Circuit early warning method and early warning system
By monitoring the power values of electrical equipment in real time through the server, plotting power curves, predicting circuit overload, and outputting early warning signals, the problem of electricity meters not protecting the circuit in time when the current or voltage exceeds the limit is solved, thus achieving accurate and timely protection of the circuit and extending the service life of electrical equipment.
Patent Information
- Application Number
- CN202311213788.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-19
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2043-09-19
AI Technical Summary
Existing electricity meters only automatically cut off the power supply when the current or voltage in the circuit exceeds a certain threshold, which may accelerate the aging of the circuit, reduce the service life of electrical equipment, and cause the protection circuit to be untimely.
The server receives real-time power values from electrical appliances, plots power curves, predicts power changes in electrical appliances, and outputs warning signals to remind users to disconnect the power connection in time, thus realizing early warning overload protection for the circuit.
It provides accurate and timely protection for circuits, preventing circuit aging and extending the service life of electrical equipment.
Smart Images

Figure CN117310272B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of electricity meter technology, and in particular to a circuit early warning method and early warning system. Background Technology
[0002] An electricity meter is an instrument used to monitor electrical energy. Users can use the electricity meter to understand their electricity usage and thus manage the electricity consumption of electrical appliances. In actual electricity usage scenarios, due to users adding electrical appliances, using high-power appliances, or using high loads for extended periods, the circuit may experience overload. Overload can cause the circuit to malfunction and even damage the electricity meter or electrical appliances.
[0003] An electricity meter protects a circuit by detecting the current or voltage in the circuit. When the current or voltage in the circuit exceeds a certain threshold, the electricity meter will automatically cut off the power supply, thereby achieving overload protection.
[0004] However, existing electricity meters only automatically cut off the power supply when the current or voltage in the circuit exceeds a certain threshold. Exceeding the threshold may accelerate the aging of the circuit and reduce the lifespan of electrical equipment in the circuit, thus resulting in untimely protection circuits. Summary of the Invention
[0005] This application provides a circuit early warning method and system to solve the problem that existing electricity meters only automatically cut off the power supply when the current or voltage of the circuit exceeds a certain threshold, which may accelerate the aging of the circuit, reduce the service life of electrical equipment in the circuit, and thus lead to untimely protection of the circuit. The system realizes circuit early warning overload protection, and accurately and timely protects the circuit.
[0006] In a first aspect, this application provides a circuit early warning method applied to a server, comprising:
[0007] Receive the power value of electrical appliances in real time from the electricity meter;
[0008] Plot a first power curve based on the power value of the electrical equipment;
[0009] For the current power value, the following warning steps are executed:
[0010] A second power value is obtained, wherein the measurement time of the second power value is earlier than the measurement time of the first power value, and the measurement time of the second power value differs from the measurement time of the first power value by a first duration.
[0011] The first slope is determined based on the first power value, the measurement time of the first power value, the second power value, and the measurement time of the second power value;
[0012] Extend the first power curve along the direction of the first slope to draw the second power curve;
[0013] When the second power curve and the highest power curve of the electrical appliance intersect within a second time period, and the first ratio corresponding to the intersection point is greater than or equal to the second ratio, an early warning signal is output. The early warning signal is used to indicate that the electricity meter may be overloaded at the time corresponding to the intersection point, so as to remind the user to determine whether to disconnect the electricity meter from the electrical appliance through a relay. The first ratio is the ratio between the predicted power value corresponding to the intersection point and the average power value of the electrical appliance, and the second ratio is the ratio between the actual power value preset by the user and the average power value of the electrical appliance, or the ratio preset by the user.
[0014] Using the circuit early warning method provided in the first aspect, the server can receive the power value of electrical appliances from the electricity meter in real time, enabling real-time monitoring of the power value. The server plots a first power curve based on the power value, which reflects the real-time change of the power value over time. Therefore, the server can predict the power value of the electrical appliances at subsequent times based on the first power curve. The server then executes an early warning step for the current first power value. This early warning step includes: acquiring a second power value, where the measurement time of the second power value is earlier than the measurement time of the first power value, and the measurement time of the second power value differs from the measurement time of the first power value by a first time interval. The server can determine a first slope based on the first power value, the measurement time of the first power value, and the measurement times of the second power value and the second power value. The first slope indicates the direction of the extension of the first power curve. The server can extend the first power curve along the direction of the first slope to obtain the trend of the power value of the electrical equipment at subsequent times, and plot the second power curve. When the second power curve and the highest power curve of the electrical equipment intersect within a second time period, and the first ratio corresponding to the intersection point is greater than or equal to the second ratio, a warning signal is output. The warning signal indicates that the energy meter may be overloaded at the time corresponding to the intersection point, reminding the user to determine whether to disconnect the energy meter from the electrical equipment via a relay. Thus, overload protection for the circuit is achieved, allowing the user to know at what time the circuit may be overloaded, and the user can disconnect the circuit before the overload, avoiding accelerated circuit aging and extending the service life of the electrical equipment, thereby facilitating accurate and timely circuit protection.
