Coolant control system and method for bench testing of hybrid powertrain
By introducing a water temperature regulation device and a multi-valve control system into the hybrid powertrain bench test, an independent circulation loop was formed, which solved the coolant control problem of the hybrid powertrain bench under steady-state and transient conditions, and achieved precise regulation of coolant temperature and flow, ensuring the effectiveness and authenticity of the verification.
Patent Information
- Application Number
- CN202310961787.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-28
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2043-07-28
AI Technical Summary
The existing hybrid powertrain bench coolant control system has an excessive flow rate under transient conditions, which leads to engine overcooling and fails to realistically simulate the vehicle warm-up process, affecting the validity of the verification. Furthermore, the flow control does not meet the vehicle requirements under steady-state conditions.
The system employs a water temperature regulating device, a mechanical ball valve, a terminal controller, an outlet water temperature sensor, a first confluence valve, a circulating water temperature sensor, a solenoid valve, a replenishment tank, and a branch circulation monitoring device to form two independent coolant circulation loops. PID control is used to achieve precise regulation of coolant temperature and flow rate.
It achieves realistic simulation of the hybrid powertrain bench under steady-state and transient conditions of the vehicle, ensuring the accuracy of coolant temperature and flow control, avoiding engine overcooling and temperature shock, and maximizing the reproduction of the vehicle's operating state.
Smart Images

Figure CN116952597B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of hybrid powertrain bench testing equipment, specifically relating to a coolant control system and method for hybrid powertrain bench testing. Background Technology
[0002] With increasingly stringent national emission regulations and the rapid development of hybrid technology, both hybrid powertrain test benches and engine test benches are paying close attention to the impact of coolant temperature and flow rate changes under transient conditions on fuel consumption, emissions, and even energy consumption. This is especially true because the engine in a hybrid powertrain frequently starts and stops under different demands, and the coolant temperature changes during these processes differ from those in a conventional engine. Particularly under WLTC and other regulatory conditions, whether the hybrid powertrain's coolant temperature and flow rate can reach the vehicle testing limits becomes a key focus. Currently, hybrid powertrain test benches widely use water-cooled heat exchangers for coolant temperature control. While this method can accurately control the engine's coolant temperature under steady-state conditions, the coolant volume generally far exceeds the vehicle's radiator capacity, resulting in excessively high flow rates under transient conditions. This can lead to engine overcooling and missed detection of issues such as knocking. Furthermore, the distortion of the temperature rise rate and flow rate changes during the warm-up process significantly reduces the effectiveness of related verifications on hybrid powertrain test benches.
[0003] Therefore, when conducting relevant transient operating condition simulation verification on the hybrid powertrain bench, it is necessary to ensure that the coolant temperature change and flow rate conform to the target boundary of the whole vehicle.
[0004] Currently, bench coolant temperature and flow control systems typically employ two three-way proportional valves, one for flow control and the other for temperature control. For example, CN204440208U discloses a coolant temperature and flow control device for engine bench testing. This device inputs a target flow rate value to a flow controller unit, and the feedback value from the engine coolant flow sensor controls the three-way proportional valve to adjust the flow ratio between the coolant circulation pump and the bypass branch, ensuring that the coolant flow back to the engine reaches the target control value. Similarly, the device inputs a target temperature value to a temperature controller unit, and the feedback value from the temperature sensor located at the engine inlet adjusts the corresponding proportional valve, ensuring that the ratio of cold water in the heat exchanger to hot water in the electric heater reaches the target temperature. The control device has the following problems: (1) When using a single three-way proportional solenoid valve to control the flow, the flow control cannot meet the same level as the whole vehicle when the engine is running at low speed and low load; (2) Because there is always a flow relationship between the engine and the expansion tank and heat exchanger, the current system cannot realize the real warm-up process of the engine in the whole vehicle state by fully closing its solenoid valve, so the engine will not really enter the whole vehicle cooling small circulation state.
