A device for tying and positioning steel bars of a horizontal beam on water in a wharf project and a construction method thereof
By designing a water cross beam reinforcement positioning device for dock engineering, the problems of low craftsmanship and high safety hazards in traditional binding processes are solved, and a higher quality and safe reinforcement binding effect is achieved.
Patent Information
- Application Number
- CN202310016378.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-01-06
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2043-01-06
AI Technical Summary
The binding process of water beam reinforcement bars in traditional dock projects has problems such as low craftsmanship, easy axis deviation, uneven control of stirrup spacing, large construction safety risks, and difficulty in transporting and lifting of steel bars.
A docking and positioning device for binding and positioning of steel bars on the water beam of the dock was designed, including a composite plastic plate bottom mold, bottom pad device, bottom steel bar point rod, pin, side steel bar point rod, clamping device and steel bar positioning snap. Through the synergy of these components, all-round positioning and fixing of stirrups can be achieved.
This device improves the construction quality and safety of steel bar binding, reduces construction time and cost, avoids the risks of stirrup inclination and steel bar deformation, and ensures the overall force of the beam.
Smart Images

Figure CN116025170B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of wharf engineering construction, and more specifically, to a wharf engineering overwater crossbeam reinforcement binding and positioning device and a construction method thereof. Background Art
[0002] In the traditional dock project, due to the limitation of the on-site construction platform, the steel bar binding of the water beam is usually done by manually drawing the steel bar position on the bottom mold with a stone pencil, laying the bottom concrete protective layer pad, and placing and installing the stirrups and main bars. This is time-consuming and labor-intensive, and the work efficiency is very low. In addition, the overall axis is prone to deviation, resulting in uneven control of the spacing of the stirrups. Especially when the spacing of the stirrups is dense, it is easy to cause bubbles, honeycombs, holes, etc. on the surface of the beam concrete. In severe cases, it affects the uneven force of the beam as a whole, causing quality accidents. At the same time, the overall tilt of the steel bar is prone to occur during the binding process, requiring secondary manual and crane adjustments, which not only increases the cost expenditure but also increases the probability of safety accidents such as injuries to operators and machinery and facilities. In addition, since the amount of steel bars used in the dock beam is large and it is independent of the water and presents an island shape, if the steel bars are hoisted on water after being tied on land, large-scale ship machinery and equipment are required to cooperate. During the construction process, if the operation and command are improper, there is a risk of collision, resulting in overall deformation of the steel bars, and the quality of the project and construction safety are difficult to guarantee.
[0003] In order to solve the adverse effects of traditional binding technology, patent CN215033214U discloses a prefabricated crossbeam reinforcement binding support device, including at least two support frames arranged at intervals in front and back; each support frame includes: at least two brackets, the two brackets are arranged symmetrically on the left and right, and the lower ends of the two brackets are connected by a cross bar; and at least two groups of main beam reinforcement positioning rod groups, the two groups of main beam reinforcement positioning rod groups are spaced apart from each other and are installed between the upper ends of the two brackets in a detachable manner, each group of the main beam reinforcement positioning rod group includes at least one first positioning rod, and the first positioning rod is provided with at least two spaced reinforcement positioning grooves along its axial direction, wherein each first positioning rod can slide up and down along the two brackets and be fixed by a fixing device. Although the support frame in this device can adjust the distance between the two positioning rods according to actual needs, thereby adjusting the distance between the main beam reinforcements, it has a wide range of applications and strong practicality; but the device is also unable to perform equal spacing positioning control on the stirrups, and bubbles and honeycombs are likely to appear on the surface of the cross beam concrete due to the dense spacing of the stirrups, which affects the overall uneven force of the cross beam. In addition, after completing the binding of all the crossbeam steel bars, the device needs to be moved with the help of other equipment, which may easily cause collision accidents and cause deformation of the steel bars, and the quality of the steel bars and construction safety cannot be guaranteed.