[0015] In one possible design, the method further includes: when the second power curve and the highest power curve of the electrical appliance intersect within a second time period, and the first ratio corresponding to the intersection is less than the second ratio, or when the second power region and the highest power curve of the electrical appliance do not intersect within the second time period, the above prediction steps are continued to be performed from the current moment after the first time period.
[0016] As can be seen, the server can determine whether an overload has occurred and decide whether to output a warning signal based on two conditions: the existence of an intersection between the second power curve and the highest power curve of the electrical equipment within a second time period, and the first ratio corresponding to the intersection being greater than or equal to the second ratio. This improves the accuracy of the overload warning protection for the circuit.
[0017] In one possible design, the first duration is taken as: a pre-set duration and the minimum duration between the current moment and the moment when the change in the power value of the electrical appliance is greater than the maximum power value of a single electrical appliance.
[0018] It is evident that when executing the next warning step, the server needs to consider the possibility of sudden changes in the power value of the electrical equipment. If the power value of the electrical equipment changes suddenly, and the difference between the time of the change and the time of executing the current warning step is less than the preset time, the server does not need to wait for the preset time before executing the next warning step. Instead, it executes the next warning step at the moment the power value of the electrical equipment changes. This fully considers the possibility of sudden changes in the power value of the electrical equipment, thereby improving the accuracy of the overload protection warning and protecting the circuit accurately and promptly.
[0019] In one possible design, the output warning signal includes: sending the warning signal to a terminal device; or displaying the predicted power value and time corresponding to the intersection point based on the warning signal; or providing a voice prompt for the warning signal.
[0020] Based on this, users can determine at what time an overload might occur and what the predicted power value would be at the time of the overload, according to the predicted power value and time corresponding to the intersection point. This allows users to decide whether to disconnect the electricity meter from the electrical equipment in advance via a relay, thus achieving early circuit protection and preventing damage to the electricity meter or electrical equipment.
[0021] In one possible design, the method further includes storing at least one of the power values of all the electrical devices, the first power curve, the second power curve, and all the warning signals.
[0022] Because the server has a large storage space, it can store relevant data generated during the execution of the circuit warning method, thus saving storage space in the electricity meter.
[0023] In one possible design, the method further includes: receiving a user-preset actual power value from the terminal device; or, receiving a user-preset ratio from the terminal device.
[0024] In a second aspect, this application provides a circuit early warning system, comprising: electrical equipment, an electricity meter, a relay, a network device, a terminal device, and a server as described in any of the first aspects above.
[0025] In one possible design, the energy meter is also used for:
[0026] When the power value of the electrical appliance is continuously greater than or equal to the user-preset actual power value for a third time period, the relay is driven to disconnect the electrical connection between the energy meter and the electrical appliance.
[0027] If the power value of the electrical appliance is lower than the user-preset actual power value within a third time period, the electrical connection between the electricity meter and the electrical appliance shall be maintained.
[0028] As can be seen, by monitoring the power value of electrical appliances, the electricity meter can determine whether the power value of the electrical appliances is greater than or equal to the user's preset actual power value within a third time period. If so, it will drive the relay to disconnect the electricity meter from the electrical appliance, thereby realizing automatic overload protection of the circuit.
[0029] In one possible design, the electricity meter is also used to: collect voltage and current values; and obtain the power value of the electrical device based on the voltage and current values.
[0030] The beneficial effects provided in the second aspect and its various possible designs can be found in the first aspect and its various possible implementations, and will not be repeated here. Attached Figure Description
[0031] Figure 1 This is a schematic diagram of the circuit early warning system provided in an embodiment of this application;
[0032] Figure 2 A flowchart of the circuit early warning method provided in the embodiments of this application;
[0033] Figure 3 A schematic diagram of the first power curve and the second power curve provided for embodiments of this application;
[0034] Figure 4 A schematic diagram of the intersection points provided in the embodiments of this application;
[0035] Figure 5 A schematic diagram of the first duration provided for an embodiment of this application. Detailed Implementation
[0036] In this application, "at least one" means one or more, and "more than one" means two or more. "And / or" describes the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can mean: A alone, A and B simultaneously, or B alone, where A and B can be singular or plural. The character " / " generally indicates that the preceding and following related objects are in an "or" relationship. "At least one of the following" or similar expressions refer to any combination of these items, including any combination of single or plural items. For example, at least one of a, b, or c alone can mean: a alone, b alone, c alone, a combination of a and b, a combination of a and c, a combination of b and c, or a, b, and c, where a, b, and c can be single or multiple. Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0037] The terms “center,” “longitudinal,” “lateral,” “up,” “down,” “left,” “right,” “front,” and “rear,” etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.
[0038] The terms "connected" and "connected" should be interpreted broadly. For example, in circuit structures, "connected" or "connected" can refer not only to physical connections but also to electrical or signal connections. This could be a direct connection (physical connection) or an indirect connection via at least one intermediate component, as long as the circuit is connected. It could also refer to the internal connection between two components. Similarly, a signal connection can refer to a connection via a circuit or a medium, such as radio waves. Those skilled in the art will understand the specific meaning of these terms in this application based on the specific circumstances.
