Methods for correcting deviation and lowering rails for quay container cranes
By arranging load-bearing beams and jack components on the quay crane, and combining them with a tractor, the quay crane can be corrected and lowered onto the track, solving the problem of quay crane derailment, improving operational efficiency and reducing costs.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-17
- Publication Date
- 2026-03-10
AI Technical Summary
In existing technologies, quay cranes are prone to damage, derailment, or even overturning, which affects dock operations. Conventional handling methods require large equipment and are costly and time-consuming.
The method of correcting deviation and lowering the rails is adopted. By arranging load-bearing beams and vertical jack components on the sea side of the quay crane, combined with horizontal jacks and a traction vehicle, the deviation of the entire quay crane is corrected and lowered onto the rails, avoiding the use of large hoisting equipment.
It reduced the impact on dock operations, improved operational efficiency, reduced costs, and avoided the use of large equipment.
Smart Images

Figure CN116573534B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the field of crane manufacturing and installation, in particular to a deviation rectification and track falling method for a shore-based container crane. BACKGROUND
[0002] With the continuous development of global trade, the container transportation business is increasing, and various container loading and unloading wharfs are continuously increasing. The shore-based container crane (hereinafter referred to as the shore crane) is also developing in a large scale. In the busy loading and unloading process of various wharfs, the shore crane plays an important role, but in the operation process, various unpredictable accidents may occur, such as sudden movement of the shore crane caused by sudden strong wind, collision between the shore cranes, sudden movement of the container ship under the shore crane, or collision with the shore crane due to operation error when stopping, etc. This may easily cause one or more shore cranes to be damaged and derailed (as shown in FIG. 1), or even overturned. Such accidents will have a serious impact on the normal production and operation of the wharf. Figure 1
[0003] When the above problems occur, it is an important consideration to restore the normal operation of the wharf as soon as possible. In addition to the necessary temporary reinforcement of the damaged and derailed shore crane, it is also necessary to rectify the deviation and fall the track, so that it can be moved to the non-normal operation area on the track, thereby reducing the impact on the wharf operation.
[0004] The conventional treatment method usually needs to use large lifting equipment to lift the whole machine and place it on the track after being properly positioned, or even may need to dismantle the shore crane in place. This method needs large equipment, has a long operation period, is high in cost, and needs a suitable wharf and position for operation, so the feasibility is poor.
[0005] Therefore, the present application provides a deviation rectification and track falling method for a shore-based container crane to overcome the above technical problems. SUMMARY
[0006] The technical problem solved by the present application is to overcome the defects of the prior art that the shore crane is easily damaged and derailed, or even overturned, and to provide a deviation rectification and track falling method for a shore-based container crane.
[0007] The present application solves the above technical problems by the following technical scheme:
[0008] The present application provides a deviation rectification and track falling method for a shore-based container crane, characterized in that the deviation rectification and track falling method comprises the following steps:
[0009] S1, arranging a load distribution beam and a vertical jack assembly under the balance beam of the large truck running mechanism on the sea side of the shore crane;
[0010] S2, welding horizontal jacking supports on the load distribution beam, and arranging horizontal jacks on the horizontal jacking supports for jacking the vertical jack assembly to make the vertical jack assembly produce displacement in the horizontal direction;
[0011] S3, arranging a tractor on the side of the moving direction of the land-side trolley traveling mechanism of the quay crane, and fixing the tractor with the balance beam of the land-side trolley traveling mechanism of the quay crane;
[0012] S4, adjusting the position of the sea-land side trolley traveling mechanism of the quay crane in the sea-land side direction by the horizontal jacks, and adjusting the position of the land-side trolley traveling mechanism of the quay crane in the left-right side direction by the tractor, so that the quay crane rotates and is rectified.
[0013] According to one embodiment of the present application, the step S4 further comprises the following step:
[0014] S5, when the quay crane rotates to the state that the wheels of the trolley traveling mechanism are parallel to the quay trolley track, arranging a jacking trolley under the balance beam of the trolley traveling mechanism, jacking up the quay crane by the jacking trolley, and moving the jacking trolley in the sea-land side direction by a traction mechanism until the wheels of the trolley traveling mechanism are aligned with the quay trolley track, and then lowering the jacking trolley to make the wheels of the trolley traveling mechanism fall onto the quay trolley track.
[0015] According to one embodiment of the present application, in the step S5, a temporary rigid track perpendicular to the trolley track is arranged under the jacking trolley.
