A charging control method and control system for a transcranial magnetic stimulation power supply
Through series and parallel resonance circuit and model prediction control, constant current or constant power charging of transcranial magnetic stimulation power is realized, solving the problems of output power mutation and poor waveform quality in the prior art, and improving the power utilization rate and repetition frequency.
Patent Information
- Application Number
- CN202210827051.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-13
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2042-07-13
AI Technical Summary
When the existing transcranial magnetic stimulation power supply is running refrequency, it is difficult to achieve constant power or constant current charging methods, resulting in sudden changes in the output power, poor quality of the waveform on the input side, and low charging power utilization.
The series-parallel resonant circuit is combined with model prediction control. By sampling the voltage of the DC bus capacitor and load capacitor in real time, predicting the charging current and switching cycle, adjusting the duty cycle of the switch tube, realizing constant current or constant power charging, avoiding direct measurement of charging power and current, real-time update of switching frequency and duty cycle.
The input waveform quality of the front-end PFC circuit is improved, the power utilization rate is improved, the charging time is reduced, and the TMS repetition frequency is increased.
Smart Images

Figure CN115313684B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of medical instrument power supplies, and more specifically, relates to a charging control method and a control system for a transcranial magnetic stimulation power supply. Background Art
[0002] As a non-invasive and non-intrusive neuromodulation technology, transcranial magnetic stimulation (TMS) is widely used in the causes of mental disorders and the treatment of mental illnesses. As an important component of TMS equipment, pulse power supply plays a decisive role in the performance of TMS equipment. With the rapid development of power electronics technology, the requirements for TMS power supply systems are no longer limited to output performance, but also put forward requirements for power supply performance, power efficiency, power density, electromagnetic interference and reliability.
[0003] The output side of the transcranial magnetic stimulation power supply usually uses a high-voltage capacitor as the terminal energy storage, and charges the output voltage to a set value through a capacitor charging power supply, and then discharges the load stimulation coil. Under heavy frequency operation, the output capacitor (load capacitor) voltage needs to be repeatedly charged to the set value after discharge. Unlike conventional steady-state DC power supplies, the TMS charging power supply load is a capacitor, and its output voltage will continue to change during the charging process; after the discharge is completed, there is a sudden change in the output voltage and power. Because the TMS power supply charging process is highly nonlinear, and the discharge coil is equivalent to a pulse load. In the prior art, the TMS power supply design process faces the following problems:
[0004] (1) When the TMS power supply is in repetitive operation, the existing constant current or fixed frequency charging method usually adopts PI control, which has poor dynamic characteristics of the load. When the TMS power supply is in repetitive operation, there is a sudden change in output power and a long transition process. During this transition process, the existing PI control cannot achieve constant power or constant current charging, and low-frequency harmonics of the discharge frequency will be introduced on the input side, resulting in poor input waveform quality of the front-end PFC circuit, making it difficult to meet various harmonic standards (such as EN60555-2, IEC555-2, IEC61000-3-2, GB / T14549-1993 "Power Quality Public Grid Harmonics", etc.).
[0005] (2) Under constant current charging mode, as the output voltage increases, the power of the power supply increases, and the charging power reaches the maximum power at the end of charging. However, the front-end FPC circuit and the back-end charging circuit are designed according to the maximum power. The average power during the charging process is lower than the maximum power, resulting in low charging power utilization. Summary of the invention
[0006] In view of the defects of the prior art and the need for improvement, the present invention provides a charging control method and control system for a transcranial magnetic stimulation power supply, which aims to reduce the impact of TMS repetition frequency operation on the power grid side and improve the input side power quality, power supply utilization and TMS repetition frequency.
[0007] To achieve the above-mentioned object, according to one aspect of the present invention, a charging control method for a transcranial magnetic stimulation power supply is provided, wherein the transcranial magnetic stimulation power supply comprises a DC bus capacitor and a series-parallel resonant circuit, wherein the series-parallel resonant circuit comprises a switch tube, a series-parallel resonant capacitor and a load capacitor, and the control method comprises a model predictive control step, wherein the model predictive control step comprises:
[0008] Under DCM1 and DCM2 respectively, by sampling the input voltage V of the DC bus capacitor during the current resonance process in And load capacitance C o The output voltage V o , get the initial voltage value V of the series-parallel resonant capacitor 1N 、V 2N ;
[0009] With the initial voltage value V 1N 、V 2N The input voltage of the DC bus capacitor and the output voltage of the load capacitor in the current resonance process are used as inputs to predict the charging current I of the load capacitor in the next resonance process. pred,ave and critical switching period T s,critical ;
[0010] The switching period T of the following resonant process update Greater than the critical switching period T s,critical is a constraint condition, based on the charging current I pred,ave And reference current I o,ref , the charge conservation is satisfied through the resonance process, and the switching period T of the next resonance process is obtained update ;
[0011] With the switching period T update The duty cycle D of the switch tube in the next resonance process satisfies Get the switch duty cycle of the next resonance process, where:
[0012] The switching period T of the following resonant process update And the duty cycle D of the switch tube are used as input, and through PWM modulation, a control signal that triggers the switch tube to turn on and off is generated to achieve current or power charging control.
