Environmentally friendly construction method and system for power transmission and transformation equipment

By analyzing the image data of the power transmission and transformation equipment construction site and generating an environmentally friendly construction plan, the problem of neglecting environmental protection in the existing construction methods is solved, and environmentally friendly construction and environmental impact are reduced at the construction site.

CN116503205BActive Publication Date: 2025-03-25HUANGSHI POWER SUPPLY CO +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310596311.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-05-25
Publication Date
2025-03-25
Estimated Expiration
2043-05-25

AI Technical Summary

Technical Problem

The existing construction methods of power transmission and transformation equipment rarely consider environmental protection factors, resulting in poor environmental protection indicators for construction.

Method used

By obtaining image data of the construction site, identifying the construction area and adjacent areas, generating environmentally friendly construction plans for each area, and adjusting the construction plan according to the construction progress data.

Benefits of technology

Environmentally friendly construction at the construction site of power transmission and transformation equipment has been achieved, environmentally friendly indicators of construction have been improved, and the impact on the environment has been reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116503205B_ABST
    Figure CN116503205B_ABST
Patent Text Reader

Abstract

The present invention provides a method and system for environmentally friendly construction of power transmission and transformation equipment. The method comprises: acquiring first image data of a construction site, and determining a first construction plan according to the first image data; acquiring second image data of the construction site, and determining a second construction plan according to the second image data; and implementing environmentally friendly construction of the power transmission and transformation equipment according to the first construction plan and the second construction plan. The solution of the present invention can determine a suitable construction plan by performing image analysis on the construction site, thereby satisfying the environmentally friendly construction of the power transmission and transformation equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric power construction, and in particular to an environmentally friendly construction method, system, electronic equipment and computer storage medium for power transmission and transformation equipment. Background Art

[0002] Power transmission and transformation equipment is an important part of the power system, mainly including power transmission, power transformation, power distribution and various special-purpose electrical equipment. The construction of power transmission and transformation equipment needs to consider the protection of the construction site environment to avoid adverse effects of construction on the local environment. However, the existing construction methods rarely consider the factor of environmental protection, or only rely on the personal experience of construction personnel, resulting in less than ideal environmental protection indicators (mainly related to noise and safety). The technical solution of the present invention is intended to solve this technical problem. Summary of the invention

[0003] In order to at least solve the technical problems existing in the above-mentioned background technology, the present invention provides an environmentally friendly construction method, system, electronic equipment and computer storage medium for power transmission and transformation equipment.

[0004] A first aspect of the present invention provides an environmentally friendly construction method for power transmission and transformation equipment, the method comprising the following steps:

[0005] Acquire first image data of the construction site, and determine a first construction plan according to the first image data;

[0006] Acquire second image data of the construction site, and determine a second construction plan according to the second image data;

[0007] The environmentally friendly construction of the power transmission and transformation equipment is implemented according to the first construction plan and the second construction plan.

[0008] In some embodiments, the first image data and / or the second image data are obtained by capturing images with a camera deployed at a high location at the construction site and / or a camera installed on an unmanned aerial vehicle device.

[0009] In some embodiments, determining a first construction plan according to the first image data includes:

[0010] Identify the power transmission and transformation equipment construction area and several adjacent areas in the first image data, and determine the first shape data of the power transmission and transformation equipment construction area, and the second attribute data and second shape data of each of the adjacent areas;

[0011] An environmental protection plan for the adjacent area is generated according to the first attribute data of the power transmission and transformation equipment, the first shape data and the second attribute data and the second shape data of each of the adjacent areas.

