A dynamic alarm method, device, equipment and storage medium

By dynamically adjusting the voltage value of the battery at different altitudes, it solves the problem of delayed or incorrect battery alarms under the influence of altitude in the existing technology, achieves more accurate and timely battery alarms, and improves the safety of the battery charging process.

CN117207844BActive Publication Date: 2024-10-01CHONGQING JINKANG NEW ENERGY VEHICLE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311290923.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-08
Publication Date
2024-10-01
Estimated Expiration
2043-10-08

AI Technical Summary

Technical Problem

Existing battery alarm methods fail to effectively consider the impact of altitude on battery charge and discharge performance, resulting in alarm delays or alarm errors that may occur at different altitudes, affecting battery safety.

Method used

By collecting the voltage value of the single battery during the charging process and detecting the actual altitude of the vehicle, the altitude difference is calculated and the voltage value is adjusted. The adjusted voltage value is compared with the alarm threshold to determine the target battery with charging failure, and Implement corresponding warning measures.

Benefits of technology

It achieves more timely and accurate battery alarms at different altitudes, reduces alarm sensitivity at high altitudes and alarm hysteresis at low altitudes, and improves the safety of the battery charging process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117207844B_ABST
    Figure CN117207844B_ABST
Patent Text Reader

Abstract

The present application relates to a dynamic alarm method, device, equipment and storage medium. The dynamic alarm method includes: collecting the voltage value of each single battery during the charging process and detecting the actual altitude of the vehicle; calculating the difference between the actual altitude and the standard altitude, and using the difference to adjust the voltage value of each single battery to reduce the voltage value at high altitudes, or increase the voltage value at low altitudes; comparing the adjusted voltage value of each single battery with the alarm threshold in turn to determine the target battery with a charging fault, and after determining the target battery, executing the alarm measures. By adopting the dynamic alarm method provided by the present application, the voltage value of the single battery when charging at different altitudes can be dynamically adjusted, so that based on the adjusted voltage value, more timely and accurate alarms can be achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of new energy vehicle technology, and in particular to a dynamic alarm method, device, equipment and storage medium. Background Art

[0002] Battery safety is very important for new energy vehicles. In order to detect voltage abnormalities during charging in a timely manner, the voltage value of the single battery during charging can be monitored, and an alarm can be issued when the voltage value is too high.

[0003] However, the current alarm method is relatively simple and does not provide alarms for different altitudes. This is because those skilled in the art generally believe that altitude has no effect on the charge and discharge performance of the battery. However, the inventors of this application have discovered that, in fact, the charge and discharge performance of the battery will be affected as the altitude changes. If a single alarm method is used at different altitudes, it may cause alarm delays or alarm errors, thereby causing battery safety accidents. Summary of the invention

[0004] Based on this, the present application provides a dynamic alarm method, device, equipment and storage medium, which can dynamically adjust the voltage value of a single battery when charging at different altitudes, so that based on the adjusted voltage value, a more timely and accurate alarm can be achieved.

[0005] In a first aspect, the present application provides a dynamic alarm method for application in an in-vehicle scenario, the dynamic alarm method comprising: collecting the voltage value of each single cell during the charging process, and detecting the actual altitude of the vehicle; calculating the difference between the actual altitude and the standard altitude, and using the difference to adjust the voltage value of each single cell to reduce the voltage value at high altitudes, or to increase the voltage value at low altitudes; comparing the adjusted voltage value of each single cell with the alarm threshold in turn to determine the target battery with a charging fault, and executing alarm measures after determining the target battery.

[0006] In combination with the first aspect, in a first possible implementation manner of the first aspect, the aforementioned use of the difference to adjust the voltage value of each single cell includes: determining the adjustment coefficient corresponding to the type of the single cell, wherein the types include lithium iron phosphate batteries and ternary lithium batteries, and the adjustment coefficient of the ternary lithium battery is greater than the adjustment coefficient of the lithium iron phosphate battery; and adjusting the voltage value of each single cell using the product of the adjustment coefficient and the difference.

[0007] In combination with the first possible implementation of the first aspect, in the second possible implementation of the first aspect, the mathematical expression for adjusting the voltage value of each single cell using the product of the adjustment coefficient and the difference includes: V_corrected = V_measured - K × H; wherein V_corrected is the adjusted voltage value, V_measured is the collected voltage value, K is the adjustment coefficient, and K is a positive number, and H is the difference between the actual altitude and the standard altitude.

[0008] In combination with the first aspect, in a third possible implementation manner of the first aspect, the aforementioned comparing the adjusted voltage value of each single cell with the alarm threshold in turn to determine the target battery with a charging fault includes: comparing the adjusted voltage value of each single cell with the alarm threshold in turn to compare the abnormal battery with charging abnormality, wherein the adjusted voltage value of the abnormal battery is greater than the alarm threshold; judging whether the abnormal battery has a history of charging failure, if a charging failure has occurred and the number of abnormalities in this charging process is greater than the first number, or if no charging failure has occurred and the number of abnormalities is greater than the second number, then determining that the abnormal battery is a target battery with a charging failure; wherein the number of abnormalities is the number of times the abnormal battery has an abnormality in this charging process, and the first number is less than the second number.

[0009] In combination with the third possible implementation method of the first aspect, in the fourth possible implementation method of the first aspect, after determining whether the abnormal battery has a history of overcharging failure, the above also includes: if no overcharging failure has occurred, obtaining a preset number threshold as the first number; if an overcharging failure has occurred, lowering the minimum number threshold to obtain a second number, wherein the minimum number threshold is the minimum value of the number thresholds historically set for the abnormal battery.