[0039] This application provides a circuit early warning method and system. The server utilizes the power-time curve of an electrical appliance, obtaining a slope from the power values at two different measurement times. This slope is then extended along the power-time curve to create an extended curve. Based on this extended curve, the server can predict the power value at subsequent times. By determining whether the extended curve intersects with the monthly maximum power curve and comparing the power value at the intersection with the user-set power value, the server determines whether the circuit is overloaded. Therefore, the server can decide whether to issue an early warning to the user, allowing the user to adjust their power consumption or disconnect the circuit via a relay, thus achieving accurate and timely circuit protection against overload.
[0040] The circuit warning method provided in this application is executed by a server, or by a circuit warning device within the server. The circuit warning device can be implemented through a combination of software and / or hardware.
[0041] Please see Figure 1 , Figure 1 A schematic diagram of the circuit warning system provided in an embodiment of this application is shown. Figure 1 As shown, the circuit early warning system of this application may include: electrical equipment 11, electricity meter 12, relay 13, network equipment 14, server 15 and terminal equipment 16.
[0042] Among them, electrical equipment 11 and electricity meter 12 are connected by signal, electricity meter 12 is connected by signal to relay 13, and electricity meter 12 is connected to server 15 through network device 14.
[0043] The server 15 and the terminal device 16 can be directly or indirectly connected via wired or wireless communication methods. Wired communication methods can include coaxial cable, fiber optic cable, digital subscriber line (DSL), etc. Wireless communication methods can include Bluetooth, infrared, Wi-Fi, microwave, etc.
[0044] The number of electrical devices 11 can be one or more. Electrical devices 11 can be household appliances, such as microwave ovens, washing machines, dishwashers, water heaters or air conditioners, or industrial electrical appliances, such as electric motors, transformers or welding machines.
[0045] The electricity meter 12 is used to obtain one or more electrical parameters, such as current, voltage, or power, during the operation of the electrical equipment 11. The electricity meter 12 can be a digital electricity meter, a smart electricity meter, or a multi-functional electricity meter, etc.
[0046] The electricity meter 12 includes a clock, which is a device with a calendar, clock information, and pulse output. The electricity meter 12 may also be equipped with an EIA-485 interface or a wireless communication module. The EIA-485 interface or wireless communication module is used to communicate with external devices. These external devices may be network device 14, server 15, terminal device 16, or other devices.
[0047] The relay 13 is used to control the connection or disconnection of the electricity meter 12. The relay 13 can be a voltage relay, current relay, time relay, speed relay, or pressure relay, etc.
[0048] The current flows from the input terminal of relay 13 to the output terminal of relay 13, then into the energy meter 12, and then out of the energy meter 12 into the electrical equipment 11.
[0049] The network device 14 is used to connect the server 15 and the electricity meter 12. The network device 14 can be a gateway, router, or other similar device.
[0050] When network device 14 is a gateway, network device 14 can communicate with electricity meter 12 via wired communication through the EIA-485 interface on electricity meter 12, and can also communicate with electricity meter 12 via wireless communication module on electricity meter 12.
[0051] Among them, server 15 can be a cloud platform, an independent physical server, a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communication, middleware services, domain name services, security services, content delivery network (CDN), and big data and artificial intelligence platforms.
[0052] The terminal device 16 can be a mobile phone, tablet computer, laptop computer, wearable device, in-vehicle device, augmented reality (AR) / virtual reality (VR) device, ultra-mobile personal computer (UMPC), netbook, personal digital assistant (PDA), smart TV, smart screen, high-definition TV, 4K TV, smart speaker, smart projector, etc. This application does not impose any restrictions on the specific type of terminal device. The terminal device 15 has an application (APP), webpage, or public account installed.
[0053] The following embodiments of this application will be used to illustrate the concept of having Figure 1 Taking the circuit early warning system with the structure shown as an example, combined with Figures 2 to 5 This application provides a detailed description of the circuit early warning method.
[0054] Please see Figure 2 , Figure 2 A flowchart of a circuit warning method provided in an embodiment of this application is shown. Figure 2 As shown, the circuit early warning method of this application may include:
[0055] S101. Receive the power value of electrical equipment in real time from the electricity meter.
[0056] The power rating of an electrical appliance is the amount of power it generates during actual operation. When there is only one electrical appliance, the power rating is the power of that single appliance. When there are multiple electrical appliances, the power rating is the sum of the power ratings of all the appliances.
[0057] Among them, the electricity meter can be used to collect voltage and current values, and thus, the electricity meter can obtain the power value of electrical equipment based on the voltage and current values.
[0058] Among them, voltage value is the magnitude of the voltage generated by the electrical equipment during actual operation, and current value is the magnitude of the current generated by the electrical equipment during actual operation.
[0059] Based on this, the electricity meter can send the power value of the electrical equipment to the server in real time, and the server can receive the power value of the electrical equipment from the electricity meter in real time.
[0060] In some examples, the server can receive the power value of an appliance from the electricity meter at fourth intervals, such as 2ms, 5ms, or 10ms, thereby reducing the number of appliances whose power values need to be transmitted and saving network resources.
[0061] Of course, the server can also receive the power values of each electrical appliance from the electricity meter, thereby improving the accuracy of the first power curve drawn based on the power values of the electrical appliances.