[0012] In some embodiments, the first attribute data includes location attributes and device attributes of the power transmission and transformation equipment;

[0013] Then, generating an environmental protection plan for the adjacent area according to the first attribute data of the power transmission and transformation equipment, the first shape data and the second attribute data and the second shape data of each adjacent area includes:

[0014] Determine a first type of adjacent area according to the location attribute of the power transmission and transformation equipment and the first shape data, and generate a first environmental protection plan for the first type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the first type of adjacent area;

[0015] Determine a second type of adjacent area according to the equipment attribute of the power transmission and transformation equipment and the first shape data, and generate a second environmental protection plan for the second type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the second type of adjacent area;

[0016] The first environmental protection scheme and the second environmental protection scheme are integrated to obtain the environmental protection scheme.

[0017] In some embodiments, the generating a first environmental protection scheme for the first type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the first type of adjacent area, and the generating a second environmental protection scheme for the second type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the second type of adjacent area, include:

[0018] Determine a first influence coefficient of the first type of adjacent area and a second influence coefficient of the second type of adjacent area according to the device attribute;

[0019] generating a first environmental protection plan for the first type of adjacent area according to the first influence coefficient of the first type of adjacent area, the second attribute data of the adjacent area corresponding to the first type of adjacent area, and the second shape data;

[0020] And, a second environmental protection plan for the second type of adjacent area is generated according to the second influence coefficient of the second type of adjacent area, the second attribute data of the adjacent area corresponding to the second type of adjacent area, and the second shape data.

[0021] In some embodiments, determining the second construction plan according to the second image data includes:

[0022] The construction progress data of the power transmission and transformation equipment construction area is obtained based on the second image data, the first construction plan is evaluated based on the construction progress data, and the second construction plan is generated based on the evaluation result.

[0023] In some embodiments, the evaluating the first construction plan according to the construction progress data and generating the second construction plan according to the evaluation result includes: generating the second construction plan according to the construction progress data, and calculating the deviation between the second construction plan and the first construction plan;

[0024] If the deviation is greater than the deviation threshold, the second construction plan is confirmed; otherwise, the first construction plan continues to be confirmed.

[0025] A second aspect of the present invention provides an environmental protection construction system for power transmission and transformation equipment, comprising an acquisition module, a processing module, and a storage module; the processing module is connected to the acquisition module and the storage module;

[0026] The storage module is used to store executable computer program code;

[0027] The acquisition module is used to acquire image data of the construction site and transmit it to the processing module;

[0028] It is characterized in that: the processing module is used to execute the method as described in any of the preceding items by calling the executable computer program code in the storage module.

[0029] The third aspect of the present invention also provides an electronic device, comprising: a memory storing executable program code; a processor coupled to the memory; the processor calls the executable program code stored in the memory to execute the method as described in any of the preceding items.

[0030] A fourth aspect of the present invention provides a computer storage medium having a computer program stored thereon, and the computer program, when executed by a processor, executes the method as described in any of the preceding items.

[0031] The beneficial effects of the present invention are:

[0032] The solution of the present invention can determine a suitable construction plan by performing image analysis on the construction site, thereby meeting the requirements of environmentally friendly construction of power transmission and transformation equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0034] Figure 1 It is a schematic diagram of a flow chart of an environmentally friendly construction method for power transmission and transformation equipment disclosed in an embodiment of the present invention;

[0035] Figure 2 It is a structural schematic diagram of an environmentally friendly construction system for power transmission and transformation equipment disclosed in an embodiment of the present invention. DETAILED DESCRIPTION

[0036] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] The terms used in the embodiments of the present application are only for the purpose of describing specific embodiments, and are not intended to limit the present application. The singular forms "a", "said" and "the" used in the embodiments of the present application and the appended claims are also intended to include plural forms, unless the context clearly indicates other meanings, and "multiple" generally includes at least two.

[0038] It should be understood that the term "and / or" used in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.

[0039] It should be understood that although the terms first, second, third, etc. may be used to describe ... in the embodiments of the present application, these ... should not be limited to these terms. These terms are only used to distinguish .... For example, without departing from the scope of the embodiments of the present application, the first ... may also be referred to as the second ..., and similarly, the second ... may also be referred to as the first ....

