Wind turbine monitoring method and related equipment
By obtaining predicted meteorological change curves and vibration data change curves, combined with the vibration sensor of the wind turbine, the problem that the vibration monitoring of the wind turbine is limited to two directions is solved, and the comprehensive monitoring and fault detection of the wind turbine status is realized. Improves operational security.
Patent Information
- Application Number
- CN202211159653.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-22
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2042-09-22
AI Technical Summary
The monitoring of the vibration of the entire machine by wind turbines is limited to two directions, and there is a lack of a method to combine meteorological data to control the operating status of the wind turbine.
By obtaining the predicted meteorological change curve and the wind turbine vibration data change curve obtained by the vibration sensor, the working state of the wind turbine is determined, and state adjustment or fault detection is performed when the difference is less than or greater than the preset difference.
The wind turbine status monitoring and fault detection based on meteorological data are realized, and the operation reliability and safety of the wind turbine are improved.
Smart Images

Figure CN115478992B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of wind power generation, and in particular to a wind turbine generator monitoring method and related equipment. Background Art
[0002] With the development of new energy, wind power accounts for an increasing proportion of energy, and the national installed capacity continues to break new records. However, the vibration monitoring of wind turbines is currently limited to monitoring in two directions. There is still a lack of a better method that can combine past meteorological data to control the future operating status of wind turbines. Summary of the invention
[0003] In view of the above problems, the present invention provides a wind turbine monitoring method and related equipment, the main purpose of which is to solve the problem of the lack of a better method for combining meteorological data to control wind turbines.
[0004] In order to solve at least one of the above technical problems, in a first aspect, the present invention provides a wind turbine monitoring method, the method comprising:
[0005] Obtaining a forecasted weather change curve within a first preset time;
[0006] Acquiring a vibration data variation curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time;
[0007] The working state of the target wind turbine is determined based on the predicted meteorological change curve and the vibration data change curve.
[0008] Optionally, the above method further includes:
[0009] Obtain a wind rose diagram of the location of the target wind turbine;
[0010] Determining a target vibration sensor from among a plurality of vibration sensors disposed on the fuselage of the target wind turbine based on the wind rose diagram;
[0011] A vibration data variation curve of the target wind turbine is obtained based on the target vibration sensor.
[0012] Optionally, the determining the working state of the target wind turbine generator based on the predicted meteorological change curve and the vibration data change curve includes:
[0013] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve within the second preset time is less than or equal to the preset difference,
[0014] The operating state of the target wind turbine is determined based on the predicted meteorological change curve within the first preset time.
[0015] Optionally, the above method further includes:
[0016] When the difference between the predicted meteorological change curve within the second preset time and the measured meteorological change curve within the second preset time is less than the preset difference, the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is obtained;
[0017] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than the preset difference, a fault condition of the target wind turbine is detected.
[0018] Optionally, when the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than a preset difference, detecting a fault condition of the target wind turbine generator includes:
[0019] Acquire vibration data variation curves of at least two wind turbines other than the target wind turbine to determine an average vibration data variation curve;
[0020] When the vibration data variation curve of the target wind turbine generator is inconsistent with the average vibration data variation curve of the at least two wind turbine generators, maintenance information is sent to the user.
[0021] Optionally, the above method further includes:
[0022] When the vibration data change curve of the target wind turbine generator is inconsistent with the average vibration data change curve of the at least two wind turbine generators, the vibration data change curves of all wind turbine generators in the wind turbine generator group where the target wind turbine generator is located are obtained to determine the target vibration data change curve;
[0023] The working state of the target wind turbine is determined based on the predicted meteorological change curve and the target vibration data change curve.
[0024] Optionally, the step of obtaining a vibration data change curve through a vibration sensor includes:
[0025] The vibration data change curve in three-dimensional direction is obtained through the vibration sensor.
[0026] In a second aspect, an embodiment of the present invention further provides a wind turbine monitoring device, comprising:
[0027] A first acquisition unit, used to acquire a predicted meteorological change curve within a first preset time;
[0028] A second acquisition unit, configured to acquire a vibration data variation curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time;
[0029] A determination unit is used to determine the working state of the target wind turbine based on the above-mentioned predicted meteorological change curve and the above-mentioned vibration data change curve.
[0030] To achieve the above objective, according to a third aspect of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium includes a stored program, wherein when the program is executed by a processor, the steps of the above wind turbine monitoring method are implemented.
