A drilling device for elevator rail processing
By designing a fully automatic elevator track drilling equipment, using the collaborative work of clamping, conveying, supporting and drilling mechanisms, the problem of low efficiency and low quality of rapid symmetrical drilling processing on elevator tracks has been solved, and high efficiency has been achieved. , Precise drilling processing.
Patent Information
- Application Number
- CN202210987066.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-17
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2042-08-17
AI Technical Summary
The prior art is difficult to achieve rapid symmetrical drilling on elevator tracks, resulting in low drilling efficiency and low product quality.
A fully automatic drilling equipment including a frame, conveying mechanism, clamping mechanism, mounting frame, drilling mechanism and discharging mechanism is designed. Through the clamping and conveying of the clamping mechanism, the limiting and supporting of the supporting mechanism, and the precise adjustment and processing of the drilling mechanism, fully automated drilling processing of the elevator track is realized.
It improves the production efficiency and product quality of the elevator track, realizes rapid and symmetrical drilling processing of the elevator track, and ensures the accuracy and stability of drilling.
Smart Images

Figure CN115383176B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of automated production equipment for elevator guide rails, and in particular to a punching device for elevator rail processing. Background Art
[0002] The elevator rail is an elevator component composed of a steel rail and a connecting plate, which is divided into a car guide rail and a counterweight guide rail. The guide rail plays a guiding role and also bears the impact force of the car and elevator during braking and the impact force of the safety clamp during emergency braking. In order to install the elevator guide rail, holes are set at both ends of the elevator guide rail. The existing hole processing is realized by manual methods, including drilling and chamfering. This method is not only labor-intensive, but also has poor dimensional stability, which affects product quality and is prone to missed processing.
[0003] In the invention patent with the publication number CN110842248A, an automatic drilling machine for elevator guide rails is proposed. In the invention, due to the structural characteristics of the elevator guide rails, it is determined that transporting them through the T-shaped top plane can obtain better stability and is more convenient. When the drill bit collides with the elevator guide rail, it is turned over to provide a flat surface without protruding structures for the processing device to process. During the processing, the clamping device effectively ensures the accuracy of positioning. However, when symmetrically drilling holes on the elevator rail, the position of the processing device needs to be repeatedly adjusted, which reduces the drilling efficiency. In addition, in the process of adjusting the position of the processing device, it is easy to affect the accuracy of drilling, which reduces the product quality of the elevator rail.
[0004] In order to solve the above-mentioned technical problems, the present invention proposes a punching device for elevator rail processing. Summary of the invention
[0005] 1. Technical issues to be resolved
[0006] In view of the shortcomings of the prior art, the present invention provides a punching device for elevator rail processing, which solves the problem that in the process of elevator rail punching processing in the prior art solution, it is impossible to achieve fast and symmetrical punching processing on the elevator rail, which reduces the punching efficiency and also reduces the quality of the elevator rail product.
[0007] (II) Technical solution
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0009] A punching device for elevator rail processing, comprising a frame, a conveying mechanism is arranged inside the frame, a clamping mechanism is arranged above the conveying mechanism, a mounting frame is arranged in the middle of the top of the frame, a punching mechanism is arranged inside the mounting frame, a supporting mechanism is arranged at the bottom of the inner wall of the frame and below the punching mechanism, a discharging frame is arranged on one side of the bottom of the inner wall of the frame, and a discharging mechanism is arranged on the top of the discharging frame;
[0010] The clamping mechanism sends the elevator rail into the interior of the mounting frame through the conveying mechanism, the supporting mechanism supports and limits the elevator rail below the punching mechanism, the punching mechanism performs punching processing on the interior of the elevator rail, the clamping mechanism turns the elevator rail 180° and then continues the punching processing through the punching mechanism, the clamping mechanism sends the elevator rail after the punching processing to the top of the discharging rack through the conveying mechanism, and the discharging mechanism places the elevator rail above the discharging rack and sends it to the next step;
[0011] The clamping mechanism includes a connecting frame, and the bottom of the connecting frame is fixedly connected to the top of the conveying mechanism. A clamping plate is movably arranged on one side of the connecting frame, wherein a clamping groove is opened inside the clamping plate, and limiting plates are arranged on both sides of the inside of the clamping plate, and electromagnets are arranged on both sides of the inside of the clamping plate, and a magnet block is arranged on one side of the two limiting plates.