[0010] In combination with the first aspect, in a fifth possible implementation of the first aspect, the aforementioned execution of alarm measures includes: obtaining a set of abnormal voltage values ​​of the target battery during this charging process, wherein each abnormal voltage value in the set is an adjusted voltage value, and each abnormal voltage value is greater than an alarm threshold; determining, from multiple alarm intervals, a target alarm interval to which the maximum voltage value in the set belongs, or determining a target alarm interval in which all abnormal voltage values ​​in the set are most concentrated; and executing alarm measures corresponding to the target alarm interval.

[0011] In combination with the fifth possible implementation method of the first aspect, in the sixth possible implementation method of the first aspect, the alarm measures corresponding to the aforementioned target alarm interval include: if the target alarm interval is the first alarm interval, prompting the user to continue observing; if the target alarm interval is the second alarm interval, stopping charging and prompting the user to continue observing; if the target alarm interval is the third alarm interval, stopping charging, sending the number of the target battery with charging failure to the after-sales management system, and prompting the user to contact after-sales processing as soon as possible.

[0012] On the second aspect, the present application also provides a dynamic alarm device, which includes: a collection unit, used to collect the voltage value of each single battery during the charging process and detect the actual altitude of the vehicle; an adjustment unit, used to calculate the difference between the actual altitude and the standard altitude, and use the difference to adjust the voltage value of each single battery to reduce the voltage value at high altitude, or increase the voltage value at low altitude; an alarm unit, used to compare the adjusted voltage value of each single battery with the alarm threshold in turn to determine the target battery with a charging fault, and after determining the target battery, execute alarm measures.

[0013] In combination with the second aspect, in a first possible implementation manner of the second aspect, the adjustment unit is specifically used to: determine the adjustment coefficient corresponding to the type of single cell battery, wherein the types include lithium iron phosphate batteries and ternary lithium batteries, and the adjustment coefficient of the ternary lithium battery is greater than the adjustment coefficient of the lithium iron phosphate battery; and adjust the voltage value of each single cell battery using the product of the adjustment coefficient and the difference.

[0014] In combination with the first feasible embodiment of the second aspect, in the second feasible embodiment of the second aspect, the adjustment unit is specifically used for: V_corrected=V_measured-K×H; wherein, V_corrected is the adjusted voltage value, V_measured is the collected voltage value, K is the adjustment coefficient, and K is a positive number, and H is the difference between the actual altitude and the standard altitude.

[0015] In combination with the second aspect, in a third possible implementation manner of the second aspect, the alarm unit is specifically used to: compare the adjusted voltage value of each single battery with the alarm threshold in turn to identify the abnormal battery with charging abnormality, wherein the adjusted voltage value of the abnormal battery is greater than the alarm threshold; determine whether the abnormal battery has a history of overcharging failure, if an overcharging failure has occurred and the number of abnormalities in this charging process is greater than the first number, or if no overcharging failure has occurred and the number of abnormalities is greater than the second number, then determine that the abnormal battery is a target battery with a charging failure; wherein the number of abnormalities is the number of times the abnormal battery has an abnormality in this charging process, and the first number is less than the second number.

[0016] In combination with the third possible implementation mode of the second aspect, in the fourth possible implementation mode of the second aspect, the alarm unit is also used to: if no overcharging failure occurs, obtain a preset number threshold as the first number; if an overcharging failure occurs, lower the minimum number threshold to obtain the second number, wherein the minimum number threshold is the minimum value of the number thresholds set in the abnormal battery history.

[0017] In combination with the second aspect, in a fifth possible implementation manner of the second aspect, the alarm unit is specifically used to: obtain a set of abnormal voltage values ​​of the target battery during the current charging process, wherein each abnormal voltage value in the set is an adjusted voltage value, and each abnormal voltage value is greater than an alarm threshold; determine, from multiple alarm intervals, a target alarm interval to which the maximum voltage value in the set belongs, or determine a target alarm interval in which all abnormal voltage values ​​in the set are most concentrated; and execute alarm measures corresponding to the target alarm interval.

[0018] In combination with the fifth possible implementation method of the second aspect, in the sixth possible implementation method of the second aspect, the alarm unit is specifically used for: if the target alarm interval is the first alarm interval, prompting the user to continue observing; if the target alarm interval is the second alarm interval, stopping charging and prompting the user to continue observing; if the target alarm interval is the third alarm interval, stopping charging, sending the number of the target battery with charging failure to the after-sales management system, and prompting the user to contact after-sales processing as soon as possible.

[0019] In a third aspect, the present application also provides a dynamic alarm device, which includes a processor and a memory, and the processor and the memory are connected via a bus; the processor is used to execute multiple instructions; the memory is used to store multiple instructions, and the instructions are suitable for being loaded by the processor and executed by a dynamic alarm method such as the first aspect or any one of the embodiments of the first aspect.

[0020] In a fourth aspect, the present application further provides a computer-readable storage medium, in which a plurality of instructions are stored, and the instructions are suitable for being loaded by a processor and executed by a dynamic alarm method such as the first aspect or any one embodiment of the first aspect.

[0021] In summary, the present application proposes a dynamic alarm method, device, equipment and storage medium, wherein the dynamic alarm method first adjusts the voltage value of each single cell based on the difference between the actual altitude and the standard altitude, so as to reduce the voltage value at high altitude, thereby reducing the alarm sensitivity at high altitude, or increase the voltage value at low altitude, thereby increasing the alarm sensitivity at low altitude, and then compares the adjusted voltage value of each single cell with the alarm threshold in turn to determine the target battery with charging fault, and finally, after determining the target battery, an alarm is issued and an alarm measure is executed. It can be seen that the present application dynamically adjusts the voltage value of the single cell when charging at different altitudes, so that based on the adjusted voltage value, a more timely and accurate alarm can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 A schematic flow chart of a dynamic alarm method in an embodiment of the present application;

[0023] Figure 2 A schematic block diagram of a dynamic alarm device in an embodiment of the present application;

