A split-layer frame curtain wall system

By designing a disassembled frame curtain wall system and using components such as lifting rings, sliding plates and screws, the problems of poor internal visual effects and structural safety hazards in the construction of existing disassembled curtain walls are solved, and a more efficient and safe construction process is achieved.

CN116290504BActive Publication Date: 2025-05-06CHINA CONSTR EIGHTH BUREAU CONSTR TECH (SHANDONG) CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310250398.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-16
Publication Date
2025-05-06
Estimated Expiration
2043-03-16

AI Technical Summary

Technical Problem

The existing disassembled curtain wall construction methods have problems such as poor internal visual effects and structural safety hazards, and the traditional disassembled columns are complex and time-consuming.

Method used

A disassembled frame curtain wall system is designed, including vertical beams, fixing parts and cross beams. Through structural components such as lifting rings, sliding plates, limiting plates and screws, the movement of the fixing parts on the cross beam and the fixing of the vertical beams is realized.

Benefits of technology

The system improves the interior viewing effect of the split-level curtain wall, enhances the safety of the structure, simplifies the construction process, and reduces installation time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116290504B_ABST
    Figure CN116290504B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of curtain wall, specifically to a staggered frame curtain wall system, comprising: a vertical beam, a lifting ring is arranged at the bottom of the vertical beam; a fixing piece, a sliding plate is arranged at the bottom of the fixing piece, a plug-in rod is arranged at the top of the sliding plate, a limit plate is arranged at the top of the sliding plate, and a plug-in plate is arranged at the end of the limit plate; and a cross beam, which is arranged at the bottom of the fixing piece; the beneficial effect is: the fixing piece proposed by the present invention is provided with a limit plate at the bottom, the limit plate is pressed into the bottom of the fixing piece, the sliding plate is plugged into the plug-in groove, and the limit plate moves at the bottom of the fixing piece under the push of a first spring, the limit plate and the sliding plate are located in the slide groove, so that the fixing piece can move at the top of the cross beam, the vertical beam is plugged into the top of the fixing piece, a screw is used to be plugged into the first screw hole and the second screw hole, the vertical beam is fixed to the top of the fixing piece, the screw pushes the top holding plate, so that the top holding plate moves in the second screw hole, and the triangular block moves in the through groove.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of curtain walls, in particular to a staggered frame curtain wall system. Background Art

[0002] As people's aesthetic requirements for buildings continue to improve, the design of building facades is also constantly pursuing boldness and novelty. Various forms of curtain walls have become the mainstream of building exterior decoration. Horizontal and vertical curtain wall facades have become aesthetically fatigued. As for the current development direction of curtain walls, staggered curtain walls have become a development trend of curtain walls in the future.

[0003] The staggered frame curtain wall system is the safest and most effective way to achieve the shape of the building facade. There are currently two methods for the construction of staggered curtain walls: one is to install vertical decorative strips on the curtain wall beams to simulate structural staggered levels, and the other is to stagger the curtain wall columns;

[0004] Generally, vertical decorative strips are installed on curtain wall beams. The simulated structural staggered approach has a poor internal visual effect, and the curtain wall beams are the secondary keels of the curtain wall, which poses a safety hazard to the curtain wall structure system. The traditional staggered column approach is more complicated and wastes time during installation. Summary of the invention

[0005] The object of the present invention is to provide a staggered frame curtain wall system to solve the problems raised in the above background technology.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a staggered frame curtain wall system, comprising: a vertical beam, a lifting ring is arranged at the bottom of the vertical beam; a fixing member, a sliding plate is arranged at the bottom of the fixing member, a plug-in rod is arranged at the top of the sliding plate, a limit plate is arranged at the top of the sliding plate, and a plug-in plate is arranged at the end of the limit plate; and a horizontal beam, which is arranged at the bottom of the fixing member.

[0007] Preferably, the top and bottom of the beam are provided with limit strips, the top of the limit strip is provided with teeth, the top and bottom of the beam are provided with slide grooves, the bottom and top of the beam are provided with plug-in grooves, the sliding plate is plugged into the plug-in groove, and the sliding plate can slide in the slide groove.

[0008] Preferably, a lifting ring is sleeved on the surface of the vertical beam, and the lifting ring can slide up and down on the surface of the vertical beam. A fixed plate is arranged at the bottom of the lifting ring. There are two groups of fixed plates, and the two groups of fixed plates are symmetrically distributed at the bottom of the lifting ring. A first screw is arranged on the top of the fixed plate, and the bottom of the first screw is supported on the top of the fixed plate.