[0013] Furthermore, a charging step is included, and the charging step includes:
[0014] The load capacitor Co In the process of charging from zero voltage to the voltage corresponding to the rated power, the model predictive control step is adopted to perform constant current charging;
[0015] The load capacitor C o In the process of charging from the voltage corresponding to the rated power to the set voltage, the model predictive control step is adopted to perform constant power charging at the rated power.
[0016] Further,
[0017] During the constant current charging process, the reference current I o,ref The maximum current allowed by the power system;
[0018] During the constant power charging process, the reference current I o,ref is the load capacitance C o The output current I o ,in, P N is the load capacitance C o Rated power, V o is the load capacitance C o output voltage.
[0019] Furthermore, the next resonance process load capacitance C o The charging current I pred,ave and critical switching period T s,critical Respectively meet:
[0020] I pred,ave =I o,ave
[0021] T s,critical =t I +t II +t III
[0022] Among them, t I ,t II ,t III Respectively represent the duration of the three operating stages of the series-parallel resonant circuit under DCM1 or DCM2;
[0023] In DCM1 and DCM2, I o,ave They can be expressed as:
[0024]
[0025]
[0026] Among them, V in is the input voltage of the DC bus capacitor at the current moment, T sis the current switching cycle, C s is the series resonant capacitor, k is the resonant parameter, and
[0027] Furthermore, the switching period T of the next resonance process update for:
[0028]
[0029] Among them, I o,ref is the reference current, T s is the switching period of the current resonance process.
[0030] According to another aspect of the present invention, a charging control system of a transcranial magnetic stimulation power supply is provided, wherein the transcranial magnetic stimulation power supply comprises a DC bus capacitor and a series-parallel resonant circuit, wherein the series-parallel resonant circuit comprises a switch tube, a series-parallel resonant capacitor and a load capacitor, and the control system comprises a model prediction control unit, wherein the model prediction control unit comprises:
[0031] The resonant capacitor voltage initial value calculation node is used to sample the input voltage V of the DC bus capacitor at the current moment under DCM1 and DCM2 respectively. in And load capacitance C o The output voltage V o , get the initial voltage value V of the series-parallel resonant capacitor 1N 、V 2N ;
[0032] The load capacitor charging current prediction node is used to predict the voltage with the initial value V 1N 、V 2N The input voltage of the DC bus capacitor and the output voltage of the load capacitor in the current resonance process are used as inputs to predict the charging current I of the load capacitor in the next resonance process. pred,ave and critical switching period T s,critical ;
[0033] The switching cycle prediction node is used to predict the switching cycle T of the next resonant process. update Greater than the critical switching period T s,critical is a constraint condition, based on the charging current I pred,ave And reference current I o,ref , the charge conservation is satisfied through the resonance process, and the switching period T of the next resonance process is obtained update ;
[0034] The switch duty cycle prediction node is used to predict the switching cycle T update The duty cycle D of the switch tube in the next resonance process satisfies Get the switch duty cycle of the next resonance process, where:
[0035] PWM modulation node, used for the switching period T of the following resonant process update With the duty cycle D of the switch tube as input, through PWM modulation, a control signal that triggers the switch tube to turn on and off is generated to achieve current or power charging control.
[0036] Furthermore, it also includes:
[0037] Constant current charging module is used to charge the load capacitor C o During the process of charging from zero voltage to the voltage corresponding to the rated power, constant current charging is performed through the model prediction control unit;
[0038] Constant power charging module, used to charge the load capacitor C o During the process of charging from the voltage corresponding to the rated power to the set voltage, the model prediction control unit is used to perform constant power charging at the rated power.
[0039] Further,
[0040] In the constant current charging module, the reference current I o,ref The maximum current I allowed by the power system o ;
[0041] In the constant power charging module, the reference current I o,ref is the load capacitance C o The output current I o ,in, P N is the load capacitance C o Rated power, V o is the load capacitance C o output voltage.