[0004] Therefore, how to design a device with simple structure, easy installation and convenient transportation, which can not only effectively assist in the binding of the steel bars of the water beam of the dock project, but also effectively improve the safety of on-site water operations while improving the qualified rate and construction efficiency of the steel bar binding construction quality, has become a technical problem that needs to be urgently solved by technical personnel in this field. Summary of the invention
[0005] In order to solve the problems of poor quality, high safety risk and high cost of steel bar binding of water beams caused by various unfavorable factors existing in traditional binding processes and existing technologies, this application provides the following technical solutions:
[0006] A device for tying and positioning steel bars of a horizontal beam on water in a wharf project, comprising a composite plastic plate bottom mold, a bottom support, a bottom steel bar point rod, a latch, a side steel bar point rod, a clamping device and a steel bar positioning buckle;
[0007] A plurality of bottom supports are placed on the composite plastic board bottom mold at equal intervals; the bottom steel bar point rods are placed on the bottom supports and fixedly connected to the composite plastic board bottom mold by latches; the side steel bar point rods are arranged at both ends of the bottom steel bar point rods and fixedly connected by a plurality of screws; the clamping device is arranged on the side steel bar point rods; the bottom steel bar point rods are used to locate the bottom transverse beam stirrups; the clamping device is used to locate the vertical beam stirrups; the top transverse beam stirrups are connected by steel bar positioning buckles.
[0008] The bottom support is formed by welding a steel pipe and an iron plate.
[0009] A plurality of I-beams are arranged at equal intervals under the composite plastic plate bottom mold.
[0010] The placement positions of the multiple bottom supporters on the composite plastic plate bottom mold are consistent with the placement positions of the multiple I-beams under the composite plastic plate bottom mold.
[0011] The bottom layer of steel bar point rods is composed of multiple sections of square steel connected by multiple screws, and multiple positioning screws are anchored in the square steel.
[0012] The spacing between the positioning screws is determined according to the diameter of the crossbeam stirrups.
[0013] The latch is formed by welding a round steel bar and a nut.
[0014] The clamping devices are provided in plurality and are respectively arranged at the middle and upper parts of the side steel bar point rods.
[0015] The clamping device comprises a left nut, a screw rod, a right nut and a steel bar holder. The left nut and the right nut are both sleeved on the screw rod, and the steel bar holder is arranged at one end of the screw rod.
[0016] A construction method for a dock engineering overwater beam reinforcement binding and positioning device comprises the following steps:
[0017] S1: After the piles are sunk to form the beam support system, the I-beam frame is installed, the composite plastic board bottom formwork is laid, and the bottom support pads are placed;
[0018] S2: Install the bottom reinforcement point rods and side reinforcement point rods, and install the latches;
[0019] S3: while installing the clamping device, simultaneously install the first crossbeam stirrups from both ends of the crossbeam, and adjust the position of the clamping device so that it clamps the first crossbeam stirrups;
[0020] S4: Install the second cross beam stirrups synchronously with the first cross beam stirrups as the reference, and install the top steel bar positioning buckle;
[0021] S5: Repeat S4 to install all the beam stirrups;
[0022] S6: Install the main reinforcement of the beam;
[0023] S7: Install the bottom and outer protective layer pads of the beam reinforcement, and release the clamping device and the top reinforcement positioning buckle;
[0024] S8: Remove the pins, bottom support pads, side reinforcement point rods, and bottom reinforcement point rods in sequence, and the crossbeam reinforcement binding construction is completed.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] 1. The present invention provides a dock engineering water beam reinforcement binding and positioning device with simple structural composition and connection relationship between components, which can make the water beam reinforcement binding construction more convenient and quick, and effectively shorten the construction time.