[0009] Preferably, the interior of the vertical beam is hollow, a first screw hole is provided on the surface of the vertical beam, a screw is screwed into the first screw hole, the plug-in plate is plugged into the bottom of the fixing part, limiting strips are provided at both ends of the limiting plate, the limiting plate can move on the top of the sliding plate, and a limiting hole is provided on the surface of the plug-in plate.

[0010] Preferably, a second screw hole is opened on the surface of the fixing piece, and a plug-in rod is inserted into the bottom of the fixing piece. The plug-in rod can move up and down inside the fixing piece. The diameter of the plug-in rod is consistent with the diameter of the limiting hole. The plug-in rod can be inserted into the limiting hole. A first spring is arranged at the end of the limiting plate, and the other end of the first spring is connected to the surface of the fixing piece.

[0011] Preferably, a second spring is provided at the top of the plug-in rod, the other end of the second spring is connected to the inside of the fixing part, a through groove is provided on the top surface of the plug-in rod, a top holding plate is provided in the second screw hole, the top holding plate can move in the second screw hole, and a triangular block is installed at the end of the top holding plate.

[0012] Preferably, the triangular block is inserted into the through slot, and the bottom of the triangular block is supported on the bottom of the through slot, so that the insertion rod can be moved downward when the triangular block moves.

[0013] Preferably, when the first screw rod supports the fixing plate, the bottom of the fixing plate is supported on the top of the limiting strip, and the teeth on the surface of the fixing plate mesh with the teeth on the top of the limiting strip.

[0014] Preferably, an arc groove is provided at the bottom of the lifting ring, the arc groove at the bottom of the lifting ring is supported on the top of the screw rod screwed in the first screw hole, and there are two groups of arc grooves.

[0015] Preferably, another set of sliding plates is also inserted into the sliding groove at the bottom of the cross beam, and vertical beams can be arranged on the top and bottom of the cross beam.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] The fixing member proposed in the present invention is provided with a limit plate at the bottom of the fixing member, the limit plate is pressed into the bottom of the fixing member, the sliding plate is inserted in the insertion groove, and the limit plate is moved at the bottom of the fixing member under the pushing of the first spring, the limit plate and the sliding plate are located in the sliding groove, so that the fixing member can move at the top of the cross beam, the vertical beam is inserted in the top of the fixing member, and the screw is inserted in the first screw hole and the second screw hole to fix the vertical beam on the top of the fixing member, the screw pushes the top holding plate, so that the top holding plate moves in the second screw hole, the triangular block moves in the through groove, so that the insertion rod descends, the insertion rod is inserted in the limit hole, the position of the limit plate is moved, so that when the sliding plate moves in the slide groove and passes through the insertion groove, due to the limitation of the limit plate, the sliding plate will not fall off from the insertion groove, the first screw is screwed to make the lifting ring descend, the lifting ring holds the surface of the screw in the first screw hole to prevent the screw from loosening, and the fixing plate descends, the fixing plate is held on the top of the limit strip, and the position of the fixing member is fixed. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention;

[0019] Figure 2 It is a schematic diagram of the three-dimensional structure of the crossbeam of the present invention;

[0020] Figure 3 This is a schematic diagram of the three-dimensional structure of the vertical beam of the present invention;

[0021] Figure 4 It is a schematic diagram of the cross-sectional three-dimensional structure of the fixing member of the present invention;

[0022] Figure 5 for Figure 4 A schematic diagram of the enlarged structure in the middle.

[0023] In the figure: vertical beam 1, fixing part 2, horizontal beam 3, slide groove 4, limit strip 5, plug-in groove 6, first screw hole 7, lifting ring 8, first screw rod 9, fixing plate 10, plug-in plate 11, limit hole 12, first spring 13, limit plate 14, sliding plate 15, plug-in rod 16, through groove 17, second spring 18, triangular block 19, top holding plate 20, second screw hole 21. DETAILED DESCRIPTION

