Construction method and system for a progressive and regressive assembled steel box tied arch bridge

By erecting a steel platform on the embankment and using a full-turn crane to lift the steel main beam and steel box arch ribs segmentally, the problems of high lifting height and limited working space in the construction of the steel box tie rod arch bridge are solved, safe and efficient bridge deck lifting is achieved, and construction costs are reduced.

CN115323931BActive Publication Date: 2025-08-05CHINA RAILWAY BRIDGE BUREAU GRP NO 6 ENG CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202211042523.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-29
Publication Date
2025-08-05
Estimated Expiration
2042-08-29

AI Technical Summary

Technical Problem

In the prior art, large temporary structures such as high lifting height, limited working space, and large investment in large temporary structures such as trest bridges during construction, resulting in increased construction costs and safety risks.

Method used

The progressive and regressive assembly method is adopted. By erecting a steel platform on the embankment and using a full-turn crane, the steel main beams and steel box arch ribs are lifted segment by segment, and the completed steel main beams are used as the lifting platform to lower the lifting height and complete subsequent lifting operations on the bridge deck.

Benefits of technology

The water surface or ground lifting operation is transformed into bridge deck lifting, which reduces the lifting height, avoids the problem of narrow bridge deck space, improves construction safety and efficiency, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115323931B_ABST
    Figure CN115323931B_ABST
Patent Text Reader

Abstract

The present application relates to a construction method and system for a progressive and regressive assembled steel box tie-arch bridge, wherein the method comprises: setting up a steel platform and a full-turn crane on the embankment; using the full-turn crane to sequentially hoist several segmental steel main beams along the longitudinal direction of the bridge, the full-turn crane hoists the first segmental steel main beam on the steel platform, and the subsequent segmental steel main beams are all hoisted on the completed steel main beam using the full-turn crane; using the full-turn crane to sequentially hoist several segmental steel box arch ribs in a direction opposite to the direction of advancement of the steel main beam construction; removing the full-turn crane, steel platform and steel box arch rib supports, and removing the steel main beam supports after completing the installation of the steel box tie-arch bridge boom and the construction of the bridge deck system. The present application realizes the conversion of water or ground hoisting operations to bridge deck hoisting operations, significantly reducing the lifting height, while avoiding the problems of narrow bridge deck space and large interference in hoisting operations, making it safer and more efficient, and significantly reducing investment costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge engineering, and in particular to a construction method and system for a progressive and regressive assembled steel box tie arch bridge. Background Art

[0002] Currently, steel-box tied-arch bridges are widely used in bridge engineering. They possess the general characteristics of arch bridges, while also possessing their own unique features. They combine the advantages of both arch and beam structures, effectively sharing loads and fully utilizing the structural properties and combined effects of the beam's bending and the arch's compression. Key construction methods include in-situ support assembly, vertical arch rib lifting, and beam-arch top-pushing.

[0003] In related technologies, for the construction of steel box tie-arch bridges where the bridge deck is high above the river surface and the bridge deck width is narrow and the working space is limited, it is generally necessary to build a trestle on the water surface, and park or run ordinary cranes or gantry cranes on the trestle to assemble steel main beams and steel box arch ribs.

[0004] However, in related technologies, when using traveling cranes or gantry cranes on trestle bridges for hoisting operations, the lifting height cannot meet the assembly requirements of both the steel main beams and the arch ribs. Furthermore, the use of large-scale lifting equipment for assembly places high demands on on-site access roads and construction trestle bridges, significantly increasing construction costs and safety risks. Therefore, how to reduce the lifting height, avoid working in confined spaces, and reduce the investment in large temporary structures such as trestle bridges are urgent technical issues that need to be addressed by those skilled in the art. Summary of the Invention

[0005] The embodiments of the present application provide a construction method and system for a progressive and regressive assembly of a steel box tie arch bridge to solve the problems in the related art of high hoisting height, limited working space, and large investment in large temporary structures such as trestles during the construction of steel box tie arch bridges.