[0031] In order to achieve the above-mentioned purpose, according to the fourth aspect of the present invention, there is provided an electronic device, comprising at least one processor and at least one memory connected to the above-mentioned processor; wherein the above-mentioned processor is used to call the program instructions in the above-mentioned memory to execute the steps of the above-mentioned wind turbine monitoring method.
[0032] By means of the above technical scheme, the wind turbine monitoring method and related equipment provided by the present invention solve the problem that there is currently a lack of a better method for combining meteorological data to control wind turbines. The present invention obtains a predicted meteorological change curve within a first preset time; obtains a vibration data change curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time to determine the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve. In the above scheme, since the present invention first obtains meteorological change data (predicted) for a period of time, and then obtains vibration data (measured) of the wind turbine for a period of time, the actual meteorological changes can be indirectly determined based on the measured vibration data of the wind turbine, and compared with the predicted meteorological change curve to evaluate the credibility of the predicted meteorological change curve, thereby determining whether to adjust the working state of the wind turbine based on the preset meteorological change curve in the future.
[0033] Correspondingly, the wind turbine monitoring device, equipment and computer-readable storage medium provided by the embodiments of the present invention also have the above-mentioned technical effects.
[0034] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented according to the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are listed below. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:
[0036] Figure 1 A schematic diagram of a flow chart of a wind turbine monitoring method provided by an embodiment of the present invention is shown;
[0037] Figure 2 A schematic block diagram showing the composition of a wind turbine monitoring device provided by an embodiment of the present invention is shown;
[0038] Figure 3 A schematic block diagram of the composition of a wind turbine monitoring electronic device provided by an embodiment of the present invention is shown. DETAILED DESCRIPTION
[0039] The exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present invention and to enable the scope of the present invention to be fully communicated to those skilled in the art.
[0040] In order to solve the problem of the lack of a better method for combining meteorological data to control wind turbines, an embodiment of the present invention provides a wind turbine monitoring method, such as Figure 1 As shown, the method includes:
[0041] S101, obtaining a predicted meteorological change curve within a first preset time;
[0042] Exemplarily, based on the current time period, a weather change curve within a period of time is first obtained, and this curve can be obtained based on predictions from channels such as the Meteorological Bureau.
[0043] S102, obtaining a vibration data variation curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time;
[0044] Exemplarily, the vibration data change curve of the wind turbine over a period of time can be obtained based on the vibration sensor. The vibration data change curve is obtained through actual measurement, and the second preset time for obtaining the vibration data change curve is within the first preset time. For example: based on the current time 9 o'clock, the vibration data change curve of half an hour (9 o'clock-9:30) is measured, and then the predicted meteorological change curve of two hours (9 o'clock-11 o'clock) is obtained.
[0045] S103: Determine the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve.
[0046] Exemplarily, based on the predicted meteorological change curve and the vibration data change curve, it is determined in which working state the wind turbine should be controlled, for example, whether the wind turbine should be shut down or controlled to work normally.
[0047] By means of the above technical scheme, the wind turbine monitoring method provided by the present invention solves the problem that there is currently a lack of a better method for combining meteorological data to control wind turbines. The present invention obtains a predicted meteorological change curve within a first preset time; obtains a vibration data change curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time to determine the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve. In the above scheme, since the present invention first obtains meteorological change data (predicted) for a period of time, and then obtains vibration data (measured) of the wind turbine for a period of time, the actual meteorological changes can be indirectly determined based on the measured vibration data of the wind turbine, and compared with the predicted meteorological change curve to evaluate the credibility of the predicted meteorological change curve, thereby determining whether to adjust the working state of the wind turbine based on the preset meteorological change curve in the future.
[0048] In one embodiment, the method further includes:
[0049] Obtain a wind rose diagram of the location of the target wind turbine;
[0050] Determining a target vibration sensor from among a plurality of vibration sensors disposed on the fuselage of the target wind turbine based on the wind rose diagram;
[0051] A vibration data variation curve of the target wind turbine is obtained based on the target vibration sensor.
[0052] For example, a wind rose diagram is also called a wind frequency rose diagram, which can be drawn according to the percentage values of various wind directions in a certain area based on the average statistics over many years and at a certain ratio, or it can be drawn based on predicted meteorological data.
[0053] Exemplarily, this method sets up multiple vibration sensors on the fuselage of the wind turbine, and determines the wind force, wind direction and other data at the location of the target wind turbine by obtaining the wind rose diagram of the location of the target wind turbine. Based on this data, it is determined which part of the target wind turbine fuselage vibration sensor should be turned on to ensure the accuracy of the data obtained by the vibration sensor.