[0016] According to one embodiment of the present application, in the step S5, the traction mechanism is a tractor or a winch.
[0017] According to one embodiment of the present application, between the step S2 and the step S3, a thick steel plate is arranged under the wheels of the land-side trolley traveling mechanism of the quay crane.
[0018] According to one embodiment of the present application, the vertical jack assembly comprises a vertical jack seat and a vertical jack, the vertical jack seat is arranged on the thick steel plate, and the vertical jack is installed on the vertical jack seat.
[0019] According to one embodiment of the present application, in the step S3, the tractor is fixedly connected with the lug plate on the balance beam of the land-side trolley traveling mechanism of the quay crane by a steel wire rope and a shackle.
[0020] According to one embodiment of the present application, in the step S3, when the quay crane is rectified, the land-side trolley traveling mechanism of the quay crane and the sea-side trolley traveling mechanism of the quay crane simultaneously produce force.
[0021] According to one embodiment of the present invention, in step S1, the vertical jack assembly and the load-bearing beam have a smooth and flat contact. The vertical jack assembly lifts the balance beam on the sea side of the quay bridge, so that the wheels of the trolley traveling mechanism on the sea side of the quay bridge are lifted into the air.
[0022] According to one embodiment of the present invention, lubricating oil or grease is applied between the vertical jack assembly and the load-bearing beam.
[0023] The positive and progressive effects of this invention are as follows:
[0024] This invention relates to a method for correcting and lowering the track of a quay container crane, which uses a sliding mechanism to achieve overall machine correction and track lowering. This method reduces the impact on the user's terminal operations, improves operational efficiency, avoids the use of large lifting equipment, and reduces costs. Attached Figure Description
[0025] The above and other features, properties and advantages of the present invention will become more apparent from the following description taken in conjunction with the accompanying drawings and embodiments, in which the same reference numerals always denote the same features, wherein:
[0026] Figure 1 This is a schematic diagram of the derailment state of a quay crane in the existing technology.
[0027] Figure 2 This is a schematic diagram showing the arrangement of the load-bearing beam and jack assembly in the method for correcting deviation and lowering the track for a quayside container crane according to the present invention.
[0028] Figure 3 This is a schematic diagram showing the arrangement of vertical and horizontal jacks in the method for correcting and lowering a container crane at the shore of the present invention.
[0029] Figure 4 This is a schematic diagram of the traction of the quay crane on the land side in the method for correcting deviation and lowering the track for a quay container crane, which is a method of the present invention.
[0030] Figure 5 This is a schematic diagram of the quay crane's alignment process in the quay crane alignment and track lowering method of the present invention.
[0031] Figure 6 This is a schematic diagram of the whole quay crane being moved and lowered onto the rails in the method for correcting deviation and lowering rails for quay container cranes according to the present invention.
[0032] [Attached image labels]
[0033] 10 large trolley traveling mechanism on the sea side of the quay bridge
[0034] Balance beam 20
[0035] 30 load-bearing beam
[0036] 31 pad beams
[0037] Vertical jack support 40
[0038] Vertical jack 41
[0039] 50mm thick steel plate
[0040] Horizontal lifting support 60
[0041] Horizontal jack 61
[0042] 70 gantry crane traveling mechanism on the land side of the quay crane
[0043] tractor 80
[0044] Wire ropes and shackles 81
[0045] Lifting trolley 90
[0046] Dock marine survey track 11
[0047] Landside Rail 71 at the Wharf
[0048] Adjust A towards the sea side
[0049] Adjust B towards the land side
[0050] Adjust C to the right of the sea Detailed Implementation
[0051] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
[0052] Embodiments of the invention will now be described in detail with reference to the accompanying drawings. Preferred embodiments of the invention will now be described in detail, examples of which are shown in the drawings. Wherever possible, the same reference numerals will be used in all the drawings to denote the same or similar parts.
[0053] Furthermore, although the terminology used in this invention is selected from commonly known and used terms, some terms mentioned in this specification may have been selected by the applicant in his or her judgment, and their detailed meanings are explained in the relevant sections of the description herein.
[0054] Furthermore, the invention should be understood not only through the actual terminology used, but also through the meaning implied by each term.