[0024] Figure 3 This is a structural block diagram of a dynamic alarm device in an embodiment of the present application. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0026] At present, those skilled in the art generally believe that the altitude has no effect on the charge and discharge performance of the battery, but the inventors of this application have found through testing that the charge and discharge performance of the battery is actually affected by the altitude: on the one hand, the altitude will affect the charge and discharge performance of the battery by affecting the oxygen content of the air. Although the battery is sealed, the battery cannot be completely isolated from the air exchange with the external environment, and the oxygen content of the air decreases with the increase of the altitude, which makes the reaction speed of the battery at high altitudes decrease, and the reaction speed at low altitudes increases; on the other hand, the altitude will affect the charge and discharge performance of the battery by affecting the thermal performance of the battery. Since the activity of the battery is affected by the temperature, and the ambient temperature decreases with the increase of the altitude, the reaction speed of the battery at high altitudes decreases, and the reaction speed at low altitudes increases. In addition, it should be noted that although the heat dissipation of the battery will deteriorate due to the decrease in air pressure, thereby increasing the temperature to a certain extent, the heat dissipation problem caused by the decrease in air pressure on the battery temperature is not as good as the environmental cooling problem caused by the decrease in air pressure on the battery temperature, and the inventors of this application have found through actual testing that the overall temperature of the battery decreases with the increase in altitude.

[0027] Therefore, the battery's charge and discharge performance will be affected by the altitude, especially when the thermal management system is not effective or fails. As the altitude increases, the battery's activity decreases, and the battery's reaction speed during charging decreases as the altitude increases, so the voltage rises slowly. Since the current alarm method is relatively simple and does not consider the impact of different altitudes on the battery's charge and discharge performance, at low altitudes, the battery voltage may rise quickly and the alarm may not be issued in time, resulting in a phenomenon of alarm hysteresis. At high altitudes, the battery voltage may rise slowly and the alarm may be issued too early, resulting in a false alarm.

[0028] In this regard, the present application provides a dynamic alarm method, specifically: collecting the voltage value of each single battery during the charging process and detecting the actual altitude of the vehicle; calculating the difference between the actual altitude and the standard altitude, and using the difference to adjust the voltage value of each single battery to reduce the voltage value at high altitudes, or increase the voltage value at low altitudes; comparing the adjusted voltage value of each single battery with the alarm threshold in turn to determine the target battery with a charging fault, and after determining the target battery, executing the alarm measures.

[0029] It should be noted that, since the voltage boost speed of the battery at high altitude is relatively slow compared to the standard altitude, in order to reduce the alarm error caused by the slow voltage boost when the battery is charged at high altitude, as well as the battery undervoltage or other safety problems caused by the alarm error, the dynamic alarm method provided by the present application adjusts the voltage value of the single battery at high altitude to be relatively low, thereby reducing the alarm sensitivity at high altitude. On the contrary, since the voltage boost speed of the battery at low altitude is relatively fast compared to the standard altitude, in order to reduce the alarm hysteresis problem caused by the fast voltage boost when the battery is charged at low altitude, as well as the battery overcharge and other safety problems caused by the alarm hysteresis problem, the dynamic alarm method provided by the present application adjusts the voltage value of the single battery at low altitude to be relatively high, thereby improving the alarm sensitivity at low altitude. It can be seen that since the dynamic alarm method provided by the present application dynamically adjusts the voltage value of the single battery at different altitudes, more timely and accurate alarms can be achieved based on the adjusted voltage value. This application can be especially applied to the scenario where the thermal management system is not effective or fails, because when the thermal management system is effective and not failed, the thermal management system can adjust the temperature of the battery, thereby reducing the impact of altitude on the charging performance of the battery cell. When the thermal management system is not effective or fails, the battery cannot adjust the temperature autonomously, and it is easy to have problems such as alarm hysteresis and alarm error. Therefore, when the dynamic alarm method of this application is applied in the scenario where the thermal management system is not effective or fails, a more significant effect can be achieved.

[0030] It should also be noted that the dynamic alarm device and dynamic alarm equipment proposed in this application can be a cloud server or a vehicle-mounted terminal, such as a controller specifically used for alarms, or a battery management system (Battery Management System, BMS), etc. This application does not limit this. In addition, the dynamic alarm device and dynamic alarm equipment can communicate with other devices or servers, and execute the dynamic alarm method proposed in this application.

[0031] In order to better understand the dynamic alarm method of this application, Figure 1 As shown, the present application provides an embodiment of a dynamic alarm method. Next, the present application will take the dynamic alarm device as the execution subject to Figure 1 The dynamic alarm described is explained below, specifically:

[0032] 101: Collect the voltage value of each single battery during the charging process and detect the actual altitude of the vehicle.

[0033] Among them, the dynamic alarm device collects the voltage values ​​U1, U2, U3...Un of n (n≥2) single cells in the battery pack in real time during the entire charging process from the start of charging to the end of charging, in units of V (volts), and the collection period can be a fixed value, such as collecting once per second. In addition, in order to improve the accuracy of the collected voltage value, and thus improve the accuracy of the alarm, after collecting the voltage value of each single cell, the dynamic alarm device can also filter out invalid data in the voltage value of each single cell, including filtering out data whose voltage value exceeds the measurable range of the voltage measuring device, and further determining the corresponding measurable range according to the type of the single cell, for example, when the single cell is a lithium iron phosphate battery, filter out data whose voltage value is greater than 3.9V or less than 1.0V, and when the single cell is a ternary lithium battery, filter out data whose voltage value is greater than 4.8V or less than 1.0V.

[0034] It should be noted that if the dynamic alarm device is a vehicle-mounted terminal, the actual altitude of the vehicle can be detected by an altimeter. If an altimeter is not installed on the vehicle, or in order to obtain more accurate data, the vehicle's Global Positioning System (GPS) position data can be uploaded to the cloud server in real time. The cloud server will query the altitude data corresponding to the longitude and latitude points in the vehicle's GPS position data in the built-in three-dimensional map database to obtain the actual altitude of the vehicle.