[0062] Based on this, the server can receive the power values of electrical appliances from the electricity meter in real time. The server can then store the power values of the electrical appliances in the server so as to draw a first power curve based on the power values of the electrical appliances.
[0063] S102. Draw the first power curve based on the power value of the electrical equipment.
[0064] The first power curve represents the relationship between the power value of the electrical appliance and the measurement time. The first power curve changes over time, reflecting the real-time variation of the electrical appliance's power value.
[0065] The server establishes a Cartesian coordinate system with the measurement time as the X-axis, the power value of the electrical appliance as the Y-axis, and the initial measurement time as the origin. The server can map the power value of the electrical appliance received from the electricity meter to the measurement time of the power value in the aforementioned Cartesian coordinate system to obtain multiple coordinate points. The server can connect two adjacent coordinate points with a straight line to draw the first power curve.
[0066] In some examples, the server can map the power value of an electrical appliance and the measurement time of that power value to the aforementioned rectangular coordinate system at fifth intervals to obtain multiple coordinate points, and connect adjacent coordinate points with a straight line to obtain the first power curve.
[0067] Thus, the interval between the x-coordinates of two adjacent coordinate points is the fifth time interval. In other words, the slope of the first power curve changes once every fifth time interval. The fifth time interval can be, for example, 2 minutes, 5 minutes, or 10 minutes.
[0068] Below, in conjunction with Figure 3 The first power curve is illustrated by example.
[0069] Figure 3 This is a schematic diagram of the first power curve and the second power curve provided in the embodiments of this application. Figure 3 As shown, time T3 is the initial measurement time. The server starts plotting the first power curve OA from time T3. Figure 3 In the diagram, time T0 is the current time, time T1 is before time T0, and the time interval between time T1 and time T0 is the fifth time interval. Time T2 is before time T1, and the time interval between time T2 and time T1 is the fifth time interval. Time T3 is before time T2, and the time interval between time T3 and time T2 is the fifth time interval.
[0070] It is evident that by taking the power value of an electrical device at every fifth time interval to plot the first power curve, the complexity of the first power curve can be reduced, thereby saving server computing resources.
[0071] In other examples, the server can map the power value of each electrical device and the measurement time of each electrical device to the aforementioned Cartesian coordinate system to obtain multiple coordinate points, and connect adjacent coordinate points with a straight line to obtain the first power curve.
[0072] Because the server receives power values from electrical devices in real time, the initial power curve plotted by the server also changes in real time. The initial power curve changes every time the server receives a power value.
[0073] It is evident that plotting the first power curve based on the power values of each electrical device received by the server can improve the accuracy of the obtained first power curve.
[0074] Of course, in addition to using the periodic or real-time sampling methods described above to obtain multiple coordinate points, the server can also use a random sampling method to obtain multiple coordinate points, and this application does not limit this.
[0075] For the first power value at the current moment, the following warning steps are executed: S103 to S108.
[0076] Wherein, the first power value is the power value of the electrical appliance at the current moment, that is, the power value of the electrical appliance corresponding to the latest coordinate point in the first power curve. For example, the first power value can be: Figure 3 P0 in the middle.
[0077] S103, Obtain the second power value.
[0078] The measurement time of the second power value is earlier than the measurement time of the first power value, and the measurement time of the second power value differs from the measurement time of the first power value by a first time interval. For example... Figure 3 As shown, the first power value is P0, the second power value can be P1, the measurement time of P1 is time T1, and the duration between time T1 and time T0 is the first duration.
[0079] S104. Determine the first slope based on the first power value, the measurement time of the first power value, the measurement time of the second power value and the measurement time of the second power value.
[0080] The first slope is used to indicate the direction of extension of the first power curve.
[0081] like Figure 3 As shown, the first power value is P0, and the measurement time of the first power value is T0. The second power value is P1, and the measurement time of the second power value is T1. The server can calculate the slope between point A (T0, P0) and point B (T1, P1) using the slope formula between the two points, thereby obtaining the first slope.
[0082] In some examples, the first slope can be determined using Formula 1 as follows.
[0083]
[0084] Where k represents the first slope, y2 represents the second power value, y1 represents the first power value, x2 represents the measurement time of the second power value, and x1 represents the measurement time of the first power value.
[0085] Based on this, the server can determine the first slope, and thus the server can extend the first power curve according to the first slope.
[0086] S105. Extend the first power curve along the direction of the first slope to draw the second power curve.
[0087] Since the power output of electrical equipment is relatively stable during operation and does not change suddenly, the trend of the first power curve is essentially a straight line. Therefore, the server can take the current power value and a power value from a previous moment on the first power curve. Based on the measurement times of these two power values, the server can calculate the first slope. The server can then use the direction of the first slope as the direction of the power value of the electrical equipment at subsequent moments. By extending the first power curve along the direction of the first slope, the server can obtain a power value curve for subsequent moments, thereby enabling the prediction of the power value at later moments.
[0088] like Figure 3 As shown, the first slope is obtained from point A (T0, P0) and point B (T1, P1). The first power curve is extended along the direction of the first slope to obtain the extended straight line AC, thereby drawing the second power curve OC.
