A hydraulic lifting device

By incorporating a fixed beam, base, hydraulic lifter, and lifting point support plate assembly into the lifting device, the problem of lifting point misalignment was solved, enabling precise alignment and safe lifting of the steel structure frame, and shortening the installation time.

CN116040452BActive Publication Date: 2026-11-17CHINA CONSTR FOURTH ENG DIV CORP LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310088235.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-01-17
Publication Date
2026-11-17
Estimated Expiration
2043-01-17

AI Technical Summary

Technical Problem

The existing lifting point design is rather vague and prone to deviation, which makes it impossible to accurately align and install during the lifting process, prolonging the installation time and increasing safety risks.

Method used

Design a hydraulic lifting device, including a fixed beam, a base, a hydraulic lifter, a traction rope bundle, a box-shaped crossbeam, and a lifting point support plate assembly. The symmetrically arranged lifting point support plate assembly provides lateral constraint to the steel structure frame, ensuring that the lifting points remain fixed during the lifting process. The synchronous hydraulic lifter enables precise alignment and installation.

Benefits of technology

It achieves precise alignment of the lifting points during the lifting process, reduces installation time, improves safety and stability of the lifting points, and avoids the need for re-coordination.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116040452B_ABST
    Figure CN116040452B_ABST
Patent Text Reader

Abstract

This invention discloses a hydraulic lifting device, comprising: a fixed beam pre-embedded in the main body of a building; a set of bases symmetrically welded to both sides of the fixed beam; a hydraulic lifter locked above the bases; and a traction rope bundle installed below the hydraulic lifter. This invention, by setting up a lifting point support plate assembly located on both sides of a steel structure frame, can provide lateral constraint to the steel structure frame, thereby forming lifting point support at the steel structure frame. By synchronously activating the hydraulic lifter, and simultaneously setting up a movable and adjustable support plate, it can be appropriately adjusted according to the size of the steel structure frame, minimizing the distance between the support plate and the steel structure frame, and precisely adjusting the lifting points. This improves the accuracy of the lifting points during the lifting process, allowing for precise alignment and installation after lifting without the need for further coordination, minimizing installation time, and thus improving the safety factor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention is a hydraulic lifting tool, belonging to the field of building construction technology. Background Technology

[0002] With the rapid development of my country's construction industry, lifting equipment has become a standard piece of equipment in the construction of high-rise buildings. Lifting equipment is the equipment used in lifting machinery to lift heavy objects.

[0003] In the design of single-point lifting equipment for the installation of large-span steel structure frames, most lifting equipment uses a single hydraulic hoist in conjunction with a grab clamp or hoist to lift the steel structure frame. However, large-span steel structure frames usually require multiple lifting points to assist in the lifting process. During the lifting process, since large-span steel structure frames are heavy structures, the requirements for their lifting points are high.

[0004] The existing lifting point design is rather vague, basically adopting a range design, which makes it easy for the lifting points to shift. Inaccurate lifting points will cause the installation to be unable to be accurately aligned after shifting during the lifting process. This requires re-coordination of the installation parts to complete the installation, which will further prolong the installation time. Since large-span steel structure frames are heavy structures, the longer the suspension installation time, the higher the test of the safety of the lifting ropes. At the same time, the risk factor is directly proportional to the installation time. Summary of the Invention

[0005] To address the shortcomings of existing technologies, the present invention aims to provide a hydraulic lifting device that solves the problem that the lifting point design of existing lifting devices is relatively vague and basically adopts a range design, which easily leads to lifting point misalignment. Inaccurate lifting points will cause misalignment during the lifting process, making it impossible to accurately align and install. This requires re-coordination of the installation parts to complete the installation, which further prolongs the installation time.

[0006] To achieve the above objectives, the present invention is implemented through the following technical solution: A hydraulic lifting device includes: a fixed beam pre-embedded in the main body of a building; A set of bases symmetrically welded to both sides of the fixed beam; A hydraulic lifter secured above the base; A traction rope bundle installed below the hydraulic lifter; A box-shaped crossbeam is vertically locked below the traction rope bundle; Two sets of symmetrically installed suspension point bracket plate assemblies on the upper surface of the box-shaped crossbeam; Each set of the suspension point support plate assembly consists of two symmetrically arranged support plates. The bottom of the support plate is installed on the box-shaped crossbeam. The two support plates located between different sets above the box-shaped crossbeam form a suspension point bearing part. The suspension point bearing part can be used to stably place the steel structure frame on the prefabricated component.