[0027] 2. The present invention provides a device for binding and positioning reinforcement of a water crossbeam of a dock project. By providing positioning components such as positioning screws, clamping devices and top reinforcement positioning buckles, the stirrups of the water crossbeam can be fixed in all directions up, down, left and right. This can not only avoid safety accidents caused by the inclination of stirrups, effectively reduce safety hazards in the construction process of the water dock, reduce the safety risks brought about in the construction process, but also reduce the secondary inspection and adjustment operations on the spacing between stirrups, effectively avoid idle work of manpower and machinery, and reduce unnecessary cost expenditure.
[0028] 3. The above-water crossbeam reinforcement binding and positioning device for dock engineering provided by the present invention can not only effectively overcome the major problem of construction limitation due to the narrow above-water working platform, but also the components in the device are small in size, easy to transport and install, and can meet the standardized, normalized and refined construction requirements without the need for large machinery and equipment.
[0029] 4. Compared with conventional methods, the construction method of the above-water crossbeam reinforcement binding and positioning device for a wharf project provided by the present invention not only has higher construction efficiency, but also can effectively reduce the cost expenditure of labor and mechanical equipment, thus playing an effect of adding value to the construction of seaport wharf projects and having a strong value for promotion and application.
[0030] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application so that it can be implemented in accordance with the contents of the specification, and to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the following is a detailed description of the preferred embodiments of the present application in conjunction with the accompanying drawings as follows.
[0031] Based on the detailed description of the specific embodiments of the present application in combination with the accompanying drawings below, those skilled in the art will become more aware of the above and other objects, advantages and features of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can also be obtained based on these drawings without creative work. In all drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, each element or part is not necessarily drawn according to the actual scale.
[0033] Figure 1 It is a front view of a device for tying and positioning steel bars of a horizontal beam on water in a wharf project provided by the present invention;
[0034] Figure 2 It is a side view of a device for tying and positioning steel bars of a horizontal beam on water in a wharf project provided by the present invention;
[0035] Figure 3 This is a schematic diagram of the structural composition of a device for tying and positioning steel bars of a horizontal beam on water in a wharf project provided by the present invention;
[0036] Figure 4 It is a top view of a clamping device in a steel bar binding and positioning device for a horizontal beam on water in a wharf project provided by the present invention;
[0037] Figure 5It is a schematic diagram of a steel bar positioning buckle in a steel bar binding and positioning device for a water beam of a wharf project provided by the present invention;
[0038] Among them: 1. I-beam; 2. Composite plastic board bottom mold; 3. Bottom support; 4. Bottom steel bar positioning rod; 4a. Positioning screw; 5. Pin; 6. Side steel bar positioning rod; 7. Clamping device; 7a. Left nut; 7b. Screw; 7c. Right nut; 7d. Steel bar holder; 8. Crossbeam stirrups; 9. Steel bar positioning buckle; 10. Crossbeam main reinforcement. DETAILED DESCRIPTION
[0039] To make the purpose, technical scheme and advantages of the embodiment of the present application clearer, the technical scheme in the embodiment of the present application will be clearly and completely described below in conjunction with the accompanying drawings in the embodiment of the present application. Obviously, the described embodiment is a part of the embodiment of the present application, rather than all of the embodiments. In the following description, specific details such as specific configuration and components are provided only to help fully understand the embodiments of the present application. Therefore, it should be clear to those skilled in the art that various changes and modifications can be made to the embodiments described herein without departing from the scope and spirit of the present application. In addition, for clarity and brevity, the description of known functions and structures is omitted in the embodiment.
[0040] The term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can mean: A exists alone, B exists alone, and A and B exist at the same time. The term " / and" in this article describes another type of association object relationship, indicating that there can be two relationships. For example, A / and B can mean: A exists alone, and A and B exist alone. In addition, the character " / " in this article generally indicates that the previous and next associated objects are in an "or" relationship.
[0041] It should also be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusions.
[0042] Example 1
[0043] This embodiment provides a structural composition of a device for tying and positioning steel bars of an overwater beam of a dock project.