[0012] Preferably, electric push rods are provided on both sides of the connecting frame, and one end of the driving shafts of the two electric push rods are fixedly connected to the two sides of the front side of the splint respectively.
[0013] Preferably, the supporting mechanism includes a fixed block located at the bottom of the inner wall of the frame, and a first screw is rotatably provided on the front and back of the fixed block, first movable blocks are threadedly connected to both sides of the surface of the first screw, and connecting blocks are provided on the tops of the two first movable blocks, a servo electric cylinder 1 is provided on the tops of the two connecting blocks, and a supporting frame is provided at one end of the driving shaft of the two servo electric cylinders 1, a positioning plate is movably provided on one side of the two supporting frames, and an electric push rod 2 is provided on one side of the two positioning plates, a servo motor 3 is provided on the front and rear sides of one side of the fixed block, and one end of the output shaft of the two servo motors 3 is fixedly connected to one end of the two first screws through a coupling.
[0014] Preferably, the punching mechanism includes two movable frames symmetrically arranged inside the mounting frame, a second screw is rotatably arranged inside the two movable frames, and second movable blocks are threadedly connected to the surfaces of the second screw, a first drilling motor and a second drilling motor are respectively arranged on the tops of the second movable blocks on both sides, and a drill mounting seat is arranged at one end of the output shaft of the first drilling motor and the second drilling motor, a first drill bit and a second drill bit are respectively arranged inside the two drill mounting seats, a servo motor 2 is arranged inside the two movable frames, and one end of the output shaft of the two servo motors 2 is respectively fixedly connected to one end of the two second screws through a coupling.
[0015] Preferably, the unloading mechanism includes an unloading rack, which is located above the discharging rack, and a unloading table is movably provided on the top of the unloading rack, cylinders are provided on both sides of the bottom of the unloading table, and the unloading table is movably connected through two cylinders, and a unloading trough is opened inside the unloading table.
[0016] Preferably, the support mechanism also includes a material receiving bin located at the top of the fixed block, and a collecting frame is movably provided inside the material receiving bin, a material drop opening is provided on one side of the top of the material receiving bin, and the front of the collecting frame extends to the front of the frame.
[0017] Preferably, the support mechanism further comprises two electric push rods three located at the front and back of the frame, and a limiting block is provided at one end of the driving shaft of the two electric push rods three, and limiting grooves are provided inside the two limiting blocks.
[0018] Preferably, the punching mechanism also includes linear motors disposed on both sides of the inner wall of the mounting frame, and a fixed frame is disposed between the two linear motors, the interior of the fixed frame is slidably connected to the two sides of the movable frame, and fixed plates are disposed on both sides of the top of the fixed frame, one side of the two fixed plates is provided with a servo electric cylinder 2, and one end of the driving shaft of the two servo electric cylinders is respectively fixedly connected to the two sides of the top of the movable frame, sliding rods are disposed on both sides of the top of the movable frame, and the top ends of the two sliding rods are respectively slidably connected to the interiors of the two fixed plates.
[0019] The working principle of the punching equipment for elevator rail processing specifically includes the following steps:
[0020] The first step is to put the elevator track into the frame, use two electric push rods to push the clamping plate close to one side of the elevator track, one side of the elevator track slides into the clamping groove inside the clamping plate, and cooperate with the two limit plates inside the clamping plate to complete the clamping of the elevator track;
[0021] Step 2: The conveyor belt conveys the clamping mechanism, and the clamping mechanism drives the elevator rail to slide into the interior of the mounting frame;
[0022] Step 3: The two servo electric cylinders push the two support frames upward until the tops of the two support frames contact the two sides of the bottom of the elevator track. The two servo motors drive the two first screws to rotate, so that the two support frames are close to each other. One side of the two support frames clamps and limits the two sides of the elevator track. The two electric push rods push the two positioning plates to position the two sides of the elevator track respectively. At the same time, the two electric push rods push the two limit blocks to approach the elevator track respectively, and clamp and limit the two sides below the elevator track through the limit grooves inside the two limit blocks.