[0040] As used herein, the words "if" and "if" may be interpreted as "at the time of" or "when" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrases "if it is determined" or "if (stated condition or event) is detected" may be interpreted as "when it is determined" or "in response to determining" or "when detecting (stated condition or event)" or "in response to detecting (stated condition or event)", depending on the context.

[0041] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a product or system including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such a product or system. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the product or system including the elements.

[0042] The preferred embodiments of the present invention are described in detail below with reference to the accompanying drawings.

[0043] See also Figure 1 As shown, the embodiment of the present invention discloses an environmentally friendly construction method for power transmission and transformation equipment, the method comprising the following steps:

[0044] Acquire first image data of the construction site, and determine a first construction plan according to the first image data;

[0045] Acquire second image data of the construction site, and determine a second construction plan according to the second image data;

[0046] The environmentally friendly construction of the power transmission and transformation equipment is implemented according to the first construction plan and the second construction plan.

[0047] The scheme of the present invention can acquire image data of the construction site, and by analyzing and identifying the captured image data, target analysis data before and during the construction can be determined, thereby determining a suitable construction plan. Therefore, the scheme of the present invention can, on the one hand, realize the requirements for environmental protection construction of power transmission and transformation equipment, and on the other hand, it does not require construction personnel to participate in the determination of specific details of environmental protection construction, which can greatly improve the efficiency of environmental protection construction.

[0048] In some embodiments, the first image data and / or the second image data are obtained by capturing images with a camera deployed at a high location at the construction site and / or a camera installed on an unmanned aerial vehicle device.

[0049] In this embodiment, high-definition cameras are deployed at a certain height at the construction site, for example, on surrounding buildings, frames, mountains, tall trees, etc. High-definition cameras can also be deployed on drones to achieve panoramic coverage of the construction site.

[0050] In some embodiments, determining a first construction plan according to the first image data includes:

[0051] Identify the power transmission and transformation equipment construction area and several adjacent areas in the first image data, and determine the first shape data of the power transmission and transformation equipment construction area, and the second attribute data and second shape data of each of the adjacent areas;

[0052] An environmental protection plan for the adjacent area is generated according to the first attribute data of the power transmission and transformation equipment, the first shape data and the second attribute data and the second shape data of each of the adjacent areas.

[0053] In this embodiment, the construction area of ​​the power transmission and transformation equipment and several adjacent areas adjacent to it can be further identified from the first image data taken. The construction area of ​​the power transmission and transformation equipment can be determined by laying out artificial marks, high-precision geographic coordinate identification, etc.; the adjacent areas are mainly various areas or closed areas located around the construction area, such as communities, ponds, rivers, fields, hillsides, etc. Then, the attributes and shapes of each area can be extracted. The extraction process can be achieved through image recognition, and the attributes and shapes of the construction area can also be obtained through associated data, such as attributes and shapes manually input / pre-stored / located on a designated server. At this point, the environmental protection plan in the adjacent areas of the construction area and the adjacent areas can be determined based on the above data of the construction area and the adjacent areas, so that during the construction process, the environmental protection hazards such as noise, dust, water pollution, structural damage, and gravel impact to each adjacent area can be reduced or eliminated.

[0054] In some embodiments, the first attribute data includes location attributes and device attributes of the power transmission and transformation equipment;

[0055] Then, generating an environmental protection plan for the adjacent area according to the first attribute data of the power transmission and transformation equipment, the first shape data and the second attribute data and the second shape data of each adjacent area includes:

[0056] Determine a first type of adjacent area according to the location attribute of the power transmission and transformation equipment and the first shape data, and generate a first environmental protection plan for the first type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the first type of adjacent area;

[0057] Determine a second type of adjacent area according to the equipment attribute of the power transmission and transformation equipment and the first shape data, and generate a second environmental protection plan for the second type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the second type of adjacent area;

[0058] The first environmental protection scheme and the second environmental protection scheme are integrated to obtain the environmental protection scheme.