[0007] As a further improvement, the base is provided with a first through hole running vertically through the middle. The first through hole is located directly below the hydraulic lifter, and the traction rope bundle passes through the middle of the first through hole. The traction rope bundle passes through the box-shaped crossbeam, and the traction rope bundle is fixedly connected to a ground anchor attached to the bottom of the box-shaped crossbeam. Each traction rope bundle is composed of at least one steel strand.

[0008] As a further improvement, the ground anchor includes an upper anchor plate fixed below the box-shaped crossbeam and a lower anchor plate snapped directly below the upper anchor plate. The upper anchor plate has several hooks welded at equal intervals on its side circumference. The hooks are embedded in the bottom of the box-shaped crossbeam. The lower anchor plate has several connecting holes. The traction rope bundle passes through the upper anchor plate, and each steel strand independently passes through one of the connecting holes. The tail end of the steel strand is welded to a connecting rod with external threads. A connecting sleeve with internal threads is sleeved on the outside of the connecting rod. Adjacent connecting sleeves are connected by steel wire ropes. The diameter of the connecting sleeve is 2 / 3 larger than the diameter of the connecting hole.

[0009] As a further improvement, it also includes several locking blocks, which are arranged in a radial circular array on the upper surface of the base with the through hole as the axis. The upper end of each locking block is provided with a locking part, which is embedded in the bottom of the hydraulic lifter.

[0010] As a further improvement, a set of inserts is integrally and symmetrically welded to the left and right side walls of the fixed beam. The inserts are inserted into the base close to one side of the fixed beam. A second through hole is provided in the middle of the insert, which coincides with the first through hole.

[0011] As a further improvement, the support plate is located on both sides of the traction rope bundle, and the bottom of the support plate is welded to the box-shaped crossbeam.

[0012] As a further improvement, the support plate includes a side plate welded to the support plate and positioning pins welded at equal intervals below the support plate. The side plate and positioning pins are embedded and installed above the box-shaped crossbeam. The side plate is provided with a plurality of bolt holes, and bolts pass through the bolt holes on the side plate and are threadedly connected to the box-shaped crossbeam.

[0013] As a further improvement, several vertical stiffening ribs are welded to the side of the box-shaped crossbeam.

[0014] As a further improvement, the side of the support plate near the lifting point bearing part is higher than the side of the support plate away from the lifting point bearing part.

[0015] As a further improvement, the lifting point bearing part also includes a first support plate and a second support plate perpendicularly intersecting the first support plate. The first support plate perpendicularly penetrates the second support plate. Two first support plates parallel to the bracket plate are welded to the upper surface of the box beam. Two second support plates perpendicular to the bracket plate are welded to one side of the bracket plate. The upper surface of the second support plate is higher than the first support plate.

[0016] The beneficial effects of this invention are: This invention utilizes a suspension point support plate assembly located on both sides of a steel structure frame. This assembly provides lateral constraint to the steel structure frame, creating suspension point supports. By simultaneously activating hydraulic lifters, two vertically mounted hydraulic lifters on the base simultaneously raise the traction rope bundles. The two ends of the box-shaped crossbeam are pulled by the traction rope bundles, thereby driving the steel structure frame upwards stably. During this process, the suspension points of the steel structure frame remain fixed due to the constraint of the two sets of suspension point support plate assemblies. This ensures that the suspension points of the steel structure frame rise along a preset path during the lifting process, allowing for precise alignment and installation with the main building upon reaching the preset position.

[0017] In the lifting equipment for installing long-span steel structure frames, multiple support plates at a single lifting point can form a load-bearing space in the middle for placing the steel structure frame, thereby providing positioning constraints for the lifting point of the steel structure frame.

[0018] Meanwhile, the adjustable support plate can be adjusted appropriately according to the size of the steel structure frame, minimizing the distance between the support plate and the steel structure frame, and precisely adjusting the lifting points to improve the accuracy of the lifting points during the lifting process. This allows for precise alignment and installation after lifting, eliminating the need for further coordination, minimizing installation time, and thus improving the safety factor. Attached Figure Description

[0019] To more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present invention and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained from these drawings without creative effort.

