A pavement waterproofing and draining construction method
By laying a cement-gravel mixture and positioning steel frame in the subgrade layer to form a layered drainage channel, the problem of drainage pipe blockage in environments with high groundwater levels and low temperatures is solved, achieving a highly efficient drainage effect.
Patent Information
- Application Number
- CN202311493326.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-10
- Publication Date
- 2025-12-12
- Estimated Expiration
- 2043-11-10
AI Technical Summary
In existing technologies, in areas with high groundwater levels, fine-grained soil in the roadbed rises with the water and blocks drainage pipes. In cold regions, low temperatures cause water bodies to freeze and block drainage pipes, resulting in poor drainage, especially in rainy or humid conditions.
A mixture of cement and crushed stone is laid on the subgrade layer to form a water blocking layer. A positioning steel frame is then installed on top, and drainage pipes are laid to form a drainage and infiltration layer. The drainage pipes are inclined downward with the center line of the road surface as the central axis. Top blocking pipes, impact pipes, inclined pipes and bottom blocking pipes are installed to form a layered drainage channel. The water flow velocity is increased by the impact pipes and the confluence impact zone to prevent blockage.
It effectively prevents fine soil from rising from the roadbed and clogging the pipes, reduces freezing blockages, improves the smoothness of drainage pipes, and ensures drainage performance, especially maintaining smooth flow in environments with high groundwater levels and low temperatures.
Smart Images

Figure CN117418437B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of pavement drainage, in particular to a pavement waterproof and drainage construction method. BACKGROUND
[0002] The waterproof and drainage construction is a construction for preventing water seepage or drainage in the process of pavement engineering construction, and poor pavement drainage can cause water in the pavement to enter the roadbed, the roadbed material performance to be reduced, the roadbed to be unstable, and the roadbed subsidence to be easily caused. In the process of pavement construction, the cast-in-place cement concrete pavement cannot be absolutely flat, and the asphalt concrete pavement structure design has a certain void ratio. In a rainy or humid state, water can accumulate in the pits and concaves.
[0003] To solve the problem of water accumulation in the pavement, a drainage layer is usually arranged between the cement concrete pavement and the asphalt concrete pavement layer, the drainage layer is arranged in parallel with the drainage pipeline, and after the water in the pits and concaves seeps into the pavement, the seeped rainwater in the pavement is discharged through the drainage pipeline.
[0004] The above-mentioned drainage pipeline is only suitable for discharging the seeped surface water, in a humid and high groundwater area, groundwater enters the internal structure of the pavement, under the continuous extrusion of the automobile load, a small amount of roadbed fine-grained soil rises with the water, the roadbed fine-grained soil continuously loses, the overall strength of the roadbed is reduced, and the rising fine-grained soil also blocks the drainage pipeline, causing poor drainage. In addition, in the high-cold area, the temperature is low, the water body is easy to freeze in the drainage pipeline, the frozen body blocks the inside of the drainage pipeline, the drainage of the drainage pipeline is hindered, and the drainage effect is poor. SUMMARY
[0005] Therefore, the present application provides a pavement waterproof and drainage construction method, which effectively solves the problems of poor drainage caused by the roadbed fine-grained soil rising with water to block the drainage pipeline in the high groundwater area, poor drainage effect caused by the frozen water body blocking the drainage pipeline in the high-cold area.
[0006] To solve the above-mentioned technical problems, the present application specifically provides the following technical scheme: a pavement waterproof and drainage construction method, comprising:
[0007] cement and gravel mixture is laid on the top of the roadbed bottom layer to form a water blocking layer;
[0008] The positioning steel frame is inserted and fixed on the water blocking layer before the water blocking layer is formed, and a plurality of drainage pipe fittings are laid on the water blocking layer at equal intervals through the positioning steel frame after the water blocking layer is formed, and asphalt gravel is laid to form a drainage permeation layer;
[0009] The asphalt concrete layers with different particle sizes are laid on the drainage permeation layer in sequence to form a pavement layer;
[0010] Wherein, with the road surface center line as the central axis, the drainage pipe pieces on both sides thereof form an inclined downward slope, the drainage pipe pieces are provided with a plurality of drainage holes upward, the drainage pipe pieces are provided with at least a top blocking pipe and a bottom blocking pipe, the top blocking pipe and the bottom blocking pipe are sequentially arranged from top to bottom, the top blocking pipe is connected with an impact pipe, and the top blocking pipe and the impact pipe form a confluence impact area at the connection position thereof, and the bottom blocking pipe is connected with an inclined pipe.
[0011] The side surface of the drainage permeation layer forms two drainage ports in the height direction, and the end portions of the top blocking pipe and the inclined pipe extend to the drainage ports at different positions.
[0012] Further,
[0013] The inclined pipe and the impact pipe both form an inclined downward slope outward from the road surface center line as the starting point;
[0014] The inclination of the inclined pipe is greater than the inclination of the bottom blocking pipe.
[0015] The inclination of the impact pipe is greater than the inclination of the top blocking pipe.