[0042] Furthermore, in the load capacitor charging current prediction node, the load capacitor C o The charging current I pred,ave and critical switching period T s,critical Respectively meet:
[0043] I pred,ave =I o,ave
[0044] T s,critical =t I +t II +t III
[0045] Among them, t I ,t II ,t IIIThey represent the duration of the three resonance processes of the series-parallel resonance circuit under DCM1 or DCM2 respectively;
[0046] In DCM1 and DCM2, I o,ave They can be expressed as:
[0047]
[0048]
[0049] Among them, V in is the input voltage of the DC bus capacitor at the current moment, T s is the current switching cycle, C s is the series resonant capacitor, k is the resonant parameter, and
[0050] Furthermore, in the switching cycle prediction node, the switching cycle T of the next resonance process update for:
[0051]
[0052] Among them, I o,ref is the reference current, T s is the switching cycle at the current moment.
[0053] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects:
[0054] (1) The present invention predicts the resonant current of the series-parallel resonant circuit in the next resonant process in real time by establishing the relationship between the output voltage of the load capacitor in the next resonant process and the initial value of the series-parallel resonant capacitor voltage at the current moment, thereby avoiding direct measurement of the charging power and charging current of the load capacitor. The switching period and duty cycle of the next resonant process are predicted based on the predicted charging current, and the switching period and duty cycle of the next resonant process are adjusted to control the charging current or power. The switching frequency and duty cycle are updated in real time to achieve full-range soft switching. In this process, since the switching frequency and duty cycle are updated in real time, there is no transition process, thereby improving the input waveform quality of the front-end PFC circuit.
[0055] At the same time, since the power supply system always operates at rated power during repetitive operation, the power utilization rate is improved, the charging time is reduced, and the repetition frequency is increased.
[0056] In summary, the TMS power charging control method of the present invention can improve the power quality on the input side of the transcranial magnetic stimulation power system, reduce the charging time, improve the power utilization rate and increase the TMS repetition frequency. BRIEF DESCRIPTION OF THE DRAWINGS
[0057] Figure 1 This is the equivalent circuit model diagram of the transcranial magnetic stimulation coil.
[0058] Figure 2 Schematic diagram of the architecture of a transcranial magnetic stimulation power supply system in an embodiment of the present invention.
[0059] Figure 3 It is a charging current and voltage curve diagram of the load capacitor during constant current and constant power charging of the transcranial magnetic stimulation power supply of the present invention.
[0060] Figure 4 is the typical waveform of the series-parallel resonant converter in DCM; where, Figure 4 (a) and Figure 4 (b) in the figure are the typical waveforms of the series-parallel resonant converter under DCM1 and DCM2 respectively.
[0061] Figure 5 It is a constant current and constant power control block diagram of the series-parallel resonant converter in an embodiment of the present invention based on model prediction under DCM1.
[0062] Figure 6 It is a constant power control block diagram of the series-parallel resonant converter in an embodiment of the present invention based on model prediction under DCM2.
[0063] Figure 7 It is a comparison diagram of the simulation waveforms of the charging method using a fixed switching frequency and the constant current and constant power charging method based on model prediction in the present invention; wherein, Figure 7 (a) is the relevant simulation waveform diagram under the fixed switching frequency charging mode. Figure 7 (b) is a related simulation waveform diagram of the constant current and constant power charging method based on model prediction in the present invention. DETAILED DESCRIPTION
[0064] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0065] Example 1
[0066] like Figure 1 As shown, the transcranial magnetic stimulation coil is equivalent to the coil inductance L m and coil loss resistance R m In series, a high-voltage capacitor (load capacitor C o) excites the stimulation coil, and the U and D terminals of the stimulation coil are connected to Figure 2 The load capacitance C o The RLC discharge circuit is formed on the upper side. The charging circuit is a series-parallel resonant circuit, and the series-parallel resonant circuit operates in discontinuous current mode (DCM). Compared with continuous current mode (CCM), the series-parallel resonance in DCM is zero voltage shutdown and approximately zero current opening, and the charging efficiency is high. At the same time, in order to reduce the impact of the charging process on the power grid, an active power factor correction circuit (APFC) is added to the front end of the series-parallel resonant circuit.
[0067] The charging control method of the transcranial magnetic stimulation power supply of the present invention comprises an APFC circuit and a series-parallel resonant circuit, wherein the APFC circuit comprises a DC bus capacitor; the series-parallel resonant circuit mainly comprises: switch tubes Q1-Q4, an LCC resonant circuit, a step-up transformer, a high-voltage rectifier bridge and a load capacitor C o The switch tubes Q1-Q4 form a full-bridge inverter unit for converting the voltage output by the DC bus capacitor into a high-frequency AC voltage to provide an excitation source for the LCC resonant circuit; the LCC resonant circuit includes a series resonant inductor L s , series resonant capacitor C s And the parallel resonant capacitor C p The step-up transformer is used to step up the output voltage of the LCC resonant circuit. The high-voltage rectifier bridge includes switch tubes D5-D7, which are used to rectify the high-frequency pulse output of the step-up transformer into a DC voltage. The isolation switch Q5 and the load capacitor C o The series connection is used to disconnect the heavy-frequency discharge circuit from the charging circuit during discharge.
