A full-prism linearity monitoring system and monitoring method for four-tower bridges in offshore space

By setting CP3 embedded parts and a total station monitoring system on the bridge tower template, the problems of accuracy and attitude control in bridge tower construction were solved, and high-precision bridge tower alignment monitoring was achieved, which is suitable for construction monitoring of bridge towers in water.

CN117990065BActive Publication Date: 2026-11-17CCCC SHEC FOURTH ENG
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410093612.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-23
Publication Date
2026-11-17
Estimated Expiration
2044-01-23

AI Technical Summary

Technical Problem

Traditional bridge tower construction suffers from problems such as high precision requirements, difficulty in controlling spatial attitude, large deformation errors of monitoring points, limited measurement base points in water, and obstructed lines of sight, resulting in large construction errors that affect subsequent construction.

Method used

A full-prism alignment monitoring system for the four-tower bridge limbs in the remote space is adopted. By setting CP3 embedded parts, clamping bolts, prism connecting rods and single prism lenses on the bridge tower template, and combining it with a total station for monitoring, a bridge axis coordinate system is established to simultaneously monitor the deformation of each segment of the bridge tower. The high-precision distance measurement of the total station is used to solve the problems of monitoring point installation errors and line-of-sight obstruction.

Benefits of technology

It improved the accuracy of bridge tower alignment monitoring, reduced construction errors, ensured the accuracy of bridge tower spatial attitude, saved construction time and money, and met the measurement needs of bridge towers in water.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117990065B_ABST
    Figure CN117990065B_ABST
Patent Text Reader

Abstract

This invention discloses a full-prism linear monitoring system for a four-tower bridge segment in offshore space. Multiple uniformly distributed single-prism lenses are installed on the four outer sides of the four-tower segment from bottom to top. A monitoring base point is set at a distance from the center of the bottom of each of the four sides of the bridge segment, and a total station is installed at each monitoring base point. This invention also discloses the monitoring method of this system. The above technical solution is simple, intuitive, and easy to implement; it can monitor the deformation of each bridge segment, avoiding the errors caused by estimation; it provides a more accurate grasp of the spatial attitude of the bridge tower; it improves the construction accuracy of the bridge tower; and it solves the problem of limited measurement base points for bridge towers in water. By using the fewest possible measurement base points, it ensures monitoring accuracy while avoiding the cumbersome construction of additional measurement base point platforms in the water, saving construction time and reducing costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the technical field of measurement and control of the alignment of ultra-high bridge towers in offshore waters, specifically relating to a full-prism alignment monitoring system for four-tower bridges in offshore space. This invention also relates to the monitoring method for this monitoring system. Background Technology

[0002] With the continuous development of the national economy and science and technology, navigation and transportation on rivers are bustling day and night. In order to reduce the impact of bridges on shipping, the spans of bridges crossing rivers are getting larger and larger. With the increase in span and main beam self-weight, the structural form of the pylon design also brings continuous challenges to the design units.

[0003] Generally, to meet the requirements of longitudinal stiffness and stress on the tower limbs, it is necessary to significantly increase the cross-sectional dimensions and wall thickness of the tower limbs. However, for large-volume concrete structures, due to the rapid development of early shrinkage and later creep, the risk of concrete cracking gradually increases with the increase of structural dimensions. Therefore, decomposing the planar diamond-shaped bridge tower longitudinally to form a frame structure, i.e., forming a spatial diamond-shaped bridge tower scheme, can not only improve the stiffness of the tower, but also greatly reduce the cross-sectional dimensions of the tower limbs, thereby reducing the problem of cracking in large-section towers and improving the longitudinal stability of the bridge tower. The spatial diamond-shaped four-tower structure will also be increasingly used in long-span cross-river bridge structures.

[0004] Traditional bridge towers often adopt H-shaped, inverted Y-shaped, and A-shaped designs. Currently, bridge towers with diamond-shaped spatial four-legged structures are relatively rare in bridges both domestically and internationally. This type of bridge tower features a novel design, complex external structure, and significant challenges in controlling its spatial posture during construction.

[0005] However, for construction companies, the more novel the structural design and the more diverse the structural forms, the greater the construction difficulty and risks, and the higher the requirements for precision. How to ensure that the spatial attitude of the bridge tower steadily increases according to the theoretical line during construction, and how to accurately measure the completed spatial attitude line of the bridge tower after construction to guide subsequent construction, has become a major challenge in this field.