[0016] Further,
[0017] The connection position of the inclined pipe and the bottom blocking pipe is located at the end portion of the bottom blocking pipe, and the connection position of the impact pipe and the top blocking pipe is away from the end portion of the bottom blocking pipe.
[0018] The end portion positions of the top blocking pipe and the inclined pipe away from the drainage port are adjacent.
[0019] Further, it also comprises:
[0020] Based on the thickness and width of the roadbed bottom layer, the end portion positions of the inclined pipe, the top blocking pipe, the bottom blocking pipe and the impact pipe are calculated.
[0021] Wherein, the distance from the end portion of the impact pipe close to the road surface center line position to the top of the drainage permeation layer is a, the distance from the end portion of the impact pipe close to the road surface center line position to the end portion of the top blocking pipe close to the road surface center line position is b, and the distance from the end portion of the bottom blocking pipe close to the road surface center line position to the end portion of the inclined pipe close to the road surface center line position is c, a:b:c=0.5:1:1.
[0022] Further,
[0023] The positioning steel frame comprises a positioning U-shaped frame arranged at the end portions of the top blocking pipe and the inclined pipe away from the drainage port, and a positioning shaft arranged in the inner side of the positioning U-shaped frame.
[0024] The positioning U-shaped frame bottom is inserted on the water blocking layer, the positioning shafts are provided in two, the external width of the top blocking pipe is greater than the external width of the inclined pipe, and the internal width of the top blocking pipe is consistent with the internal width of the inclined pipe.
[0025] The top blocking pipe is provided with side grooves on both sides close to the bottom, and the ends of the positioning shafts are connected in the side grooves and the outer wall of the inclined pipe.
[0026] Further,
[0027] The positioning steel frame further comprises a fixing frame inserted on the water blocking layer, four positioning grooves provided on the fixing frame, a positioning cylinder provided in the positioning grooves, and a movable cylinder movably provided on the positioning cylinder.
[0028] The positioning grooves are opposite to each other, the end of the movable cylinder penetrates the side of the positioning cylinder and extends into the inside of the positioning cylinder, and the length of the movable cylinder extending into the positioning cylinder is less than the internal height of the top blocking pipe and the inclined pipe.
[0029] The top blocking pipe and the inclined pipe are installed in the positioning cylinder, the impact pipe and the bottom blocking pipe are installed in the movable cylinder, the end of the impact pipe extends into the top blocking pipe, and the end of the bottom blocking pipe extends into the inclined pipe.
[0030] Further,
[0031] The positioning cylinder is provided with a first through hole, the top blocking pipe is provided with a second through hole, the inclined pipe is provided with a third through hole, and the first through hole corresponds to the second through hole and the third through hole.
[0032] The length of the second through hole and the third through hole is longer than the length of the first through hole, and the length of the first through hole is the same as the length of the positioning cylinder.
[0033] The side of the movable cylinder is provided with a connecting shaft, and the movable cylinder is rotatably installed on the inner wall of the first through hole through the connecting shaft.
[0034] Further,
[0035] The ends of the impact pipe and the bottom blocking pipe are provided with extension plates, and the extension plates extend into the top blocking pipe and the inclined pipe, respectively.
[0036] Further,
[0037] The outer wall of the positioning cylinder is vertically provided with mounting seats, the mounting seats are provided in two and symmetrically arranged on the two sides of the first through hole, a first threaded groove is formed in the mounting seat, a first threaded bolt is mounted on the mounting seat, and the first threaded groove is matched with the first threaded bolt;
[0038] Second threaded grooves are formed in the inner walls of the positioning cylinder, the top blocking pipe and the inclined pipe, and second threaded bolts are arranged in the second threaded grooves.
[0039] The end portions of the first threaded bolt and the second threaded bolt abut against the outer wall of the movable cylinder.
[0040] Further,
[0041] The upper surface of the water blocking layer forms an inclined downward slope outward from the center line of the road surface, and the inclination of the water blocking layer is smaller than the inclination of the bottom blocking pipe.
[0042] Compared with the prior art, the present application has the following beneficial effects:
[0043] In the present application, the water blocking layer is laid on the roadbed bottom layer, and a plurality of drainage pipe fittings are arranged in the drainage permeable layer, and the first layer and the second layer are sequentially formed from bottom to top to block the rising of the fine-grained soil of the roadbed, so that the underground water and the fine-grained soil of the roadbed are blocked below the drainage permeable layer, and the situation that the fine-grained soil of the roadbed blocks the pipe is reduced.
[0044] The impact pipe, the top blocking pipe, the inclined pipe and the bottom blocking pipe are sequentially arranged from top to bottom to provide a drainage channel in layers, so that the water in the roadbed at different depths is discharged.
[0045] The impact pipe is arranged on the top blocking pipe, the intersection impact area is formed at the connection between the top blocking pipe and the impact pipe, the high-speed flowing water in the impact pipe and the low-speed flowing water in the top blocking pipe meet and produce an impact effect at the intersection impact area, on the one hand, the double water flow impact collection makes the flowing speed faster, and the freezing of the water in the pipe is reduced, on the other hand, the fine-grained soil at the end of the pipe can be impacted out of the pipe by high-speed impact, so as to avoid pipe blockage.