[0035] It should also be noted that the dynamic alarm device can determine whether to trigger or stop collecting the voltage value of the single cell according to the charging state of the single cell. Taking plug-in charging as an example, when the single cell is in an uncharged state, the charging state of the AC charging port is AC_ChargeState=0, and the charging state of the DC charging port is DC_ChargeState=0, when the single cell is in a charging state, the charging state of the AC charging port is AC_ChargeState=1, or the charging state of the DC charging port is DC_ChargeState=1, when the single cell is in a charging complete state, the charging state of the AC charging port is AC_ChargeState=2, and the charging state of the DC charging port is DC_ChargeState=2; based on the various charging states of the charging port, the dynamic alarm device can trigger or stop collecting the voltage value of the single cell when detecting a jump in the charging state of the single cell, that is, triggering the collection of the voltage value of the single cell when the charging state of the AC charging port or the DC charging port changes from 0 to 1, and stopping the collection of the voltage value of the single cell when the charging state of the AC charging port or the DC charging port changes from 1 to 2.

[0036] In another practicable manner, if the vehicle uses a range extender to charge a single battery while in motion, the dynamic alarm device can also monitor the actual altitude of the vehicle in real time. Accordingly, in this embodiment, the dynamic alarm device can trigger monitoring of the actual altitude of the vehicle when it detects that the single battery is in the charging process and the car is in motion, and stop monitoring the actual altitude of the vehicle when the single battery is finished charging and / or the car is in a stationary state. In addition, the dynamic alarm device can also determine that the car is in motion when it detects that the vehicle speed is greater than the vehicle speed threshold and / or the vehicle's climbing speed is greater than the climbing threshold.

[0037] Correspondingly, when the vehicle is in motion, the collection period can also be a variable value determined according to the rate of change of the vehicle speed or the actual altitude. The faster the vehicle speed or the rate of change of the actual altitude, the shorter the collection period is, so as to ensure the real-time collection and the accuracy of subsequent alarms.

[0038] 102: Calculate the difference between the actual altitude and the standard altitude, and use the difference to adjust the voltage value of each single battery, so as to reduce the voltage value at a high altitude or increase the voltage value at a low altitude.

[0039] Among them, after the dynamic alarm device calculates the difference between the actual altitude and the standard altitude, it uses the difference to adjust the voltage value of each single cell, that is, at high altitudes, the adjusted voltage value is adjusted downward to reduce the alarm sensitivity at high altitudes, or at low altitudes, the adjusted voltage value is adjusted upward to increase the alarm sensitivity at low altitudes. Specifically: when the difference is greater than zero, the voltage value of each single cell is adjusted downward, or when the difference is less than zero, the voltage value of each single cell is adjusted upward to obtain the adjusted voltage value.

[0040] It should be noted that the standard altitude can be any value, such as a few meters to two kilometers, and the alarm threshold corresponds to the standard altitude, which is a calibration value obtained by testing at the standard altitude. When the vehicle is at the standard altitude, the alarm threshold can be used to issue a timely and accurate alarm. For example, the standard alarm threshold of a lithium iron phosphate battery can be 3.7V, and the standard alarm threshold of a ternary lithium battery can be 4.4V.

[0041] It should also be noted that the degree of adjustment is proportional to the aforementioned difference. The greater the difference, the higher the degree of adjustment. In an operative manner, the mathematical expression for adjusting the voltage value of each single cell by multiplying the adjustment coefficient and the difference includes: V_corrected = V_measured - K × H; wherein V_corrected is the adjusted voltage value, V_measured is the collected voltage value, K is the adjustment coefficient, and K is a positive number, and H is the difference between the actual altitude and the standard altitude. This embodiment provides a specific adjustment method, which uses the product of the difference H and the adjustment coefficient K to determine the degree of adjustment. It should be noted that since the adjustment coefficient K is a positive value, when the difference H is a positive value, that is, when the actual altitude is greater than the standard altitude, K × H is adjusted downward on the basis of the collected voltage value to obtain the voltage value of each single cell at a high altitude; when the difference H is a negative value, that is, when the actual altitude is less than the standard altitude, K × H is adjusted upward on the basis of the collected voltage value to obtain the voltage value of each single cell at a low altitude.

[0042] It should also be noted that different types of batteries may correspond to different adjustment coefficients. In order to obtain a more accurate adjustment coefficient, the dynamic alarm device can first determine the adjustment coefficient corresponding to the type of single cell, and then use the adjustment coefficient to calculate the adjusted alarm threshold. In an implementable manner, the aforementioned use of the difference to adjust the voltage value of each single cell includes: determining the adjustment coefficient corresponding to the type of single cell, wherein the type includes lithium iron phosphate battery and ternary lithium battery, and the adjustment coefficient of the ternary lithium battery is greater than the adjustment coefficient of the lithium iron phosphate battery; and adjusting the voltage value of each single cell by multiplying the adjustment coefficient and the difference. In this embodiment, because it is found through actual tests that the properties of lithium iron phosphate batteries are more stable, while ternary lithium batteries are more easily affected by altitude, as the altitude increases, the voltage rise rate of the ternary lithium battery is faster than that of the lithium iron phosphate battery, so the adjustment coefficient of the ternary lithium battery needs to be greater than the adjustment coefficient of the lithium iron phosphate battery.