[0023] Step 4: The linear motor drives the two fixed frames to slide, adjusts the position between the punching mechanism and the elevator track, and then pushes the movable frame downward through the two servo electric cylinders. The servo motor drives the second screw to rotate. During the rotation of the second screw, the positions of the two second movable blocks are adjusted. The second movable blocks are used to control and adjust the position of the punching. After adjusting the relative distance between the two second movable blocks, the first drill bit is used to punch the elevator track, and then the second drill bit is replaced to punch the elevator track.
[0024] Step 5. After the elevator rail is punched, two clamping mechanisms will send the elevator rail in the supporting mechanism to the top of the unloading rack, and two cylinders will be used to push the unloading table upwards. The unloading table will be used to place the punched elevator rail, and finally the unloading table will be sent to the next processing step through the unloading rack to complete the fully automatic punching of the elevator rail.
[0025] (III) Beneficial effects
[0026] The present invention provides a punching device for elevator rail processing, which has the following beneficial effects compared with the prior art:
[0027] In the present invention, the elevator rail is clamped and conveyed by a clamping mechanism, and the conveying process is more stable and simpler. Then, in the process of punching the elevator rail, the plane of the elevator rail is facing upward, which facilitates the punching mechanism to perform accurate punching on the elevator rail. In the process of processing, the elevator rail is fixed and limited by a supporting mechanism. Finally, the elevator rail after the punching process is sent to the inside of the discharge mechanism by the clamping mechanism, completing the fully automated production of feeding, punching and discharging of the elevator rail, and effectively improving the production efficiency and product quality of the elevator rail.
[0028] The present invention provides a support mechanism inside the mounting frame, and uses the support frame in the support mechanism to clamp and limit the elevator rail. The tops of the two support frames are in contact with the two sides of the bottom of the elevator rail, and one side of the two support frames clamps and limits the two sides of the elevator rail. At the same time, the two sides of the T-shaped bottom of the elevator rail are respectively in contact with the tops of the two support frames, and then the two sides of the elevator rail are positioned in cooperation with the two positioning plates to ensure the stability of the elevator rail between the two support frames. The two sides below the elevator rail are clamped and limited by the limiting grooves inside the two limiting blocks, thereby ensuring the stability of the elevator rail during the punching mechanism punching the elevator rail, and improving the accuracy of punching holes on the elevator rail.
[0029] In the present invention, a punching mechanism is arranged inside the mounting frame, and the second screw in the punching mechanism drives the two second movable blocks to adjust the relative distance between them. When performing alignment punching processing on the elevator rail, the two second movable blocks can realize precise control of alignment punching accuracy, effectively improving the punching accuracy on the elevator rail. In addition, different hole types can be processed on the elevator rail by the first drill bit and the second drill bit, effectively improving the punching efficiency of the elevator rail.
[0030] In the present invention, a material receiving bin is arranged below the punching mechanism, and waste chips generated by punching are collected through the material receiving bin. The waste chips enter the interior of the collecting frame from the material dropping opening, and the collection frame is flexibly taken out of the material receiving bin, so that the waste chips can be conveniently collected in a centralized manner, thereby preventing the punching waste chips from polluting the environment around the punching equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 A top view of a punching device structure for elevator rail processing according to the present invention;
[0032] Figure 2 A side view of the internal structure of the mounting frame of the present invention;
[0033] Figure 3 It is a top view of the fixed frame and movable frame structure of the present invention;
[0034] Figure 4 It is a top view of the frame, clamping mechanism and supporting mechanism structure of the present invention;
[0035] Figure 5 A top view of the connecting frame and the clamping plate structure of the present invention;
[0036] Figure 6 It is a side view of the fixed block structure of the present invention;
[0037] Figure 7 It is a side view of the internal structure of the material receiving bin of the present invention;
[0038] Figure 8It is a schematic diagram of the limit block structure of the present invention.