[0068] The charging control methods include:
[0069] The load capacitor C o In the process of charging from zero voltage to the voltage corresponding to the rated power, a model predictive control step is adopted to perform constant current charging at the maximum allowed charging current;
[0070] After reaching the rated power, the model predictive control step is adopted to charge at a constant power at the rated power, and the load capacitance C o Charge from the voltage corresponding to the rated power to the set voltage V o,set .
[0071] Among them, the model predictive control steps specifically include:
[0072] The series-parallel resonant circuit operates in DCM and includes two discontinuous operating modes: DCM1 and DCM2. In DCM, the series-parallel resonant circuit operates in a quasi-resonant process.
[0073] In DCM1, the series resonant capacitor C in the LCC resonant circuit s And the parallel resonant capacitor C p The initial voltage values satisfy:
[0074]
[0075] Among them, V 1N 、V 2N They are the series resonant capacitors C s And the parallel resonant capacitor C p The initial voltage value, V in 、V o are the input voltage of the DC bus capacitor and the load capacitance C at the current moment respectively. o The output voltage,
[0076] Under DCM2, the series resonant capacitor C in the series-parallel resonant circuit s And the parallel resonant capacitor C p The initial voltage values satisfy:
[0077]
[0078] The input voltage V of the DC bus capacitor is obtained by sampling in And load capacitance C o The output voltage V o , and after calculating the LCC resonance gain coefficient G, based on the above formula (1) and formula (2), the series resonant capacitor C in the series-parallel resonant circuit in the two discontinuous working modes is obtained. s And the parallel resonant capacitor C p The initial voltage value. Figure 4 (a) and Figure 4 From the typical waveform diagram of the series-parallel resonant circuit in (b), it can be seen that the resonance processes of the series-parallel resonance are independent of each other under DCM operation. Therefore, after determining the initial values of the series and parallel resonant capacitor voltages V1N and V2N, the voltage and current of the entire resonance process can be determined.
[0079] Specifically, the load capacitance C caused by the single resonance process o The voltage change is small, so when the pre-tuning process is over, the load capacitor C o The output voltage V o (k) is approximately equal to the output voltage V of the next resonance process o(k+1), where k represents the current resonant process and k+1 represents the next resonant process; Figure 4 As shown in (a), assuming that t0–t3 is the kth resonance process, the corresponding load capacitor voltage at the end of the resonance process t3 is V o (k); t4–t6 is the (k+1)th resonance process, and the corresponding load capacitor voltage at the end time t7 of the resonance process is V o (k+1), the output voltage change caused by the (k+1)th resonance process is Δu(k), then:
[0080] V o (k+1)=V o (k)+Δu(k)
[0081] Since the load capacitance voltage change value Δu caused by the single resonance process of high-frequency resonant conversion is small, and in the heavy frequency operation stage V o (k) is much smaller than Δu(k), that is, V o (k)<<Δu(k), therefore, V o (k+1) is approximately equal to V o (k), that is, V o (k+1)≈V o (k). Therefore, the output voltage of the load capacitor in the current resonance process can be used to approximate the output voltage of the load capacitor in the next resonance process. Based on the obtained series resonant capacitor C s And the parallel resonant capacitor C p The initial voltage value can be obtained under DCM1 and DCM2. The load capacitance C o The charging power and charging current.
[0082] In DCM1, the load capacitance C o Output charging power P o And charging current I o,ave for:
[0083]
[0084] Among them, T s is the switching period of the switch tubes Q1-Q4 in the series-parallel resonant circuit at the current moment.
[0085] In DCM2, the load capacitance C o Output charging power P o And charging current I o,ave for:
[0086]
[0087] The following describes the process of realizing constant current and constant power based on the model predictive control method of the present invention under DCM1 and DCM2 respectively:
[0088] like Figure 5 As shown, under DCM1, the input voltage V of the DC bus capacitor is collected in And load capacitance C o The output voltage V o The output voltage value is approximately equal to the output voltage value after the next resonance process ends. The series resonant capacitor C is calculated by formula (1). s And the parallel resonant capacitor C p The initial voltage value; the average current I of the switch tubes Q1-Q4 in the next resonant switching cycle is predicted by formula (3) pred,ave 、Charging power P o,pred and critical switching period T s,critical ; Among them, I pred,ave =I o,ave , P o,pred =P o , critical switching period T s,critical =t I +t II +t III ,like Figure 4 As shown in (a), t I ,t II ,t III They represent the duration of the three resonance processes of the LCC resonant circuit under DCM1. o,pred Less than rated power P N .