[0024] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0025] See also Figures 1 to 5 The present invention provides a technical solution: a staggered frame curtain wall system, comprising: a vertical beam 1, a lifting ring 8 is arranged at the bottom of the vertical beam 1, a lifting ring 8 is sleeved on the surface of the vertical beam 1, the lifting ring 8 can slide up and down on the surface of the vertical beam 1, a fixing plate 10 is arranged at the bottom of the lifting ring 8, the fixing plate 10 has two groups, the two groups of fixing plates 10 are symmetrically distributed at the bottom of the lifting ring 8, a first screw rod 9 is arranged at the top of the fixing plate 10, the bottom of the first screw rod 9 is supported on the top of the fixing plate 10, the interior of the vertical beam 1 is empty, a first screw hole 7 is opened on the surface of the vertical beam 1, a screw is screwed in the first screw hole 7, a plug-in plate 11 is plugged into the bottom of the fixing member 2, limiting strips are arranged at both ends of the limiting plate 14, the limiting plate 14 can move on the top of the sliding plate 15, and a limiting hole 12 is opened on the surface of the plug-in plate 11;

[0026] The fixing member 2 is provided with a sliding plate 15 at the bottom of the fixing member 2, a plug-in rod 16 is provided at the top of the sliding plate 15, a limiting plate 14 is provided at the top of the sliding plate 15, and a plug-in plate 11 is provided at the end of the limiting plate 14. A second screw hole 21 is provided on the surface of the fixing member 2, a plug-in rod 16 is plugged into the bottom of the fixing member 2, and the plug-in rod 16 can move up and down inside the fixing member 2. The diameter of the plug-in rod 16 is consistent with the diameter of the limiting hole 12, and the plug-in rod 16 can be plugged into the limiting hole 12. A first spring 13 is provided at the end of the limiting plate 14, and the other end of the first spring 13 is connected to the surface of the fixing member 2, and a second spring 18 is provided on the top of the plug-in rod 16, and the other end of the second spring 18 is connected to the fixing member 2. Inside, a through groove 17 is provided on the top surface of the plug-in rod 16, and a top holding plate 20 is provided in the second screw hole 21. The top holding plate 20 can move in the second screw hole 21. A triangular block 19 is installed at the end of the top holding plate 20. The triangular block 19 is inserted in the through groove 17, and the bottom of the triangular block 19 is supported on the bottom of the through groove 17. When the triangular block 19 moves, the plug-in rod 16 can be moved downward. When the first screw 9 supports the fixed plate 10, the bottom of the fixed plate 10 is supported on the top of the limit strip 5, and the teeth on the surface of the fixed plate 10 are meshed with the teeth on the top of the limit strip 5. An arc groove is provided at the bottom of the lifting ring 8. The arc groove at the bottom of the lifting ring 8 is supported on the top of the screw screwed in the first screw hole 7, and there are two groups of arc grooves.

[0027] The cross beam 3 is arranged at the bottom of the fixing part 2, and the top and bottom of the cross beam 3 are provided with limit strips 5, and the top of the limit strips 5 is provided with teeth. The top and bottom of the cross beam 3 are provided with slide grooves 4, and the bottom and top of the cross beam 3 are provided with plug-in grooves 6. The sliding plate 15 is plugged into the plug-in groove 6, and the sliding plate 15 can slide in the slide groove 4. Another set of sliding plates 15 is also plugged into the slide groove 4 at the bottom of the cross beam 3. The top and bottom of the cross beam 3 can be provided with vertical beams 1.

[0028] A limit plate 14 is provided at the bottom of the fixing member 2, and the limit plate 14 is pressed into the bottom of the fixing member 2. The sliding plate 15 is inserted into the insertion groove 6. Under the push of the first spring 13, the limit plate 14 moves at the bottom of the fixing member 2. The limit plate 14 and the sliding plate 15 are located in the slide groove 4, so that the fixing member 2 can move at the top of the cross beam 3. The vertical beam 1 is inserted into the top of the fixing member 2, and a screw is inserted into the first screw hole 7 and the second screw hole 21 to fix the vertical beam 1 at the top of the fixing member 2. The screw pushes the top holding plate 20 so that the top holding plate 20 is in the second screw hole 21. The triangle block 19 moves in the through groove 17, so that the plug-in rod 16 descends, and the plug-in rod 16 is inserted in the limiting hole 12, and the position of the limiting plate 14 is moved, so that when the sliding plate 15 moves in the slide groove 4 and passes through the plug-in groove 6, due to the limiting of the limiting plate 14, the sliding plate 15 will not fall off from the plug-in groove 6, and the first screw rod 9 is screwed to make the lifting ring 8 descend, and the lifting ring 8 is supported on the surface of the screw in the first screw hole 7 to prevent the screw from loosening, and the fixing plate 10 is lowered, and the fixing plate 10 is supported on the top of the limiting strip 5 to fix the position of the fixing member 2.