[0020] Figure 1 This is a three-dimensional structural diagram of a hydraulic lifting device according to the present invention.

[0021] Figure 2 This is a structural schematic diagram of a suspension point support plate assembly according to the present invention.

[0022] Figure 3 yes Figure 2 Enlarged diagram of point A in the middle.

[0023] Figure 4 yes Figure 3 Enlarged diagram of point B in the middle.

[0024] Figure 5 This is a schematic diagram of the hydraulic lifting device of a hydraulic lifting tool according to the present invention, showing its installation state.

[0025] Figure 6 This is a three-dimensional structural diagram of a base according to the present invention.

[0026] Figure 7 This is a three-dimensional structural diagram of another suspension point bracket plate assembly of the present invention.

[0027] Figure 8 This is a schematic diagram of the structure of a support plate according to the present invention.

[0028] Figure 9 This is a top view of a box-type crossbeam according to the present invention.

[0029] Figure 10 This is a module diagram of a hydraulic lifter according to the present invention. Detailed Implementation

[0030] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention. Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely to represent selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0031] In the description of this invention, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this invention, "a plurality of" means two or more, unless otherwise explicitly specified.

[0032] In the description of this invention, it should be noted that, unless otherwise explicitly specified and limited, the terms "connected" and "linked" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.

[0033] The existing lifting point design of the lifting equipment is rather vague, basically adopting a range design, which easily leads to lifting point misalignment. Inaccurate lifting points, once misaligned during lifting, cannot be accurately aligned for installation, requiring re-coordination of the installation area to complete the installation, further extending the installation time. Therefore, to solve the above technical problems, this invention discloses the following technical solution: Reference Figure 1-10 As shown, a hydraulic lifting device includes: a fixed beam 1 pre-embedded in the main body of a building; a set of bases 2 symmetrically welded to both sides of the fixed beam 1; a hydraulic lifter 3 locked above the base 2; a traction rope bundle 4 installed below the hydraulic lifter 3; a box-shaped crossbeam 5 vertically locked below the traction rope bundle 4; two sets of lifting point support plate assemblies 6 symmetrically installed on the upper surface of the box-shaped crossbeam 5; each set of the lifting point support plate assembly 6 consists of two symmetrically arranged support plates 61, the bottom of which is installed on the box-shaped crossbeam 5, and the two support plates 61 located between different sets above the box-shaped crossbeam 5 form a lifting point bearing part 62, which can be used to stably place the steel structure frame on the prefabricated component.

[0034] In this embodiment, the fixed beam 1 is vertically embedded on the main beam 10 of the building body, and a receiving cavity is provided above the main beam 10 to accommodate excess traction rope bundles 4. Two hydraulic lifters 3 are set in each lifting point, and the hydraulic lifters 3 of all lifting points are electrically connected to the same controller a.

[0035] In use, the steel structure frame at one suspension point of the large-span steel structure frame is placed in the suspension point bearing part 62 in the middle of the box beam 5, with two sets of suspension point support plate assemblies 6 located on both sides of the steel structure frame, simultaneously constraining the steel structure frame to form a suspension point support at the steel structure frame. By synchronously activating the hydraulic lifters 3, the two hydraulic lifters 3 vertically installed on the base 2 simultaneously retract the traction rope bundles 4 upwards. The two ends of the box beam 5 are pulled by the traction rope bundles 4, thereby driving the steel structure frame to rise stably upwards. During this process, due to the constraint of the two sets of suspension point support plate assemblies 6, the suspension point of the steel structure frame remains in a fixed state. During the lifting process, it can be ensured that the suspension point of the steel structure frame can rise according to the preset path, so that when it rises to the preset position, it can be immediately and accurately aligned with the main building for installation.

[0036] During the lifting of the steel structure frame, the hydraulic lifter 3 is used to provide the driving force for the lifting point. When fixed, it needs to maintain a highly stable state. At the same time, since the two hydraulic lifters 3 need to maintain a synchronous lifting state, in order to reduce the difficulty of installation and design, the two hydraulic lifters 3 at the same lifting point need to be set in a parallel and symmetrical state. Therefore, a base 2 is set to support the hydraulic lifter 3. The upper surfaces of the two bases 2 are on the same plane, which can make the two hydraulic lifters 3 in a parallel and symmetrical state.