[0089] According to the charge conservation principle, based on the average current I in the current switching cycle pred,ave and critical switching period T s,critical Update the switching period T of the next resonance process update ;
[0090] According to the charge conservation principle, the switching period T of the next resonance process update The switching cycle T at the current moment s Relationship satisfaction:
[0091] Q=I pred,ave T s =I o,ref T update (5)
[0092] Get the switching period T of the next resonance process update for:
[0093]
[0094] Among them, I o,ref is the reference current in the power system. At this time, I o,ref The maximum current I allowed by the power system o,max .
[0095] At the same time, the switching period T of the next resonance process update Also meets: the switching period T of the next resonant process update Greater than the critical switching period T s,critical ,Right now:
[0096] T update ≥T s,critical (7)
[0097] Based on the switching period T of the next resonance process obtained update , we can get the duty cycle D of the switch tube in the next resonance process as:
[0098]
[0099] in,
[0100] The switching period T of the following resonant process update The duty cycle D of the switch tube in the next resonance process is taken as input, and a PWM signal is generated through PWM modulation, which generates a control signal to trigger the switching of the switch tubes Q1-Q4 to achieve constant current charging control.
[0101] With the load capacitance C o The voltage rises, and the predicted charging power P at the current moment o,pred Gradually increase to rated power P N When constant power charging is adopted, under constant power charging, the load capacitance C o The output voltage V o With the output current I o The relationship between them is:
[0102]
[0103] The output current I o As the given value of the constant current charging based on the above model prediction, the output current I o As the reference current I in the power supply system o,ref , through formulas (5)-(7), the same method as above is used to obtain the switching period and duty cycle of the next resonant process under constant power charging. Through PWM modulation, a PWM signal is generated, which generates a control signal to trigger the switching of the switch tubes Q1-Q4, thereby realizing constant power charging control.
[0104] When the predicted charging power P o,pred Less than rated power PN When the charging power is greater than the rated power P N When charging, the rated constant power is used. Finally, constant current in the initial stage and constant power (CP) in the later stage are realized, and the minimum charging time allowed by the system is achieved.
[0105] like Figure 6 As shown, under DCM2, only during the second resonance process of the LCC resonance, the load capacitor C o Charging, the duration of the third resonance process remains unchanged, and the total time of the first two resonance processes decreases as the output voltage of the load capacitor increases. The series resonant capacitor C s And the parallel resonant capacitor C p The initial voltage value can be solved by equation (2) to obtain V 1N 、V 2N Combined with sampling, the input voltage V of the DC bus capacitor is obtained in And load capacitance C o The output voltage V o The charging current, power and soft switching critical conditions can be predicted.
[0106] The charging current of DCM2 is small and is not limited by constant current charging. DCM2 is limited by power in the early stage of charging and by critical switching cycle in the later stage of charging. That is, the switch cycle conduction time and switching cycle of the switch tube Q1-Q4 must meet the following relationship:
[0107]
[0108] Among them, t I ,t II ,t III are the durations of the three resonance processes under DCM2 respectively.
[0109] The next stage load capacitance C is predicted o After calculating the charging power, charging current and soft switching conditions, the above-mentioned constant power control model based on model prediction under DCM1 can be used to obtain the switching period of the next resonant process and the duty cycle that meets the soft switching conditions, and finally the constant power charging control based on model prediction under DCM2 is obtained. The control block diagram is shown in Figure 6 shown.
[0110] Specifically, under DCM2, the predicted average current I of the switch tubes Q1-Q4 in the current switching cycle is obtained by equations (2) and (4): pred,ave 、Charging power P o,pred and critical switching period T s,critical ;
[0111] The load capacitance C is obtained by formula (8): o The output current I o , the output current I o As the reference current I in the power supply system o,ref , through formulas (5)-(7), the switching period and duty cycle of the next resonant process under constant power charging are obtained in the same way as above. Through PWM modulation, a PWM signal is generated, which generates a control signal to trigger the switching of the switch tubes Q1-Q4, thereby realizing constant power charging control under DCM2.
[0112] After the charging voltage gradually increases, the prediction model switches from DCM1 to DCM2. The switching condition between DCM1 and DCM2 is V o =V in / (k+1). The charging current and power in this switching process will not change suddenly, and a smooth transition can be achieved.