[0046] The bottom blocking pipe is arranged below the inclined pipe, and there is an intersection point, on the one hand, the water in the bottom blocking pipe flows at low speed, which slows down the speed of the fine-grained soil of the roadbed flowing into the pipe to a certain extent, avoids the accumulation of the fine-grained soil of the roadbed at a certain position in the pipe, and reduces the blockage of the fine-grained soil of the roadbed in the pipe, on the other hand, the high-speed flowing water in the inclined pipe impacts the underground water containing the fine-grained soil of the roadbed or the road surface water at the intersection point, so that the water flows out of the pipe at high speed, the fine-grained soil of the roadbed is avoided to be blocked in the pipe, and the smoothness of the pipe is improved. BRIEF DESCRIPTION OF DRAWINGS
[0047] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the following will briefly introduce the drawings needed to be used in the description of the embodiments or the prior art. Obviously, the drawings in the following description are only exemplary, and for those skilled in the art, other drawings can also be obtained from the provided drawings without creative labor.
[0048] Figure 1 A flow chart of a road surface waterproof and drainage construction method provided by the embodiment of the present application;
[0049] Figure 2 A structural schematic diagram of a road surface structure in the embodiment of the present application;
[0050] Figure 3 A structural schematic diagram of a drainage hole in the embodiment of the present application;
[0051] Figure 4 An internal structural schematic diagram of an impact pipe and a top blocking pipe in the embodiment of the present application;
[0052] Figure 5 An internal structural schematic diagram of a bottom blocking pipe and an inclined pipe in the embodiment of the present application;
[0053] Figure 6 A structural schematic diagram of an impact pipe in the embodiment of the present application;
[0054] Figure 7 A structural schematic diagram of a top blocking pipe in the embodiment of the present application;
[0055] Figure 8 A structural schematic diagram of an inclined pipe in the embodiment of the present application;
[0056] Figure 9 A structural schematic diagram of a bottom blocking pipe in the embodiment of the present application;
[0057] Figure 10 A cross-sectional structural schematic diagram of an extension plate in the embodiment of the present application;
[0058] Figure 11 A structural schematic diagram of a positioning U-shaped frame in the embodiment of the present application;
[0059] Figure 12 A cross-sectional structural schematic diagram of an end of a top blocking pipe in the embodiment of the present application;
[0060] Figure 13 A side structural schematic diagram of a fixing frame in the embodiment of the present application;
[0061] Figure 14 A front structural schematic diagram of a fixing frame in the embodiment of the present application;
[0062] Figure 15 Structure diagram of the top blocking pipe installed in the positioning cylinder and the impact pipe installed in the movable cylinder in the embodiment of the present application;
[0063] Figure 16 Structure diagram of the movable cylinder and the positioning cylinder in the embodiment of the present application;
[0064] Figure 17 Structure diagram of the cross section of the positioning cylinder and the top blocking pipe in the embodiment of the present application;
[0065] Figure 18 Structure diagram of the top view of the positioning cylinder in the embodiment of the present application;
[0066] Figure 19 Structure diagram of the inclined pipe installed in the positioning cylinder and the bottom blocking pipe installed in the movable cylinder in the embodiment of the present application.
[0067] The reference numerals in the drawings represent the following respectively:
[0068] 1 - water blocking layer; 2 - drainage permeable layer; 3 - pavement layer; 4 - positioning steel frame; 5 - drainage pipe; 6 - pavement center line; 7 - drainage hole; 8 - drainage opening; 9 - side slot;
[0069] 41 - positioning U-shaped frame; 42 - positioning shaft; 43 - fixed frame; 44 - positioning slot; 45 - positioning cylinder; 46 - movable cylinder; 47 - first through hole; 48 - second through hole; 49 - third through hole; 410 - extension plate; 411 - mounting seat; 412 - first threaded groove; 413 - first threaded bolt; 414 - second threaded groove; 415 - second threaded bolt; 416 - connecting shaft;
[0070] 51 - top blocking pipe; 52 - bottom blocking pipe; 53 - impact pipe; 54 - inclined pipe; 55 - intersection impact area. DETAILED DESCRIPTION
[0071] The technical solutions in the embodiments of the present application will be described clearly and completely below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all the other embodiments obtained by those skilled in the art without creative labor fall within the protection scope of the present application.
[0072] As shown in Figure 1 and Figure 2 The present application provides a pavement anti-drainage construction method, which comprises:
[0073] Cement and broken stone mixture is laid on the top of the subbase layer to form the water blocking layer 1;
[0074] The positioning steel frame 4 is inserted and fixed on the water blocking layer 1 before the water blocking layer 1 is formed, and a plurality of drainage pipe fittings 5 are laid on the water blocking layer 1 at equal intervals through the positioning steel frame 4 after the water blocking layer 1 is formed, and asphalt broken stone is laid to form the drainage and permeation layer 2;
[0075] The asphalt concrete layers with different particle sizes are laid on the drainage and permeation layer 2 in sequence to form the pavement layer 3.
