A method for processing compacted piles
By using a combination of formed fillers and crevices fluid in compaction pile construction, the problem of difficult-to-control backfill quality was solved, the construction process was visualized and controllable, dust pollution and manual supervision were reduced, and construction speed and quality were improved.
Patent Information
- Application Number
- CN202310929021.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-26
- Publication Date
- 2025-09-19
- Estimated Expiration
- 2043-07-26
AI Technical Summary
In the existing compaction pile construction, the quality of backfill material is difficult to accurately control, resulting in serious dust pollution, slow construction speed, and the need for a lot of manual supervision, which affects the construction quality and schedule.
A combination of formed filler and crevices fluid is used. The formed filler is prepared before construction and backfilled on site. Parameters are adjusted in conjunction with static load tests to ensure filler quality and construction quality, and avoid on-site mixing and dust pollution.
The filler quality can be visualized and controlled, the number of supervisors can be reduced, dust pollution can be avoided, the construction speed and quality can be improved, the pile diameter accuracy can be ensured, and the construction period can be shortened.
Smart Images

Figure CN116791556B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical direction of compaction pile treatment methods, and specifically relates to a compaction pile treatment method. Background Art
[0002] This patented invention is applicable to the construction of both plain soil compaction piles and cement soil compaction piles for the project. The design drawings specify that plain soil compaction piles and cement soil compaction piles be used for foundation treatment. Based on the compaction pile construction process, an environmentally friendly compaction pile driver is used to drill holes. After acceptance, a tamping machine is used for layered backfilling. The backfill is mixed on-site with plain soil or cement soil. This makes backfill quality control difficult, requiring dedicated on-site supervision and resulting in significant dust pollution. To prevent cement soil from clumping, a mix-as-you-go method is generally adopted, with a low tamping rate, severely restricting the construction schedule.
[0003] Compaction pile construction generally uses an environmentally friendly compaction pile driver to drill holes, and then uses a tamping machine to backfill the holes in layers with plain soil or cement soil. This method requires strict control of the quality of the backfill material and the tamping quality, but the measurement during the mixing process is difficult to control accurately, the backfill rate is slow, and it is severely restricted by rainy and snowy days. In addition, someone must be arranged to supervise at all times.
[0004] In order to avoid the poor quality of compacted piles, the participants of the present invention have jointly improved a compacted pile processing method to address the above shortcomings. This method is based on the compacted pile diameter, simulates according to the design parameters, determines the filler parameters, compacts the pile in advance in the project, and makes a shaped filler with a height of 500 mm and a diameter 20 mm smaller than the hole diameter. Backfill is carried out on site, and the pores after backfilling are filled with cement slurry or chemical slurry. Summary of the Invention
[0005] The purpose of the present invention is to provide a compaction pile treatment method for existing devices to solve the problems raised in the above background technology.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a method for processing compacted piles, comprising the following steps:
[0007] S1: Pile driver hole forming;
[0008] S2: Steel pipe pile model making and placement;
[0009] S3: ramming machine backfills the filler;
[0010] S4: Remove the steel pipe pile model and separate the soil at each depth;
[0011] S5: soil parameter analysis at each depth range;
[0012] S6: Determine the molding filler parameters and gap filling liquid;
[0013] S7: Forming filler production;
[0014] S8: Backfilling of formed filler and construction of gap fluid;
[0015] S9: static load test;
[0016] S10: Molding filler parameter adjustment and processing production;
[0017] S11: Backfill construction at the construction site.
[0018] The present invention further illustrates that during the process of making and placing the steel pipe pile model in step S2, the steel pipe pile model is designed and made of 10 mm thick steel plates, and is fixed with detachable pins around it. After the traditional backfill method is completed, it is disassembled and the soil is taken out for parameter analysis.
[0019] The present invention further illustrates that, in the process of analyzing soil parameters in each depth range in step S5, the soil is analyzed by testing soil density, bearing capacity, etc. to determine the soil characteristics in each depth range.
[0020] The present invention further illustrates that in the process of determining the parameters of the forming filler and the gap filling liquid in step S6, the forming filler is composed of a lowered installation point and a gap filling liquid groove. During implementation, the parameter requirements of the forming fillers at different depths are determined according to the soil parameters within each depth range, and the parameters and type of the gap filling liquid inside the gap filling groove are determined.
[0021] The present invention further explains that during the static load test in step S9, a static load test is performed on the compacted piles after the formed filler and the gap filling are completed and solidification is completed, and the parameters of the formed filler are appropriately adjusted according to the static load test.
[0022] Compared with the prior art, the present invention has the following beneficial effects:
[0023] By providing the compaction pile treatment method, the filler quality can be visualized and controlled, and the number of quality supervision personnel can be reduced;
[0024] This compaction pile treatment method avoids dust pollution caused by on-site mixing of fillers;
[0025] This compaction pile treatment method avoids inaccurate measurement, which may lead to inaccurate mixing ratio and uneven mixing, thus affecting the quality of the pile.
[0026] This compacted pile treatment method uses the same size of molding seasoning to help check whether the pile length reaches the designed length and ensure construction quality;
[0027] This compacted pile treatment method uses a formed filler with a diameter 20mm smaller than the hole diameter for construction, which can help check the pile diameter deviation and repair the parts that do not meet the requirements;
[0028] This compaction pile treatment method can also check whether there are pile quality defects such as shrinkage holes and collapse holes during the filling process;
[0029] This compaction pile treatment method can increase labor input, shorten construction period, and avoid idle workers.