[0059] In this embodiment, the first type of adjacent area adjacent to the direct construction area can be determined according to the layout position of the power transmission and transformation equipment itself, and the second type of adjacent area adjacent to the auxiliary construction area can be determined according to the equipment attributes of the power transmission and transformation equipment. Further considering the attributes and shapes of the adjacent areas corresponding to each type of adjacent area, the environmental protection plan of the construction area and the adjacent area can be determined, and the environmental protection plan of each section of the adjacent area can be integrated to obtain the overall environmental protection plan.

[0060] Among them, the equipment attributes of power transmission and transformation equipment mainly include the equipment

[0061] The following are some examples:

[0062] The areas adjacent to / close to the construction area A of the power transmission and transformation equipment are B, C, D, and E, among which area B is a residential area, area C is a river, area D is a hillside, and area E is a road. The layout area F and the storage area G of the power transmission and transformation equipment in the construction area A are determined by the above method, thereby determining that the areas adjacent to the layout area F are B and D, and the areas adjacent to the storage area G are C and E, that is, the adjacent areas of the entire shape and outline of the construction area A are determined. Since each area B, C, D, and E has different tolerance levels to the construction of the power transmission and transformation equipment, the degree of influence of the layout area F and the storage area G on the surrounding areas is also different. Therefore, environmental protection plans of different strengths for each adjacent area are determined based on the tolerance level and the degree of influence. The environmental protection plan mainly includes the material, height, thickness, strength, structure, etc. of the blocking material. For example, the adjacent areas between area F and area D, and area G and area C can only be laid with ordinary mesh fences, while area F and area B need to be laid with enclosure materials with certain mechanical properties and sound insulation and noise reduction properties, and the adjacent areas between area G and area E can use simple brick walls as enclosures.

[0063] In some embodiments, the generating a first environmental protection scheme for the first type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the first type of adjacent area, and the generating a second environmental protection scheme for the second type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the second type of adjacent area, include:

[0064] Determine a first influence coefficient of the first type of adjacent area and a second influence coefficient of the second type of adjacent area according to the device attribute;

[0065] generating a first environmental protection plan for the first type of adjacent area according to the first influence coefficient of the first type of adjacent area, the second attribute data of the adjacent area corresponding to the first type of adjacent area, and the second shape data;

[0066] And, a second environmental protection plan for the second type of adjacent area is generated according to the second influence coefficient of the second type of adjacent area, the second attribute data of the adjacent area corresponding to the second type of adjacent area, and the second shape data.

[0067] In this embodiment, different power transmission and transformation equipment have different heights, floor areas, etc., and also involve different construction procedures, processes, equipment to be used, etc. Based on these parameters, the influence coefficient of the layout area F and the yard area G of the power transmission and transformation equipment on their respective adjacent areas can be determined. The present invention further considers the influence coefficient to generate the aforementioned environmental protection scheme. For example, when the influence coefficient is greater than the level threshold, the corresponding first / second environmental protection scheme can be raised by one or several levels.

[0068] In some embodiments, determining the second construction plan according to the second image data includes:

[0069] The construction progress data of the power transmission and transformation equipment construction area is obtained based on the second image data, the first construction plan is evaluated based on the construction progress data, and the second construction plan is generated based on the evaluation result.

[0070] In this embodiment, after the construction begins, the construction progress of the construction area can be analyzed according to a preset period, and the degree of match between the originally determined first construction plan and the current construction progress can be evaluated. When the first construction plan cannot meet the actual situation of the current construction progress, a new second construction plan can be generated.

[0071] The second construction plan includes upgrading or downgrading or keeping unchanged the material, height, thickness, strength, structure and other parameters of the enclosures of each adjacent area. The second construction plan can be generated in the same way as the first construction plan, and the details are not repeated here.