[0005] CN112284742A discloses a water temperature and flow control system for an engine test bench. It uses the vehicle radiator as a heat exchanger and places it in a water temperature control box. The flow control is achieved by controlling the second solenoid valve switch through the flow signal fed back by the flow meter in the engine coolant circuit. The temperature is controlled by the first solenoid valve of the external circulation through the temperature fed back by the temperature sensor in the engine coolant circuit to control the temperature of the engine coolant. Although this control system can effectively improve the structural consistency between the test bench cooling system and the vehicle cooling system, it also has the following problems: (1) The application scenarios of this control system are limited. Under the reliability test conditions such as thermal alternating load, the coolant temperature response process is long because the engine cannot quickly perform large circulation, which means that the reliability transient verification cannot be achieved; (2) When the medium in the water temperature control box is water, the heat exchange effect of the vehicle radiator will decrease over time due to the increase of scale on the outer surface, thus deviating from the heat exchange state of the vehicle. Summary of the Invention
[0006] The purpose of this invention is to provide a coolant control system and method for bench testing of hybrid powertrains, so as to realize both steady-state and transient condition simulation and verification of the whole vehicle.
[0007] The coolant control system for hybrid powertrain bench testing according to the present invention includes a water temperature regulating device, a mechanical ball valve, and a terminal controller. The mechanical ball valve is located between the coolant circulation inlet and outlet of the water temperature regulating device (i.e., the coolant circulation outlet of the water temperature regulating device is connected to the inlet of the mechanical ball valve via a pipeline, and the coolant circulation inlet of the water temperature regulating device is connected to the outlet of the mechanical ball valve via a pipeline). It also includes an outlet water temperature sensor, a first confluence valve, a circulating water temperature sensor, a solenoid valve, a coolant reservoir, and a branch circulation monitoring device. The outlet water temperature sensor is installed at the outlet of a small circulation pipe inside the test component and is used to detect the outlet water temperature of the small circulation pipe inside the test component. The first inlet of the first confluence valve is connected to the outlet of the test component via a pipeline, and the second inlet of the first confluence valve is connected to the inlet of the solenoid valve and the water temperature regulating device. The coolant circulation outlet of the regulating device is connected via a pipeline, and the outlet of the first confluence valve is connected to the coolant circulation inlet of the water temperature regulating device via a pipeline. A circulating water temperature sensor is installed between the first confluence valve and the coolant circulation inlet of the water temperature regulating device (i.e., the circulating water temperature sensor is installed on the pipeline connecting the outlet of the first confluence valve and the coolant circulation inlet of the water temperature regulating device). The circulating water temperature sensor is used to detect the circulating water temperature, that is, to detect the temperature of the water flowing into the coolant circulation inlet of the water temperature regulating device (i.e., the coolant temperature). A branch circulation monitoring device is installed between the first confluence valve and the solenoid valve (i.e., the branch circulation monitoring device is installed on the pipeline connecting the second inlet of the first confluence valve and the inlet of the solenoid valve). The outlet of the solenoid valve is connected to the inlet of the tested component and the replenishment tank via a pipeline, and the replenishment tank is connected to the vent of the tested component via a pipeline. The outlet water temperature sensor, the first confluence valve, the circulating water temperature sensor, the solenoid valve, the branch circulation monitoring device, and the terminal controller are electrically connected. The terminal controller acquires the outlet water temperature of the small circulation pipe inside the tested component, the water temperature of the coolant circulation inlet of the water flowing into the water temperature regulating device, and the signal monitored by the branch circulation monitoring device. After making a judgment, it controls the first confluence valve and the solenoid valve.
[0008] Preferably, the branch circulation monitoring device is a branch water temperature sensor, which is electrically connected to the terminal controller. The branch water temperature is used to determine whether the branch is open. If the branch water temperature detected by the sensor rises, it indicates that the branch is open, and coolant flows between the second inlet and outlet of the first confluence valve. The coolant in the tested component only flows in its own small circulation loop, while the coolant in the temperature regulating device circulates between the mechanical ball valve, the first confluence valve, and the temperature regulating device, thus forming two independent coolant circulation loops.
[0009] Preferably, the branch circulation monitoring device is a branch pressure sensor, which is electrically connected to the terminal controller. The branch is open based on the branch water pressure detected by the branch pressure sensor. If the branch water pressure detected by the branch pressure sensor increases, it indicates that the branch is open, and coolant flows between the second inlet and outlet of the first confluence valve.
[0010] Preferably, the branch circulation monitoring device includes a branch water temperature sensor and a branch pressure sensor, which are electrically connected to the terminal controller. The branch water temperature sensor detects the branch water temperature, and the branch pressure sensor detects the branch water pressure, thus determining whether the branch is open for more accurate results.