[0055] like Figures 2 to 6 As shown, this invention discloses a method for correcting deviation and lowering the track for a quay container crane, which includes the following steps:
[0056] Step S1: Arrange the load-sharing beam 30 and the vertical jack assembly under the balance beam 20 of the trolley traveling mechanism 10 on the sea side of the shore bridge.
[0057] More specifically, preferably, a relatively long rigid load-sharing beam 30 is arranged on the ground corresponding to the large balance beam 20 on the sea side of the quay crane. The load-sharing beam 30 needs to span the longitudinal beams on the wharf. A thick steel plate (not shown in the figure) is welded to the upper part of the load-sharing beam 30.
[0058] The upper surface of the thick steel plate here needs to be smooth and flat; for example, lubricating grease can be applied to the thick steel plate. At the same time, a vertical jack support 40 is arranged on the upper part of this thick steel plate. The bottom surface of the vertical jack support 40 needs to be ground smooth and flat. A large-tonnage vertical jack 41 is arranged on the vertical jack support 40, and a pad beam 31 is arranged on the upper part of the vertical jack 41. The vertical jack 41 is used to lift the balance beam 20 on the sea side of the quay crane, so that the wheels of the trolley traveling mechanism 10 on the sea side of the quay crane are lifted into the air.
[0059] Preferably, in step S1, the vertical jack assembly and the load-bearing beam have a smooth and flat contact. The vertical jack assembly lifts the balance beam on the sea side of the quay crane, thus suspending the wheels of the trolley traveling mechanism on the sea side of the quay crane. To ensure smoothness between the vertical jack assembly and the load-bearing beam, lubricating oil or grease can preferably be applied between them.
[0060] Step S2: Weld a horizontal lifting support 60 onto the load-bearing beam 30, and arrange a horizontal jack 61 on the horizontal lifting support 60 to lift the vertical jack assembly, so that the vertical jack assembly produces a horizontal displacement.
[0061] The process between steps S2 and S3 further includes: placing a thick steel plate 50 under the wheels of the trolley traveling mechanism 40 on the land side of the quay crane to facilitate the trolley wheels sliding sideways on the steel plate when the whole machine is rotating to correct its deviation.
[0062] The vertical jack assembly preferably includes a vertical jack base 60 and a vertical jack 61, with the vertical jack base 60 arranged on a thick steel plate 50 and the vertical jack 61 installed on the vertical jack base 60.
[0063] Step S3: Arrange a tractor 80 on one side of the moving direction of the trolley traveling mechanism 70 on the land side of the quay crane, and fix it to the balance beam of the trolley traveling mechanism 70 on the land side of the quay crane.
[0064] Preferably, the traction mechanism 70 can be configured as a tractor or a winch. In step S3, when the entire quay crane is correcting its course, the trolley travel mechanism on the sea side and the trolley travel mechanism on the land side of the quay crane exert force simultaneously.
[0065] In step S3, the tractor 80 is fixedly connected to the ear plate on the balance beam of the trolley traveling mechanism 70 on the land side of the quay crane via a steel wire rope and shackle 81, so as to ensure that the position of the trolley traveling mechanism 10 on the sea side of the quay crane and the position of the trolley traveling mechanism 70 on the land side of the quay crane exert force simultaneously when the whole machine is corrected.
[0066] Step S4: The horizontal jack 61 adjusts the position of the gantry crane traveling mechanism 10 on the sea side of the quay crane in the sea-land direction, and the tractor 80 adjusts the gantry crane traveling mechanism 70 on the land side of the quay crane in the left-right direction, so that the entire quay crane rotates and corrects the deviation of the entire quay crane.
[0067] Furthermore, the step S4 is followed by the following steps:
[0068] Step S5: When the entire quay crane rotates until the wheels of the trolley travel mechanism (including the trolley travel mechanism 10 for quay crane sea surveying and the trolley travel mechanism 70 for quay crane landside) are parallel to the quay crane track, a lifting trolley 90 is arranged under the balance beam of the trolley travel mechanism (including the trolley travel mechanism 10 for quay crane sea surveying and the trolley travel mechanism 70 for quay crane landside). The trolley lifts the entire quay crane and uses a traction mechanism to pull the lifting trolley to move in the sea-land direction until the wheels of the trolley travel mechanism are aligned with the quay track. Then, the lifting trolley is lowered to lower the wheels of the trolley travel mechanism (including the trolley travel mechanism 10 for quay crane sea surveying and the trolley travel mechanism 70 for quay crane landside) onto the quay track.