[0044] Please refer to the attached Figure 1-3 , Figure 1 This is a front view of a device for tying and positioning steel bars for a horizontal beam on water in a wharf project provided by the present invention. Figure 2This is a side view of a device for tying and positioning steel bars for a horizontal beam on water in a wharf project provided by the present invention. Figure 3 The present invention is a schematic diagram of the structural composition of a device for tying and positioning steel bars of a horizontal beam on water in a wharf project.
[0045] A device for tying and positioning steel bars of a horizontal beam on water for a dock project, comprising an I-beam 1, a composite plastic plate bottom mold 2, a bottom support 3, a bottom steel bar point rod 4, a latch 5, a side steel bar point rod 6, a clamping device 7 and a steel bar positioning buckle 9;
[0046] A plurality of I-beams 1 are placed at equal intervals below the composite plastic board bottom mold 2; a plurality of bottom supports 3 are placed at equal intervals above the composite plastic board bottom mold 2; the bottom steel bar point rods 4 are placed on the bottom supports 3, and are fixedly connected to the composite plastic board bottom mold 2 via latches 5; the side steel bar point rods 6 are arranged at both ends of the bottom steel bar point rods 4, and are fixedly connected via a plurality of screws; the clamping device 7 is arranged on the side steel bar point rods 6; the bottom steel bar point rods 4 are used to position and bind the bottom transverse beam stirrups 8; the clamping device 7 is used to position and bind the vertical beam stirrups 8; and the top transverse beam stirrups 8 are connected in pairs via steel bar positioning buckles 9.
[0047] Furthermore, the I-beam 1 has high rigidity, stable pressure bearing capacity, and uniform overall force; and by arranging the I-beam 1 at intervals, the I-beam's own weight can be effectively reduced.
[0048] Furthermore, the composite plastic board bottom mold 2 is easy to cut, has a light weight, is stronger than bamboo plywood, is not easily deformed, and has good water resistance and corrosion resistance.
[0049] Furthermore, the bottom support 3 is formed by welding a steel pipe and an iron plate; the specifications and dimensions of the steel pipe and the iron plate should be calculated based on the upper load during the beam reinforcement binding process.
[0050] Furthermore, the bottom support 3 is located at the lower part of the bottom steel bar point rod 4, and its cross section is consistent with the bottom steel bar point rod 4 in the width direction, and is connected in line and surface, which is easy to install and remove.
[0051] Furthermore, the placement positions of the multiple bottom supports 3 on the composite plastic plate bottom mold 2 are consistent with the placement positions of the multiple I-beams 1 under the composite plastic plate bottom mold 2 to ensure stable load force.
[0052] Furthermore, the bottom steel bar point rod 4 is composed of multiple sections of square steel connected by multiple screws, which is easy to disassemble. The specifications and dimensions of the square steel should be calculated based on the upper load during the crossbeam steel bar binding process.
[0053] Furthermore, a plurality of positioning screws 4 a are anchored on the square steel, and the spacing between the positioning screws 4 a is determined according to the diameter of the crossbeam stirrups 8 .
[0054] Furthermore, the pin 5 is welded by a round steel and a nut; the pin 5 is located at the nodes of the bottom steel bar point rod 4 and the side steel bar point rod 6, and is set at four places in total; the pin 5 passes through the bottom steel bar point rod 4 and the composite plastic board bottom mold 2, and is set close to one side of the I-beam 1.
[0055] Furthermore, the material of the side reinforcement point rod 6 is square steel, and reserved holes are arranged in the middle and upper parts.
[0056] Furthermore, the clamping device 7 is provided in plurality, and is respectively arranged at the middle and upper parts of the side reinforcement point rod 6, so that the clamping of the crossbeam stirrups is made tighter and more stable, and is not easily affected by wind and waves.