[0039] In the figure, 10, frame; 20, mounting frame; 30, discharging frame; 40, conveyor belt; 101, connecting frame; 102, clamping plate; 103, limit plate; 104, electromagnet; 105, magnet block; 106, electric push rod 1; 201, fixed block; 202, first screw rod; 203, first movable block; 204, connecting block; 205, servo electric cylinder 1; 206, support frame; 207, positioning plate; 208, electric push rod 2; 209, servo motor 3; 210, receiving bin; 211, collection frame; 212, servo motor 3; 213, servo motor 3; 214, servo motor 3; 215, servo motor 3; 216, servo motor 3; 217, servo motor 3; 218, servo motor 3; 219, servo motor 3; 220, servo motor 3; 221, servo motor 3; 222, servo motor 3; 223, servo motor 3; 224, servo motor 3; 225, servo motor 3; 226, servo motor 3; 227, servo motor 3; 228, servo motor 3; 229, servo motor 3; 229, servo motor 3; 221, servo motor 3; 221, servo motor 3; 222, servo motor 3; 223, servo motor 3; 224, servo motor 3; 225, servo motor 3; 226, servo motor 3; 227, servo motor 2. Material drop opening; 213. Electric push rod three; 214. Limit block; 215. Limit groove; 301. Movable frame; 302. Second screw rod; 303. Second movable block; 304. First drilling motor; 305. Second drilling motor; 306. Drill bit mounting seat; 307. First drill bit; 308. Second drill bit; 309. Servo motor two; 310. Linear motor; 311. Fixed frame; 312. Fixed plate; 313. Servo electric cylinder two; 314. Slide bar; 401. Material discharge rack; 402. Material discharge table. DETAILED DESCRIPTION
[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0041] Embodiment 1:
[0042] See also Figure 1-8 As shown, a punching device for elevator rail processing includes a frame 10, a conveying mechanism is arranged inside the frame 10, and a clamping mechanism is arranged above the conveying mechanism, a mounting frame 20 is arranged in the middle of the top of the frame 10, and a punching mechanism is arranged inside the mounting frame 20, a supporting mechanism is arranged at the bottom of the inner wall of the frame 10 and below the punching mechanism, a discharging frame 30 is arranged on one side of the bottom of the inner wall of the frame 10, and a discharging mechanism is arranged on the top of the discharging frame 30;
[0043] The clamping mechanism sends the elevator rail into the interior of the mounting frame 20 through the conveying mechanism, the supporting mechanism supports and limits the elevator rail below the punching mechanism, the punching mechanism punches holes in the interior of the elevator rail, the clamping mechanism turns the elevator rail 180° and continues to punch holes through the punching mechanism, the clamping mechanism sends the punched elevator rail to the top of the discharging rack 30 through the conveying mechanism, the discharging mechanism places the elevator rail above the discharging rack 30 and sends it to the next step;
[0044] Due to the T-shaped structural characteristics of the elevator rail, the elevator rail is clamped and conveyed by a clamping mechanism, and the conveying process is more stable and simpler. Then, in the process of punching the elevator rail, the plane of the elevator rail is facing upward, which makes it convenient for the punching mechanism to perform precise punching on the elevator rail. In the process of processing, the elevator rail is fixed and limited by the supporting mechanism. Finally, the clamping mechanism is used to deliver the elevator rail after the punching process to the inside of the discharge mechanism, completing the fully automated production of feeding, punching and discharging of the elevator rail, effectively improving the production efficiency and product quality of the elevator rail.
[0045] As a preferred embodiment of the above-mentioned embodiment, the conveying mechanism in the present invention includes a conveyor belt 40, wherein driving gears are arranged on both sides of the conveyor belt 40, and the interior of the driving gear is rotated by a driving motor as a driving force, and the conveyor belt 40 is driven to rotate inside the frame 10 by the rotation of the driving gear, and the elevator rail is transported inside the frame 10 by the conveyor belt 40.
[0046] As a preferred embodiment of the above, the clamping mechanism in the present invention includes a connecting frame 101, and the bottom of the connecting frame 101 is fixedly connected to the top of the conveying mechanism, and a clamping plate 102 is movably provided on one side of the connecting frame 101, wherein a clamping groove is opened inside the clamping plate 102, and limiting plates 103 are provided on both sides of the inside of the clamping plate 102, and electromagnets 104 are provided on both sides of the inside of the clamping plate 102, and magnet blocks 105 are provided on one side of the two limiting plates 103. By energizing the electromagnet 104, the magnetism of the electromagnet 104 and the magnet block 105 on one side of the limiting plate 103 are opposite, so that one side of the limiting plate 103 extends out of the inside of the clamping plate 102, and the elevator guide rail is positioned and clamped by the clamping groove and the limiting plate 103 inside the clamping plate 102.