[0011] Preferably, the control system further includes a flow meter, which is installed between the solenoid valve and the coolant circulation outlet of the water temperature regulating device (i.e., the flow meter is installed on the pipeline connecting the inlet of the solenoid valve and the coolant circulation outlet of the water temperature regulating device). The flow meter is electrically connected to the terminal controller and is used to send the detected coolant flow rate to the terminal controller for monitoring the coolant circulation flow rate.
[0012] Preferably, the control system further includes an inlet water temperature sensor, which is installed between the solenoid valve and the device under test (i.e., the inlet water temperature sensor is installed on the pipeline connecting the outlet of the solenoid valve and the inlet of the device under test). The inlet water temperature sensor is electrically connected to the terminal controller, and the inlet water temperature sensor sends the detected coolant temperature entering the device under test to the terminal controller for monitoring the inlet water temperature of the device under test.
[0013] Preferably, the water temperature regulating device includes an expansion tank, a circulating water pump, a radiator, a heating element, and a second confluence valve. The inlet of the circulating water pump serves as the coolant inlet for the water temperature regulating device, and is connected to the outlet of the mechanical ball valve and the expansion tank via a pipeline. The outlet of the circulating water pump is connected to the coolant inlet of the radiator and the inlet of the heating element via a pipeline. The outlet of the heating element is connected to the first inlet of the second confluence valve via a pipeline, and the coolant outlet of the radiator is connected to the second inlet of the second confluence valve via a pipeline. The outlet of the second confluence valve serves as the coolant outlet for the water temperature regulating device, and is connected to the inlet of the mechanical ball valve via a pipeline. The circulating water pump, the heating element, and the second confluence valve are electrically connected to a terminal controller, which controls the circulating water pump, the heating element, and the second confluence valve.
[0014] Preferably, the coolant reservoir and the expansion tank are connected by a pipeline, and the liquid level in the coolant reservoir is the same as the liquid level in the expansion tank. This can prevent the coolant from expanding and overflowing due to the height difference between the two at high temperatures.
[0015] The coolant control method for hybrid powertrain bench testing described in this invention employs the aforementioned coolant control system, and the method includes: If the tested component needs to undergo transient vehicle operating condition simulation verification, the terminal controller first controls the first inlet of the first confluence valve to close and the second inlet to open, and controls the solenoid valve to fully close. Then, when the branch circulation monitoring device detects coolant flow between the second inlet and outlet of the first confluence valve (i.e., detects that the first inlet of the first confluence valve is closed and the second inlet is open), PID control is performed on the opening degree of the second confluence valve (corresponding to the opening degree of the first inlet and the second inlet) and the heating power of the heating component based on ΔT. Finally, when T1=T2=Tz, the first inlet of the first confluence valve is controlled to open and the second inlet to close, and the solenoid valve is controlled to return to the preset initial opening degree. Here, T1 is the outlet water temperature of the small circulation pipe inside the tested component detected by the outlet water temperature sensor, T2 is the circulating water temperature detected by the circulating water temperature sensor, ΔT= T1-T2, and Tz is the preset warm-up end temperature threshold. When the branch circulation monitoring device detects coolant circulation between the second inlet and outlet of the first confluence valve, the radiator is isolated from the tested component. The coolant circulation is divided into two parts: one part flows out from the outlet of the first confluence valve, passes through the circulating water pump, radiator, heating element, second confluence valve, mechanical ball valve, and flow meter, and returns to the second inlet of the first confluence valve. The other part of the coolant circulates only through the small circulation path of the tested component itself, thus achieving heat exchange between the two parts of the coolant without interference, forming two independent coolant circulation loops. During the warm-up process, the first part of the coolant circulates and heats its internal components through the heating element and the first confluence valve until the water temperature detected by the circulating water temperature sensor reaches the preset warm-up end temperature threshold. At the same time, the water temperature detected by the outlet water temperature sensor also reaches the warm-up end temperature threshold. The terminal controller controls the first inlet of the first confluence valve to open and the second inlet to close, and controls the solenoid valve to return to the preset initial opening. At this time, because the coolant temperature on both sides is the same, there will be no strong temperature shock, and it will smoothly transition to the large circulation mode of the hybrid powertrain, thereby realizing the transition from the small circulation of the hybrid engine to the large circulation control of the entire large control system, and realizing the real warm-up process of the tested component.