[0030] This compaction pile treatment method avoids the inability to mix fillers due to rainy days, and construction can be carried out immediately after the rain. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0032] Figure 1 This is a schematic diagram of the installation of the steel pipe pile model of the present invention;
[0033] Figure 2 It is a schematic diagram of the overall effect of the present invention;
[0034] Figure 3 This is a schematic diagram of the structure of the molded filler of the present invention.
[0035] In the figure: 1. Steel pipe pile model; 2. Formed filler; 201. Lowering installation point; 202. Crack filling groove. DETAILED DESCRIPTION
[0036] The following is a non-limiting detailed description of the technical solutions of the present invention in conjunction with preferred embodiments and the accompanying drawings. Obviously, the embodiments described are only some of the embodiments of the present invention, not all of them. All other embodiments derived by persons of ordinary skill in the art based on the embodiments of the present invention without inventive effort are also within the scope of protection of the present invention.
[0037] See also Figure 1-3 The present invention provides a technical solution: a method for processing compacted piles, comprising the following steps:
[0038] S1: Pile driver hole forming;
[0039] S2: Fabrication and placement of steel pipe pile model 1;
[0040] S3: ramming machine backfills the filler;
[0041] S4: Remove the steel pipe pile model 1 and separate the soil at each depth;
[0042] S5: soil parameter analysis at each depth range;
[0043] S6: Determine the parameters of the molding filler 2 and the gap filling liquid;
[0044] S7: Forming filler 2 production;
[0045] S8: Backfilling of formed filler 2 and construction of gap fluid;
[0046] S9: static load test;
[0047] S10: Molding filler 2 parameter adjustment and processing production;
[0048] S11: Backfill construction at the construction site.
[0049] During the process of making and placing the steel pipe pile model 1 in step S2, the steel pipe pile model 1 is designed and made of 10 mm thick steel plates and is fixed with detachable pins on all sides. After the traditional backfill method is completed, it is disassembled and the soil is taken out for parameter analysis.
[0050] During the soil parameter analysis of each depth range in step S5, the soil is analyzed by testing the soil density and bearing capacity to determine the soil characteristics within each depth range.
[0051] In the process of determining the parameters of the formed filler 2 and the gap filling liquid in step S6, the formed filler 2 is composed of a lowered installation point 201 and a gap filling liquid tank 202. During the implementation process, the parameter requirements of the formed filler 2 at different depths are determined according to the soil parameters within each depth range, and the parameters and types of the gap filling liquid inside the gap filling tank 202 are determined.
[0052] During the static load test in step S9, a static load test is performed on the formed filler 2 and the compacted piles after the gap filling construction is completed and solidification is completed. The parameters of the formed filler 2 are appropriately adjusted according to the static load test.
[0053] In the description of the present invention, it should be understood that the terms "up", "down", "front", "back", "left", "right", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only used to facilitate the description of the present invention, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0054] Finally, it should be noted that the above embodiments are intended only to illustrate the technical solutions of the present invention and are not intended to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art will appreciate that modifications may be made to the technical solutions described in the aforementioned embodiments, or that some of the technical features may be replaced with equivalents. Such modifications or replacements do not deviate from the spirit and scope of the technical solutions of the various embodiments of the present invention.
Claims
1. A method for processing compacted piles, characterized in that: The following steps are involved: S1: Pile driver hole forming; S2: Fabrication and placement of steel pipe pile model (1); S3: ramming machine backfills the filler; S4: Steel pipe pile model (1) Extraction and separation of soil at each depth; S5: soil parameter analysis at each depth range; S6: Determination of molding filler (2) parameters and gap filling liquid; S7: Forming filler (2) production; S8: Forming filler (2) backfill and gap fluid construction; S9: static load test; S10: Molding filler (2) parameter adjustment and processing production; S11: Backfill construction at the construction site.
2. A compaction pile processing method according to claim 1, characterized in that: During the process of making and placing the steel pipe pile model (1) in step S2, the steel pipe pile model (1) is designed and made of 10 mm thick steel plates, and is fixed with detachable pins on all sides. After the traditional backfill method is completed, it is disassembled and the soil is taken out for parameter analysis.
3. A compaction pile processing method according to claim 1, characterized in that: During the soil parameter analysis of each depth range in step S5, the soil is analyzed by testing the soil density and bearing capacity to determine the soil characteristics within each depth range.
4. A compaction pile processing method according to claim 1, characterized in that: In the process of determining the parameters of the formed filler (2) and the gap filling liquid in step S6, the formed filler (2) is composed of a lowered installation point (201) and a gap filling liquid tank (202). During the implementation process, the parameter requirements of the formed filler (2) at different depths are determined based on the soil parameters within each depth range, and the parameters and type of the gap filling liquid inside the gap filling liquid tank (202) are determined.
5. The method for processing compacted piles according to claim 1, characterized in that: During the static load test in step S9, a static load test is performed on the formed filler (2) and the compacted piles after the gap filling construction is completed and solidification is completed. The parameters of the formed filler (2) are appropriately adjusted according to the static load test.
Citation Information
Patent Citations
Foundation treatment method for improving strength of lime-soil compaction piles through PS solution
CN113481965A
Construction method suitable for quick backfilling of locally-excavated groove of municipal road
CN115110390A