[0043] It should also be noted that the adjustment coefficients corresponding to different models of batteries produced by different manufacturers may also be different. The adjustment coefficient can be a preset calibration value, and the specific value is obtained by fitting the measured data. Specifically: first detect the voltage value of the single battery that needs to be alarmed at different actual altitudes, then take the voltage value that needs to be alarmed at the actual altitude as V_corrected, take the voltage value that needs to be alarmed at the standard altitude (i.e., the alarm threshold) as V_measured, and calculate the difference between the actual altitude and the standard altitude, fit the voltage value that needs to be alarmed at different actual altitudes, and obtain the functional relationship between V_corrected and V_measured, and H V_corrected = V_measured-K×H, so as to obtain the specific value of the adjustment parameter K in the functional relationship. It should be noted that the voltage value that needs to be alarmed refers to: if the dynamic alarm device immediately triggers the process of detecting the target battery with charging fault when detecting the voltage value that needs to be alarmed, then the dynamic alarm device can detect the battery that does have a charging fault, and when the voltage value of the battery continues to rise at the current rising rate, there is enough time to ensure that the dynamic alarm device executes the alarm measures. It can be seen that based on the adjustment coefficient provided in this application, the accuracy of alarms can be improved, making alarms more timely and accurate.

[0044] 103: Compare the regulated voltage value of each single battery with the alarm threshold in sequence to determine the target battery with charging failure, and execute alarm measures after determining the target battery.

[0045] Among them, the dynamic alarm device compares the adjusted voltage value of each single cell with the alarm threshold in turn. If there is a single cell whose adjusted voltage value is greater than the alarm threshold, it can be determined that the single cell is a target battery with a charging fault, or the single cell can be first identified as an abnormal battery, and then further determined how many times the single cell is identified as an abnormal battery during this charging process (i.e., the number of times the voltage value is greater than the adjusted alarm threshold), and the number of times is used to determine whether the single cell is a target battery with a charging fault, and if so, the alarm measures are executed. In addition, the target battery number can also be output and uploaded to the cloud server to help technicians quickly determine the fault point, thereby achieving rapid maintenance, or as a basis for determining whether the single cell has a charging fault in the past.

[0046] In an implementable manner, in order to improve the accuracy of the alarm, the dynamic alarm device can also obtain different number thresholds according to whether the abnormal battery has a history of overcharging failure. For example, in the case where the abnormal battery has a history of overcharging failure, a first number with a smaller value is obtained as the number threshold, and in the case where the abnormal battery has not had a history of overcharging failure, a second number with a larger value is obtained as the number threshold. Specifically, the aforementioned step of comparing the adjusted voltage value of each single battery with the alarm threshold in turn to determine the target battery with a charging failure includes: comparing the adjusted voltage value of each single battery with the alarm threshold in turn to compare the abnormal battery with charging abnormality, wherein the adjusted voltage value of the abnormal battery is greater than the alarm threshold; judging whether the abnormal battery has a history of overcharging failure, if an overcharging failure occurs and the number of abnormalities in this charging process is greater than the first number, or if no overcharging failure occurs and the number of abnormalities is greater than the second number, then determining the abnormal battery as a target battery with a charging failure; wherein the number of abnormalities is the number of times the abnormal battery has an abnormality in this charging process, and the first number is less than the second number.

[0047] For example, assuming that the adjusted voltage value of single cell battery x is greater than the alarm threshold, then single cell battery x is determined to be an abnormal battery with charging abnormality, and then it is determined whether single cell battery x has had an overcharging failure in at least one charging process in the history. If single cell battery x has had an overcharging failure in the history, the number of times single cell battery x is determined to be an abnormal battery in this charging process (the number of times it is determined to be an abnormal battery, that is, the number of times the adjusted voltage value is greater than the alarm threshold) is compared with the first number (for example, 3 times). If the number of times single cell battery x is determined to be an abnormal battery in this charging process is less than or equal to the first number, then it is determined that single cell battery x has not had a charging failure. On the contrary, if single cell battery x is determined to be an abnormal battery in this charging process, If the number of times the single cell x is determined to be an abnormal battery is greater than the first number, the single cell x is determined to be a target battery with a charging fault; in addition, if the single cell x has not had a charging fault in history, the number of times the single cell x is determined to be an abnormal battery in this charging process (the number of times it is determined to be an abnormal battery, i.e., the number of times the adjusted voltage value is greater than the alarm threshold) is compared with the second number (e.g., 5 times). If the number of times the single cell x is determined to be an abnormal battery in this charging process is less than or equal to the second number, it is determined that the single cell x has not had a charging fault. On the contrary, if the number of times the single cell x is determined to be an abnormal battery in this charging process is greater than the second number, it is determined that the single cell x is a target battery with a charging fault. In addition, when determining whether the abnormal battery has had a charging fault in history, it is also possible to query whether the abnormal battery has been determined to be a target battery with a charging fault within the most recent preset time (e.g., 30 days). If so, it is determined that the abnormal battery has had a charging fault in history. On the contrary, it is determined that the abnormal battery has not had a charging fault in history.

[0048] Furthermore, in order to determine the first number and the second number, the dynamic alarm device can also directly obtain the standard number threshold, or lower the minimum value to obtain it. Specifically, after determining whether the abnormal battery has a history of overcharging failure, it also includes: if no overcharging failure has occurred, then obtain the preset number threshold as the first number; if an overcharging failure has occurred, then lower the minimum number threshold to obtain the second number, wherein the minimum number threshold is the minimum value of the number thresholds that have been set in the history of the abnormal battery. In this embodiment, the standard number threshold is also adjusted according to whether the abnormal battery has a history of overcharging failure to obtain the first number and the second number of the abnormal battery, and the first number is always kept smaller than the second number, because abnormal batteries that have had a history of failure are prone to failure again, so relative to abnormal batteries that have not had a history of overcharging failure, a lower number threshold needs to be set.

[0049] For example, as the number of charging failures increases, the number threshold corresponding to the single cell becomes smaller. For example, assuming that when the single cell X has not had a charging failure, a preset number threshold N1 is obtained as the first number, and then after the first charging failure occurs, N1 is lowered to obtain N2 to obtain the second number, and then after the second charging failure occurs, N2 is lowered to obtain N3 to obtain the third number... until the number decreases to zero, prompting the technician to replace the single cell and disable the single cell.