[0006] On the one hand, the present application provides a construction method for a progressive and regressive assembled steel box tied arch bridge, the technical solution adopted is:

[0007] A construction method for a progressive and regressive assembled steel box tied arch bridge, comprising:

[0008] Complete the foundation and substructure construction at both ends of the steel box tied arch bridge;

[0009] A steel platform is set up on the embankment at one end of the steel box tied arch bridge, and a full-slewing crane is set up on the steel platform;

[0010] The fully-rotating crane is used to sequentially hoist several segmental steel main beams along the longitudinal direction of the bridge. When constructing each segmental steel main beam, the fully-rotating crane is used to first erect a steel main beam support, and then assemble the steel main beam components on the steel main beam support. The fully-rotating crane hoists the first segmental steel main beam on the steel platform, and the subsequent segmental steel main beams are hoisted on the completed steel main beam using the fully-rotating crane.

[0011] A fully rotating crane traveling on the completed steel main beam is used to sequentially hoist several segments of steel box arch ribs in a direction opposite to the direction of steel main beam construction. During the construction of each segment of steel box arch rib, a steel box arch rib support is first erected, and then the steel box arch rib components are assembled on the steel box arch rib support.

[0012] The fully rotating crane, the steel platform and the steel box arch rib support are dismantled, and the steel main beam support is dismantled after the installation of the steel box tied arch bridge hangers and the construction of the bridge deck system are completed.

[0013] In some embodiments, the subsequent plurality of segmental steel main beams are hoisted on the completed steel main beam using the full-rotation crane, including:

[0014] During the construction of the steel main beam on the embankment, the steel main beam bracket and the steel main beam components are hoisted from the ground to the bridge deck height using the fully rotating crane;

[0015] After the construction of the steel main beam on the embankment is completed, a lifting station is assembled on the steel platform, and a longitudinal track along the longitudinal direction of the bridge is assembled on the completed steel main beam. The steel main beam supports and steel main beam components in several subsequent segmental steel main beams are lifted to the bridge deck through the lifting station and transported to the lifting range of the full-rotating crane by a longitudinal trolley running on the longitudinal track.

[0016] In some embodiments, the method of sequentially hoisting a plurality of segmented steel box arch ribs in a direction opposite to the construction advancement direction of the steel main beam using a full-rotation crane traveling on the completed steel main beam includes:

[0017] Carry out the construction of several segments of steel box arch ribs in sequence until the steel box arch ribs are closed;

[0018] Carry out the construction of subsequent segmental steel box arch ribs after the steel box arch rib closure section;

[0019] Assemble the steel box arch rib closure section.

[0020] In some embodiments, when the construction of several segmented steel box arch ribs is carried out in sequence to the steel box arch rib closing section, the steel box arch rib bracket and the steel box arch rib component are lifted to the bridge deck by the lifting station and transported to the lifting range of the full-rotation crane by the longitudinal movement trolley.

[0021] In some embodiments, the steel box arch rib closing section is arranged at the arch waist of the steel box arch rib close to the steel platform and close to the arch foot section.

[0022] In some embodiments, the construction of the subsequent segmental steel box arch ribs after the closing of the steel box arch ribs includes:

[0023] The lifting station, the longitudinal moving track and the longitudinal moving trolley are dismantled, and the full-rotation crane is retreated to the steel platform to carry out the construction of the subsequent steel box arch rib arch foot section after the steel box arch rib closing section.

[0024] In some embodiments, the lifting station, the longitudinal movement track and the longitudinal movement trolley are all assembled using the full-rotation crane.

[0025] In a second aspect, the present application provides a construction system for a progressive and regressive assembled steel box tied arch bridge, comprising:

[0026] A steel platform is located on the embankment at one end of the steel box tied arch bridge;

[0027] A full-rotation crane is used to hoist the steel main beams and steel box arch ribs, and the full-rotation crane hoists the steel main beams and steel box arch ribs to be constructed on the steel platform and the completed steel main beams;

[0028] Steel main beam support, which is used to temporarily support the steel main beam;

[0029] Steel box arch rib supports are installed on the steel main beam to temporarily support the steel box arch ribs.