[0054] In one embodiment, the determining the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve includes:
[0055] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve within the second preset time is less than or equal to the preset difference,
[0056] The operating state of the target wind turbine is determined based on the predicted meteorological change curve within the first preset time.
[0057] Exemplarily, if the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve within the second preset time is less than or equal to the preset difference, it is proved that the above-mentioned predicted meteorological change curve is credible, and the subsequent working state of the target wind turbine generator can be determined based on the predicted meteorological change curve within the first preset time. For example: based on the current time 9 o'clock, the vibration data change curve of half an hour (9 o'clock-9:30) is measured, and then the predicted meteorological change curve of two hours (9 o'clock-11 o'clock) is obtained. The meteorological change data reflected by the predicted meteorological change data from 9 o'clock to 9:30 is that the wind force is relatively strong, and the meteorological change data reflected by the vibration data change curve is also relatively strong. The data difference between the two is less than or equal to the preset difference, which proves that the meteorological change data reflected by the predicted meteorological change curve is credible. After verification by the vibration data change curve, the subsequent working state of the target wind turbine generator can continue to be determined based on the predicted meteorological change curve within the first preset time (9 o'clock-11 o'clock).
[0058] In one embodiment, the method further includes:
[0059] When the difference between the predicted meteorological change curve within the second preset time and the measured meteorological change curve within the second preset time is less than the preset difference, the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is obtained;
[0060] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than the preset difference, a fault condition of the target wind turbine is detected.
[0061] Exemplarily, if the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than the preset difference, is there still a fault in the target wind turbine for measuring the vibration data change curve? Therefore, the present scheme will also detect the fault condition of the above-mentioned target wind turbine (including the target vibration sensor of the target wind turbine) in this case. For example: based on the current time 9 o'clock, the vibration data change curve of half an hour (9 o'clock-9:30) is measured, and then the predicted meteorological change curve of two hours (9 o'clock-11 o'clock) is obtained. The predicted meteorological change data from 9 o'clock to 9:30 is The meteorological change data reflected is that the wind force is relatively strong, and the meteorological change data reflected by the vibration data change curve is also that the wind force is relatively weak. The data difference between the two is greater than the preset difference. At this time, there are two situations: the predicted meteorological change curve is unreliable and the target vibration sensor of the target wind turbine is faulty. In order to prevent the predicted meteorological change curve from being rashly classified as unreliable, this method first detects the fault condition of the target vibration sensor of the target wind turbine to ensure the problem. This method can also be indirectly used to detect the fault condition of the target vibration sensor of the target wind turbine, reducing manual regular inspections. If the target vibration sensor is faulty, it can be determined in time.
[0062] In one embodiment, when the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than a preset difference, detecting a fault condition of the target wind turbine generator includes:
[0063] Acquire vibration data variation curves of at least two wind turbines other than the target wind turbine to determine an average vibration data variation curve;
[0064] When the vibration data variation curve of the target wind turbine generator is inconsistent with the average vibration data variation curve of the at least two wind turbine generators, maintenance information is sent to the user.
[0065] Exemplarily, to ensure the accuracy of the detection results, the method obtains vibration change data of at least two wind turbines other than the above-mentioned target wind turbine, takes the average value to determine the average vibration data change curve, if the average vibration data change curve and the vibration data change curve are inconsistent, it can be determined that the above-mentioned target wind turbine has indeed failed, and thus maintenance information is provided to the user. While preventing the hasty exclusion of the predicted meteorological change data, the target wind turbine is also detected.
[0066] In one embodiment, the method further includes:
[0067] When the vibration data change curve of the target wind turbine generator is inconsistent with the average vibration data change curve of the at least two wind turbine generators, the vibration data change curves of all wind turbine generators in the wind turbine generator group where the target wind turbine generator is located are obtained to determine the target vibration data change curve;
[0068] The working state of the target wind turbine is determined based on the predicted meteorological change curve and the target vibration data change curve.
[0069] Exemplarily, if the vibration data change curve of the target wind turbine is inconsistent with the average vibration data change curve of the at least two wind turbines mentioned above, it may reflect that the vibration curve of the target wind turbine mentioned above is faulty and unreliable. Therefore, in order to ensure the accuracy of the measurement and comparison results, the present method no longer uses the vibration data change curve of the target wind turbine alone, but takes the target vibration data change curve determined by the vibration data change curves of all wind turbines in the generator group where the target wind turbine is located as a benchmark, and compares this data with the predicted meteorological change curve to determine the subsequent control of the working state of the target wind turbine, thereby ensuring the accuracy of the measurement results.