[0006] A detailed analysis of the problems and defects of existing technologies:

[0007] Firstly, in traditional bridge tower construction, monitoring points are installed on the side of the tower after it reaches a certain height. These monitoring points are then continuously monitored at regular intervals to obtain deformation data. This is done to understand the deformation pattern of the tower and guide the construction of subsequent tower segments. However, this method only measures the deformation of the tower segment with monitoring points and does not consider the deformation errors during the construction of subsequent tower segments, resulting in certain errors in the spatial orientation of the tower during construction.

[0008] Secondly, during the construction of traditional bridge towers, the deformation patterns may not be synchronized at different stages or under different working conditions due to the influence of the external environment and temporary loads. In the construction of four-tower bridges, the impact of asynchronous deformation is even more pronounced due to factors such as sunlight. If the displacement and deformation of each segment are not monitored and the deformation patterns of different tower members are not understood, the spatial orientation of the bridge tower during construction will deviate from the design position.

[0009] Third, in traditional bridge tower monitoring, the length from the center of the monitoring prism to the concrete surface cannot be accurately determined due to the influence of the installation accuracy of the embedded parts. This makes it impossible to directly calculate the center deviation of the completed tower segment through the monitoring prism center. After the bridge tower construction is completed, it is impossible to fully grasp the spatial alignment and attitude of the bare tower during the construction period through monitoring data, and it is impossible to make an accurate assessment of the overall bridge tower attitude, which will have a certain impact on the subsequent steel beam or cable construction.

[0010] Fourth, the four-tower bridge in the water is limited by the geographical environment. The onshore measurement base points do not meet the construction requirements. The existing structures are close to the construction area of ​​the bridge towers, and it is not possible to set up measurement base points at a long distance. The measurement base points under the towers are limited, and the measurement lines of sight between the four towers are mutually blocked. The elevation angle of the measurement lines of sight under the towers is large. When using the traditional total station three-dimensional coordinate method for deformation monitoring, the data accuracy of angle and direction is low. Summary of the Invention

[0011] This invention provides a full-prism alignment monitoring system for four-tower bridges in offshore space, with the aim of improving the accuracy of bridge tower alignment monitoring.

[0012] To achieve the above objectives, the technical solution adopted by the present invention is as follows:

[0013] The present invention relates to a four-tower bridge pier full-prism linear monitoring system for offshore space. The four-tower bridge piers are formed by pouring concrete from bridge tower templates. Multiple uniformly distributed single-prism lenses are set on the four outer sides of the four-tower bridge piers from bottom to top. At a distance from the center of the bottom of the four sides of the four-tower bridge piers, a tower-under-the-tower monitoring base point is set at each of the four tower-under-the-tower monitoring base points, and a total station is set at each tower-under-the-tower monitoring base point.

[0014] CP3 embedded parts are installed in the concrete of the bridge tower; with the single prism lens not installed, the threaded part of the clamping bolt is screwed through the template opening on the bridge tower template into the threaded hole of the CP3 embedded part, and the clamping bolt is clamped to the bridge tower template; with the single prism lens installed, the threaded end of the prism connecting rod is screwed into the threaded hole of the CP3 embedded part; the single prism lens is installed on the outward-facing end of the prism connecting rod.

[0015] To achieve the same inventive objective as the aforementioned technical solution, this invention also provides a monitoring method for the above-described offshore space four-tower limb bridge full-prism linear monitoring system, which includes the following steps:

[0016] Step 1: Drilling holes in the bridge tower template;

[0017] Step 2: Install CP3 embedded parts;

[0018] Step 3: Remove the clamping bolts;

[0019] Step 4: Install the standard monitoring prism connecting rod and single prism lens;

[0020] Step 5: Establishing the bridge axis coordinate system;

[0021] Step 6: As-built measurement of the current tower segment;

[0022] Step 7: Initial data acquisition for the current segment monitoring prism;

[0023] Step 8: Determine the distance and direction data between the two monitoring points using two coordinates;

[0024] Step 9: Calculation of the spatial alignment of the tower limbs;

[0025] Step 10: Calculation of pre-deflection of the tower segment.