[0113] like Figure 7 (a) and Figure 7 As shown in (b), the simulation waveforms of the fixed switching frequency and constant power charging method in the prior art and the series-parallel resonant charging control method based on model prediction in this embodiment are compared. The transcranial magnetic stimulation power supply structure adopts Figure 2 The circuit shown in the figure has an active power factor correction circuit in the front stage and a series-parallel resonant topology in the rear stage. The figure shows the front-end APFC input AC current I of the series-parallel resonant circuit operating at a constant switching frequency. in , the input voltage of the DC bus capacitor of APFC output V in , load capacitance C o Output charging power P o , output capacitor voltage V o Simulation waveform diagram.
[0114] It can be seen from the figure that when a fixed switching frequency and constant power charging method is used, repeated low-frequency oscillations will be superimposed on the input AC current waveform, and the output power only reaches the rated power at a limited point, the power utilization rate is low, and the charging time is long. In the constant current and constant power charging process based on model predictive control proposed in this embodiment, the impact of repeated frequency operation on the quality of the input current waveform on the grid side is reduced. Figure 7 In (a), the fixed switching frequency charging method is used. Figure 7 The repetitive low-frequency oscillations in the input current waveform of the charging mode in (b) are significantly reduced, thereby improving the quality of the input current waveform.
[0115] It should be noted that the model predictive control method in this embodiment is applied in the constant current charging and constant power charging processes. In other embodiments, the current or power can also be controlled only by using this control method.
[0116] Example 2
[0117] Based on the above method, the present invention provides a charging control system for a transcranial magnetic stimulation power supply, which mainly includes:
[0118] Constant current charging module is used to charge the load capacitor C o During the process of charging from zero voltage to the voltage corresponding to the rated power, constant current charging is performed through the model prediction control unit;
[0119] Constant power charging module, used to charge the load capacitor C o Charge from the voltage corresponding to the rated power to the set voltage V o,set During the process, the model predicts the control unit to perform constant power charging;
[0120] Based on the prediction control unit includes:
[0121] The node for calculating the initial value of the resonant capacitor voltage is used to calculate the input voltage V of the DC bus capacitor in the current resonant process under DCM1 and DCM2 respectively. in And load capacitance C o The output voltage V o As input, we get the series resonant capacitor C s And the parallel resonant capacitor C p The initial voltage value V 1N 、V 2N ;
[0122] Load capacitor charging current prediction node, used to calculate the series resonant capacitor C s And the parallel resonant capacitor C p The initial voltage value V 1N 、V 2N And the input voltage of the DC bus capacitor and the load capacitance C during the current resonance process o The output voltage is taken as input, and the load capacitance C of the next resonance process is obtained. o Output charging power P o,pred 、Charging current I pred,ave and critical switching period T s,critical ;
[0123] The switching cycle prediction node is used to predict the switching cycle T of the next resonant process. update Greater than the critical switching period T s,critical As a constraint, based on the charging current I o,ave And reference current I o,ref, the switching period T of the next resonant process update The switching cycle T at the current moment s The charge conservation is satisfied between them, and the switching period T of the next resonance process is obtained. update ;
[0124] The switch duty cycle prediction node is used to predict the switching period T of the next resonant process. update The relationship between the duty cycle D of the switch tube in the next resonance process is satisfied, and the duty cycle D of the switch tube in the next resonance process is obtained;
[0125] PWM modulation node, used for the switching period T of the following resonant process update The duty cycle D of the switch tube in the next resonance process is used as input, and a PWM signal is generated through PWM modulation, which generates a control signal that triggers the switch tubes Q1-Q4 to turn on and off, thereby realizing current or power charging control.
[0126] In the constant current charging module, the reference current I o,ref is the maximum current allowed by the power system. In the constant power charging module, the reference current I o,ref is the load capacitance C o The output current I o ,in, P N is the load capacitance C o Rated power.
[0127] When P o,pred <P N When P o,pred ≥P N When the battery is charged at constant power.
[0128] In the load capacitor charging current prediction node, the input voltage of the DC bus capacitor and the load capacitance C in the next resonance process o The output voltage of the DC bus capacitor is V in And load capacitance C o The output voltage V o Equal, the load capacitance C is obtained by formula 3 or 4 o Output charging power P o And charging current I o,ave ;
[0129] Specifically, the next resonance process load capacitance C o Output charging power P o,pred 、Charging current I pred,ave and critical switching period T s,critical , respectively, with the load capacitance C o Output charging power P o And charging current Io,ave The relationship between them is:
[0130] I pred,ave =I o,ave
[0131] P o,pred =P o
[0132] T s,critical =t I +y II +t III
[0133] Among them, t I ,t II ,t III They respectively represent the duration of the three resonance processes of the series-parallel resonant circuit under DCM1 or DCM2.
[0134] In the switching cycle prediction node, according to the charge conservation principle, the switching cycle T of the next resonance process update The switching cycle T at the current moment s The relationship satisfies formula (5).