[0076] The drainage pipe fittings 5 on both sides of the pavement center line 6 form an inclined downward slope, and the drainage pipe fittings 5 are arranged in parallel, as shown in Figure 3 The drainage pipe fittings 5 are provided with a plurality of drainage holes 7 upward, and the drainage pipe fittings 5 at least have the top blocking pipe 51 and the bottom blocking pipe 52, which are arranged in sequence from top to bottom, as shown in Figure 4 The top blocking pipe 51 is connected with the impact pipe 53, and the top blocking pipe 51 and the impact pipe 53 form the intersection impact area 55 at the connection position, as shown in Figure 5 The bottom blocking pipe 52 is connected with the inclined pipe 54.
[0077] The side surface of the drainage and permeation layer 2 forms two drainage openings 8 along the height direction, and the end portions of the top blocking pipe 51 and the inclined pipe 54 extend to the drainage openings 8 at different positions upward and downward, respectively.
[0078] In the application, the aperture of the drainage hole 7 needs to be controlled according to the actual situation, and if the particle size of the material in the upper part of the pavement layer is small, the aperture of the drainage hole 7 also needs to be reduced.
[0079] The pavement layer can be laid by using the asphalt concrete with different particle sizes, and the particle size gradually decreases from bottom to top.
[0080] In addition, in the application, the water blocking layer 1 is laid on the subbase layer, and the drainage pipe fittings 5 are arranged on the drainage and permeation layer 2, and the blocking layers of the first layer and the second layer are formed in sequence from bottom to top to block the upward rising of the fine particle soil of the subbase, so that the underground water and the fine particle soil are blocked below the drainage and permeation layer 2, and the situation that the subbase fine particle soil blocks the pipeline due to the upward rising of the underground water is reduced.
[0081] The impact pipe 53, the top blocking pipe 51, the inclined pipe 54 and the bottom blocking pipe 52 are arranged in sequence from top to bottom to provide the drainage channels in layers, so that the water bodies in different depth layers of the subbase are drained, and the water bodies in different depths are drained at the vertical line position close to the center line 6. In order to save the position of the water body drainage, two drainage openings 8 are arranged to drain the water bodies of the plurality of drainage pipelines, and the two drainage openings 8 also have the corresponding effect of sharing one drainage opening 8, and the specific effect is as follows.
[0082] The top blocking pipe 51 and the impact pipe 53 share one drainage port 8, the impact pipe 53 is arranged on the top blocking pipe 51, and a meeting impact area 55 is formed at the connection of the top blocking pipe 51 and the impact pipe 53, the high-speed water flow in the impact pipe meets the low-speed water flow in the top blocking pipe 51 at the meeting impact area 55 and generates an impact, on the one hand, the double water flow impact collection makes the flow speed faster, reduces the freezing of the water body in the pipe, and on the other hand, the high-speed impact can knock the fine soil at the end of the pipe out of the pipe, avoiding pipe blockage.
[0083] The inclined pipe 54 and the bottom blocking pipe 52 share one drainage port 8, the bottom blocking pipe 52 is arranged below the inclined pipe 54, and there is a meeting point, on the one hand, the low-speed water flow in the bottom blocking pipe 52 slows down the speed of the fine soil of the roadbed flowing into the pipe to a certain extent, avoiding the accumulation of the fine soil of the roadbed at a position in the pipe and reducing the blockage of the fine soil of the roadbed in the pipe, and on the other hand, the high-speed water flow in the inclined pipe 54 impacts the groundwater or road surface water containing the fine soil of the roadbed at the meeting point, so that the water flows out of the pipe at high speed, avoiding the blockage of the fine soil of the roadbed in the pipe and improving the smoothness of the pipe.
[0084] To ensure the downward flow of the water body, the inclined pipe 54 and the impact pipe 53 form a downward slope outward from the center line 6 of the road surface as a starting point, and to ensure the impact and water flow speed effect, the application also makes the following design, as shown in Figure 4 and Figure 5 The inclination of the inclined pipe 54 is greater than that of the bottom blocking pipe 52, and the inclination of the impact pipe 53 is greater than that of the top blocking pipe 51.
[0085] The inclination of the inclined pipe 54 is greater than that of the bottom blocking pipe 52, and the bottom blocking pipe 52 not only blocks the fine soil of the roadbed, but also makes part of the fine soil of the roadbed flowing in the pipe flow at low speed, avoiding the blockage of the pipe by the accumulation of the fine soil flowing at high speed in a short time, the water body entering the bottom blocking pipe 52 first flows at low speed to avoid the blockage and accumulation of the fine soil in a short time, and then flows at high speed in the second half of the inclined pipe 54 to quickly drain the pipe and also to avoid surface blockage, the different inclination designs above achieve the segmented speed regulation effect of the water body flow.