[0089] S106. Determine whether the second power curve and the highest power curve of the electrical equipment intersect within the second time period.
[0090] If yes, the server executes S107; otherwise, the server executes S109.
[0091] The maximum power curve of the electrical equipment corresponds to the highest power value over a specific period of time, such as a month or a quarter. This curve reflects the maximum power the equipment can achieve under normal use, thus providing a basis for the server to determine whether it is overloaded based on the second power curve. The maximum power curve of the electrical equipment can be pre-stored on the server.
[0092] In some examples, the server can retrieve the power value of the electrical appliances from the electricity meter every six hours throughout the day of a month. The server can record the retrieved power values of the electrical appliances and thus obtain the maximum power curve of the electrical appliances based on these power values.
[0093] Specifically, if the power value of the electrical device obtained in the current transaction is greater than the power value of the electrical device recorded in the previous transaction, the server records the power value of the electrical device obtained in the current transaction, overwriting the power value of the electrical device recorded in the previous transaction. If the power value of the electrical device obtained in the current transaction is less than or equal to the power value of the electrical device recorded in the previous transaction, the server does not record the power value of the electrical device obtained in the current transaction.
[0094] At the end of the month, the power consumption value of the electrical equipment recorded by the server for the last time is the highest power consumption value for that month. Therefore, the server can obtain a maximum power consumption curve based on this highest power consumption value. The server can store this maximum power consumption curve.
[0095] The intersection point indicates at what point in the future the electrical appliance will reach its maximum power value. The x-axis of the intersection point represents the measurement time of the predicted power value, and the y-axis represents the predicted power value, which is equal to the maximum power value.
[0096] The second duration represents the time limit for the server to predict the power value of the electrical equipment; that is, the maximum duration for which the server can predict the power value of the electrical equipment is the second duration. If the difference between the time corresponding to the intersection point and the current time is greater than the second duration, the predicted power value and the measurement time of the predicted power value may no longer be of reference value. Therefore, the server needs to output a warning signal only when the second power curve and the highest power curve of the electrical equipment intersect within the second duration, and the first ratio corresponding to the intersection point is greater than or equal to the second ratio, in order to improve the accuracy of the overload protection warning for the circuit.
[0097] For example, the second duration can be less than or equal to 24 hours. Since the types and quantities of electrical appliances used by users do not change much throughout the day, setting the second duration to less than or equal to 24 hours can improve the accuracy of overload protection warnings through the second power curve.
[0098] Below, in Figure 3 Based on, combined Figure 4 Explain the intersection point.
[0099] like Figure 4 As shown, λ is the maximum power curve of the electrical appliance, and Pmax is the maximum power value. Point D is the intersection of the second power curve OC and the maximum power curve λ of the electrical appliance, and time T4 is the prediction time corresponding to point D. Therefore, point D indicates that starting from T0, after a time interval of (T4-T0), the power value of the electrical appliance will reach the maximum power value Pmax.
[0100] S107. Determine whether the first ratio corresponding to the intersection point is greater than or equal to the second ratio.
[0101] If yes, the server executes S108; otherwise, the server executes S109.
[0102] The first ratio is the ratio between the predicted power value at the intersection point and the average power value of the electrical equipment. This first ratio reflects the increase in the predicted power value relative to the average power value of the electrical equipment.
[0103] The average power value of the electrical appliances is the average power value of the electrical appliances within a preset time period. The preset time period could be, for example, the past six months, the past quarter, or the past month. The server calculates the average or weighted average power value of multiple electrical appliances based on the power values obtained from the electricity meter within the preset time period. The server can then determine the average power value of the electrical appliances as the average power value.
[0104] The second ratio can be expressed in various ways.
[0105] As a feasible representation, the second ratio is the ratio between the user-preset actual power value and the average power value of the electrical equipment. The second ratio reflects the maximum increase in the user's desired power value relative to the average power value of the electrical equipment. The second ratio represents a safe increase in the power value of the electrical equipment; if the increase in the power value relative to the average power value exceeds the second ratio, it indicates that an overload may occur.
[0106] The user-preset actual power value is a value set by the user in advance through the terminal device. The user can estimate the actual power value based on the power value of the electrical appliance during actual use and send it to the server through the terminal device. Thus, the server can store the user-preset actual power value.
[0107] It is evident that when users are familiar with the actual power values of electrical appliances, they can preset an actual power value through the terminal device, which can improve the accuracy of the second ratio and thus improve the accuracy of determining whether to output a warning signal based on the second ratio.
[0108] As another feasible representation, the second ratio is a user-preset ratio.
[0109] In this application, the user-preset ratio is a value that the user sets in advance through the terminal device. The terminal device sends the user-preset ratio to the server, so that the server can store the user-preset ratio. For example, the user-preset ratio can be set to 1.5 or 2, etc., and this application does not limit it.
[0110] It is evident that when users are unaware of the actual power consumption of electrical appliances, they can directly set a ratio as a second ratio through their terminal devices, thereby improving the user experience.
[0111] Based on this, the server can determine whether the circuit is overloaded based on the following two conditions, and decide whether to output a warning signal, thereby improving the accuracy of the circuit's overload protection.