[0016] Preferably, if the test component needs to be verified under steady-state vehicle operating conditions, the terminal controller first controls the first inlet of the first confluence valve to open and the second inlet to close, and controls the solenoid valve to maintain a preset initial opening. Then, when the branch circulation monitoring device detects that there is no coolant flow between the second inlet and outlet of the first confluence valve (i.e., the first inlet of the first confluence valve is detected to be open and the second inlet to be closed), the PID control is performed on the opening of the second confluence valve (corresponding to the opening of the first inlet and the second inlet) and the heating power of the heating component according to T1. The opening of the solenoid valve is controlled according to the preset engine speed MAP to meet the flow requirements of the hybrid powertrain under different speed conditions, thereby realizing temperature and flow control under steady-state conditions or actual vehicle hot-engine conditions. The preset initial opening is the opening obtained through calibration to meet the flow requirements of the test component at idle speed.
[0017] The present invention has the following beneficial effects: (1) It not only realizes the coolant temperature change and flow control boundary under the simulated real transient conditions of the whole vehicle, but also ensures the coolant temperature and flow control under steady-state conditions.
[0018] (2) It can simulate the coolant temperature and flow control of a hybrid engine under the WLTC cycle during start-stop operation, and restore the real operating state of the vehicle to the greatest extent, ensuring the accuracy and effectiveness of the boundary.
[0019] (3) By forming a flow control method of branch and main flow through solenoid valve and first confluence valve, the system has a wider flow control range. It can meet the changes in coolant flow under the actual vehicle boundary through real-time correction, and avoid the occurrence of problems such as knocking of the whole vehicle due to the large difference between the test flow and the whole vehicle. Attached Figure Description
[0020] Figure 1 This is a schematic diagram of the coolant control system used for the bench test of the hybrid powertrain in this embodiment.
[0021] Figure 2 This is the control flowchart of the terminal controller when the test component needs to be verified by vehicle steady-state operating condition simulation in this embodiment.
[0022] Figure 3 This is the control flowchart of the terminal controller when the test component needs to be verified by vehicle transient operating condition simulation in this embodiment.
[0023] Figure 4 This is a partial diagram showing the temperature control effect during a WLTC cycle test. Detailed Implementation
[0024] like Figure 1As shown, the coolant control system for the hybrid powertrain bench test in this embodiment includes a water temperature regulating device, a mechanical ball valve 17, a terminal controller 11, an outlet water temperature sensor 2, a first confluence valve 3, a circulating water temperature sensor 4, a solenoid valve 13, a replenishment tank 5, a flow meter 12, an inlet water temperature sensor 14, and a branch circulation monitoring device.
[0025] The branch circulation monitoring device includes a branch water temperature sensor 15 and a branch pressure sensor 16.
[0026] The water temperature regulating device includes an expansion tank 6, a circulating water pump 7, a radiator 8, a heating element 9, and a second confluence valve 10. The inlet of the circulating water pump 7 serves as the coolant inlet for the water temperature regulating device, and is connected to the outlet of the mechanical ball valve 17 and the expansion tank 6 via a pipeline. The outlet of the circulating water pump 7 is connected to the coolant inlet of the radiator 8 and the inlet of the heating element 9 via a pipeline. The outlet of the heating element 9 is connected to the first inlet of the second confluence valve 10 via a pipeline, and the coolant outlet of the radiator 8 is connected to the second inlet of the second confluence valve 10 via a pipeline. The radiator 8 has a benchtop chilled water inlet 18 and a benchtop chilled water outlet 19. The outlet of the second confluence valve 10 serves as the coolant outlet for the water temperature regulating device, and is connected to the inlet of the mechanical ball valve 17 via a pipeline. A water outlet temperature sensor 2 is installed at the outlet of a small circulation pipe inside the tested component 1 (e.g., a hybrid engine) to provide real-time and accurate feedback of the internal temperature signal. The first inlet of the first confluence valve 3 is connected to the outlet of the tested component 1 via a pipeline, and is positioned as close as possible to the outlet of the tested component 1 to enhance the temperature control effect of the entire control system and effectively reduce temperature shocks during the switching between large and small circulation cycles. The second inlet of the first confluence valve 3 is connected to the inlet of the solenoid valve 13 and the outlet of the second confluence valve 10 via a pipeline. The outlet of the first confluence valve 3 is