[0086] The inclination of the impact pipe 53 is greater than that of the top blocking pipe 51, the water in the impact pipe 53 flows at a high speed, the water in the top blocking pipe 51 flows at a low speed compared with the water in the impact pipe 53, the high-speed water in the impact pipe 53 and the low-speed water in the top blocking pipe 51 meet at the intersection impact area 55 and generate an impact, the double water flow impact gathering makes the flow speed faster, reduces the freezing of the water in the pipe, and the high-speed impact can also drive the fine soil at the end of the pipe out of the pipe, avoids the pipe blockage, and the high-speed impact water can also impact the formed ice in the pipe and accelerate the melting of the ice.
[0087] In addition, in the present application, as shown in Figure 4 and Figure 5 The connection position of the inclined pipe 54 and the bottom blocking pipe 52 is at the end of the bottom blocking pipe 52, the connection position of the impact pipe 53 and the top blocking pipe 51 is away from the end of the bottom blocking pipe 52, and the connection positions of the inclined pipe 54 and the bottom blocking pipe 52 and the impact pipe 53 and the top blocking pipe 51 are on the same vertical line, which is also for the positioning of the steel frame 4.
[0088] In order to save the position of the pipe, the end positions of the top blocking pipe 51 and the inclined pipe 54 are adjacent to the end position of the drain outlet 8, the end positions of the top blocking pipe 51 and the inclined pipe 54 are close to each other, and the positioning steel frame 4 is used for fixing.
[0089] The pavement drainage construction method provided by the present application also comprises the following steps:
[0090] Based on the thickness and width of the roadbed bottom layer, the end positions of the inclined pipe 54, the top blocking pipe 51, the bottom blocking pipe 52 and the impact pipe 53 are calculated.
[0091] The distance from the end of the impact pipe 53 close to the position of the pavement center line 6 to the top of the drain permeable layer 2 is a, the distance from the end of the impact pipe 53 close to the position of the pavement center line 6 to the end of the top blocking pipe 51 close to the position of the pavement center line 6 is b, the distance from the end of the bottom blocking pipe 52 close to the position of the pavement center line 6 to the end of the inclined pipe 54 close to the position of the pavement center line 6 is c, and a:b:c = 0.5:1:1.
[0092] The above-mentioned proportional end position setting is to enable the inclined pipe 54, the top blocking pipe 51, the bottom blocking pipe 52 and the impact pipe 53 to be dispersed (wherein the top blocking pipe 51 and the inclined pipe 54 are arranged close to each other), and in the actual application process, the position of the drain outlet 8 is usually fixed, so the calculation of the position of the end of the pipe according to the proportion can usually obtain the fixed form of the pipe (which needs to ensure that the pipe is always inclined downward).
[0093] A proportion range value can also be set, for example, so that a occupies 20% to 35% of the drainage permeable layer 2, to adjust the position of the pipeline during installation.
[0094] The setting of the a:b:c=0.5:1:1 ratio is adjusted based on actual conditions, assuming that the road surface is narrow and the pipeline arrangement may not have enough space, at this time, a can be set to approach 0 (the end of the impact pipe 53 close to the road surface center line 6 position approaches the top of the drainage permeable layer 2), and the distance from the end of the bottom blocking pipe 51 to the water body group fault 1 is also set to approach 0.
[0095] In the present application, the top blocking pipe 51, the bottom blocking pipe 52, the impact pipe 53, and the inclined pipe 54 are installed and fixed by the positioning steel frame 4. The positioning steel frame 4 of the present application adopts the following preferred embodiments, as shown in Figure 11 and Figure 12 The positioning steel frame 4 includes a positioning U-shaped frame 41 arranged at the end of the top blocking pipe 51 and the inclined pipe 54 away from the drainage port 8, and a positioning shaft 42 arranged inside the positioning U-shaped frame 41. The positioning U-shaped frame 41 is inserted into the water body blocking layer 1 at the bottom, and the positioning shaft 42 is arranged in two. The outer width of the top blocking pipe 51 is greater than the outer width of the inclined pipe 54, and the inner width of the top blocking pipe 51 is consistent with the inner width of the inclined pipe 54. The two sides of the top blocking pipe 51 close to the bottom are each provided with a side slot 9, and the ends of the positioning shaft 42 are connected to the side slot 9 and the outer wall of the inclined pipe 54, respectively.
[0096] In the above embodiment, the outer width of the top blocking pipe 51 is greater than the outer width of the inclined pipe 54, and the two sides of the top blocking pipe 51 close to the bottom are each provided with a side slot 9. The top of the positioning U-shaped frame 41 corresponds to the installation of the side slot 9, and the side of the positioning U-shaped frame 41 corresponds to the installation of the outer side of the inclined pipe 54. The width of the positioning U-shaped frame 41 from the cross section is the same as the width of the pipeline, which reduces the horizontal occupation space of the positioning U-shaped frame 41 and enables the pipeline to be closely arranged, avoiding the water body from entering the horizontal gap between the pipelines.
[0097] In addition, the positioning shaft 42 is arranged to enable the positioning blocking pipe 51 and the inclined pipe 54 to be fixed on the positioning U-shaped frame 41.