[0057] Furthermore, as attached Figure 5 As shown, Figure 5 It is a schematic diagram of a steel bar positioning buckle in a water beam steel bar binding and positioning device for a dock project provided by the present invention. The top steel bar positioning buckle 9 is a flat steel with slots at both ends. The size of the slot is consistent with the diameter of the beam stirrup 8, and is used to clamp the tops of two adjacent beam stirrups 8; the top steel bar positioning buckle 9 can effectively ensure that the spacing between the top transverse beam stirrups 8 is consistent, and plays a stabilizing role.
[0058] Furthermore, the top steel bar positioning buckles 9 are cross-installed between adjacent cross beam stirrups 8, so that the overall stability of the upper portion of the cross beam stirrups 8 can be effectively guaranteed.
[0059] Furthermore, since the above-water crossbeam reinforcement binding and positioning device for a dock project provided in this embodiment is actually used in seaport projects or isolated islands and is susceptible to corrosion from seawater, all components in the device will be subjected to anti-corrosion protection on their surfaces before use (by adopting measures such as painting with anti-corrosion paint) to ensure their own rigidity and strength, and thus ensure the stability of their bearing capacity.
[0060] Example 2
[0061] Based on the above-mentioned embodiment 1, this embodiment provides a structural composition and installation method of a clamping device in a steel bar binding and positioning device for an overwater beam of a wharf project.
[0062] Please refer to the attached Figure 4 , Figure 4 The present invention is a top view of a clamping device in a steel bar binding and positioning device for an overwater crossbeam of a wharf project.
[0063] The clamping device 7 includes a left nut 7a, a screw rod 7b, a right nut 7c and a steel bar holder 7d. The left nut 7a and the right nut 7c are both sleeved on the screw rod 7b, and the steel bar holder 7d is arranged at one end of the screw rod 7b.
[0064] Furthermore, the steel bar holder 7d is welded from left to right in sequence by a nut and a hinge, and a spring is also provided at an appropriate position on the left upper end of the hinge (holes can be drilled there and both ends of the spring can be screwed directly into the holes with a buffer ring, or both ends of the spring can be directly welded to the hinge), so that the steel bar holder 7d has a better clamping force, so as to better clamp the crossbeam stirrups 8.
[0065] Furthermore, the provision of the nut is to facilitate timely replacement of the steel bar holder 7d when the spring is damaged or the elastic force is insufficient due to improper use, which is beneficial to continuous operation of on-site construction.
[0066] Furthermore, the hinge is made of a steel plate with a rough surface to increase friction, thereby better clamping the crossbeam stirrups 8.
[0067] The installation method of the clamping device 7 specifically includes the following steps:
[0068] Step 1: After the side reinforcement point rod 6 is installed, insert the screw 7b into the reserved hole in the middle and upper part;
[0069] Step 2: Install the right nut 7c and the steel bar holder 7d in sequence, and clamp the crossbeam stirrup 8 with the steel bar holder 7d;
[0070] Step 3: Adjust the position of the right nut 7c and install the left nut 7a.
[0071] Furthermore, when adjusting the position of the right nut 7c in the step three, the side steel bar point rod 6 is used as a reference, and compared with the center distance of the first pair of positioning screws 4a on the bottom steel bar point rod 4 (when installing the bottom steel bar point rod 4, its position is determined according to the requirements of the steel bar construction drawing), that is, the center position of the lateral installation of the first row of crossbeam stirrups 8, the right nut 7c is tightened toward the side steel bar point rod 6, and then the left nut 7a is screwed on and tightened, so that the entire clamping device 7 is fixed on the side steel bar point rod 6.