[0047] Electric push rods 106 are provided on both sides of the connecting frame 101, and one end of the driving shaft of the two electric push rods 106 is fixedly connected to the two sides of the front side of the clamping plate 102 respectively. The two electric push rods 106 are used to push the clamping plate 102 close to one side of the elevator track, and one side of the elevator track slides into the clamping groove inside the clamping plate 102, and cooperates with the two limit plates 103 inside the clamping plate 102 to complete the stable clamping of the elevator track, and then the elevator track is stably transported through the conveying mechanism, and the elevator track is punched.
[0048] As a preferred embodiment of the above, the support mechanism in the present invention includes a fixed block 201 located at the bottom of the inner wall of the frame 10, and the front and back sides of the fixed block 201 are rotatably provided with first screws 202, wherein the two sides of the surface of the first screw 202 are provided with external threads with opposite rotation directions, the two sides of the surface of the first screw 202 are threadedly connected with first movable blocks 203, and the tops of the two first movable blocks 203 are provided with connecting blocks 204. During the rotation of the first screw 202, the two first movable blocks 203 move in relative directions or in opposite directions on the surface of the first screw 202, and the tops of the two connecting blocks 204 are provided with servo electric cylinders 205, and one end of the driving shaft of the two servo electric cylinders 205 is provided with a support frame 206. The two servo electric cylinders 205 are used to rotate The two support frames 206 are pushed upward until the tops of the two support frames 206 contact the two sides of the bottom of the elevator track, one side of the two support frames 206 clamps and limits the two sides of the elevator track, and at the same time, the two sides of the T-shaped bottom of the elevator track contact the tops of the two support frames 206 respectively, one side of the two support frames 206 is movably provided with a positioning plate 207, and one side of the two positioning plates 207 is provided with an electric push rod 208, and the two positioning plates 207 are pushed by the two electric push rods 208 to position the two sides of the elevator track to ensure the stability of the elevator track between the two support frames 206, and servo motors 3 209 are provided on the front and rear sides of one side of the fixed block 201, and one end of the output shaft of the two servo motors 3 209 is fixedly connected to one end of the two first screws 202 through a coupling.
[0049] As a preferred embodiment of the above, the punching mechanism of the present invention includes two movable frames 301 symmetrically arranged inside the mounting frame 20, and second screws 302 are rotatably arranged inside the two movable frames 301, wherein the surfaces of the second screws 302 are provided with external threads with opposite rotation directions on both sides, and the surfaces of the second screws 302 are provided with second movable blocks 303 threadedly connected on both sides, and the tops of the second movable blocks 303 on both sides are respectively provided with a first drilling motor 304 and a second drilling motor 305, and one end of the output shaft of the first drilling motor 304 and the second drilling motor 305 is provided with a drill mounting seat 306, and the two drill mounting seats 306 are provided with a plurality of screws. The first drill bit 307 and the second drill bit 308 are respectively arranged inside, and the positions of the two second movable blocks 303 are controlled by the second screw rod 302. The positions of the two second movable blocks 303 are adjusted during the rotation of the second screw rod 302, and the second movable blocks 303 are used to control and adjust the position of the holes. When the elevator rail is punched, the two second movable blocks 303 can realize the precise control of the punching precision, effectively improving the punching precision on the elevator rail. In addition, the first drill bit 307 and the second drill bit 308 can realize different hole processing on the elevator rail, effectively improving the punching efficiency of the elevator rail. The two movable frames 301 are both provided with servo motors 309 inside, and one end of the output shaft of the two servo motors 309 is respectively fixedly connected to one end of the two second screw rods 302 through a coupling, and the two servo motors 309 are used as the driving force of the two second screw rods 302 to make the two second screw rods 302 rotate inside the two movable frames 301.