[0029] Although the above describes the illustrative specific implementation methods of the present application so that technicians in this technical field can understand the present application, the present application is not limited to the scope of the specific implementation methods. For ordinary technicians in this technical field, as long as various changes are within the spirit and scope of the present application defined and determined by the attached claims, all application creations using the concept of the present application are protected.

Claims

1. A split-layer frame curtain wall system, characterized in that: The staggered frame curtain wall system comprises: A vertical beam (1), wherein a lifting ring (8) is provided at the bottom of the vertical beam (1); A fixing member (2), a sliding plate (15) is arranged at the bottom of the fixing member (2), a plug-in rod (16) is arranged at the top of the sliding plate (15), a limiting plate (14) is arranged at the top of the sliding plate (15), and a plug-in plate (11) is arranged at the end of the limiting plate (14); and A crossbeam (3) is arranged at the bottom of the fixing member (2); The top and bottom of the crossbeam (3) are provided with limit strips (5), the top of the limit strips (5) are provided with teeth, the top and bottom of the crossbeam (3) are provided with slide grooves (4), the bottom and top of the crossbeam (3) are provided with plug-in grooves (6), the sliding plate (15) is plugged into the plug-in groove (6), and the sliding plate (15) can slide in the slide groove (4); The surface of the vertical beam (1) is sleeved with a lifting ring (8), and the lifting ring (8) can slide up and down on the surface of the vertical beam (1). A fixing plate (10) is provided at the bottom of the lifting ring (8). The fixing plates (10) have two groups, and the two groups of fixing plates (10) are symmetrically distributed at the bottom of the lifting ring (8). A first screw rod (9) is provided at the top of the fixing plate (10), and the bottom of the first screw rod (9) is supported on the top of the fixing plate (10); The interior of the vertical beam (1) is hollow, a first screw hole (7) is provided on the surface of the vertical beam (1), a screw rod is screwed into the first screw hole (7), the plug-in plate (11) is plugged into the bottom of the fixing member (2), limiting strips are provided at both ends of the limiting plate (14), the limiting plate (14) can move on the top of the sliding plate (15), and a limiting hole (12) is provided on the surface of the plug-in plate (11).

2. The staggered frame curtain wall system according to claim 1, characterized in that: A second screw hole (21) is provided on the surface of the fixing member (2), a plug-in rod (16) is plugged into the bottom of the fixing member (2), the plug-in rod (16) can move up and down inside the fixing member (2), the diameter of the plug-in rod (16) is consistent with the diameter of the limiting hole (12), the plug-in rod (16) can be plugged into the limiting hole (12), a first spring (13) is provided at the end of the limiting plate (14), and the other end of the first spring (13) is connected to the surface of the fixing member (2).

3. The staggered frame curtain wall system according to claim 2, characterized in that: A second spring (18) is arranged at the top of the plug-in rod (16), and the other end of the second spring (18) is connected to the inside of the fixing member (2). A through groove (17) is provided on the top surface of the plug-in rod (16), and a top holding plate (20) is arranged in the second screw hole (21). The top holding plate (20) can move in the second screw hole (21), and a triangular block (19) is installed at the end of the top holding plate (20).

4. The staggered frame curtain wall system according to claim 3, characterized in that: The triangular block (19) is inserted into the through groove (17), and the bottom of the triangular block (19) is supported on the bottom of the through groove (17). When the triangular block (19) moves, the insertion rod (16) can be moved downward.

5. The staggered frame curtain wall system according to claim 4, characterized in that: When the first screw rod (9) supports the fixing plate (10), the bottom of the fixing plate (10) is supported on the top of the limiting strip (5), and the teeth on the surface of the fixing plate (10) mesh with the teeth on the top of the limiting strip (5).

6. The staggered frame curtain wall system according to claim 5, characterized in that: The bottom of the lifting ring (8) is provided with an arc groove, the arc groove at the bottom of the lifting ring (8) is supported on the top of the screw rod screwed in the first screw hole (7), and there are two groups of arc grooves.

7. The staggered frame curtain wall system according to claim 6, characterized in that: Another set of sliding plates (15) is also inserted into the sliding groove (4) at the bottom of the cross beam (3), and vertical beams (1) may be provided at the top and bottom of the cross beam (3).

Citation Information

Patent Citations

  • Coating process of aluminum-plastic board

    CN111392468A

  • Curtain unit and curtain that constitutes thereof

    CN205296495U