[0112] These two conditions include condition 1 and condition 2.
[0113] Condition 1: The second power curve and the highest power curve of the electrical equipment intersect within the second time period.
[0114] Condition 2: The first ratio corresponding to the intersection point is greater than or equal to the second ratio.
[0115] In some examples, when the server determines that conditions 1 and 2 are met simultaneously, that is, when the server determines that the second power curve and the highest power curve of the electrical appliance intersect within the second time period, and the first ratio corresponding to the intersection point is greater than or equal to the second ratio, it indicates that the power value of the electrical appliance can reach the highest power value, and the increase in the power value of the electrical appliance relative to the average power value of the electrical appliance exceeds the safe increase.
[0116] Based on this, the server can determine that an overload of the circuit may occur at the time corresponding to the intersection point. Therefore, the server can execute S108 to realize the circuit's early warning overload protection.
[0117] In other examples, when the server determines that condition 1 is met but condition 2 is not met, that is, when the server determines that the second power curve and the highest power curve of the electrical appliance intersect within the second time period, but the first ratio corresponding to the intersection point is less than the second ratio, it means that in the subsequent second time period, although the power value of the electrical appliance can reach the highest power value, the increase of the power value of the electrical appliance relative to the average power value of the electrical appliance does not exceed the second ratio, and therefore does not exceed the safe increase of the power value of the electrical appliance.
[0118] Based on this, the server can determine that no circuit overload will occur in the future, and thus, the server can execute S109.
[0119] In other examples, when the server determines that condition 1 is not met, that is, when the server determines that the second power curve and the highest power curve of the electrical device do not intersect within the second time period, it means that the power value of the electrical device has not reached the highest power value corresponding to the highest power curve within the subsequent second time period, which means that the electrical device is operating relatively smoothly.
[0120] Based on this, the server can determine that no circuit overload will occur in the future, and thus, the server can execute S109.
[0121] S108. Output a warning signal. The warning signal is used to indicate that the electricity meter may be overloaded at the time corresponding to the intersection point, so as to remind the user to determine whether to disconnect the electricity meter from the electrical equipment through the relay.
[0122] S109. Starting from the current moment, continue executing the above-mentioned warning steps after the first duration: S103 to S108.
[0123] In summary, after completing the warning steps S103 to S108 for the first power value at the current moment, when the server determines that an overload of the circuit may occur at the intersection point, the server can output a warning signal to achieve overload protection for the circuit. When the server determines that no overload of the circuit will occur in subsequent moments, the server can, after a first time interval, obtain the latest power value at this moment and execute the warning steps S103 to S108 again, thereby updating the obtained second power curve and realizing real-time overload warning for the circuit.
[0124] In some examples, the first duration is taken as: a preset duration, and the minimum duration between the current moment and the moment when the change in the power value of the appliance exceeds the maximum power value of the single appliance.
[0125] The preset duration can be, for example, 2 minutes, 5 minutes, or 10 minutes.
[0126] The change in the power value of an electrical appliance refers to the difference between the power value of the electrical appliance at a certain measurement moment and the power value of the electrical appliance at the previous measurement moment.
[0127] The maximum power value of a single electrical appliance can be expressed in several ways.
[0128] As a feasible representation, the maximum power value of a single electrical appliance is the power value indicated by the maximum power of any one of the electrical appliances. For example, the maximum power value of a single electrical appliance can be Pmax.
[0129] As another feasible way of representing it, the maximum power value of a single electrical appliance is the power value within the maximum power range of any one of the electrical appliances. For example, the maximum power value of a single electrical appliance can be any power value within Pmax ± 10%.
[0130] Since the power value of electrical equipment is relatively stable during operation and does not change suddenly, when the change in the power value of an electrical appliance exceeds the maximum power value of a single appliance, it indicates that the power value of the appliance has changed abruptly, which may be abnormal.
[0131] Therefore, when executing the next warning step, the server needs to consider the possibility of sudden changes in the power value of electrical equipment.
[0132] When the power value of an electrical device changes abruptly, and the difference between the time of the change and the time of executing the current warning step is less than a preset time, the server does not need to wait for the preset time before executing the next warning step. Instead, it executes the next warning step at the moment the power value of the electrical device changes abruptly. This fully considers the situation of sudden changes in the power value of the electrical device, thereby improving the accuracy of the overload protection warning and protecting the circuit accurately and in a timely manner.
[0133] like Figure 5 As shown, at the current time T1, with a preset duration of (T0-T1), the server performed an early warning step at T1. The server should then perform the next early warning step at T0. Since a point C occurs between T1 and T0 where the power value of an electrical device changes abruptly, and (Ta-T1) is less than (T0-T1), the server should perform the next early warning step at Ta.