[0050] In one implementable manner, the dynamic alarm device can also execute different alarm measures according to the alarm interval in which the adjusted voltage value is located, thereby reducing the occurrence of battery overcharging and damage and improving the safety and service life of the battery. Specifically, the aforementioned execution of alarm measures includes: obtaining a set of abnormal voltage values ​​of the target battery during the current charging process, wherein each abnormal voltage value in the set is an adjusted voltage value, and each abnormal voltage value is greater than the alarm threshold; from multiple alarm intervals, determining the target alarm interval to which the maximum voltage value in the set belongs, or determining the target alarm interval in which all abnormal voltage values ​​in the set are most concentrated; and executing the alarm measures corresponding to the target alarm interval.

[0051] When executing the alarm measure, the dynamic alarm device first obtains all the adjusted voltage values ​​in the current charging process, and selects the abnormal voltage values ​​greater than the alarm threshold value to obtain a set of abnormal voltage values, and then determines the maximum voltage value from the set (the maximum voltage value is the abnormal voltage value with the largest value in the set), and determines the target alarm interval where the maximum voltage value is located from multiple alarm intervals. For example, the dynamic alarm device collects multiple voltage values ​​of the single cell x in the current charging process. Voltage values ​​Ux1, Ux2, Ux3...Uxm, first adjust the multiple voltage values ​​to obtain Ux1', Ux2', Ux3'...Uxm', filter out the voltage values ​​whose values ​​are greater than the alarm threshold, and obtain a set of abnormal voltage values ​​Ux2', Ux3' and Ux5'. Assuming that Ux3' is the maximum voltage value in the set, first determine that the alarm interval where Ux3' is located is the second alarm interval, and then use the second alarm interval where Ux3' is located as the target alarm interval. In addition, the dynamic alarm device can also determine the target alarm interval in which all abnormal voltage values ​​in the set are most concentrated from multiple alarm intervals. For example, in the set of the aforementioned abnormal voltage values ​​Ux2', Ux3' and Ux5', Ux2' and Ux3' are both in the second alarm interval, while Ux5' is in the first alarm interval. Therefore, it can be determined that the second alarm interval contains the most abnormal voltage values, that is, it is the alarm interval with the most concentrated abnormal voltage values. Therefore, the second alarm interval is used as the target alarm interval. After determining the target alarm interval, the dynamic alarm device executes the measures corresponding to the target alarm interval. This application does not limit the specific measures, but in the order of intervals from small to large, the urgency of the alarm measures in the first interval, the alarm measures in the second interval, and the alarm measures in the third interval increase in sequence.

[0052] It should be noted that this embodiment can be applied to the scenario where the car generates electricity while in motion. In this scenario, the dynamic alarm device can collect the voltage value of each single battery at different altitudes during a charging process. Since the present application can adjust the voltage value of the single battery at different altitudes, the voltage values ​​adjusted at different altitudes are comparable. Therefore, by statistically analyzing and comparing the voltage values ​​adjusted at different altitudes, the target alarm interval can be determined.

[0053] It should also be noted that there is no overlap between the aforementioned multiple intervals and after merging, they form a complete and continuous large interval. The lower limit value of the minimum interval is the alarm threshold, and the upper limit value of the maximum interval is the maximum value of the measurable range. The present application does not limit the specific data of the aforementioned multiple alarm intervals, and different types of batteries can correspond to different multiple alarm intervals. Taking the aforementioned multiple alarm intervals as three alarm intervals as an example, assuming that the intervals are arranged in order from small to large, the aforementioned multiple alarm intervals include a first alarm interval, a second alarm interval, and a third alarm interval. The lower limit value of the first alarm interval is the alarm threshold, and the upper limit value of the third alarm interval is the maximum value of the measurable range. The three alarm intervals corresponding to the lithium iron phosphate battery and the ternary lithium battery are as follows:

[0054] Warning interval Lithium iron phosphate battery Ternary lithium battery First warning interval (3.7,3.75] (4.4,4.43] Second warning interval (3.75,3.78] (4.43,4.46] The third warning interval (3.78,3.9] (4.46,4.8]

[0055] More specifically, the alarm measures corresponding to the aforementioned target alarm interval include: if the target alarm interval is the first alarm interval, prompting the user to continue observing; if the target alarm interval is the second alarm interval, stopping charging and prompting the user to continue observing; if the target alarm interval is the third alarm interval, stopping charging, sending the number of the target battery with charging failure to the after-sales management system, and prompting the user to contact after-sales as soon as possible.

[0056] The present application also provides a dynamic alarm device, such as Figure 2 As shown. The embodiment of the present application can divide the functional modules of the device according to the above method example. For example, each functional module can be divided according to each function, or two or more functions can be integrated into one module. The above integrated modules can be implemented in the form of hardware or in the form of software functional modules. It should be noted that the division of modules in the embodiment of the present application is schematic and is only a logical function division. There may be other division methods in actual implementation. Specifically, Figure 2 As shown, the dynamic alarm device includes: a collection unit 210, which is used to collect the voltage value of each single battery during the charging process and detect the actual altitude of the vehicle; an adjustment unit 220, which is used to calculate the difference between the actual altitude and the standard altitude, and use the difference to adjust the voltage value of each single battery to reduce the voltage value at a high altitude, or increase the voltage value at a low altitude; an alarm unit 230, which is used to compare the adjusted voltage value of each single battery with the alarm threshold in turn to determine the target battery with a charging fault, and after determining the target battery, execute the alarm measure.

[0057] In another practicable manner, the adjustment unit 220 is specifically used to: determine the adjustment coefficient corresponding to the type of single cell battery, wherein the types include lithium iron phosphate batteries and ternary lithium batteries, and the adjustment coefficient of the ternary lithium battery is greater than the adjustment coefficient of the lithium iron phosphate battery; and adjust the voltage value of each single cell battery by multiplying the adjustment coefficient by the difference.