[0030] In some embodiments, the present invention further comprises:

[0031] a lifting station, which is provided on the steel platform and is used to lift the steel main beam components, the steel main beam supports, the steel box arch rib supports and the steel box arch rib components to the bridge deck height;

[0032] Longitudinal track, which is provided on the steel platform and the completed steel main beam and is arranged along the longitudinal direction of the bridge;

[0033] A longitudinal moving trolley is mounted on the longitudinal moving track and is used for transporting steel main beam components, steel main beam supports, steel box arch rib supports and steel box arch rib components.

[0034] In some embodiments, the azimuth crane has a self-propelled function.

[0035] The beneficial effects of the technical solution provided by this application include:

[0036] The embodiment of the present application provides a construction method for a progressive and retrograde assembly of a steel box tie-arch bridge, which first builds a steel platform on the embankment, uses the steel platform as a platform for a full-rotation crane to carry out the hoisting construction of the steel main beam support and the steel main beam of the first section, uses the steel main beam support as a temporary support to support the steel main beam, and then uses the completed steel main beam as a platform for a full-rotation crane to carry out the hoisting construction of the steel main beam support and the steel main beam of the subsequent sections. At the same time, the hoisting construction of the subsequent steel box arch ribs is also carried out by moving the full-rotation crane on the steel main beam. Therefore, the water surface or ground hoisting operation is converted to the bridge deck hoisting operation, the lifting height is greatly reduced, and the progressive and retrograde assembly avoids the problems of narrow bridge deck space and large interference in hoisting operations. Compared with the traditional in-situ bracket assembly method, it is safer and more efficient, and the investment cost is greatly reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0038] Figure 1 Schematic diagram of the implementation of building a steel platform in step S1 and step S2 in a construction method for a progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application;

[0039] Figure 2 A schematic diagram illustrating the implementation of step S2 in a construction method for a progressive and regressive steel box tied arch bridge provided in an embodiment of the present application;

[0040] Figure 3 Schematic diagram of the implementation of step S301 in a construction method for progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application;

[0041] Figure 4 for Figure 3 Cross-sectional view along line AA;

[0042] Figure 5 A schematic diagram illustrating the implementation of the forward movement of the full-rotation crane in step S302 of a construction method for a progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application;

[0043] Figure 6 Schematic diagram of the implementation of the construction of subsequent segmental steel main beams by a fully rotating crane in step S302 of a construction method for a progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application;

[0044] Figure 7Schematic diagram of the implementation of setting up the lifting station, longitudinal track and longitudinal trolley in step S302 of the construction method of the progressive and regressive assembly steel box tied arch bridge provided in an embodiment of the present application;

[0045] Figure 8 for Figure 7 Cross-sectional view along the midline BB;

[0046] Figure 9 A schematic diagram illustrating the implementation of the construction of the last segment of the steel main beam component in step S302 of a construction method for a progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application;

[0047] Figure 10 Schematic diagram of the implementation of the construction of the first segment steel box arch rib member in step S401 of the construction method of the progressive and regressive assembly steel box tied arch bridge provided in an embodiment of the present application;

[0048] Figure 11 Schematic diagram of the implementation of the full-rotation crane retreat in step S401 of the construction method of the progressive and retreat type steel box tied arch bridge provided in an embodiment of the present application;

[0049] Figure 12 Schematic diagram of the implementation of step S401 in a construction method for progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application;

[0050] Figure 13 This is a schematic diagram of the implementation of the full-rotation crane retreating to the steel platform in step S402 of a construction method for progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application;

[0051] Figure 14 Schematic diagram of the implementation of step S402 in the construction method of a progressive and regressive assembly steel box tied arch bridge provided in an embodiment of the present application;

[0052] Figure 15 Schematic diagram of the implementation of step S403 in the construction method of a progressive and regressive assembly steel box tied arch bridge provided in an embodiment of the present application;

[0053] Figure 16 Schematic diagram of the implementation of step S5 in the construction method of a progressive and regressive assembly of a steel box tied arch bridge provided in an embodiment of the present application.