[0134] In this embodiment, the server receives the power value of the electrical appliance from the electricity meter in real time, enabling real-time monitoring of the appliance's power value. The server plots a first power curve based on the appliance's power value, which reflects the change in the appliance's power value over time. Therefore, the server can predict the appliance's power value at subsequent times based on the first power curve. The server executes an early warning step for the current first power value. This early warning step includes: acquiring a second power value, where the measurement time of the second power value is earlier than the measurement time of the first power value, and the measurement time of the second power value differs from the measurement time of the first power value by a first time interval. The server can... Based on the first power value, the measurement time of the first power value, the second power value, and the measurement time of the second power value, a first slope is determined. The first slope indicates the direction of extension of the first power curve. The server can extend the first power curve along the direction of the first slope to obtain the trend of the power value of the electrical appliance at subsequent times, and plot the second power curve. When the second power curve and the highest power curve of the electrical appliance intersect within a second time period, and the first ratio corresponding to the intersection point is greater than or equal to the second ratio, a warning signal is output. The warning signal indicates that the energy meter may be overloaded at the time corresponding to the intersection point, reminding the user to determine whether to disconnect the energy meter from the electrical appliance via a relay. Thus, overload protection for the circuit is achieved, allowing the user to know at what time the circuit may be overloaded. The user can disconnect the circuit before an overload occurs, avoiding accelerated circuit aging and extending the lifespan of the electrical appliance, thereby facilitating accurate and timely circuit protection.
[0135] Based on the description of the above embodiments, the server can adopt various implementation methods to output warning signals.
[0136] In some examples, the server can send a warning signal to the terminal device; or, the server can display the predicted power value and time corresponding to the intersection based on the warning signal; or, the server can provide a voice prompt for the warning signal.
[0137] Based on this, users can determine at what time an overload might occur and what the predicted power value would be at the time of the overload, according to the predicted power value and time corresponding to the intersection point. This allows users to decide whether to disconnect the electricity meter from the electrical equipment in advance via a relay, thus achieving early circuit protection and preventing damage to the electricity meter or electrical equipment.
[0138] In other examples, the server may also send the first ratio to the terminal device.
[0139] Users can obtain the first ratio through their terminal devices, allowing them to understand the increase in the predicted power value compared to the average power value of the electrical equipment. Based on this first ratio, users can then reset a more reasonable second ratio or a user-preset actual power value, improving the accuracy of the warning and thus accurately protecting the circuit.
[0140] In some examples, the server can store the power values of all electrical appliances.
[0141] The server can store the power values of all electrical appliances in its memory, allowing it to plot a primary power curve based on these values. Furthermore, because servers have large storage capacity, using a server to store all the power values reduces the need to store excessive power values in the electricity meter, thus saving storage space.
[0142] In some examples, the server can store the initial power curve.
[0143] The server can store the first power curve in its memory so that it can plot the second power curve based on the first power curve. Furthermore, users can view the first power curve through the server to understand how the power value of electrical appliances changes over time.
[0144] In some examples, the server can store a second power curve.
[0145] The server can store the second power curve in its memory, allowing it to determine whether to issue a warning signal based on this curve. Furthermore, users can view the second power curve through the server to understand how the power consumption of electrical appliances changes over time.
[0146] In some examples, the server can store all warning signals.
[0147] The server can store all warning signals in its memory, allowing it to output warning signals to remind users to determine whether to disconnect the electricity meter from electrical appliances via a relay. Furthermore, users can view all warning signals through the server, thus understanding the circuit's overload warning status.
[0148] Based on the description of the above embodiments, the server can obtain the user-preset actual power value or the user-preset ratio in the following manner.
[0149] Specifically, the server can receive the user-preset actual power value from the terminal device, or the server can receive the user-preset ratio from the terminal device.
[0150] Users can estimate the actual power consumption of electrical appliances based on their actual usage and send it to the server via their terminal devices.
[0151] Users can also preset a ratio based on their expected increase in the power value of electrical appliances, and send it to the server through the terminal device.
[0152] Therefore, the server can use the ratio between the user-preset actual power value and the average power value of the electrical equipment as the second ratio, or the server can use the user-preset ratio as the second ratio, and the server can then determine the relationship between the first ratio and the second ratio.
[0153] In addition to servers providing early warning overload protection for circuits, electricity meters can provide automatic overload protection for circuits.
[0154] In some examples, the electricity meter can detect whether the power value of an electrical appliance is continuously greater than or equal to the user-preset actual power value over a third time period.
[0155] The third duration is used to indicate the duration for which the power value of the electrical appliance is greater than or equal to the user-preset actual power value.
[0156] For example, the third duration can be 60 seconds. When the power value of an electrical appliance is greater than or equal to the user's preset actual power value for a short period of time, it may be due to fluctuations in the power grid. Such fluctuations are normal. Therefore, the State Grid stipulates that the standard for judging overload is that the power value of an electrical appliance is greater than or equal to the user's preset actual power value for more than 60 seconds before it is judged as an overload.
[0157] The user-preset actual power value can be obtained by the electricity meter from the server through the gateway. The gateway can convert the user-preset actual power value into a format that the electricity meter can process through a preset protocol. For example, the preset protocol can be the DL / T645-2007 protocol, and the format that the electricity meter can process can be, for example, binary format.
[0158] Based on this, when the power value of the electrical appliance is detected by the electricity meter to be greater than or equal to the user-preset actual power value for a third time period, the electricity meter drives the relay to disconnect the electrical connection between the electricity meter and the electrical appliance.