[0135] In the switch duty cycle prediction node, the switching period T of the next resonance process update The duty cycle D of the switch tube in the next resonant process satisfies:
[0136]
[0137] in,
[0138] In the present invention, during the entire charging process, the load capacitor C o In the process of charging from zero voltage to the voltage corresponding to the rated power, constant current charging (i.e. Figure 3 AB phase); charging from the voltage corresponding to the rated power to the set voltage V o,set During the process, constant power charging (i.e. Figure 3 This charging method with constant current in the initial stage of charging and constant power in the later stage can reduce the capacity of the charging power supply and the front-end power factor correction circuit, and during the heavy frequency operation, the series-parallel resonant converter operates within the constant power charging range.
[0139] Specifically, the output voltage is zero during the initial charging, corresponding to Figure 3 At point A in the trajectory, the load capacitor is equivalent to a short circuit, the output power is low, and the series-parallel resonant circuit operates at the maximum allowable charging current; as the load capacitor voltage increases, the output power gradually reaches the rated value; then the constant power charging method is adopted to reduce the charging current to achieve constant power charging, and finally charge to the set voltage Vo,set . During the repetitive frequency operation stage, the RLC discharge circuit will feed back part of the energy to the load capacitor, so that the charging voltage of the load capacitor starts from a higher voltage. By reasonably selecting the resonant parameters and the ratio of the step-up transformer, the series-parallel resonant conversion circuit can operate within the constant power range of the B-C segment to achieve repetitive frequency constant power charging. Since the charging voltage is within the constant power range after the repetitive frequency operation, constant power operation can be achieved during the entire repetitive frequency operation process. The constant power charging method can ensure that the series-parallel resonant conversion circuit is equivalent to a constant load relative to the previous APFC in the charging link, thereby reducing the impact of the charging process on the power grid and improving the waveform quality on the input side of the previous APFC. At the same time, the use of the constant power charging mode also simplifies the loss calculation of the series-parallel resonant converter and the system heat dissipation design. The charging process operates along the maximum charging current and maximum charging power, reducing the charging time and obtaining a higher repetition frequency. V in the figure o '、V o ″, respectively represent the typical output capacitor voltage in the constant power stage and constant current stage, V o,max , P max They respectively represent the maximum voltage and output power allowed in the load capacitor in the power supply system.
[0140] The constant current and constant power charging control method in the present invention is a new time domain model prediction method, which can realize constant current or constant power output under the condition of ensuring soft switching operation. By establishing the load capacitor output voltage and the series resonant capacitor C in the series-parallel resonant circuit s And the parallel resonant capacitor C p The relationship between the initial value of the voltage avoids directly measuring the charging power and charging current of the load capacitor. By real-time predicting the operating state (resonant current) of the series-parallel resonant circuit in the next resonant process, adjusting the switching frequency and duty cycle of the switch tubes Q1-Q4 in the series-parallel resonant circuit to achieve constant current or constant power charging, updating the switching frequency and duty cycle in real time, and realizing full-range soft switching, the dynamic process can be basically ignored, there is no transition process, and the input waveform quality of the front-end APFC circuit is improved; and within the current and power allowable range of the entire power supply system, the charging time is reduced and the repetition frequency is increased. At the same time, the model predictive control method proposed in the present invention can quickly respond to the sudden change of capacitor voltage during repeated discharge, realize soft switching operation, and overcome the deficiency that traditional PI control cannot accurately track output power or current.
[0141] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A charging control method for a transcranial magnetic stimulation power supply, wherein the transcranial magnetic stimulation power supply comprises a DC bus capacitor and a series-parallel resonant circuit, wherein the series-parallel resonant circuit comprises a switch tube, a series-parallel resonant capacitor and a load capacitor, wherein: The control method includes a model predictive control step, and the model predictive control step includes: Under DCM1 and DCM2 respectively, by sampling the input voltage V of the DC bus capacitor during the current resonance process in And load capacitance C o The output voltage V o , get the initial voltage value V of the series-parallel resonant capacitor 1N 、V 2N ; With the initial voltage value V 1N 、V 2N The input voltage of the DC bus capacitor and the output voltage of the load capacitor in the current resonance process are used as inputs to predict the charging current I of the load capacitor in the next resonance process. pred,ave and critical switching period T s,critical ; The switching period T of the following resonant process update Greater than the critical switching period T s,critical is a constraint condition, based on the charging current I pred,ave And reference current I o,ref , the charge conservation is satisfied through the resonance process, and the switching period T of the next resonance process is obtained update ; With the switching period T update The duty cycle D of the switch tube in the next resonance process satisfies Get the switch duty cycle of the next resonance process, where: The switching period T of the following resonant process update And the duty cycle D of the switch tube are used as input, and through PWM modulation, a control signal that triggers the switch tube to turn on and off is generated to achieve current or power charging control.