[0050] As a preferred embodiment of the above-mentioned embodiment, the unloading mechanism in the present invention includes an unloading rack 401, which is located above the unloading rack 30, and a unloading table 402 is movably arranged on the top of the unloading rack 401, cylinders are arranged on both sides of the bottom of the unloading table 402, and the unloading table 402 is movably connected through two cylinders, and a unloading trough is opened inside the unloading table 402, and the unloading table 402 is pushed upward by two cylinders, and the elevator rail after the punching process is placed by the unloading table 402, and finally the unloading table 402 is sent to the next processing step through the unloading rack 30.
[0051] Embodiment 2:
[0052] The support mechanism in the present invention also includes a material receiving bin 210 located at the top of the fixed block 201, and a collecting frame 211 is movably arranged inside the material receiving bin 210, a material drop opening 212 is provided on one side of the top of the material receiving bin 210, and the front of the collecting frame 211 extends to the front of the frame 10, a through hole is provided inside the support frame 206, and a material drop hopper is provided at the bottom of the through hole, and waste chips generated by punching are collected through the material receiving bin 210, and the waste chips enter the interior of the collecting frame 211 from the material drop opening 212, and the collection frame 211 is flexibly taken out of the material receiving bin 210, so that the waste chips can be conveniently collected in a centralized manner.
[0053] Embodiment 3:
[0054] The supporting mechanism in the present invention also includes two electric push rods 3 213 located on the front and back of the frame 10, and one end of the driving shaft of the two electric push rods 3 213 is provided with a limit block 214, and the inside of the two limit blocks 214 is provided with a limit groove 215. After the elevator track is limited and supported by the two support frames 206, the two electric push rods 3 213 are used to push the two limit blocks 214 closer to the elevator track, and the limit grooves 215 inside the two limit blocks 214 are used to clamp and limit the two sides below the elevator track, thereby ensuring the stability of the elevator track during the punching process of the punching mechanism, and improving the accuracy of punching on the elevator track.
[0055] Embodiment 4:
[0056] The punching mechanism in the present invention also includes linear motors 310 disposed on both sides of the inner wall of the mounting frame 20, and a fixed frame 311 is disposed between the two linear motors 310, the interior of the fixed frame 311 is slidably connected to the two sides of the movable frame 301, and fixed plates 312 are disposed on both sides of the top of the fixed frame 311, and servo electric cylinders 313 are disposed on one side of the two fixed plates 312, and one end of the driving shaft of the two servo electric cylinders 313 is respectively fixedly connected to the two sides of the top of the movable frame 301, and the two fixed frames 311 are driven by the linear motor 310 to slide, and the position between the punching mechanism and the elevator track is adjusted, and then the movable frame 301 is pushed downward by the two servo electric cylinders 313, so that the first drill bit 307 and the second drill bit 308 complete the punching process on the surface of the elevator track. Slide bars 314 are provided on both sides of the top of the movable frame 301, and the top ends of the two slide bars 314 are respectively slidably connected to the inside of the two fixed plates 312. The two slide bars 314 are used to improve the stability of the movable frame 301 when descending, thereby improving the punching accuracy of the punching mechanism inside the movable frame 301.
[0057] Embodiment 5:
[0058] See also Figure 1-8As shown, the present invention also discloses the working principle of the punching device for elevator rail processing, which specifically includes the following steps:
[0059] The first step is to put the elevator rail into the frame 10, and use two electric push rods 106 to push the clamping plate 102 close to one side of the elevator rail. One side of the elevator rail slides into the clamping groove inside the clamping plate 102, and cooperates with the two limit plates 103 inside the clamping plate 102 to complete the clamping of the elevator rail;
[0060] Step 2: The conveyor belt 40 conveys the clamping mechanism, and the elevator rail is driven by the clamping mechanism to slide into the interior of the mounting frame 20;
[0061] Step 3: The two servo electric cylinders 1 205 push the two support frames 206 upward until the tops of the two support frames 206 contact the two sides of the bottom of the elevator track. The two servo motors 3 209 drive the two first screws 202 to rotate, so that the two support frames 206 are close to each other. One side of the two support frames 206 clamps and limits the two sides of the elevator track. The two electric push rods 208 push the two positioning plates 207 to position the two sides of the elevator track respectively. At the same time, the two electric push rods 3 213 push the two limit blocks 214 to approach the elevator track respectively, and the limit grooves 215 inside the two limit blocks 214 clamp and limit the two sides below the elevator track.