[0037] When the hydraulic lifter 3 is in a parallel and symmetrical state, in order to improve the stability during the lifting process, welding is usually used to weld the bottom of the hydraulic lifter 3 to the base 2. Although this method can play a role in maintaining high stability, the inability to disassemble the hydraulic lifter 3 makes subsequent maintenance extremely inconvenient. Therefore, in this embodiment, bolts are used to connect the hydraulic lifter 3 to the base 2, and an outer cover 31 is fitted over the hydraulic lifter 3 to provide an additional layer of protection.

[0038] Furthermore, several locking blocks 9 are arranged in a radial circular array on the upper surface of the base 2 with the through hole 21 as the axis. Each locking block 9 has a locking part 91 at its upper end, which is embedded in the bottom of the hydraulic lifter 3. The locking block 9 has an L-shaped structure; one end is welded to the base 2, and the vertical extension of the other end is the locking part 91. The locking part 91 is inserted into the outer cover 31 and then embedded in the bottom of the hydraulic lifter 3. The locking blocks 9 can both press and fix the outer cover 31 and position and fix the hydraulic lifter 3, while the outer cover 31 always protects the hydraulic lifter 3. This maintains the high stability of the hydraulic lifter 3, and when disassembly is required, only the locking blocks 9 need to be unwelded.

[0039] In other embodiments, the length of the latching part 91 of the latching block 9 can be shortened so that it is only inserted into the outer cover 31. When disassembly is required, the bolts connecting the upper part of the outer cover 31 to the lower part of the hydraulic lifter 3 and the base 2 can be removed, and the hydraulic lifter 3 can be temporarily disassembled from the upper part of the outer cover 31. This greatly improves flexibility while ensuring the high stability of the hydraulic lifter 3.

[0040] In addition, to strengthen the connection between the fixed beam 1 and the base 2, a set of inserts 11 are integrally and symmetrically welded to the left and right side walls of the fixed beam 1. The inserts 11 are inserted into the base 2 close to the side of the fixed beam 1. The inserts 11 have a second through hole 111 that runs vertically through the middle of the inserts 11. The second through hole 111 coincides with the first through hole 21. By inserting the inserts 11 welded to the fixed beam 1 into the base 2 and then welding the base 2, the stability of the base 2 under load can be further enhanced.

[0041] To ensure that the traction rope bundle 4 can pass smoothly through the base 2 while the hydraulic lifter 3 is fixed, a first through hole 21 is provided in the middle of the base 2, extending vertically. The first through hole 21 is located directly below the hydraulic lifter 3, and the traction rope bundle 4 passes through the middle of the first through hole 21. After the traction rope bundle 4 passes through the box-shaped crossbeam 5, it is fixedly connected to the ground anchor 8 attached to the bottom of the box-shaped crossbeam 5. Each traction rope bundle 4 is composed of at least 16 steel strands 41. In this embodiment, the traction rope bundle 4 uses 16 steel strands 41.

[0042] Improving the stability of the lifting points also requires maintaining a stable connection between the box-shaped crossbeam 5 supporting the steel structure frame and the traction rope bundle 4. In the existing structure, steel strands 41 made of twisted steel wire can be welded and fixed to the ground anchor 8 located below the box-shaped crossbeam 5, or directly passed through the box-shaped crossbeam 5 and welded to its bottom. However, if a steel strand 41 breaks and needs to be replaced, the weld at the broken part needs to be completely disassembled and the remaining weld points cleaned, which takes a lot of time. Therefore, a detachable installation method with the ground anchor 8 is set up, which can ensure the stability of its connection. The ground anchor 8 includes an upper anchor plate 81 fixed below the box-shaped crossbeam 5 and a lower anchor plate 82 snapped directly below the upper anchor plate 81. By separating the upper anchor plate 81, it is bolted to the box-shaped crossbeam 5. Several hooks 83 are welded at equal intervals on the side ring surface of the upper anchor plate 81. The hooks 83 are embedded in the bottom of the box-shaped crossbeam 5, further fixing the upper anchor plate 81 to the bottom of the box-shaped crossbeam 5.

[0043] In addition, to enhance the stability of the box beam 5, several vertical stiffening ribs 51 are welded to the side of the box beam 5. In this embodiment, six vertical stiffening ribs 51 are welded to the long side of the box beam 5, and two vertical stiffening ribs 51 are welded to the short side.