[0058] In another practicable manner, the adjustment unit 220 is used for: V_corrected=V_measured-K×H; wherein V_corrected is the adjusted voltage value, V_measured is the collected voltage value, K is the adjustment coefficient, and K is a positive number, and H is the difference between the actual altitude and the standard altitude.

[0059] In another practicable manner, the alarm unit 230 is specifically used to: compare the adjusted voltage value of each single cell with the alarm threshold in turn to identify the abnormal battery with charging abnormality, wherein the adjusted voltage value of the abnormal battery is greater than the alarm threshold; determine whether the abnormal battery has a history of overcharging failure, if an overcharging failure has occurred and the number of abnormalities in this charging process is greater than the first number, or if no overcharging failure has occurred and the number of abnormalities is greater than the second number, then determine that the abnormal battery is a target battery with a charging failure; wherein the number of abnormalities is the number of times the abnormal battery has an abnormality in this charging process, and the first number is less than the second number.

[0060] In another practicable manner, the alarm unit 230 is also used to: if no overcharging failure occurs, obtain a preset number threshold as the first number; if an overcharging failure occurs, lower the minimum number threshold to obtain a second number, wherein the minimum number threshold is the minimum value of the number thresholds set in the abnormal battery history.

[0061] In another practicable manner, the alarm unit 230 is specifically used to: obtain a set of abnormal voltage values ​​of the target battery during the current charging process, wherein each abnormal voltage value in the set is an adjusted voltage value and each abnormal voltage value is greater than an alarm threshold; determine, from multiple alarm intervals, a target alarm interval to which the maximum voltage value in the set belongs, or determine a target alarm interval in which all abnormal voltage values ​​in the set are most concentrated; and execute alarm measures corresponding to the target alarm interval.

[0062] In another implementable manner, the alarm unit 230 is specifically used for: if the target alarm interval is the first alarm interval, prompting the user to continue observing; if the target alarm interval is the second alarm interval, stopping charging and prompting the user to continue observing; if the target alarm interval is the third alarm interval, stopping charging, sending the number of the target battery with charging failure to the after-sales management system, and prompting the user to contact after-sales as soon as possible.

[0063] This application also provides a dynamic alarm device, see Figure 3 As shown in the figure, the dynamic warning device in this embodiment may include: a processor 310 and a memory 320. The processor 310, the transceiver 320 and the memory 320 are connected via a bus 330. The processor 310 is used to execute multiple instructions; the memory 320 is used to store multiple instructions, which are suitable for the processor 310 to load and execute the dynamic warning method applied to the in-vehicle scene in the above embodiment.

[0064] The processor 310 may be an electronic control unit (ECU), a central processing unit (CPU), a general processor, a coprocessor, a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, transistor logic devices, hardware components or any combination thereof. The processor 310 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of 5SP and a microprocessor, etc. In this embodiment, the processor 310 may be a single-chip microcomputer, and various control functions may be implemented by programming the single-chip microcomputer. The processor has the advantages of powerful computing power and fast processing. Specifically, the processor 310 is used to execute the function of the acquisition unit 210, which is used to collect the voltage value of each single battery during the charging process and detect the actual altitude of the vehicle; it is also used to execute the function of the adjustment unit 220, which is used to calculate the difference between the actual altitude and the standard altitude, and use the difference to adjust the voltage value of each single battery to reduce the voltage value at high altitude, or increase the voltage value at low altitude; it is also used to execute the function of the alarm unit 230, which is used to compare the adjusted voltage value of each single battery with the alarm threshold in turn to determine the target battery with the charging fault, and after determining the target battery, execute the alarm measures.

[0065] In another practicable manner, the processor 310 is specifically used to: determine the adjustment coefficient corresponding to the type of single cell battery, wherein the types include lithium iron phosphate battery and ternary lithium battery, and the adjustment coefficient of the ternary lithium battery is greater than the adjustment coefficient of the lithium iron phosphate battery; and adjust the voltage value of each single cell battery by multiplying the adjustment coefficient by the difference.

[0066] In another practicable manner, the processor 310 is specifically configured to: V_corrected=V_measured-K×H; wherein V_corrected is the adjusted voltage value, V_measured is the collected voltage value, K is the adjustment coefficient, and K is a positive number, and H is the difference between the actual altitude and the standard altitude.

[0067] In another practicable manner, the processor 310 is specifically used to: compare the adjusted voltage value of each single cell with the alarm threshold in turn to identify the abnormal battery with charging abnormality, wherein the adjusted voltage value of the abnormal battery is greater than the alarm threshold; determine whether the abnormal battery has a history of overcharging failure, if an overcharging failure has occurred and the number of abnormalities in this charging process is greater than the first number, or if no overcharging failure has occurred and the number of abnormalities is greater than the second number, then determine that the abnormal battery is a target battery with a charging failure; wherein the number of abnormalities is the number of times the abnormal battery has an abnormality in this charging process, and the first number is less than the second number.

[0068] In another practicable manner, the processor 310 is further used to: if no overcharging failure occurs, obtain a preset number threshold as the first number; if an overcharging failure occurs, lower the minimum number threshold to obtain a second number, wherein the minimum number threshold is the minimum value of the number thresholds set in the abnormal battery history.

[0069] In another practicable manner, the processor 310 is specifically used to: obtain a set of abnormal voltage values ​​of the target battery during the current charging process, wherein each abnormal voltage value in the set is an adjusted voltage value and each abnormal voltage value is greater than an alarm threshold; determine, from multiple alarm intervals, a target alarm interval to which the maximum voltage value in the set belongs, or determine a target alarm interval in which all abnormal voltage values ​​in the set are most concentrated; and execute alarm measures corresponding to the target alarm interval.

[0070] In another implementable manner, the processor 310 is specifically used to: if the target alarm interval is the first alarm interval, prompt the user to continue observing; if the target alarm interval is the second alarm interval, stop charging and prompt the user to continue observing; if the target alarm interval is the third alarm interval, stop charging, send the number of the target battery with charging failure to the after-sales management system, and prompt the user to contact after-sales as soon as possible.