[0072] In some embodiments, the evaluating the first construction plan according to the construction progress data and generating the second construction plan according to the evaluation result includes: generating the second construction plan according to the construction progress data, and calculating the deviation between the second construction plan and the first construction plan;

[0073] If the deviation is greater than the deviation threshold, the second construction plan is confirmed; otherwise, the first construction plan continues to be confirmed.

[0074] In this embodiment, the present invention can generate the second construction plan periodically, that is, continuously generate the second construction plan according to the current construction progress, and execute the new second construction plan only when the deviation between the second construction plan and the originally determined first construction plan is too large, so as to avoid frequent and useless adjustments to the construction plan.

[0075] Among them, since the first stage of the construction process is a rapid construction period, and the last stage is mainly equipment debugging, etc. Therefore, the present invention is set to determine the deviation threshold according to the construction stage. Specifically, the closer to the start of the construction stage, the smaller the deviation threshold is, so as to increase the probability of the second construction plan being confirmed; the closer to the end of the construction stage, the larger the deviation threshold is, so as to reduce the probability of the second construction plan being over-confirmed.

[0076] See also Figure 2 As shown, the embodiment of the present invention also discloses an environmental protection construction system for power transmission and transformation equipment, including an acquisition module, a processing module, and a storage module; the processing module is connected to the acquisition module and the storage module;

[0077] The storage module is used to store executable computer program code;

[0078] The acquisition module is used to acquire image data of the construction site and transmit it to the processing module;

[0079] It is characterized in that: the processing module is used to execute the method as described in the above embodiment by calling the executable computer program code in the storage module.

[0080] An embodiment of the present invention further discloses an electronic device, comprising: a memory storing executable program code; a processor coupled to the memory; the processor calls the executable program code stored in the memory to execute the method described in the above embodiment.

[0081] The embodiment of the present invention further discloses a computer storage medium, on which a computer program is stored. When the computer program is executed by a processor, the method described in the above embodiment is executed.

[0082] The embodiment of the present invention further discloses a computer program product, which executes the method described in the above embodiment when running.

[0083] For the convenience of description, the above device is described in various units according to their functions. Of course, when implementing the present application, the functions of each unit can be implemented in the same or multiple software and / or hardware.

[0084] It can be known from the description of the above implementation methods that those skilled in the art can clearly understand that the present application can be implemented by means of software plus a necessary general hardware platform. Based on such an understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product can be stored in a storage medium such as ROM / RAM, a disk, an optical disk, etc., and includes several instructions for enabling a computer device (which can be a personal computer, an information push server, or a network device, etc.) to execute the methods described in the various implementation methods of the present application or certain parts of the implementation methods.

[0085] The device implementation described above is merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the present implementation scheme. Those of ordinary skill in the art may understand and implement it without creative work.

[0086] The present application can be used in many general or special computing system environments or configurations, such as personal computers, information push server computers, handheld or portable devices, tablet devices, multiprocessor systems, microprocessor-based systems, set-top boxes, programmable consumer electronic devices, network PCs, minicomputers, mainframe computers, and distributed computing environments including any of the above systems or devices.

[0087] The present application may be described in the general context of computer-executable instructions executed by a computer, such as program modules. Generally, program modules include routines, programs, objects, components, data structures, etc. that perform specific tasks or implement specific abstract data types. The present application may also be practiced in distributed computing environments where tasks are performed by remote processing devices connected through a communication network. In a distributed computing environment, program modules may be located in local and remote computer storage media, including storage devices.

[0088] It should be understood that although this specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each implementation mode may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

[0089] The series of detailed descriptions listed above are only specific descriptions of feasible implementation methods of the present invention. They are not intended to limit the scope of protection of the present invention. Any equivalent implementation methods or changes that do not deviate from the technical spirit of the present invention should be included in the scope of protection of the present invention.