[0062] Step 4: The linear motor 310 drives the two fixed frames 311 to slide, adjusts the position between the punching mechanism and the elevator track, and then pushes the movable frame 301 downward through the two servo electric cylinders 313. The servo motor 309 drives the second screw 302 to rotate. During the rotation of the second screw 302, the positions of the two second movable blocks 303 are adjusted. The second movable blocks 303 are used to control and adjust the position of the punching. After adjusting the relative distance between the two second movable blocks 303, the first drill bit 307 is used to punch the elevator track, and then the second drill bit 308 is replaced to punch the elevator track.
[0063] Step 5. After the elevator rail is punched, two clamping mechanisms send the elevator rail in the supporting mechanism to the top of the unloading rack 30, and use two cylinders to push the unloading table 402 upward. The unloading table 402 is used to place the elevator rail after the punching process, and finally the unloading table 402 is sent to the next processing step through the unloading rack 30 to complete the fully automatic punching process of the elevator rail.
[0064] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
[0065] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0066] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A punching device for elevator rail processing, characterized in that: The machine comprises a frame (10), a conveying mechanism is arranged inside the frame (10), a clamping mechanism is arranged above the conveying mechanism, a mounting frame (20) is arranged in the middle of the top of the frame (10), a punching mechanism is arranged inside the mounting frame (20), a supporting mechanism is arranged at the bottom of the inner wall of the frame (10) and below the punching mechanism, a discharging frame (30) is arranged on one side of the bottom of the inner wall of the frame (10), and a discharging mechanism is arranged on the top of the discharging frame (30); The clamping mechanism delivers the elevator rail into the interior of the mounting frame (20) through the conveying mechanism, the supporting mechanism supports and limits the elevator rail below the punching mechanism, the punching mechanism performs punching processing on the interior of the elevator rail, the clamping mechanism flips the elevator rail 180 degrees and then continues the punching processing through the punching mechanism, the clamping mechanism delivers the elevator rail after the punching processing to the top of the discharging rack (30) through the conveying mechanism, and the discharging mechanism places the elevator rail above the discharging rack (30) and delivers it to the next step; The clamping mechanism comprises a connecting frame (101), and the bottom of the connecting frame (101) is fixedly connected to the top of the conveying mechanism, a clamping plate (102) is movably provided on one side of the connecting frame (101), wherein a material clamping groove is provided inside the clamping plate (102), and limiting plates (103) are provided on both sides of the clamping plate (102), electromagnets (104) are provided on both sides of the clamping plate (102), and magnet blocks (105) are provided on one side of the two limiting plates (103); Electric push rods (106) are provided on both sides of the interior of the connecting frame (101), and one end of the driving shaft of the two electric push rods (106) is fixedly connected to both sides of the front side of the clamping plate (102) respectively; The support mechanism comprises a fixed block (201) located at the bottom of the inner wall of the frame (10), and the front and back sides of the fixed block (201) are both rotatably provided with a first screw rod (202), both sides of the surface of the first screw rod (202) are threadedly connected with a first movable block (203), and the tops of the two first movable blocks (203) are both provided with a connecting block (204), and the tops of the two connecting blocks (204) are both provided with a servo electric cylinder 1 (205), and the two servo electric cylinders A support frame (206) is provided at one end of a driving shaft (205), a positioning plate (207) is movably provided on one side of the two support frames (206), and an electric push rod 2 (208) is provided on one side of the two positioning plates (207), a servo motor 3 (209) is provided on the front and rear sides of one side of the fixed block (201), and one end of the output shaft of the two servo motors 3 (209) is fixedly connected to one end of the two first screw rods (202) through a coupling respectively; The punching mechanism comprises two movable frames (301) symmetrically arranged inside the mounting frame (20), a second screw rod (302) being rotatably arranged inside the two movable frames (301), and second movable blocks (303) being threadedly connected are arranged on both sides of the surface of the second screw rod (302), a first drilling motor (304) and a second drilling motor (305) are arranged on the top of the second movable blocks (303) on both sides, and a drill bit mounting seat (306) is arranged at one end of the output shaft of the first drilling motor (304) and the second drilling motor (305), a first drill bit (307) and a second