[0098] In order to avoid interference between the above structure and the bottom blocking pipe 52, the end of the bottom blocking pipe 52 is arranged away from the road surface center line 6 and away from the positioning U-shaped frame 41.
[0099] In order to install and fix the top blocking pipe 51, the bottom blocking pipe 52, the impact pipe 53, and the inclined pipe 54, as shown in Figure 13 , Figure 14 , Figure 15 , Figure 16 ,Figure 17 As shown, the positioning steel frame 4 also includes a fixed frame 43 inserted into the water blocking layer 1, four positioning slots 44 set on the fixed frame 43, positioning cylinders 45 set in the positioning slots 44, and movable cylinders 46 movably set on the positioning cylinders 45. The positioning slots 44 are opposite each other in pairs. The end of the movable cylinder 46 penetrates through the side of the positioning cylinder 45 and extends into the interior of the positioning cylinder 45. The length of the movable cylinder 46 extending into the positioning cylinder 45 is less than the internal height of the top blocking pipe 51 and the inclined pipe 54. Figure 7 and Figure 8 As shown, the top blocking tube 51 and the inclined tube 54 are installed inside the positioning cylinder 45, and the impact tube 53 and the bottom blocking tube 52 are installed inside the movable cylinder 46. The end of the impact tube 53 extends into the top blocking tube 52, and the end of the bottom blocking tube 52 extends into the inclined tube 54.
[0100] In the above embodiment, the positioning groove 44 is adapted to the side of the top blocking pipe 51 and the tilting pipe 54 that have completed the tilt adjustment, that is, the tilt of the positioning groove 44 is the same as that of the corresponding pipe.
[0101] The length of the movable cylinder 46 extending into the positioning cylinder 45 is less than the internal height of the top blocking tube 51 and the inclined tube 54, in order to avoid the movable cylinder 46 interfering with the inside of the top blocking tube 51 and being stopped during rotation.
[0102] like Figure 17 As shown, the positioning cylinder 45 has a first through-hole 47, and the top blocking tube 51 has a second through-hole 48, as... Figure 19 As shown, the inclined tube 54 has a third through-hole 49, and the first through-hole 47 corresponds to the second through-hole 48 and the third through-hole 49 respectively.
[0103] like Figure 15 As shown, the impact tube 53 passes through the first through-hole 47 and the second through-hole 48 and enters the top blocking tube 51, as... Figure 19 As shown, the bottom blocking tube 52 passes through the first through-hole 47 and the third through-hole 47 and enters the impact tube 53, as... Figure 18 As shown, a connecting shaft 416 is provided on the side of the movable cylinder 46, and the movable cylinder 46 is rotatably mounted on the inner wall of the first through-hole 47 via the connecting shaft 416.
[0104] In this invention, the movable cylinder 36 can be rotated to adjust the angle between itself and the positioning cylinder 45, thereby adjusting according to the previously calculated pipe position.
[0105] Since the thickness of the drainage permeable layer 2 is smaller than the width, the inclination of the pipe in the present application is basically small, and the angle between the positioning cylinder 45 and the movable cylinder 46 is small. In order to avoid the rotation adjustment of the movable cylinder 46 by the positioning cylinder 45 from causing stopping, the length of the second through hole 48 and the third through hole 49 is longer than the length of the first through hole 47, and the length of the first through hole 47 is the same as the length of the positioning cylinder 45.
[0106] In the above embodiment, the first through hole 47 extends from the head to the tail along the direction of the positioning cylinder 45, that is, the movable cylinder 46 can be freely rotationally adjusted on the positioning cylinder 45, but in the present embodiment, the second through hole 48 and the third through hole 49 have a certain length limit, which limits the adjustment angle of the corresponding pipe.
[0107] In order to avoid other materials in the drainage permeable layer 2 from entering the pipe through the second through hole 48 and the third through hole 49, the length of the second through hole 48 and the third through hole 48 is determined based on the angle calculation and pipe position calculation each time, so that the impact pipe 53 just abuts on the second through hole 48 to close the second through hole 48, and the bottom blocking pipe 52 just abuts on the third through hole 49 to close the third through hole 49.
[0108] In addition, in order to seal the right side of the second through hole 48 and the third through hole 49, as shown in Figure 6 、 Figure 9 and Figure 10 , the end of the impact pipe 53 and the bottom blocking pipe 52 is provided with an extension plate 410, which extends into the top blocking pipe 51 and the inclined pipe 54, respectively. The extension plate 410 can be provided with a slot structure with an opening.
[0109] In the above embodiment, the length of the extension plate 410 can be calculated according to the angle calculation, and the extension plate 410 with the corresponding length is welded at the end of the impact pipe 53 and the bottom blocking pipe 52, so that the extension plate 410 abuts on the second through hole 48 and the third through hole 49 during installation to achieve closure.