Claims

1. An environmentally friendly construction method for power transmission and transformation equipment, characterized in that: include: Acquire first image data of the construction site, and determine a first construction plan according to the first image data; Acquire second image data of the construction site, and determine a second construction plan according to the second image data; Implement environmental protection construction of power transmission and transformation equipment according to the first construction plan and the second construction plan; Determining a first construction plan according to the first image data includes: Identify the power transmission and transformation equipment construction area and several adjacent areas in the first image data, and determine the first shape data of the power transmission and transformation equipment construction area, and the second attribute data and second shape data of each adjacent area; Generate an environmental protection plan for the adjacent area according to the first attribute data and the first shape data of the power transmission and transformation equipment and the second attribute data and the second shape data of each adjacent area; The first attribute data includes the location attribute and the equipment attribute of the power transmission and transformation equipment; then, according to the first attribute data and the first shape data of the power transmission and transformation equipment and the second attribute data and the second shape data of each adjacent area, an environmental protection plan for the adjacent area is generated, including: Determine a first type of adjacent area according to the location attribute of the power transmission and transformation equipment and the first shape data, and generate a first environmental protection plan for the first type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the first type of adjacent area; Determine a second type of adjacent area according to the equipment attributes of the power transmission and transformation equipment and the first format data, and generate a second environmental protection plan for the second type of adjacent area according to the second attribute data and the second format data of the adjacent area corresponding to the second type of adjacent area; The first environmental protection plan and the second environmental protection plan are integrated to obtain an environmental protection plan.

2. The environmental protection construction method for power transmission and transformation equipment according to claim 1, characterized in that: The first image data and / or the second image data are obtained by shooting with a camera arranged at a high position at the construction site and / or a camera installed on an unmanned aerial vehicle device.

3. The environmental protection construction method for power transmission and transformation equipment according to claim 1, characterized in that: Generating a first environmental protection scheme for the first type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the first type of adjacent area, and generating a second environmental protection scheme for the second type of adjacent area according to the second attribute data and the second shape data of the adjacent area corresponding to the second type of adjacent area, including: Determine a first influence coefficient of a first type of adjacent area and a second influence coefficient of a second type of adjacent area according to device attributes; Generate a first environmental protection plan for the first type of adjacent area according to the first influence coefficient of the first type of adjacent area, the second attribute data of the adjacent area corresponding to the first type of adjacent area, and the second shape data; And, a second environmental protection plan for the second type of adjacent area is generated according to the second influence coefficient of the second type of adjacent area, the second attribute data of the adjacent area corresponding to the second type of adjacent area, and the second shape data.

4. An environmentally friendly construction method for power transmission and transformation equipment according to any one of claims 1 to 3, characterized in that: Determining a second construction plan according to the second image data includes: The construction progress data of the power transmission and transformation equipment construction area is obtained based on the second image data recognition, the first construction plan is evaluated based on the construction progress data, and the second construction plan is generated based on the evaluation result.

5. The environmental protection construction method for power transmission and transformation equipment according to claim 4, characterized in that: Evaluating the first construction plan according to the construction progress data, and generating a second construction plan according to the evaluation result, including: generating the second construction plan according to the construction progress data, and calculating the deviation between the second construction plan and the first construction plan; If the deviation is greater than the deviation threshold, the second construction plan is confirmed; otherwise, the first construction plan is continued to be confirmed.

6. A power transmission and transformation equipment environmental protection construction system, comprising an acquisition module, a processing module, and a storage module; the processing module is connected to the acquisition module and the storage module; the storage module is used to store executable computer program codes; the acquisition module is used to acquire image data of the construction site and transmit it to the processing module; it is characterized in that: The processing module is used to execute the method according to any one of claims 1 to 5 by calling the executable computer program code in the storage module.

7. An electronic device comprising: A memory storing executable program code; A processor coupled to the memory; characterized in that: the processor calls the executable program code stored in the memory to execute the method according to any one of claims 1-5.

8. A computer storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 5 is executed.

Citation Information