[0054] In the figure: 1. Foundation and lower structure; 2. Steel platform; 3. Full-revolving crane; 4. Steel main beam; 401. Steel main beam component; 5. Steel main beam support; 6. Lifting station; 7. Longitudinal movement trolley; 8. Steel box arch rib; 801. Steel box arch rib component; 802. Steel box arch rib closing section; 9. Steel box arch rib support; 10. Hanging rod. DETAILED DESCRIPTION

[0055] To make the purpose, technical solutions, and advantages of the embodiments of this application more clear, the technical solutions in the embodiments of this application will be clearly and completely described below in conjunction with the drawings in the embodiments of this application. Obviously, the described embodiments are part of the embodiments of this application, not all of the embodiments. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of this application.

[0056] The embodiments of the present application provide a construction method and system for a progressive and regressive assembly of a steel box tie-arch bridge, which can solve the problems of the current steel box tie-arch bridge hoisting operation, such as the bridge deck being high above the river surface or the ground, the bridge deck being narrow, the limited working space, and the problem of increased construction costs caused by the investment of a water trestle.

[0057] Reference Figure 1-16 As shown, a construction method of a progressive and regressive assembled steel box tied arch bridge provided by the present application includes the following steps:

[0058] S1: Complete the construction of the foundation and substructure 1 at both ends of the steel box tied arch bridge.

[0059] Reference Figure 1 Specifically, the foundation and lower structure 1 include piers and foundations at both ends of the arch bridge.

[0060] S2: A steel platform 2 is set up on the embankment at one end of the steel box tied arch bridge, and a full-rotation crane 3 is set up on the steel platform 2.

[0061] Reference Figure 2 Specifically, when the steel platform 2 is built, it is erected along the bridge axis on one side of the steel box tied arch bridge. The steel platform 2 serves as the bearing foundation of the full-revolving crane 3. When erecting the full-revolving crane 3, an ordinary crane is used to lift and assemble the components of the full-revolving crane 3 on the shore land. The full-revolving crane 3 has a self-propelled function.

[0062] S3: Use a fully revolving crane 3 to sequentially hoist several segments of steel main beams 4 along the longitudinal direction of the bridge. For each segment of steel main beam 4, a fully revolving crane 3 is first used to set up the steel main beam supports 5. Steel main beam components 401 are then assembled on the steel main beam supports 5. The fully revolving crane 3 then hoists the first segment of steel main beam 4 onto the steel platform 2. Subsequent segments of steel main beams 4 are then hoisted using the fully revolving crane 3 from the completed steel main beams 4. Adjacent steel main beam components 401 are connected and secured by welding or bolting.

[0063] Specifically, refer to Figure 3-9 As shown, including:

[0064] S301: Construction of the first segment steel main beam 4 is performed on the steel platform 2.

[0065] Reference Figure 3 and Figure 4 During the construction of the first section steel main beam 4, materials such as the steel main beam component 401 and the steel main beam support 5 are transported by land to the lifting range of the full-revolving crane 3, and then lifted from the ground to the bridge deck height by the full-revolving crane 3.

[0066] S302: The full-revolving crane 3 automatically moves forward a distance of a segment steel main beam 4, and then performs hoisting construction of the next segment steel main beam 4, and repeats this step until the construction of the subsequent segment steel main beam 4 is completed.

[0067] When the full-revolving crane 3 moves, a track for the full-revolving crane 3 to move needs to be set up on the built steel main beam 4, and the full-revolving crane 3 moves on the track by itself.

[0068] Furthermore, during construction of the steel main beam 4 located on the embankment, the steel main beam bracket 5 and the steel main beam component 401 are transported by land to the lifting range of the full-revolving crane 3, and then lifted from the ground to the bridge deck level using the full-revolving crane 3. In this step, the lifting range of the full-revolving crane 3 must meet the requirements for lifting components on the land near the bank, and the full-revolving bridge deck crane must be equipped with sufficient wire rope length.