[0071] In one embodiment, the present application further provides a computer-readable storage medium storing a plurality of instructions, which are suitable for being loaded by a processor and executing the method in any of the above embodiments. The processor is used to execute the plurality of instructions; the memory is used to store the plurality of instructions, which are loaded by the processor and executed by the dynamic warning method applied to the in-vehicle scenario in the above embodiment.

[0072] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0073] The above embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent of the present application shall be subject to the attached claims.

Claims

1. A dynamic alarm method, It is characterized in that include: Collect the voltage value of each single battery during the charging process and detect the actual altitude of the vehicle; Calculate the difference between the actual altitude and the standard altitude, and when the thermal management system is not effective or fails, use the difference to adjust the voltage value of each single battery, so as to reduce the voltage value at high altitude, thereby reducing the alarm sensitivity at high altitude, or increase the voltage value at low altitude, thereby improving the alarm sensitivity at low altitude; The adjusted voltage value of each single battery is compared with the alarm threshold in turn to determine the abnormal battery, and according to the number of times the abnormal battery is determined to be abnormal during this charging process, determine whether the abnormal battery is a target battery with a charging fault, and after determining the target battery, obtain a set of abnormal voltage values ​​of the target battery during this charging process, and from multiple alarm intervals, determine the target alarm interval to which the maximum voltage value in the set belongs, or determine the target alarm interval in which all abnormal voltage values ​​in the set are most concentrated, and execute the alarm measures corresponding to the target alarm interval, wherein each abnormal voltage value in the set is an adjusted voltage value, and each abnormal voltage value is greater than the alarm threshold.

2. The method according to claim 1, It is characterized in that The voltage value of each single battery is adjusted by using the difference, including: Determine the adjustment coefficient corresponding to the type of the single cell, wherein the type includes lithium iron phosphate battery and ternary lithium battery, and the adjustment coefficient of the ternary lithium battery is greater than the adjustment coefficient of the lithium iron phosphate battery; The voltage value of each single battery is adjusted by multiplying the adjustment coefficient by the difference.

3. The method according to claim 2, It is characterized in that The mathematical expression for adjusting the voltage value of each single battery by multiplying the adjustment coefficient by the difference value includes: V_corrected=V_measured-K×H; Wherein, V_corrected is the adjusted voltage value, V_measured is the collected voltage value, K is the adjustment coefficient, and K is a positive number, and H is the difference between the actual altitude and the standard altitude.

4. The method according to claim 1, It is characterized in that Comparing the regulated voltage value of each single battery with the alarm threshold in turn to determine the abnormal battery, and determining whether the abnormal battery is a target battery with a charging fault according to the number of times the abnormal battery is determined to be abnormal during the current charging process includes: Comparing the regulated voltage value of each single battery with the alarm threshold in turn to identify abnormal batteries with abnormal charging, wherein the regulated voltage value of the abnormal battery is greater than the alarm threshold; Determine whether the abnormal battery has a history of overcharging failure, if an overcharging failure has occurred and the number of abnormalities during this charging process is greater than the first number, or if no overcharging failure has occurred and the number of abnormalities is greater than the second number, determine that the abnormal battery is a target battery with a charging failure; The number of abnormal times is the number of times the abnormal battery has abnormalities during the current charging process, and the first number is less than the second number.

5. The method according to claim 4, It is characterized in that After determining whether the abnormal battery has a history of overcharging failure, the method further includes: If no overcharging failure occurs, a preset number threshold is obtained as the first number; If an overcharging fault occurs, the minimum number threshold is lowered to obtain a second number, wherein the minimum number threshold is the minimum value of the number thresholds historically set for the abnormal battery.

6. The method according to claim 1, It is characterized in that Executing the alarm measures corresponding to the target alarm interval includes: If the target warning interval is the first warning interval, prompting the user to continue observing; If the target warning interval is the second warning interval, charging is stopped and the user is prompted to continue observing; If the target warning interval is the third warning interval, charging is stopped, the number of the target battery with charging failure is sent to the after-sales management system, and the user is prompted to contact after-sales service as soon as possible.

7. A dynamic alarm device, It is characterized in that include: The acquisition unit is used to collect the voltage value of each single battery during the charging process and detect the actual altitude of the vehicle; an adjusting unit, configured to calculate a difference between the actual altitude and the standard altitude, and, when the thermal management system is not effective or fails, to adjust the voltage value of each single battery using the difference, so as to reduce the voltage value at a high altitude, thereby reducing the alarm sensitivity at a high altitude, or to increase the voltage value at a low altitude, thereby increasing the alarm sensitivity at a low altitude; An alarm unit is used to compare the adjusted voltage value of each single battery with the alarm threshold in turn to determine the abnormal battery, determine whether the abnormal battery is a target battery with a charging fault according to the number of times the abnormal battery is determined to be abnormal during this charging process, and after determining the target battery, obtain a set of abnormal voltage values ​​of the target battery during this charging process, determine from multiple alarm intervals a target alarm interval to which the maximum voltage value in the set belongs, or determine a target alarm interval in which all abnormal voltage values ​​in the set are most concentrated, and execute alarm measures corresponding to the target alarm interval, wherein each abnormal voltage value in the set is an adjusted voltage value, and each abnormal voltage value is greater than the alarm threshold.

8. A dynamic alarm device, It is characterized in that The dynamic alarm device includes a processor and a memory, and the processor and the memory are connected via a bus; the processor is used to execute multiple instructions; the memory is used to store the multiple instructions, and the instructions are suitable for being loaded by the processor and executing the dynamic alarm method described in any one of claims 1 to 6.

9. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores a plurality of instructions, and the instructions are suitable for being loaded by a processor and executing the dynamic alarm method according to any one of claims 1 to 6.