure; performing pipeline construction simulation based on the optimized model and pipeline construction drawings, and optimizing the pipeline construction drawings according to the simulation results; assisting in mechanical and electrical pipeline installation based on the optimized pipeline construction drawings; the pipeline construction simulation based on the optimized model and the pipeline construction drawings specifically comprises the following steps: classifying pipeline priorities according to pipeline types to be pre-constructed; performing pipeline construction simulation according to the pipeline priorities, and performing pipeline collision detection during the construction process; forming optimized pipeline construction drawings according to the simulation results of the pipeline construction simulation; performing pipeline construction simulation according to the pipeline priorities, and performing pipeline collision detection during the construction process, which specifically comprises: performing pipeline construction simulation of the first priority on the optimized model according to the preset positions of the original pipeline construction drawings; performing pipeline construction simulation of the second priority after completing pipeline construction simulation of the first priority, and performing collision detection after the construction is completed; performing pipeline construction simulation of the third priority after collision detection; repeating the above construction and detection steps to complete the overall pipeline construction; the pipeline space review step is performed after all pipeline construction simulations are completed, and specifically comprises the following steps: determining the position of a marker pipeline and obtaining the distance from the marker pipeline to the floor top surface, wherein the marker pipeline is the pipeline with the farthest distance to the floor top surface among all pipelines; determining the radius of the marker pipeline and obtaining the maximum height of the overall pipeline construction model; comparing the obtained maximum height with the maximum height in the preset pipeline construction drawings, and determining whether the optimized pipeline construction position will affect the floor height, if the obtained maximum height is less than or equal to the preset maximum height, the optimized pipeline construction drawings are exported, and if the obtained maximum height is greater than the preset maximum height, the model is adjusted; the model adjustment specifically comprises the following steps: adjusting the position of the marker pipeline so that the maximum height of the overall pipeline construction model corresponding to the marker pipeline is less than or equal to the preset maximum height; adjusting the positions of the remaining pipelines according to the position of the marker pipeline; the position adjustment specifically comprises the following steps: determining the priority of the marker pipeline; adjusting the pipelines with priorities higher than the marker pipeline in reverse order of priority; adjusting the pipelines with priorities lower than the marker pipeline in ascending order of priority; determining the distance from the farthest end of the adjusted pipeline model to the floor and determining the size relationship with the maximum height in the preset pipeline construction drawings, if the distance is less than or equal to the preset maximum height, the optimized pipeline construction drawings are exported, and if the obtained maximum height is greater than the preset maximum height, the model adjustment step is repeated.
2. A method for BIM+ three-dimensional laser-assisted mechanical and electrical pipeline installation according to claim 1, characterized by, The calibration parameters include floor spacing, parallelism of the floor, and inclination of the floor.
3. A method for BIM+ three-dimensional laser-assisted mechanical and electrical pipeline installation according to any one of claims 1-2, characterized in that, In the pipeline building simulation, the installation position of each pipeline is adjusted to obtain the installation range of each pipeline, wherein the installation range is determined according to the collision detection.
4. A method for BIM+ three-dimensional laser-assisted mechanical and electrical pipeline installation according to claim 3, characterized by, Based on the optimized pipeline building drawing, the mechanical and electrical pipeline installation is assisted, specifically including the following steps: According to the optimized pipeline building drawing and according to the priority of the pipeline, the pipeline is built in turn. The implementation position of the pipeline is confirmed by the three-dimensional laser scanner, and whether the pipeline in the building is within the corresponding installation range is confirmed.
5. A method for BIM+ three-dimensional laser-assisted mechanical and electrical pipeline installation according to claim 4, characterized by, In the pipeline installation process, the implementation position of the pipeline is confirmed by the three-dimensional laser scanner, and the collision is checked in the corresponding simulation result.
Citation Information
Patent Citations
An assembled construction method of electromechanical pipelines based on the BIM technology
CN109543233A
Automatic pipeline comprehensive method and related product
CN111143924A