[0070] In one embodiment, the step of obtaining a vibration data change curve through a vibration sensor includes:
[0071] The vibration data change curve in three-dimensional direction is obtained through the vibration sensor.
[0072] For example, wind turbines are designed with cabin vibration sensors to monitor the vibration of the wind turbine cabin and string their signals into the independent control system safety chain to ensure the safe operation of the unit. The main principle is to use the PCH vibration sensor to monitor the instantaneous acceleration of the cabin in the X and Y directions in real time. When the monitored instantaneous acceleration value exceeds the threshold in extreme wind speeds, frequent gusts, or a mechanical failure of the wind turbine itself, the signal is input into the main control system to forcibly disconnect the unit safety chain to ensure the safety of the unit. However, the PCH vibration sensors in the currently operating wind turbines only have X and Y directions. The monitoring of the whole cabin in Z direction is missing. This invention adds a Z direction vibration monitoring program to the PCH and monitors the vibration data in X, Y and Z directions in real time through upgrading and optimizing the main control system. When the wind speed is extreme or the wind direction changes rapidly, when the composite vibration acceleration in X, Y and Z directions is greater than 7m / s2, the unit vibration fault is triggered, which is conducive to timely understanding the operating status of important large components such as the unit tower and blades. At the same time, when the instantaneous acceleration in Z direction monitored by PCH exceeds 4.5m / s2, the wind turbine can also report a fault and shut down, effectively ensuring the safe operation of the unit.
[0073] Furthermore, as a response to the above Figure 1 In order to realize the method shown in the figure, the embodiment of the present invention also provides a wind turbine monitoring device for monitoring the above Figure 1 The device embodiment corresponds to the aforementioned method embodiment. For ease of reading, this device embodiment will not repeat the details of the aforementioned method embodiment one by one, but it should be clear that the device in this embodiment can correspond to all the contents of the aforementioned method embodiment. Figure 2 As shown, the device includes: a first acquisition unit 21, a second acquisition unit 22 and a determination unit 23, wherein
[0074] A first acquisition unit 21 is used to acquire a predicted meteorological change curve within a first preset time;
[0075] A second acquisition unit 22, configured to acquire a vibration data variation curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time;
[0076] The determination unit 23 is used to determine the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve.
[0077] Exemplarily, the above unit is also used for:
[0078] Obtain a wind rose diagram of the location of the target wind turbine;
[0079] Determining a target vibration sensor from among a plurality of vibration sensors disposed on the fuselage of the target wind turbine based on the wind rose diagram;
[0080] A vibration data variation curve of the target wind turbine is obtained based on the target vibration sensor.
[0081] Exemplarily, the above-mentioned determining the working state of the target wind turbine based on the above-mentioned predicted meteorological change curve and the above-mentioned vibration data change curve includes:
[0082] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve within the second preset time is less than or equal to the preset difference,
[0083] The operating state of the target wind turbine is determined based on the predicted meteorological change curve within the first preset time.
[0084] Exemplarily, the above unit is also used for:
[0085] When the difference between the predicted meteorological change curve within the second preset time and the measured meteorological change curve within the second preset time is less than the preset difference, the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is obtained;
[0086] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than the preset difference, a fault condition of the target wind turbine is detected.
[0087] Exemplarily, when the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than a preset difference, detecting a fault condition of the target wind turbine generator includes:
[0088] Acquire vibration data variation curves of at least two wind turbines other than the target wind turbine to determine an average vibration data variation curve;
[0089] When the vibration data variation curve of the target wind turbine generator is inconsistent with the average vibration data variation curve of the at least two wind turbine generators, maintenance information is sent to the user.
[0090] Exemplarily, the above unit is also used for:
[0091] When the vibration data change curve of the target wind turbine generator is inconsistent with the average vibration data change curve of the at least two wind turbine generators, the vibration data change curves of all wind turbine generators in the wind turbine generator group where the target wind turbine generator is located are obtained to determine the target vibration data change curve;
[0092] The working state of the target wind turbine is determined based on the predicted meteorological change curve and the target vibration data change curve.