[0159] If the power value of an electrical appliance is detected by the electricity meter to be less than the user-preset actual power value within a third time period, the electricity meter will maintain the electrical connection between the electricity meter and the electrical appliance.
[0160] In summary, by detecting the power value of electrical equipment, it can be determined whether the power value of the electrical equipment is greater than or equal to the user's preset actual power value within the third time period. If so, the relay is driven to disconnect the electrical connection between the energy meter and the electrical equipment, thereby realizing automatic overload protection of the circuit.
[0161] In the circuit warning system provided in this application embodiment, the server can use a first power curve to obtain a first slope from the power values at two different measurement times. Extending the first power curve along the first slope direction allows for prediction of power values at subsequent times. By determining whether there is an intersection with each highest power curve and comparing the predicted power value with the user-set power value, the server determines whether the circuit is overloaded and decides whether to issue a warning to the user. This allows the user to adjust their electricity usage based on the warning or disconnect the circuit via a relay, achieving circuit overload protection and thus accurately and promptly protecting the circuit. The electricity meter can detect the power value of electrical appliances in real time. By judging the relationship between the power value of the electrical appliances and the user-preset actual power value, automatic overload protection of the circuit can be achieved. Therefore, the circuit warning system provided in this application embodiment can achieve both automatic overload protection and warning overload protection of the circuit.
[0162] In the several embodiments provided in this application, it should be understood that the disclosed systems, apparatuses, and methods can be implemented in other ways. For example, the apparatus embodiments described above are merely illustrative. For instance, the division of modules or units is only a logical functional division, and in actual implementation, there may be other division methods. For example, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed.
[0163] Those skilled in the art will understand that although some embodiments herein include certain features included in other embodiments, combinations of features from different embodiments are intended to be within the scope of this application and form different embodiments. For example, in the claims, any of the claimed embodiments can be used in any combination.
[0164] The above-described embodiments are only used to illustrate the technical solutions of this application, and are not intended to limit them. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of this application.
Claims
1. A circuit early warning method, characterized in that, Applied to a server, the method includes: Receive the power value of electrical appliances in real time from the electricity meter; Plot a first power curve based on the power value of the electrical equipment; For the current power value, the following warning steps are executed: A second power value is obtained, wherein the measurement time of the second power value is earlier than the measurement time of the first power value, and the measurement time of the second power value differs from the measurement time of the first power value by a first duration. The first slope is determined based on the first power value, the measurement time of the first power value, the second power value, and the measurement time of the second power value; Extend the first power curve along the direction of the first slope to draw the second power curve; When the second power curve and the highest power curve of the electrical appliance intersect within a second time period, and the first ratio corresponding to the intersection point is greater than or equal to the second ratio, an early warning signal is output. The early warning signal is used to indicate that the electricity meter may be overloaded at the time corresponding to the intersection point, so as to remind the user to determine whether to disconnect the electricity meter from the electrical appliance through a relay. The first ratio is the ratio between the predicted power value corresponding to the intersection point and the average power value of the electrical appliance, and the second ratio is the ratio between the actual power value preset by the user and the average power value of the electrical appliance, or the ratio preset by the user.
2. The method according to claim 1, characterized in that, The method further includes: If the second power curve and the highest power curve of the electrical appliance intersect within a second time period, and the first ratio corresponding to the intersection is less than the second ratio, or if the second power curve and the highest power curve of the electrical appliance do not intersect within a second time period, the above-mentioned warning steps shall continue to be executed after the first time period starting from the current moment.
3. The method according to claim 1 or 2, characterized in that, The first duration is taken as: a preset duration, and the minimum duration between the current moment and the moment when the change in the power value of the electrical appliance is greater than the maximum power value of a single electrical appliance.
4. The method according to claim 1 or 2, characterized in that, Output warning signals, including: Send the warning signal to the terminal device; Alternatively, the predicted power value and time corresponding to the intersection can be displayed based on the warning signal; Alternatively, the warning signal can be prompted by voice.
5. The method according to claim 1 or 2, characterized in that, The method further includes: The device stores at least one of the following: the power values of all the electrical devices, the first power curve, the second power curve, and all the warning signals.
6. The method according to claim 1 or 2, characterized in that, The method further includes: Receive the user-preset actual power value from the terminal device; Alternatively, it can receive a user-preset ratio from the terminal device.
7. A circuit early warning system, characterized in that, include: Electrical equipment, electricity meters, relays, network equipment, terminal equipment, and servers as described in any one of claims 1-6.
8. The system according to claim 7, characterized in that, The electricity meter is also used for: When the power value of the electrical appliance is continuously greater than or equal to the user-preset actual power value for a third time period, the relay is driven to disconnect the electrical connection between the energy meter and the electrical appliance. If the power value of the electrical appliance is lower than the user-preset actual power value within a third time period, the electrical connection between the electricity meter and the electrical appliance shall be maintained.
9. The system according to claim 8, characterized in that, The electricity meter is also used for: Collect voltage and current values; The power value of the electrical device is obtained based on the voltage and current values.
Citation Information
Patent Citations
Integrated photovoltaic module power control method with inclined characteristic protection
CN106059484A
Auxiliary detection method for checking correctness after guiding of automatic power curves
CN109557363A