connected to the inlet of the circulating water pump 7 via a pipeline. The circulating water temperature sensor 4 is installed on the pipeline connecting the outlet of the first confluence valve 3 to the inlet of the circulating water pump 7. The branch water temperature sensor 15 and the branch pressure sensor 16 are installed on the pipeline connecting the second inlet of the first confluence valve 3 to the inlet of the solenoid valve 13. The outlet of the solenoid valve 13 is connected to the inlet of the tested component 1 and the replenishment vessel 5 via a pipeline, and the solenoid valve 13 is positioned as close as possible to the inlet of the tested component 1 to enhance the temperature control effect of the entire control system and effectively reduce temperature shocks during the switching between large and small circulation cycles. The replenishment vessel 5 is connected to the vent of the tested component 1 via a pipeline. The replenishment vessel 5 and the expansion tank 6 are connected by a pipeline, and the liquid level in the replenishment vessel 5 is the same as that in the expansion tank 6. The flow meter 12 is installed on the pipeline connecting the inlet of the solenoid valve 13 to the outlet of the second confluence valve 10, and the inlet water temperature sensor 14 is installed on the pipeline connecting the outlet of the solenoid valve 13 to the inlet of the measured component 1. The outlet water temperature sensor 2, the first confluence valve 3, the circulating water temperature sensor 4, the circulating water pump 7, the heating component 9, the second confluence valve 10, the flow meter 12, the solenoid valve 13, the water temperature sensor 14, the branch water temperature sensor 15, and the branch pressure sensor 16 are all electrically connected to the terminal controller 11.
[0027] The internal circulation loop of Test Component 1 should be arranged according to the actual vehicle layout to facilitate the reproduction of the real vehicle's warm-up transient operating conditions on the hybrid powertrain bench. If the inlet and outlet water control system of Test Component 1 uses a wax thermostat, the corresponding wax thermostat needs to be removed; if an electronic thermostat is used, the electronic thermostat needs to be fully open. The valve characteristics of the first confluence valve 3 and the solenoid valve 13 should be superior to the opening characteristics of the corresponding wax thermostat or temperature control system to ensure the authenticity of the coolant temperature rise of the entire system. The operating status of the circulating water pump 7 should be correlated with the operating status of the engine water pump inside Test Component 1. That is, when the engine water pump inside Test Component 1 is running, the circulating water pump 7 also runs; when the engine water pump inside Test Component 1 stops running, the circulating water pump 7 also stops running, thereby ensuring that the coolant state of the control system is consistent every time the engine starts and stops.
[0028] After the control system is powered on, the first inlet of the first confluence valve 3 is open and the second inlet is closed (i.e., the coolant flow direction is A→AB), and the solenoid valve 13 is at the preset initial opening. The flow rate of the entire system is regulated once through the mechanical ball valve 17 of the bypass branch to obtain the safe flow rate of the entire system. At this time, the entire system can perform coolant temperature and flow rate control under steady-state conditions.
[0029] like Figure 2 As shown, if the test component 1 needs to undergo vehicle steady-state operating condition simulation verification, the terminal controller 11 will perform the following steps: S11, control the first inlet of the first confluence valve 3 to open and the second inlet to close, control the solenoid valve 13 to maintain the preset initial opening, and then execute S12. The preset initial opening is the opening obtained through calibration that meets the flow requirements of the tested component 1 at idle speed.
[0030] S12. Determine whether there is coolant flow between the second inlet and outlet of the first confluence valve 3. If yes, return to execute S11; otherwise, execute S13. Specifically, if the branch water temperature detected by the branch water temperature sensor 15 rises and the branch water pressure detected by the branch pressure sensor 16 increases, it indicates that there is coolant circulating between the second inlet and outlet of the first confluence valve 3 (i.e., the coolant flow direction is B→AB).
[0031] S13. Based on T1, PID control is performed on the opening degree of the second confluence valve 10 (corresponding to the opening degree of the first inlet and the second inlet) and the heating power of the heating component 9. The opening degree of the solenoid valve 13 is controlled according to the preset engine speed MAP to meet the flow requirements of the hybrid powertrain under different speed conditions, thereby realizing temperature and flow control under steady-state conditions or actual vehicle hot-engine conditions, and then the process ends. Here, T1 is the outlet water temperature of the small circulation pipe inside the tested component 1 detected by the outlet water temperature sensor 2.