[0110] After the angle of the movable cylinder 46 is adjusted based on the calculation, the movable cylinder 46 needs to be fixed, and the present application is designed as follows: the outer wall of the positioning cylinder 45 is vertically provided with mounting seats 411, the mounting seats 411 are provided in two and symmetrically arranged on the two sides of the first through hole 47, the first threaded grooves 412 are arranged in the mounting seats 411, the first threaded bolts 413 are arranged on the mounting seats 411, the first threaded grooves 412 are matched with the first threaded bolts 413, the second threaded grooves 414 are arranged in the inner walls of the positioning cylinder 45, the top blocking pipe 51 and the inclined pipe 54, the second threaded bolts 415 are arranged in the second threaded grooves 414, and the end portions of the first threaded bolts 413 and the second threaded bolts 415 abut against the outer wall of the movable cylinder 46.
[0111] When the first threaded bolts 413 and the second threaded bolts 415 are rotated and abut against the upper and lower sides of the movable cylinder 46, the movable cylinder 46 is fixed, in addition, the rotation of the second threaded bolts 415 is also the process of fixing the top blocking pipe 51 in the positioning cylinder 45 and fixing the inclined pipe 54 in the positioning cylinder 45, and after the fixing is completed, the installation of the pipeline is started.
[0112] In summary, the main forming steps of the drainage and permeation layer 2 are as follows:
[0113] According to the position of the drainage port 8 and the distance ratio of the end portion of the pipeline, the end position of the inclined pipe 54, the top blocking pipe 51, the bottom blocking pipe 52 and the impact pipe 53 is calculated, so that the angle of the corresponding pipeline is calculated;
[0114] Based on the position and angle of the corresponding pipeline, the length of the second through hole 48, the third through hole 49 and the extension plate 410 is calculated, the bottom blocking pipe 52 and the inclined pipe 54 are punched according to the size of the corresponding port, and the positioning groove 44 is arranged on the fixing frame 43;
[0115] The positioning cylinder 45 is fixed in the positioning groove 44, the fixing frame 43 is inserted into the water body group fault 1, the height of the fixing frame 43 is adjusted according to the position and angle of the pipeline, the angle of the movable cylinder 46 is adjusted, the movable cylinder 46 is temporarily fixed by another clamp or manually, the top blocking pipe 51 and the inclined pipe 54 are respectively inserted into the positioning cylinder 45, the bottom blocking pipe 52 and the impact pipe 53 are respectively inserted into the movable cylinder 46, and the position is adjusted (so that the center line position is aligned);
[0116] After the position is adjusted, the first threaded bolts 413 and the second threaded bolts 415 are rotated and abut against the upper and lower sides of the movable cylinder 46, so that the movable cylinder 46 is fixed, and the top blocking pipe 51 is fixed in the positioning cylinder 45 and the inclined pipe 54 is fixed in the positioning cylinder 45 through the second threaded bolts 415;
[0117] The positioning U-shaped frame 41 is inserted into the water body blocking layer 1, the positioning U-shaped frame 41 is clamped with the top blocking pipe 51 and the inclined pipe 54 away from the end of the drainage port 8 by driving the positioning U-shaped frame 41 to move, and the top blocking pipe 51 and the inclined pipe 54 are fixed on the positioning U-shaped frame 41 away from the end of the drainage port 8 by the positioning shaft 42, after the water body blocking layer 1 is formed, the asphalt gravel is laid between the pipes in the cross-sectional direction to form the drainage permeable layer 2.
[0118] In the present application, in order to achieve the drainage effect, the pipes are closely arranged along the length direction of the road surface, that is, the impact pipe 53, the top blocking pipe 51, the inclined pipe 54 and the bottom blocking pipe 52 at a certain width position form a drainage pipe group, and corresponding drainage pipe groups are arranged at adjacent width positions, and the adjacent drainage pipe groups are closely arranged.
[0119] In order to avoid the water body from entering the deeper layer (the water body blocking layer 1) and flowing down, the upper surface of the water body blocking layer 1 forms an inclined downward slope outward from the road center line 6 as a starting point, the inclination of the water body blocking layer 1 is smaller than the inclination of the bottom blocking pipe 52, and the water body can flow down along the surface of the water body blocking layer 1.
[0120] The above examples are only exemplary embodiments of the present application and are not used to limit the present application, the protection scope of the present application is defined by the claims. Those skilled in the art can make various modifications or equivalent replacements to the present application within the spirit and protection scope of the present application, and such modifications or equivalent replacements are also regarded as falling within the protection scope of the present application.
Claims
1. A method of constructing a road surface drainage barrier, characterized by, The application relates to a waterproof and drainage construction method for a road surface. A cement and gravel mixture is laid on the top of a roadbed base layer to form a water blocking layer; Before the water blocking layer is formed, a positioning steel frame is inserted and fixed on the water blocking layer, and after the water blocking layer is formed, a plurality of drainage pipes are laid on the water blocking layer at equal intervals through the positioning steel frame, and asphalt gravel is laid to form a drainage and permeation layer; Different sizes of asphalt concrete layers are laid on the drainage and permeation layer in sequence to form a road surface layer; The drainage pipes on both sides of the road surface center line form an inclined downward slope, the drainage pipes are provided with a plurality of drainage holes upward, the drainage pipes are provided with at least a top blocking pipe and a bottom blocking pipe, the top blocking pipe and the bottom blocking pipe are arranged in sequence from top to bottom, the top blocking pipe is connected with an impact pipe, and the top blocking pipe and the impact pipe are connected to form an intersection impact area, and the bottom blocking pipe is connected with an inclined pipe. The side surface of the drainage and permeation layer is provided with two drainage openings in the height direction, and the end portions of the top blocking pipe and the inclined pipe extend to the drainage openings at different positions.