2. The charging control method according to claim 1, characterized in that: The charging step further comprises: The load capacitor C o In the process of charging from zero voltage to the voltage corresponding to the rated power, the model predictive control step is adopted to perform constant current charging; The load capacitor C o In the process of charging from the voltage corresponding to the rated power to the set voltage, the model predictive control step is adopted to perform constant power charging at the rated power.
3. The charging control method according to claim 2, characterized in that: During the constant current charging process, the reference current I o,ref The maximum current allowed by the power system; During the constant power charging process, the reference current I o,ref is the load capacitance C o The output current I o ,in, P N is the load capacitance C o Rated power, V o is the load capacitance C o output voltage.
4. The control method according to claim 3, characterized in that: The next resonance process load capacitance C o The charging current I pred,ave and critical switching period T s,critical Respectively meet: I pred,ave =I o,ave T s,critical =t I +t II +t III Among them, t I ,t II ,t III Respectively represent the duration of the three operating stages of the series-parallel resonant circuit under DCM1 or DCM2; In DCM1 and DCM2, I o,ave They can be expressed as: Among them, V in is the input voltage of the DC bus capacitor at the current moment, T s is the current switching cycle, C s is the series resonant capacitor, k is the resonant parameter, and 5. The control method according to claim 4, characterized in that: The switching period T of the next resonance process update for: Among them, I o,ref is the reference current, T s is the switching period of the current resonance process.
6. A charging control system for a transcranial magnetic stimulation power supply, the transcranial magnetic stimulation power supply comprising a DC bus capacitor and a series-parallel resonant circuit, the series-parallel resonant circuit comprising a switch tube, a series-parallel resonant capacitor and a load capacitor, characterized in that: The control system includes a model prediction control unit, and the model prediction control unit includes: The resonant capacitor voltage initial value calculation node is used to sample the input voltage V of the DC bus capacitor at the current moment under DCM1 and DCM2 respectively. in And load capacitance C o The output voltage V o , get the initial voltage value V of the series-parallel resonant capacitor 1N 、V 2N ; The load capacitor charging current prediction node is used to predict the voltage with the initial value V 1N 、V 2N The input voltage of the DC bus capacitor and the output voltage of the load capacitor in the current resonance process are used as inputs to predict the charging current I of the load capacitor in the next resonance process. pred,ave and critical switching period T s,critical ; The switching cycle prediction node is used to predict the switching cycle T of the next resonant process. update Greater than the critical switching period T s,critical is a constraint condition, based on the charging current I pred,ave And reference current I o,ref , the charge conservation is satisfied through the resonance process, and the switching period T of the next resonance process is obtained update ; The switch duty cycle prediction node is used to predict the switching cycle T update The duty cycle D of the switch tube in the next resonance process satisfies Get the switch duty cycle of the next resonance process, where: PWM modulation node, used for the switching period T of the following resonant process update With the duty cycle D of the switch tube as input, through PWM modulation, a control signal that triggers the switch tube to turn on and off is generated to achieve current or power charging control.
7. The charging control system according to claim 6, characterized in that: Also includes: Constant current charging module is used to charge the load capacitor C o During the process of charging from zero voltage to the voltage corresponding to the rated power, constant current charging is performed through the model prediction control unit; Constant power charging module, used to charge the load capacitor C o During the process of charging from the voltage corresponding to the rated power to the set voltage, the model prediction control unit is used to perform constant power charging at the rated power.
8. The charging control system according to claim 7, characterized in that: In the constant current charging module, the reference current I o,ref The maximum current I allowed by the power system o ; In the constant power charging module, the reference current I o,ref is the load capacitance C o The output current I o ,in, P N is the load capacitance C o Rated power, V o is the load capacitance C o output voltage.
9. The charging control system according to claim 8, characterized in that: In the load capacitor charging current prediction node, the load capacitor C o The charging current I pred,ave and critical switching period T s,critical Respectively meet: I pred,ave =I o,ave T s,critical =t I +t II +t III Among them, t I ,t II ,t III They represent the duration of the three resonance processes of the series-parallel resonance circuit under DCM1 or DCM2 respectively; In DCM1 and DCM2, I o,ave They can be expressed as: Among them, V in is the input voltage of the DC bus capacitor at the current moment, T s is the current switching cycle, C s is the series resonant capacitor, k is the resonant parameter, and 10. The charging control system according to claim 9, characterized in that: In the switching cycle prediction node, the switching cycle T of the next resonance process update for: Among them, I o,ref is the reference current, T s is the switching cycle at the current moment.