[0032] Under steady-state operating conditions, the coolant outlet of component 1 is pumped into the radiator 8 and heating element 9 via the first confluence valve 3 and the circulating water pump 7, and then returns to component 1 via the second confluence valve 10 and the solenoid valve 13. When the outlet water temperature sensor 2 detects that the outlet water temperature of the small circulation pipe inside component 1 has not reached the preset temperature, the terminal controller 11 performs PID control on the second confluence valve 10 and the heating element 9 until the outlet water temperature of the small circulation pipe inside component 1 reaches the preset temperature.
[0033] like Figure 3 As shown, if the test component 1 needs to undergo a full vehicle transient condition (such as WLTC) simulation verification, the terminal controller 11 performs the following steps: S21, control the first inlet of the first confluence valve 3 to close and the second inlet to open, control the solenoid valve 13 to close completely, and then execute S22.
[0034] S22. Determine whether there is coolant flow between the second inlet and outlet of the first confluence valve 3. If yes, execute S23; otherwise, return to execute S21.
[0035] S23. Perform PID control on the opening degree of the second confluence valve 10 (corresponding to the opening degree of the first inlet and the opening degree of the second inlet) and the heating power of the heating component 9 based on ΔT (the purpose is to maintain...). Figure 1 The temperature control section on the left side of the test component 1 is kept at the same temperature as the small circulation at any given time, and then S24 is executed. Here, ΔT = T1 - T2, where T2 is the circulating water temperature detected by the circulating water temperature sensor 4, and Tz is the preset warm-up end temperature threshold. The warm-up end temperature threshold is determined by the coolant circulation conditions of the test component 1, and can be referenced from the performance curve of a wax-type thermostat or the relevant characteristics of an electronic thermostat. The terminal controller 11 controls the heating power of the heating component 9 to ensure that the heating rate of the heating component 9 is greater than the temperature rise rate of the small circulation inside the test component 1, thereby achieving simultaneous opening and closing of both (two) circulations.
[0036] S24. Determine whether T1=T2=Tz (i.e., whether the outlet water temperature of the small circulation pipe inside the tested component is equal to the circulating water temperature and equal to the preset warm-up end temperature threshold). If yes, execute S25; otherwise, continue executing S24.
[0037] S25, control the first inlet of the first confluence valve 3 to open and the second inlet to close, control the solenoid valve 13 to return to the preset initial opening degree, and then end.
[0038] Figure 4 These are partial temperature control effects observed on a hybrid powertrain test bench during a WLTC cycle test. Figure 4As can be seen, regardless of steady-state or transient conditions, the system coolant temperature follows the corresponding real vehicle coolant temperature, thus maximally replicating the coolant temperature and flow control in the actual vehicle operation.
Claims
1. A coolant control system for bench testing of a hybrid powertrain, comprising a water temperature regulating device, a mechanical ball valve (17), and a terminal controller (11), wherein the mechanical ball valve (17) is located between the coolant circulation inlet and outlet of the water temperature regulating device; characterized in that: It also includes an outlet water temperature sensor (2), a first confluence valve (3), a circulating water temperature sensor (4), a solenoid valve (13), a replenishment tank (5), and a branch circulation monitoring device; the outlet water temperature sensor (2) is installed at the outlet of the small circulation pipe inside the test piece (1); the first inlet of the first confluence valve (3) is connected to the outlet of the test piece (1) through a pipe; the second inlet of the first confluence valve (3) is connected to the inlet of the solenoid valve (13) and the coolant circulation outlet of the water temperature regulating device through a pipe; the outlet of the first confluence valve (3) is connected to the coolant circulation inlet of the water temperature regulating device through a pipe; the circulating water temperature sensor (4) is installed between the first confluence valve (3) and the coolant circulation inlet of the water temperature regulating device; the branch circulation monitoring device is installed between the first confluence valve (3) and the solenoid valve (13); the outlet of the solenoid valve (13) is connected to the inlet of the test piece (1) and the replenishment tank (5). The outlet water temperature sensor (2), the first confluence valve (3), the circulating water temperature sensor (4), the solenoid valve (13), the branch circulation monitoring device, and the terminal controller (11) are electrically connected through pipelines. The water temperature regulating device includes a circulating water pump (7), a heating component (9), and a second confluence valve (10). The inlet of the circulating water pump (7) serves as the coolant circulation inlet of the water temperature regulating device and is connected to the outlet of the mechanical ball valve (17) through a pipeline. The outlet of the