[0069] Reference Figure 7 After the construction of the steel main beam 4 on the embankment is completed, the lifting station 6 is assembled on the steel platform 2, and the longitudinal movement track along the longitudinal direction of the bridge is assembled on the completed steel main beam 4. The steel main beam bracket 5 and the steel main beam component 401 in the subsequent several segment steel main beams 4 are lifted to the bridge deck through the lifting station 6, and are transported to the lifting range of the full-rotation crane 3 by the longitudinal movement trolley 7 running on the longitudinal movement track.

[0070] Among them, the lifting station 6, the longitudinal movement track and the longitudinal movement trolley 7 are all assembled using the full-rotation crane 3.

[0071] Reference Figure 6 After the construction of the steel main beam 4 on the embankment is completed, the full-wheel crane can also directly lift the steel main beam component 401 and the steel main beam support 5 from the ground to carry out the construction of the first section of the steel main beam 4 located on the river surface. After the construction of the steel main beam 4 in this section is completed, the lifting station 6, longitudinal movement track and longitudinal movement trolley 7 can be constructed.

[0072] S4: A full-rotating crane 3 traveling on the completed steel main beam 4 is used to sequentially hoist several segmented steel box arch ribs 8 in a direction opposite to the construction advancement direction of the steel main beam 4. During the construction of each segmented steel box arch rib 8, a steel box arch rib support 9 is first erected, and then the steel box arch rib component 801 is assembled on the steel box arch rib support 9.

[0073] Specifically, refer to Figure 10-16 Shown, including:

[0074] S401: construct several segments of steel box arch ribs 8 in sequence until the steel box arch rib closing section 802.

[0075] Reference Figure 10-12 Among them, the steel box arch rib bracket 9 and the steel box arch rib component 801 are lifted to the bridge deck by the lifting station 6, and transported to the lifting range of the full-rotation crane 3 by the longitudinal movement trolley 7.

[0076] Furthermore, after the full-revolving crane 3 completes the construction of a section of steel box arch rib 8, it moves back a distance of a section of steel main beam 4 before carrying out the hoisting construction of the next section of steel box arch rib 8.

[0077] S402: Carry out construction of the subsequent segment steel box arch rib 8 of the steel box arch rib closing section 802.

[0078] Reference Figure 13 and Figure 14 , wherein the steel box arch rib closing section 802 is arranged at the arch waist of the steel box arch rib 8 on the side close to the steel platform 2 and close to the arch foot section. When constructing the subsequent segment steel box arch rib 8 of the closing section, the lifting station 6 and the longitudinal movement track and the longitudinal movement trolley 7 are first dismantled, and the full-revolving crane 3 retreats to the steel platform 2 to carry out the subsequent steel box arch rib 8 arch foot section construction of the steel box arch rib closing section 802. Accordingly, the steel box arch rib bracket 9 and the steel box arch rib component 801 are transported by land to the lifting range of the full-revolving bridge crane.

[0079] S403: Assemble the steel box arch rib closing section 802.

[0080] Reference Figure 15 In order to ensure the consistency of the internal forces of the arch ribs on both sides, a predetermined force is applied to the steel box arches at both ends of the closing mouth according to the internal force value measured at the corresponding position of the closing section on the other side, and the closing section is installed and welded at the designed closing temperature.

[0081] S5: dismantle the full-slewing crane 3, the steel platform 2 and the steel box arch rib support 9, and dismantle the steel main beam support 5 after completing the installation of the steel box tied arch bridge hanger 10 and the bridge deck system construction.

[0082] Reference Figure 16 Specifically, a ground crane is used to dismantle the full-rotating crane 3 and the steel platform 2, and then the subsequent processes of the steel box tied arch bridge are completed. The subsequent processes include, in order, the dismantling of the steel box arch rib support 9, the installation of the hanger 10, the construction of the bridge deck system, and the dismantling of the steel main beam support 5.