[0026] The first step is to drill holes at appropriate positions on the template surface in the direction of the monitoring base point under the corresponding tower before the bridge tower template is hoisted in sections. The diameter of the template opening is consistent with the major diameter of the threaded hole of the CP3 embedded part.

[0027] The second step is to install the CP3 embedded part inside the bridge tower formwork before assembling the bridge tower formwork. Then, use clamping bolts to screw into the threaded holes of the CP3 embedded part through the openings in the formwork on the outside of the bridge tower formwork, and tighten the clamping bolts so that the clamping bolts and the CP3 embedded part are completely clamped onto the formwork.

[0028] In step 3, the bridge tower formwork posture is adjusted and the bridge tower concrete is poured. After the bridge tower concrete is poured, wait for it to solidify to a certain strength and before the bridge tower formwork is removed, then remove the clamping bolts on the outer side of the bridge tower formwork.

[0029] The fourth step involves installing a single prism lens on the outer end of the prism connecting rod during the as-built measurement alignment monitoring after the bridge tower formwork is removed, and then screwing the single prism lens into the threaded hole of the pre-embedded CP3 component.

[0030] In step 5, to facilitate bridge tower construction surveying and make the survey data results more intuitive and clear, before the survey, the design coordinate system is converted into a relatively independent bridge axis mileage coordinate system in conjunction with the survey control network and the bridge tower design structural dimensions; its definition is as follows: the longitudinal direction of the bridge is the X-axis, that is, the mileage direction, and the direction pointing to the larger mileage is the positive direction; the transverse direction of the bridge is the Y-axis, that is, the offset direction, and the direction pointing to the upstream side is the positive direction.

[0031] In step 6, after the concrete pouring of the current segment of the bridge tower is completed, a total station is used to collect the coordinates of the corner points on the top surface of the current segment of the tower. The center data of the current segment of the tower is calculated using the corner point data. This working condition data is used as the initial value of the center line of the current segment of the tower.

[0032] The seventh step involves setting up a total station at the base measurement points in the four directions of the tower during the same time period as the completion measurement of the current tower segment. The station is aimed at the center of the single prism lens to obtain the center data of the monitoring prism and uses this data as the initial value of the monitoring prism.

[0033] The 8th step is as follows: During observation, given the high distance measurement accuracy of the total station, each tower limb monitoring prism only takes the distance direction value from the prism center to the measurement base point at the bottom of the tower as the basis. The distance direction of every two monitoring points connects the longitudinal and transverse directions of the tower limb. Among them, the X-axis of tower limb 1 is the distance direction data of monitoring point L1, and the Y-value is the distance direction data of monitoring point L2; and so on. The numbering is defined as follows: the prefix of the tower limb corner point number is j, and the prefix of the monitoring prism number is L.

[0034] The ninth step involves, after completing the initial data acquisition, measuring the monitoring prisms at different heights on the outer side of the tower limb according to different working conditions, calculating the change in the current monitoring prism data compared to the initial monitoring prism data, and substituting this change into the initial value data of the tower limb center. This allows the acquisition of tower limb center data at different segment heights under different working conditions, achieving the goal of accurately grasping the spatial attitude of the tower limb and providing parameters for subsequent construction.

[0035] In step 10: Considering the two parts of deformation during the bridge tower construction stage, namely the deformation caused by the self-weight of concrete and the deformation caused during the later bridge completion stage, the reverse deformation value needs to be used as the pre-deflection of the plane for the construction formwork before the bridge tower is measured.

[0036] The present invention adopts the above-mentioned technical solution, and its positive technical effects are as follows: its structure is simple and intuitive, and easy to implement; it can monitor the deformation of each bridge tower segment, avoiding the error caused by estimation; when installing the monitoring point, the top surface of the embedded part can be kept flush with the concrete surface, and when the length of the prism connecting rod is known, the center line of each completed bridge tower segment can be directly calculated by monitoring the center data of the prism, so as to more accurately grasp the spatial attitude of the bridge tower; at the same time, the line monitoring and the as-built measurement of the bridge tower segment are completed in the same time period, avoiding the deformation error caused by the time difference between the two measurements, and can monitor the deformation between different tower legs, solving the problem of asynchronous deformation caused by inconsistent temperature or load on the four tower legs, thus improving the construction accuracy of the bridge tower; by utilizing the high distance measurement accuracy of the total station, the problem of limited measurement base points for bridge towers in water is solved. With the minimum number of measurement base points, the monitoring accuracy is guaranteed, while avoiding the cumbersome construction of adding measurement base point platforms in water, saving time and money. Attached Figure Description