[0072] Example 3
[0073] Based on the above-mentioned Embodiment 1 and Embodiment 2, this embodiment provides a construction method of a device for tying and positioning a steel bar of a horizontal beam on water in a wharf project, which specifically includes the following steps:
[0074] S1: After the piles are sunk to form a beam support system, an I-beam 1 is installed, a composite plastic board bottom formwork 2 is laid, and a bottom support pad 3 is placed;
[0075] S2: Install the bottom steel bar point rod 4 and the side steel bar point rod 6, and install the latch 5;
[0076] S3: while installing the clamping device 7, simultaneously install the first crossbeam stirrup 8 from both ends of the crossbeam, and adjust the position of the clamping device 7 so that it clamps the first crossbeam stirrup 8;
[0077] S4: Using the first crossbeam stirrup 8 as a reference, synchronously install the second crossbeam stirrup 8 and install the top steel bar positioning buckle 9;
[0078] S5: Repeat S4 to install all the beam stirrups 8;
[0079] S6: Install the main reinforcement of the beam 10;
[0080] S7: Install the bottom and outer protective layer pads of the beam reinforcement, and release the clamping device 7 and the top reinforcement positioning buckle 9;
[0081] S8: Remove the pin 5, the bottom support 3, the side reinforcement point rod 6, and the bottom reinforcement point rod 4 in sequence, and the crossbeam reinforcement binding construction is completed.
[0082] Furthermore, when the first crossbeam stirrup 8 is installed in S3, its bottom needs to be installed in the first pair of positioning screws 4a of the bottom steel bar point rod 4, and then the clamping device 7 is used to clamp the vertical crossbeam stirrups 8 on both sides.
[0083] Furthermore, when adjusting the position of the clamping device 7 in S3 so that it clamps the first beam stirrup 8, it is necessary to ensure that the position and horizontality of the first beam stirrup 8 meet the requirements by adjusting the position of the clamping device 7, so as to serve as the installation positioning reference for the subsequent beam stirrups 8.
[0084] Furthermore, when removing the bottom support 3 in S8, the lever principle is used to prop up the beam stirrups 8 with a crowbar to remove the bottom support 3, so that the bound beam reinforcement falls as a whole on the bottom concrete protective layer pad.
[0085] The above are only preferred embodiments of the present application, which do not limit the protection scope of the present application. For those skilled in the art, the present application may have various modifications and changes. Within the spirit and principle of the present application, changes, modifications, replacements, integrations and parameter changes to these embodiments by conventional substitutions or by being able to achieve the same functions without departing from the principles and spirit of the present application all fall within the protection scope of the present application.
Claims
1. A device for tying and positioning steel bars of a horizontal beam on water in a wharf project, characterized in that: It comprises a composite plastic plate bottom mold (2), a bottom support (3), a bottom steel bar positioning rod (4), a latch (5), a side steel bar positioning rod (6), a clamping device (7) and a steel bar positioning buckle (9); A plurality of bottom supporters (3) are placed at equal intervals on the composite plastic board bottom mold (2); the bottom steel bar point rod (4) is placed on the bottom supporter (3) and fixedly connected to the composite plastic board bottom mold (2) via a latch (5); the side steel bar point rod (6) is arranged at both ends of the bottom steel bar point rod (4) and fixedly connected via a plurality of screws; the clamping device (7) is arranged on the side steel bar point rod (6); the bottom steel bar point rod (4) is used to locate the bottom transverse beam stirrup (8); the clamping device (7) is used to locate the vertical beam stirrup (8); and the top transverse beam stirrups (8) are connected to each other via a steel bar positioning buckle (9); The clamping devices (7) are provided in plurality and are respectively arranged at the middle and upper parts of the side steel bar point rods (6); The clamping device (7) comprises a left nut (7a), a screw rod (7b), a right nut (7c) and a steel bar holder (7d), wherein the left nut (7a) and the right nut (7c) are both sleeved on the screw rod (7b), and the steel bar holder (7d) is arranged at one end of the screw rod (7b); The steel bar positioning buckle (9) is a flat steel bar with slots at both ends, the size of the slots being consistent with the diameter of the crossbeam stirrups (8) and being used to clamp the tops of two adjacent crossbeam stirrups (8); The distance between the steel bar positioning buckle (9) and the top transverse beam stirrup (8) is consistent; The steel bar positioning buckles (9) are cross-installed and connected to adjacent crossbeam stirrups (8); The steel bar holder (7d) is welded from left to right in sequence by a nut and a hinge.