[0069] Preferably, in step S5: a temporary rigid track perpendicular to the main track is arranged under the lifting trolley.
[0070] In summary, the present invention provides a method for correcting and lowering the quay crane onto the rails, which achieves overall crane correction and lowering through a sliding mechanism. This method reduces the impact on the user's terminal operations, improves operational efficiency, avoids the use of large lifting equipment, and lowers costs.
[0071] This application uses specific terms to describe embodiments of the application. Terms such as "an embodiment," "one embodiment," and / or "some embodiments" refer to a particular feature, structure, or characteristic associated with at least one embodiment of the application. Therefore, it should be emphasized and noted that references to "an embodiment," "one embodiment," or "an alternative embodiment" in different locations throughout this specification do not necessarily refer to the same embodiment. Furthermore, certain features, structures, or characteristics in one or more embodiments of the application can be appropriately combined.
[0072] While specific embodiments of the present invention have been described above, those skilled in the art should understand that these are merely illustrative examples, and the scope of protection of the present invention is defined by the appended claims. Those skilled in the art can make various changes or modifications to these embodiments without departing from the principles and essence of the present invention, but all such changes and modifications fall within the scope of protection of the present invention.
Claims
1. A method for deviation correction derailing of a shore-based container crane, characterized in that, The deviation rectification and track leaving method comprises the following steps: S1, arranging a load distribution beam and a vertical jack assembly under the lower part of the balance beam of the land-side travelling mechanism of the shore-based container crane; S2, welding a horizontal lifting support on the load distribution beam and arranging a horizontal jack on the horizontal lifting support for lifting the vertical jack assembly to make the vertical jack assembly produce displacement in the horizontal direction; S3, arranging a tractor on the side of the land-side travelling mechanism of the shore-based container crane in the moving direction and fixing the tractor with the balance beam of the land-side travelling mechanism of the shore-based container crane; S4, adjusting the position of the land-side travelling mechanism of the shore-based container crane in the sea-land direction by the horizontal jack and adjusting the position of the land-side travelling mechanism of the shore-based container crane in the left-right direction by the tractor to rotate the whole shore-based container crane and rectify the deviation of the whole shore-based container crane; The step S4 further comprises the following steps: S5, when the wheels of the travelling mechanism are parallel to the wharf travelling track, arranging a lifting trolley under the balance beam of the travelling mechanism, lifting the whole shore-based container crane by the lifting trolley, moving the lifting trolley in the sea-land direction by a traction mechanism until the wheels of the travelling mechanism are aligned with the wharf track, and then lowering the lifting trolley to make the wheels of the travelling mechanism fall on the wharf track; The step S2 and the step S3 further comprise arranging a thick steel plate under the wheels of the land-side travelling mechanism of the shore-based container crane; The vertical jack assembly comprises a vertical jack seat and a vertical jack, the vertical jack seat is arranged on the thick steel plate, and the vertical jack is installed on the vertical jack seat; The vertical jack assembly and the load distribution beam are in smooth and flat contact, the wheels of the land-side travelling mechanism of the shore-based container crane are lifted by the vertical jack assembly to make the wheels of the land-side travelling mechanism of the shore-based container crane float.
2. A method of deviation correction derailing for a quayside container crane according to claim 1, characterized in that, In the step S5, a temporary rigid track perpendicular to the travelling track is arranged under the lifting trolley.
3. A method of deviation correction derailing for a quayside container crane according to claim 1, characterized in that, In the step S5, the traction mechanism is a tractor or a winch.
4. The method for deviation correction derailing of a quayside container crane according to claim 1, characterized in that, In the step S3, the tractor is fixedly connected with the lug plate on the balance beam of the land-side travelling mechanism of the shore-based container crane by a steel wire rope and a shackle.
5. A method of deviation correction derailing for a quayside container crane according to claim 4, characterized in that, In the step S3, when the whole shore-based container crane is rectified, the land-side travelling mechanism of the shore-based container crane and the land-side travelling mechanism of the shore-based container crane simultaneously produce force.
6. The method for deviation correction derailing of a quayside container crane according to claim 1, characterized in that, Lubricating oil or lubricating butter is applied between the vertical jack assembly and the load distribution beam.
Citation Information
Patent Citations
Rectifying device used for mounting elevated frames and bridges and rectifying method of rectifying device
CN103924521A
Ship loading and ship unloading method for gantry crane
CN109677566A