[0037] The following is a brief explanation of the contents shown in the attached figure and the markings therein:

[0038] Figure 1 This is a three-dimensional schematic diagram of the four-tower main tower structure of the present invention;

[0039] Figure 2 This is a front view of the four-tower main tower structure of the present invention;

[0040] Figure 3 This is a side view of the four-tower main tower structure of the present invention;

[0041] Figure 4 This is a frontal schematic diagram of the bridge tower full prism monitoring point of the present invention;

[0042] Figure 5 This is a side view of the bridge tower full prism monitoring point of the present invention;

[0043] Figure 6 This is a schematic diagram showing the distribution of the measurement point numbers in this invention;

[0044] Figure 7 This is a schematic diagram of the planar layout of the base points under the field measurement tower according to the present invention;

[0045] Figure 8 This is a schematic diagram of the installation of the embedded parts in this invention;

[0046] Figure 9 This is a schematic diagram of the CP3 embedded part in this invention;

[0047] Figure 10 This is a schematic diagram of the clamping bolt in this invention;

[0048] Figure 11 This is a schematic diagram of the connecting rod in the present invention;

[0049] Figure 12 This is a schematic diagram of the structure of the single-prism lens in this invention;

[0050] Figure 13 This is a schematic diagram illustrating the transformation relationship between the design coordinates and the bridge axis coordinates in this invention;

[0051] Figure 14 This is a schematic diagram showing the center distribution of the tower limbs on the cross-section of the bridge tower in this invention;

[0052] Figure 15 This is a schematic diagram of the coordinate direction and the number of the detection prism in this invention;

[0053] Figure 16 This is a schematic diagram of the pre-biasing amount in this invention.

[0054] The diagram is marked as follows:

[0055] 1. CP3 embedded parts, 2. clamping bolts, 3. prism connecting rods, 4. single prism lenses, 5. bridge tower formwork, 6. formwork openings, 7. bridge tower concrete, 8. tower base measurement benchmarks, 9. knurling on the outer circle of embedded parts, 10. knurling on the outer circle of clamping bolts, 11. flattening of clamping bolts, 12. knurling on the outer circle of connecting rods. Detailed Implementation

[0056] The specific embodiments of the present invention will be further described in detail below with reference to the accompanying drawings, so as to help those skilled in the art to have a more complete, accurate and in-depth understanding of the inventive concept and technical solution of the present invention.

[0057] like Figures 1 to 8 The structure shown in this invention is a full-prism linear monitoring system for a four-tower bridge in offshore space. The four-tower bridge is formed by pouring concrete 7 from a bridge tower template 5.

[0058] In order to solve the problems and overcome the defects of the existing technology and achieve the invention objective of improving the accuracy of bridge tower alignment monitoring, the technical solution adopted by the present invention is as follows:

[0059] like Figures 1 to 8 As shown, the offshore space four-tower limb bridge tower full prism linear monitoring system of the present invention has multiple uniformly distributed single prism lenses 4 on the four outer sides of the four-tower limb bridge tower from bottom to top; and a tower monitoring base point 8 is set at a distance from the center of the bottom of the four sides of the four-tower limb bridge tower, and a total station is set at each tower monitoring base point 8.

[0060] like Figures 8 to 12 As shown:

[0061] CP3 embedded part 1 is installed in the bridge tower concrete 7; with the single prism lens 4 not installed, the threaded part of the clamping bolt 2 is screwed through the template opening 6 on the bridge tower template 5 into the threaded hole of the CP3 embedded part 1 to clamp the clamping bolt 2 to the bridge tower template 5; with the single prism lens 4 installed, the threaded end of the prism connecting rod 3 is screwed into the threaded hole of the CP3 embedded part 1; the single prism lens 4 is installed on the outward end of the prism connecting rod 3.

[0062] Specifically, the related devices used in this invention include CP3 embedded parts 1, clamping bolts 2, prism connecting rods 3, single prism lenses 4, and total stations.