drill bit (308) are arranged inside the two drill bit mounting seats (306), and a servo motor (309) is arranged inside the two movable frames (301), and one end of the output shaft of the two servo motors (309) is fixedly connected to one end of the two second screw rods (302) through a coupling; The material discharging mechanism comprises a material discharging rack (401), the material discharging rack (401) is located above the material discharging rack (30), and a material discharging platform (402) is movably arranged on the top of the material discharging rack (401), cylinders are arranged on both sides of the bottom of the material discharging platform (402), and the material discharging platform (402) is movably connected through two cylinders, and a material discharging trough is opened inside the material discharging platform (402); The support mechanism also includes two electric push rods (213) located on the front and back of the frame (10), and one end of the driving shaft of the two electric push rods (213) is provided with a limit block (214), and the inside of the two limit blocks (214) is provided with a limit slot (215); The punching mechanism also includes linear motors (310) disposed on both sides of the inner wall of the mounting frame (20), and a fixed frame (311) is disposed between the two linear motors (310), the interior of the fixed frame (311) is slidably connected to both sides of the movable frame (301), and fixed plates (312) are disposed on both sides of the top of the fixed frame (311), servo electric cylinders (313) are disposed on one side of the two fixed plates (312), and one end of the driving shafts of the two servo electric cylinders (313) are respectively fixedly connected to both sides of the top of the movable frame (301), and sliding rods (314) are disposed on both sides of the top of the movable frame (301), and the top ends of the two sliding rods (314) are respectively slidably connected to the interiors of the two fixed plates (312); The working principle of the punching equipment used for elevator rail processing includes the following steps: The first step is to place the elevator rail into the frame (10), and use two electric push rods (106) to push the clamping plate (102) close to one side of the elevator rail. One side of the elevator rail slides into the clamping groove inside the clamping plate (102), and cooperates with the two limit plates (103) inside the clamping plate (102) to complete the clamping of the elevator rail. Step 2: The conveyor belt (40) conveys the clamping mechanism, and the elevator rail is driven by the clamping mechanism to slide into the interior of the mounting frame (20); Step 3: The two servo electric cylinders 1 (205) push the two support frames (206) upward until the tops of the two support frames (206) contact the two sides of the bottom of the elevator track. The two servo motors 3 (209) drive the two first screws (202) to rotate, so that the two support frames (206) are close to each other. One side of the two support frames (206) clamps and limits the two sides of the elevator track. The two electric push rods 2 (208) respectively push the two positioning plates (207) to position the two sides of the elevator track. At the same time, the two electric push rods 3 (213) respectively push the two limit blocks (214) to approach the elevator track, and clamp and limit the two sides below the elevator track through the limit grooves (215) inside the two limit blocks (214); Step 4: The linear motor (310) drives the two fixed frames (311) to slide, and adjusts the position between the punching mechanism and the elevator track. Then, the movable frame (301) is pushed downward by the two servo electric cylinders (313). The servo motor (309) drives the second screw (302) to rotate. During the rotation of the second screw (302), the positions of the two second movable blocks (303) are adjusted. The second movable blocks (303) are used to control and adjust the position of the punching. After adjusting the relative distance between the two second movable blocks (303), the first drill bit (307) is used to punch the elevator track. Then, the second drill bit (308) is replaced to punch the elevator track. Step 5. After the elevator rail is punched, two clamping mechanisms send the elevator rail in the support mechanism to the top of the discharge rack (30), and use two cylinders to push the discharge table (402) upward. The discharge table (402) is used to place the punched elevator rail, and finally the discharge table (402) is sent to the next processing step through the discharge rack (30), completing the fully automatic punching of the elevator rail.
2. The punching device for elevator rail processing according to claim 1, characterized in that: The support mechanism further comprises a material receiving bin (210) located at the top of the fixed block (201), and a collecting frame (211) is movably provided inside the material receiving bin (210), a material drop opening (212) is provided on one side of the top of the material receiving bin (210), and the front of the collecting frame (211) extends to the front of the frame (10).
Citation Information
Patent Citations
Automatic drilling machine for elevator guide rails
CN110842248A
Automatic sponge feeding and conveying mechanism
CN105197575A