[0083] Through the above-mentioned arrangement, a steel platform 2 is first built on the embankment, and the steel platform 2 is used as a platform for the full-rotation crane 3 to carry out the hoisting construction of the steel main beam support 5 and the steel main beam 4 of the first section, and the steel main beam support 5 is used as a temporary support to support the steel main beam 4, and then the completed steel main beam 4 is used as a platform for the full-rotation crane 3 to carry out the hoisting construction of the steel main beam support 5 and the steel main beam 4 of the subsequent sections. At the same time, the subsequent hoisting construction of the steel box arch rib 8 is also carried out by moving the full-rotation crane 3 on the steel main beam 4. Therefore, the water surface or ground hoisting operation is converted to the bridge deck hoisting operation, the lifting height is greatly reduced, and the progressive and retrograde assembly avoids the problems of narrow bridge deck space and large interference in hoisting operations. Compared with the traditional in-situ bracket assembly method, it is safer and more efficient, and the investment cost is greatly reduced.

[0084] The embodiment of the present application also provides a construction system for progressive and regressive assembly of a steel box tie arch bridge, which includes a steel platform 2, a full-rotation crane 3, a steel main beam support 5 and a steel box arch rib support 9.

[0085] Reference Figure 1-6 As shown, the steel platform 2 is arranged on the embankment at one end of the steel box tied arch bridge, and the full-revolving crane 3 is used to lift the steel main beam 4 and the steel box arch rib 8, and the full-revolving crane 3 lifts the steel main beam 4 and the steel box arch rib 8 to be constructed on the steel platform 2 and the completed steel main beam 4, and the full-revolving crane 3 has a self-propelled function; the steel main beam support 5 is supported on the embankment or the riverbed and the bottom is located underground for temporarily supporting the steel main beam 4; the steel box arch rib support 9 is erected on the steel main beam 4 for temporarily supporting the steel box arch rib 8.

[0086] Reference Figure 7 As shown, a lifting station 6 is also built on the steel platform 2. Specifically, the lifting station 6 is built after the full-rotating crane 3 is moved out of the steel platform 2. The lifting station 6 is used to lift the steel main beam component 401, the steel main beam support 5, the steel box arch rib support 9 and the steel box arch rib component 801 to the bridge deck height.

[0087] Reference Figure 7-12 As shown, further, longitudinal tracks are laid on the steel platform 2 and the completed steel main beam 4, and the longitudinal tracks are arranged along the longitudinal direction of the bridge. A longitudinal trolley 7 is installed on the longitudinal tracks, and the longitudinal trolley 7 moves on the longitudinal tracks to transport the steel main beam component 401, the steel main beam support 5, the steel box arch rib support 9 and the steel box arch rib component 801 to the lifting range of the full-rotation crane 3.

[0088] In the description of this application, it should be noted that the terms "upper" and "lower" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be internal communication between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to the specific circumstances.

[0089] It should be noted that, in this application, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprising a ..." does not exclude the presence of other identical elements in the process, method, article or device comprising the element.

[0090] The foregoing is merely a list of specific embodiments of the present application, intended to enable those skilled in the art to understand or implement the present application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application is not limited to the embodiments shown herein, but is intended to conform to the broadest scope consistent with the principles and novel features of the present application.