[0093] Exemplarily, the above-mentioned obtaining the vibration data change curve through the vibration sensor includes:
[0094] The vibration data change curve in three-dimensional direction is obtained through the vibration sensor.
[0095] By means of the above technical scheme, the wind turbine monitoring device provided by the present invention solves the problem that there is currently a lack of a better method for combining meteorological data to control wind turbines. The present invention obtains a predicted meteorological change curve within a first preset time; obtains a vibration data change curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time to determine the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve. In the above scheme, since the present invention first obtains meteorological change data (predicted) for a period of time, and then obtains vibration data (measured) of the wind turbine for a period of time, the actual meteorological changes can be indirectly determined based on the measured vibration data of the wind turbine, and compared with the predicted meteorological change curve to evaluate the credibility of the predicted meteorological change curve, thereby determining whether to adjust the working state of the wind turbine based on the preset meteorological change curve in the future.
[0096] The processor includes a kernel, and the kernel retrieves the corresponding program unit from the memory. One or more kernels can be set, and a wind turbine monitoring method is implemented by adjusting kernel parameters, which can solve the problem of the current lack of a better method for combining meteorological data to control wind turbines.
[0097] An embodiment of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium includes a stored program, and when the program is executed by a processor, the wind turbine monitoring method is implemented.
[0098] An embodiment of the present invention provides a processor, and the processor is used to run a program, wherein the wind turbine monitoring method is executed when the program is run.
[0099] An embodiment of the present invention provides an electronic device, the electronic device comprising at least one processor and at least one memory connected to the processor; wherein the processor is used to call program instructions in the memory to execute the wind turbine monitoring method as described above
[0100] An embodiment of the present invention provides an electronic device 30, such as Figure 3 As shown, the electronic device includes at least one processor 301, and at least one memory 302 and a bus 303 connected to the processor; wherein the processor 301 and the memory 302 communicate with each other through the bus 303; the processor 301 is used to call the program instructions in the memory to execute the above-mentioned wind turbine monitoring method.
[0101] The intelligent electronic devices in this article can be PCs, PADs, mobile phones, etc.
[0102] The present application also provides a computer program product, which, when executed on a process management electronic device, is suitable for executing a program for initializing the following method steps:
[0103] Obtaining a forecasted weather change curve within a first preset time;
[0104] Acquiring a vibration data variation curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time;
[0105] The working state of the target wind turbine is determined based on the predicted meteorological change curve and the vibration data change curve.
[0106] Furthermore, the above method also includes:
[0107] Obtain a wind rose diagram of the location of the target wind turbine;
[0108] Determining a target vibration sensor from among a plurality of vibration sensors disposed on the fuselage of the target wind turbine based on the wind rose diagram;
[0109] A vibration data variation curve of the target wind turbine is obtained based on the target vibration sensor.
[0110] Furthermore, the above-mentioned determination of the working state of the target wind turbine based on the above-mentioned predicted meteorological change curve and the above-mentioned vibration data change curve includes:
[0111] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve within the second preset time is less than or equal to the preset difference,
[0112] The operating state of the target wind turbine is determined based on the predicted meteorological change curve within the first preset time.
[0113] Furthermore, the above method also includes:
[0114] When the difference between the predicted meteorological change curve within the second preset time and the measured meteorological change curve within the second preset time is less than the preset difference, the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is obtained;
[0115] When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than the preset difference, a fault condition of the target wind turbine is detected.
[0116] Further, when the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than a preset difference, detecting a fault condition of the target wind turbine generator includes:
[0117] Acquire vibration data variation curves of at least two wind turbines other than the target wind turbine to determine an average vibration data variation curve;
[0118] When the vibration data variation curve of the target wind turbine generator is inconsistent with the average vibration data variation curve of the at least two wind turbine generators, maintenance information is sent to the user.
[0119] Furthermore, the above method also includes:
[0120] When the vibration data change curve of the target wind turbine generator is inconsistent with the average vibration data change curve of the at least two wind turbine generators, the vibration data change curves of all wind turbine generators in the wind turbine generator group where the target wind turbine generator is located are obtained to determine the target vibration data change curve;
[0121] The working state of the target wind turbine is determined based on the predicted meteorological change curve and the target vibration data change curve.
[0122] Furthermore, the above-mentioned obtaining of the vibration data change curve by the vibration sensor includes:
[0123] The vibration data change curve in three-dimensional direction is obtained through the vibration sensor.