[0044] A lower anchor plate 82 with the same diameter as the upper anchor plate 81 is also provided. The lower anchor plate 82 has several connecting holes 821. The traction rope bundle 4 passes through the upper anchor plate 81, and each steel strand 41 independently passes through a connecting hole 821. The tail end of the steel strand 41 is welded to a connecting rod 42 with external threads. A connecting sleeve 43 with internal threads is sleeved on the outside of the connecting rod 42. The diameter of the connecting sleeve 43 is larger than 2 / 3 of the diameter of the connecting hole 821. The connecting sleeve 43 can be locked into the outside of the connecting hole 821. The outermost ring of the connecting... The connecting rod 42 is relatively long and is connected to the adjacent connecting sleeves 43 by steel wire ropes 44 to form a protective ring. The connecting rod 42 inside the protective ring is shorter. After the connecting sleeves 43 are installed, they are connected by steel wire ropes 44 to form a connecting network inside. This can effectively prevent the connecting sleeves 43 from falling directly when they detach from the steel strands 41 at high altitudes. The connecting network can stably bind the connecting sleeves 43 together without affecting normal operation. The staff can then handle the issue during the next maintenance.

[0045] To stabilize the position of the lifting points, each set of lifting point support plate assemblies 6 above the box-shaped crossbeam 5 consists of two symmetrically arranged support plates 61. The support plates 61 are fixedly mounted on the box-shaped crossbeam 5. In this embodiment, the bottom of the support plates 61 is welded and fixed above the box-shaped crossbeam 5. A fixed lifting point center bearing part 62 is formed in the middle of the four support plates 61. The lifting point bearing part 62 also includes a first support plate 71 and a second support plate 72 perpendicularly intersecting the first support plate 71. The first support plate 71 perpendicularly penetrates the second support plate 72, and the two support plates 61 are parallel to each other. The first support plate 71 is welded to the upper surface of the box beam 5. Two second support plates 72, perpendicular to the support plate 61, are welded to one side of the support plate 61. The upper surface of the second support plate 72 is higher than the first support plate 71, allowing the steel structure frame to be placed above the first support plate 71 and the second support plate 72. This leaves space below and prevents direct contact with the box beam 5, facilitating positioning and installation after lifting when the steel structure frame is short. Furthermore, the support plate 61 provides side protection for the steel structure frame, thereby stabilizing the lifting points of the steel structure frame during the lifting process.

[0046] Meanwhile, the two support plates 61 are located on both sides of the traction rope bundle 4, which can form a protective zone around the traction rope bundle 4, effectively preventing the steel structure frame from directly contacting the traction rope bundle 4 and cutting the traction rope bundle 4.

[0047] To reduce material waste while maintaining the function of the support plate 61, the side of the support plate 61 closest to the lifting point support portion 62 is higher than the side of the support plate 61 furthest from the lifting point support portion 62. In this embodiment, the support plate 61 has a triangular structure with the hypotenuse facing outwards, and the two included angles of the hypotenuse are chamfered to improve the safety factor during use.

[0048] Example 2 This embodiment is basically the same as embodiment 1, except that: the support plate 61 is movably installed on the box beam 5. The support plate 61 includes a side plate 611 welded to the support plate 61 and a positioning pin 612 welded at equal intervals below the support plate 61. The side plate 611 and the positioning pin 612 are embedded and installed above the box beam 5. The side plate 611 is provided with a number of bolt holes. The bolts pass through the bolt holes on the side plate 611 and are threadedly connected to the box beam 5. During adjustment, the bolts on the side plate 611 need to be loosened, allowing the support plate 61 to be lifted. The support plate 61 is then moved laterally to adjust the width of the steel structure frame above the lifting point bearing part 62. The side plate 611 is then embedded into the strip groove 61 on the upper surface of the box beam 5, and the positioning pin 612 is inserted into the matching positioning pin hole 63. The side plate 611 is then connected to the box beam 5 with bolts. Therefore, the support plate 61 can be appropriately adjusted according to the size of the steel structure frame, minimizing the distance between it and the steel structure frame, and allowing for precise adjustment of the lifting point.