Claims

1. A construction method for a progressive and regressive assembled steel box tied arch bridge, characterized in that: The following steps are involved: Complete the construction of the foundation and substructure (1) at both ends of the steel box tied arch bridge; A steel platform (2) is set up on the embankment at one end of the steel box tied arch bridge, and a full-rotation crane (3) is set up on the steel platform (2); The fully revolving crane (3) is used to sequentially hoist a plurality of segmental steel main beams (4) along the longitudinal direction of the bridge. When each segmental steel main beam (4) is constructed, the fully revolving crane (3) is used to first erect a steel main beam support (402), and then assemble a steel main beam component (401) on the steel main beam support (402). The fully revolving crane (3) hoists the first segmental steel main beam (4) on the steel platform (2), and the subsequent plurality of segmental steel main beams (4) are hoisted on the completed steel main beam (4) using the fully revolving crane (3). A fully rotating crane (3) traveling on the completed steel main beam (4) is used to sequentially hoist a plurality of segmental steel box arch ribs (8) in a direction opposite to the construction advancement direction of the steel main beam (4). When constructing each segmental steel box arch rib (8), a steel box arch rib support (9) is first erected, and then a steel box arch rib component (801) is assembled on the steel box arch rib support (9); dismantling the full-rotation crane (3), the steel platform (2) and the steel box arch rib support (9), and dismantling the steel main beam support (402) after completing the installation of the steel box tie arch bridge hanger (10) and the construction of the bridge deck system; The subsequent several segmented steel main beams (4) are all hoisted on the completed steel main beam (4) using the full-rotation crane (3), including: During the construction of the steel main beam (4) on the embankment, the steel main beam support (402) and the steel main beam component (401) are hoisted from the ground to the bridge deck height using the fully rotating crane (3); After the construction of the steel main beam (4) on the embankment is completed, a lifting station (6) is assembled on the steel platform (2), and a longitudinal track along the longitudinal direction of the bridge is assembled on the completed steel main beam (4). Subsequently, the steel main beam brackets (402) and the steel main beam components (401) in several segmented steel main beams (4) are lifted to the bridge deck through the lifting station (6) and transported to the lifting range of the full-rotation crane (3) by a longitudinal trolley (7) running on the longitudinal track; The method of using a fully rotating crane (3) traveling on a completed steel main beam (4) to sequentially hoist a plurality of segmented steel box arch ribs (8) in a direction opposite to the construction advancement direction of the steel main beam (4) includes: The construction of several segments of steel box arch ribs (8) is carried out in sequence until the steel box arch rib closing section (802) is reached; Carrying out construction of the subsequent segment steel box arch rib (8) of the steel box arch rib closing section (802); Assembling the steel box arch rib closing section (802); When the construction of several segmented steel box arch ribs (8) is carried out in sequence to the steel box arch rib closing section (802), the steel box arch rib bracket (9) and the steel box arch rib component (801) are lifted to the bridge deck by the lifting station (6) and transported to the lifting range of the full-rotation crane (3) by the longitudinal moving trolley (7).

2. The construction method of the progressive and regressive assembled steel box tied arch bridge according to claim 1 is characterized by: The steel box arch rib closing section (802) is arranged at the waist of the steel box arch rib (8) close to the steel platform (2) and close to the arch foot section.

3. The construction method of the progressive and regressive assembled steel box tied arch bridge according to claim 2 is characterized by: The construction of the subsequent segment steel box arch rib (8) of the steel box arch rib closing section (802) includes: The lifting station (6) and the longitudinal moving track and longitudinal moving trolley (7) are dismantled, and the full-rotation crane (3) is retreated to the steel platform (2) to carry out the construction of the subsequent steel box arch rib (8) arch foot section of the steel box arch rib closing section (802).

4. The construction method of the progressive and regressive assembled steel box tied arch bridge according to claim 1 is characterized by: The lifting station (6), the longitudinal movement track and the longitudinal movement trolley (7) are all assembled using the full-rotation crane (3).

5. A construction system for a progressive and regressive steel box tied arch bridge, characterized in that: include: A steel platform (2) is provided on the embankment at one end of the steel box tied arch bridge; A fully revolving crane (3) is used for hoisting the steel main beam (4) and the steel box arch rib (8), and the fully revolving crane (3) hoists the steel main beam (4) and the steel box arch rib (8) to be constructed on the steel platform (2) and the completed steel main beam (4); A steel main beam support (402) for temporarily supporting the steel main beam (4); A steel box arch rib support (9) is mounted on the steel main beam (4) to temporarily support the steel box arch rib (8); A lifting station (6) is provided on the steel platform (2) and is used to lift the steel main beam component (401), the steel main beam support (402), the steel box arch rib support (9) and the steel box arch rib component (801) to the bridge deck height; A longitudinal track is provided on the steel platform (2) and the completed steel main beam (4) and is arranged along the longitudinal direction of the bridge; A longitudinal moving trolley (7) is mounted on the longitudinal moving track and is used to transport the steel main beam component (401), the steel main beam bracket (402), the steel box arch rib bracket (9) and the steel box arch rib component (801).

6. The construction system for the progressive and regressive assembled steel box tied arch bridge according to claim 5 is characterized by: The full-rotation crane (3) has a self-propelled function.

Citation Information

Patent Citations

  • Large-span flexible arch skew back joining construction method

    CN102619170A