2. The waterproof and drainage construction method for a road surface according to claim 1, wherein The inclined pipe and the impact pipe form an inclined downward slope outward from the road surface center line as a starting point. The inclination of the inclined pipe is greater than that of the bottom blocking pipe. The inclination of the impact pipe is greater than that of the top blocking pipe.
3. The waterproof and drainage construction method for a road surface according to claim 2, wherein The connection position of the inclined pipe and the bottom blocking pipe is located at the end portion of the bottom blocking pipe, and the connection position of the impact pipe and the top blocking pipe is away from the end portion of the bottom blocking pipe. The end portions of the top blocking pipe and the inclined pipe are adjacent to each other and away from the drainage openings.
4. The road surface waterproofing construction method according to claim 3, characterized by, Further comprising: Based on the thickness and width of the roadbed base layer, the end portion positions of the inclined pipe, the top blocking pipe, the bottom blocking pipe and the impact pipe are calculated. The distance from the end portion of the impact pipe close to the road surface center line to the top of the drainage and permeation layer is a, the distance from the end portion of the impact pipe close to the road surface center line to the end portion of the top blocking pipe close to the road surface center line is b, and the distance from the end portion of the bottom blocking pipe close to the road surface center line to the end portion of the inclined pipe close to the road surface center line is c, and a:b:c=0.5:1:
1.
5. The waterproof and drainage construction method for a road surface according to claim 4, wherein The positioning steel frame comprises a positioning U-shaped frame arranged at the end portions of the top blocking pipe and the inclined pipe away from the drainage openings, and a positioning shaft arranged in the inner side of the positioning U-shaped frame. The positioning U-shaped frame is inserted on the water blocking layer, the positioning shaft is arranged in two, the outer width of the top blocking pipe is greater than that of the inclined pipe, and the inner width of the top blocking pipe is consistent with that of the inclined pipe. The two side edges close to the bottom of the top blocking pipe are provided with side edge grooves, and the end portions of the positioning shaft are connected in the side edge grooves and the outer wall of the inclined pipe.
6. The road waterproof construction method of claim 5, wherein the positioning steel frame further comprises a fixing frame interposed on the water body blocking layer, four positioning grooves arranged on the fixing frame, a positioning cylinder arranged in the positioning groove, and a movable cylinder movably arranged on the positioning cylinder. The two positioning grooves are opposite to each other, the end of the movable cylinder penetrates through the side of the positioning cylinder and extends into the inside of the positioning cylinder, and the length of the movable cylinder extending into the positioning cylinder is less than the internal height of the top blocking pipe and the inclined pipe. The top blocking pipe and the inclined pipe are installed in the positioning cylinder, the impact pipe and the bottom blocking pipe are installed in the movable cylinder, the end of the impact pipe extends into the top blocking pipe, and the end of the bottom blocking pipe extends into the inclined pipe.
7. The road waterproof construction method of claim 6, wherein a first through hole is arranged on the positioning cylinder, a second through hole is arranged on the top blocking pipe, and a third through hole is arranged on the inclined pipe, and the first through hole corresponds to the second through hole and the third through hole respectively. The length of the second through hole and the third through hole is longer than the length of the first through hole, and the length of the first through hole is the same as the length of the positioning cylinder. The side of the movable cylinder is provided with a connecting shaft, and the movable cylinder is rotatably installed in the inner wall of the first through hole through the connecting shaft.
8. The road waterproof construction method of claim 7, wherein the end of the impact pipe and the bottom blocking pipe is provided with an extension plate, and the extension plate extends into the top blocking pipe and the inclined pipe respectively.
9. The road waterproof construction method of claim 8, wherein the outer wall of the positioning cylinder is vertically provided with a mounting seat, the mounting seat is provided with two mounting seats and is symmetrically arranged on both sides of the first through hole, a first threaded groove is arranged in the mounting seat, a first threaded bolt is arranged on the mounting seat, and the first threaded groove is matched with the first threaded bolt. The inner wall of the positioning cylinder, the top blocking pipe and the inclined pipe is provided with a second threaded groove, and a second threaded bolt is arranged in the second threaded groove. The end of the first threaded bolt and the second threaded bolt abuts against the outer wall of the movable cylinder.
10. The road waterproof construction method of claim 9, wherein the upper surface of the water body blocking layer forms an inclined downward slope outward from the center line of the road surface, and the inclination of the water body blocking layer is less than the inclination of the bottom blocking pipe.
Citation Information
Patent Citations
Highway pavement structure convenient for drainage
CN211227940U
Waterproof roadbed structure
CN216404946U