[0049] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention can have various modifications and variations. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A hydraulic lifting device, characterized in that, include: (1) Fixed beams embedded in the main body of the building; A set of bases (2) symmetrically welded on both sides of the fixed beam (1); A hydraulic lifter (3) is locked above the base (2); The traction rope bundle (4) is installed below the hydraulic lifter (3); A box-shaped crossbeam (5) is vertically locked below the traction rope bundle (4); Two sets of suspension point bracket plate assemblies (6) are symmetrically installed on the upper surface of the box-shaped crossbeam (5); Each set of the suspension point support plate assembly (6) consists of two symmetrically arranged support plates (61). The bottom of the support plate (61) is installed on the box beam (5). The two support plates (61) located above the box beam (5) between different sets form a suspension point bearing part (62). The suspension point bearing part (62) is used to stably place the steel structure frame on the prefabricated component. The base (2) has a first through hole (21) that runs vertically through the middle. The first through hole (21) is located directly below the hydraulic lifter (3). The traction rope bundle (4) passes through the base (2) through the first through hole (21) and passes through the box beam (5). The traction rope bundle (4) is fixedly connected to the ground anchor (8) attached to the bottom of the box beam (5). Each traction rope bundle (4) is composed of at least 16 steel strands (41). The ground anchor (8) includes an upper anchor plate (81) fixed below the box beam (5) and a lower anchor plate (82) snapped directly below the upper anchor plate (81). The upper anchor plate (81) has several hooks (83) welded at equal intervals on its side ring surface. The hooks (83) are embedded in the bottom of the box beam (5). The lower anchor plate (82) has several connecting holes (821). The traction rope bundle (4) passes through the upper anchor plate (81), and each steel strand (41) passes through a connecting hole (821) independently. The tail end of the steel strand (41) is welded to a connecting rod (42) with external threads. A connecting sleeve (43) with internal threads is sleeved on the outside of the connecting rod (42). Adjacent connecting sleeves (43) are connected by steel wire ropes (44). The diameter of the connecting sleeve (43) is greater than 2 / 3 of the diameter of the connecting hole (821).

2. The hydraulic lifting device according to claim 1, characterized in that, It also includes several locking blocks (9), which are arranged in a radial circular array on the upper surface of the base (2) with the first through hole (21) as the axis. The upper end of the locking block (9) is provided with a locking part (91), which is embedded in the bottom of the hydraulic lifter (3).

3. A hydraulic lifting device according to claim 1, characterized in that, The fixed beam (1) is also integrally and symmetrically welded with a set of inserts (11) on the left and right side walls. The inserts (11) are inserted into the base (2) on one side of the fixed beam (1). The inserts (11) have a second through hole (111) that runs vertically through the middle. The second through hole (111) coincides with the first through hole (21).

4. A hydraulic lifting device according to claim 1, characterized in that, The support plate (61) is located on both sides of the traction rope bundle (4), and the bottom of the support plate (61) is welded to the box beam (5).

5. A hydraulic lifting device according to claim 1, characterized in that, The support plate (61) includes a side plate (611) welded to the support plate (61) and a positioning pin (612) welded at equal intervals below the support plate (61). The side plate (611) and the positioning pin (612) are embedded and installed above the box beam (5). The side plate (611) is provided with a plurality of bolt holes, and the bolts pass through the bolt holes on the side plate (611) and are threadedly connected to the box beam (5).

6. A hydraulic lifting device according to claim 1 or 5, characterized in that, The box-shaped crossbeam (5) has several vertical stiffening ribs (51) welded to its side.

7. A hydraulic lifting device according to claim 1, characterized in that, The side of the support plate (61) near the lifting point bearing part (62) is higher than the side of the support plate (61) away from the lifting point bearing part (62).

8. A hydraulic lifting device according to claim 1, characterized in that, The lifting point bearing part (62) also includes a first support plate (71) and a second support plate (72) perpendicular to the first support plate (71). The first support plate (71) passes vertically through the second support plate (72). The two first support plates (71) parallel to the bracket plate (61) are welded to the upper surface of the box beam (5). The two second support plates (72) perpendicular to the bracket plate (61) are welded to one side of the bracket plate (61). The upper surface of the second support plate (72) is higher than the first support plate (71).

Citation Information

Patent Citations

  • Mounting method for top of large gas holder of steel mill

    CN112374344A

  • Hydraulic lifting and hoisting device for steel-concrete combined section of bridge