2. The device for tying and positioning steel bars of a horizontal beam on water in a wharf project according to claim 1 is characterized in that: The bottom support (3) is formed by welding a steel pipe and an iron plate.
3. A device for tying and positioning steel bars of a horizontal beam on water in a wharf project according to claim 1 or 2, characterized in that: A plurality of I-beams (1) are also arranged at equal intervals under the composite plastic plate bottom mold (2).
4. The device for tying and positioning steel bars of a horizontal beam on water in a wharf project according to claim 3 is characterized in that: The placement positions of the plurality of bottom supporters (3) on the composite plastic plate bottom mold (2) are consistent with the placement positions of the plurality of I-beams (1) under the composite plastic plate bottom mold (2).
5. The device for tying and positioning steel bars of a horizontal beam on water in a wharf project according to claim 4 is characterized in that: The bottom layer of steel bar point rods (4) are composed of multiple sections of square steel connected by multiple screws, and multiple positioning screws (4a) are also anchored in the square steel.
6. The device for tying and positioning steel bars of a horizontal beam on water in a wharf project according to claim 5 is characterized in that: The spacing between the positioning screws (4a) is determined according to the diameter of the crossbeam stirrups (8).
7. A device for tying and positioning steel bars of a horizontal beam on water in a wharf project according to claim 1 or 2, characterized in that: The latch (5) is formed by welding a round steel bar and a nut.
8. A construction method for a dock engineering overwater beam reinforcement binding and positioning device according to any one of claims 1 to 7, characterized in that: The following steps are involved: S1: After the piles are sunk to form a beam support system, the I-beam (1) is erected, the composite plastic board bottom formwork (2) is laid, and the bottom support pad (3) is placed; S2: Install the bottom reinforcement point rod (4) and the side reinforcement point rod (6), and install the latch (5); S3: while installing the clamping device (7), simultaneously installing the first crossbeam stirrup (8) from both ends of the crossbeam, and adjusting the position of the clamping device (7) so that it clamps the first crossbeam stirrup (8); S4: Using the first crossbeam stirrup (8) as a reference, synchronously install the second crossbeam stirrup (8) and install the steel bar positioning buckle (9); S5: Repeat S4 to install all the beam stirrups (8); S6: Install the main reinforcement of the beam (10); S7: Install the bottom and outer protective layer pads of the crossbeam reinforcement, and release the clamping device (7) and the reinforcement positioning buckle (9); S8: Remove the latch (5), the bottom support (3), the side reinforcement point rod (6), and the bottom reinforcement point rod (4) in sequence, and the crossbeam reinforcement binding construction is completed; When the first crossbeam stirrup (8) is installed in S3, its bottom needs to be installed in the first pair of positioning screws (4a) of the bottom steel bar point rod (4), and then the vertical crossbeam stirrups (8) on both sides are clamped by the clamping device (7); When adjusting the position of the clamping device (7) in S3 so that it clamps the first crossbeam stirrup (8), it is necessary to ensure the position and horizontality of the first crossbeam stirrup (8) by adjusting the position of the clamping device (7), so as to serve as a reference for the installation and positioning of subsequent crossbeam stirrups (8); When removing the bottom support (3) in S8, the crossbeam stirrups (8) are propped up with a crowbar to remove the bottom support (3), so that the bound crossbeam reinforcements fall entirely onto the bottom concrete protective layer pad.
Citation Information
Patent Citations
Steel bar binding and positioning device for prefabricated approach bridge box girder of long-piled wharf
CN115070935A
Bent cap steel reinforcement framework shaping and binding rack
CN211113221U
Steel bar length control tool for assembly type composite floor slab
CN215618959U