[0124] It should be noted that in the above embodiments, the description of each embodiment has its own emphasis, and for parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0125] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0126] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded computer, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0127] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0128] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process in the computer or other programmable device. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0129] The present application also provides a computer program product, which includes computer software instructions. When the computer software instructions are executed on a processing device, the processing device is caused to execute the following Figure 1This corresponds to the flow of control of the memory in the embodiment.
[0130] The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on the computer, the process or function according to the embodiment of the present application is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable devices. The computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, the computer instructions can be transmitted from a website site, a computer, a server or a data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (digital subscriber line, DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) mode to another website site, computer, server or data center. The computer-readable storage medium can be any available medium that a computer can store or a data storage device such as a server or a data center that includes one or more available media integration. The available medium can be a magnetic medium, (e.g., a floppy disk, a hard disk, a tape), an optical medium (e.g., a DVD), or a semiconductor medium (e.g., a solid state drive (SSD)), etc.
[0131] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0132] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or units, which can be electrical, mechanical or other forms.
[0133] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0134] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0135] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the various embodiments of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (Read-Only Memory, ROM), random access memory (Random Access Memory, RAM), disk or optical disk and other media that can store program codes.
[0136] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some of the technical features therein by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A wind turbine monitoring method, characterized in that: include: Obtaining a forecasted weather change curve within a first preset time; Acquiring a vibration data variation curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time; Determine the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve; The determining the working state of the target wind turbine generator based on the predicted meteorological change curve and the vibration data change curve includes: In the case where the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve within the second preset time is less than or equal to the preset difference, Determining the working state of the target wind turbine based on the predicted meteorological change curve within the first preset time; When the difference between the predicted meteorological change curve within the second preset time and the measured meteorological change curve within the second preset time is less than the preset difference, obtaining the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve; When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than a preset difference, a fault condition of the target wind turbine is detected.
2. The method according to claim 1, characterized in that Also includes: Obtaining a wind rose diagram of the location of the target wind turbine; determining a target vibration sensor from among a plurality of vibration sensors provided on a fuselage of the target wind turbine based on the wind rose diagram; A vibration data variation curve of the target wind turbine is acquired based on the target vibration sensor.
3. The method according to claim 1, characterized in that When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than a preset difference, detecting a fault condition of the target wind turbine generator comprises: Acquiring vibration data variation curves of at least two wind turbines other than the target wind turbine to determine an average vibration data variation curve; When the vibration data variation curve of the target wind turbine generator is inconsistent with the average vibration data variation curve of the at least two wind turbine generators, maintenance information is sent to the user.
4. The method according to claim 3, characterized in that Also includes: When the vibration data change curve of the target wind turbine generator is inconsistent with the average vibration data change curve of the at least two wind turbine generators, obtaining the vibration data change curves of all wind turbine generators in the wind turbine generator group where the target wind turbine generator is located to determine the target vibration data change curve; The operating state of the target wind turbine is determined based on the predicted meteorological change curve and the target vibration data change curve.
5. The method according to claim 1, characterized in that The step of obtaining a vibration data variation curve through a vibration sensor includes: The vibration data change curve in three-dimensional direction is obtained through the vibration sensor.
6. A wind turbine monitoring device, characterized in that: A first acquisition unit, used to acquire a predicted meteorological change curve within a first preset time; A second acquisition unit, configured to acquire a vibration data variation curve of a target wind turbine within a second preset time based on a vibration sensor, wherein the first preset time includes the second preset time; a determination unit, configured to determine the working state of the target wind turbine based on the predicted meteorological change curve and the vibration data change curve; The determining the working state of the target wind turbine generator based on the predicted meteorological change curve and the vibration data change curve includes: In the case where the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve within the second preset time is less than or equal to the preset difference, Determining the working state of the target wind turbine based on the predicted meteorological change curve within the first preset time; When the difference between the predicted meteorological change curve within the second preset time and the measured meteorological change curve within the second preset time is less than the preset difference, obtaining the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve; When the difference between the meteorological change data reflected by the predicted meteorological change curve within the second preset time and the meteorological change data reflected by the vibration data change curve is greater than a preset difference, a fault condition of the target wind turbine is detected.
7. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored program, wherein when the program is executed by a processor, the steps of the wind turbine monitoring method according to any one of claims 1 to 5 are implemented.
8. An electronic device, characterized in that: The electronic device includes at least one processor and at least one memory connected to the processor; wherein the processor is used to call program instructions in the memory to execute the steps of the wind turbine monitoring method according to any one of claims 1 to 5.