circulating water pump (7) is connected to the inlet of the heating component (9) through a pipeline, and the outlet of the heating component (9) is connected to the first inlet of the second confluence valve (10) through a pipeline. The outlet of the second confluence valve (10) serves as the coolant circulation outlet of the water temperature regulating device and is connected to the inlet of the mechanical ball valve (17) through a pipeline. The circulating water pump (7), the heating component (9), the second confluence valve (10), and the terminal controller (11) are electrically connected. If the test component (1) needs to be verified by vehicle transient operating condition simulation, the terminal controller (11) first controls the first inlet of the first confluence valve (3) to close and the second inlet to open, and controls the solenoid valve (13) to close completely; then, when the branch circulation monitoring device detects that there is coolant flow between the second inlet and outlet of the first confluence valve (3), the opening degree of the second confluence valve (10) and the heating power of the heating component (9) are controlled by PID according to ΔT; finally, when T1=T2=Tz, the first inlet of the first confluence valve (3) is opened and the second inlet is closed, and the solenoid valve (13) is restored to the preset initial opening degree; where T1 is the outlet water temperature of the small circulation pipe inside the test component (1) detected by the outlet water temperature sensor (2), T2 is the circulation water temperature detected by the circulation water temperature sensor (4), ΔT= T1-T2, and Tz is the preset warm-up end temperature threshold.
2. The coolant control system for bench testing of a hybrid powertrain according to claim 1, characterized in that: The branch circulation monitoring device is a branch water temperature sensor (15), which is electrically connected to the terminal controller (11).
3. The coolant control system for bench testing of a hybrid powertrain according to claim 1, characterized in that: The branch circulation monitoring device is a branch pressure sensor (16), which is electrically connected to the terminal controller (11).
4. The coolant control system for bench testing of a hybrid powertrain according to claim 1, characterized in that: The branch circulation monitoring device includes a branch water temperature sensor (15) and a branch pressure sensor (16), and the branch water temperature sensor (15) and the branch pressure sensor (16) are electrically connected to the terminal controller (11).
5. The coolant control system for bench testing of a hybrid powertrain according to claim 1, characterized in that: It also includes a flow meter (12), which is installed between the solenoid valve (13) and the coolant circulation outlet of the water temperature regulating device. The flow meter (12) is electrically connected to the terminal controller (11).
6. The coolant control system for bench testing of a hybrid powertrain according to claim 1, characterized in that: It also includes an inlet water temperature sensor (14), which is installed between the solenoid valve (13) and the measured component (1), and is electrically connected to the terminal controller (11).
7. The coolant control system for bench testing of a hybrid powertrain according to any one of claims 1 to 6, characterized in that: The water temperature regulating device also includes an expansion tank (6) and a radiator (8). The inlet of the circulating water pump (7) is connected to the expansion tank (6) through a pipeline, the outlet of the circulating water pump (7) is connected to the coolant inlet of the radiator (8) through a pipeline, and the coolant outlet of the radiator (8) is connected to the second inlet of the second confluence valve (10) through a pipeline.
8. The coolant control system for bench testing of a hybrid powertrain according to claim 7, characterized in that: The replenishment vessel (5) is connected to the expansion tank (6) through a pipeline, and the liquid level of the replenishment vessel (5) is the same as the liquid level of the expansion tank (6).
9. The coolant control system for bench testing of a hybrid powertrain according to claim 7, characterized in that: If the test component (1) needs to be verified by vehicle steady-state operation simulation, the terminal controller (11) first controls the first inlet of the first confluence valve (3) to open and the second inlet to close, and controls the solenoid valve (13) to maintain the preset initial opening. When the branch circulation monitoring device detects that there is no coolant flow between the second inlet and outlet of the first confluence valve (3), the opening degree of the second confluence valve (10) and the heating power of the heating component (9) are controlled by PID according to T1, and the opening degree of the solenoid valve (13) is controlled according to the preset engine speed MAP; wherein, the preset initial opening degree is the opening degree obtained by calibration to meet the flow requirements of the tested component (1) at idle speed.
Citation Information
Patent Citations
Water temperature and flow control system for engine pedestal
CN112284742A
Cooling fluid temperature and flow control device for engine bench test
CN204440208U
Automobile bench engine temperature control system and method, electronic equipment and storage medium
CN114526146A
Cooling control method and device for fuel cell engine and auxiliary machine
CN116072938A