[0063] Its structure and function are as follows:

[0064] 1. For example Figure 9 As shown, CP3 embedded part 1 is a type of railway settlement monitoring CP3 embedded part, made of stainless steel rod, with knurled outer circle 9 on the surface, and is a standard part. The function of the knurled outer circle 9 of the embedded part is to increase friction and improve the connection strength with the bridge tower concrete 7.

[0065] 2. For example Figure 10 As shown, the clamping bolt 2 is a machined part that matches the CP3 embedded part 1. The material is stainless steel, and the surface is provided with the outer circle knurling 10 of the clamping bolt, which is used to increase the friction. At its end, there is also a clamping bolt flat 11, which consists of two milled planes for tightening or loosening with a wrench. The bolt length is not less than the template thickness.

[0066] 3. For example Figure 11 As shown, the prism connecting rod 3 is a standard stainless steel CP3 connecting rod for railway settlement observation. One end is equipped with a screw that matches the threaded hole of the CP3 embedded part 1; the other end is equipped with an adapter with an annular groove, which can be connected to the single prism lens 4. Its surface is also provided with knurled outer circle 12 to increase friction.

[0067] 4. For example Figure 12 As shown, the single prism lens 4 is equipped with a prism frame that matches the prism connecting rod 3. The single prism lens 4 is used in conjunction with a total station monitoring instrument.

[0068] To achieve the same inventive objective as the aforementioned technical solution, this invention also provides a monitoring method for the above-described offshore space four-tower limb bridge full-prism linear monitoring system, which includes the following steps:

[0069] Step 1: Make 5 holes in the bridge tower formwork:

[0070] Before hoisting the 5-section formwork of the bridge tower, drill holes at appropriate positions on the formwork surface in the direction of the corresponding monitoring base point 8 under the tower, and drill the formwork opening 6. The diameter of the formwork opening 6 is consistent with the major diameter of the threaded hole of the CP3 embedded part 1.

[0071] After the initial drilling, if the template is not replaced subsequently, the drilling location can be reused, which can reduce damage to the integrity of the template's appearance.

[0072] Step 2, Install CP3 Embedded Part 1:

[0073] like Figure 8 As shown, before the bridge tower formwork 5 is assembled, the CP3 embedded part 1 is installed on the inside of the bridge tower formwork 5. The clamping bolt 2 is screwed into the threaded hole of the CP3 embedded part 1 through the formwork opening 6 on the outside of the bridge tower formwork 5, and the clamping bolt 2 is tightened so that the clamping bolt 2 and the CP3 embedded part 1 are completely clamped on the formwork 5.

[0074] This effectively prevents gaps at the opening from causing grout leakage, thus ensuring the construction quality of the concrete in this area.

[0075] Step 3: Remove clamping bolt 2:

[0076] After the bridge tower formwork 5 is adjusted, the bridge tower concrete 7 is poured. After the bridge tower concrete 7 is poured, wait for it to solidify to a certain strength and before the bridge tower formwork 5 is removed, then remove the clamping bolts 2 on the outer side of the bridge tower formwork 5.

[0077] By tightening bolt 2, the surface of CP3 embedded part 1 can be made completely flush with the surface of bridge tower concrete 7, which improves the accuracy of the monitoring prism line measurement and ensures the accuracy of the bridge tower spatial line calculation using the monitoring prism.

[0078] Step 4: Install the standard monitoring prism connecting rod 3 and single prism lens 4:

[0079] like Figure 4 As shown, after the bridge tower formwork 5 is removed, during the as-built measurement and alignment monitoring, the single prism lens 4 is installed on the outer end of the prism connecting rod 3, and together with the single prism lens 4, it is screwed into the threaded hole of the pre-embedded CP3 pre-embedded part 1.

[0080] The CP3 embedded part 1 on the bridge tower concrete 7 can keep the center of the single prism lens 4 perpendicular to the plane of the bridge tower concrete 7, thus improving the accuracy of line measurement.

[0081] Step 5: Establishing the bridge axis coordinate system:

[0082] like Figure 13As shown, in order to facilitate bridge tower construction surveying and make the survey data results more intuitive and clear, before the survey, the design coordinate system is transformed into a relatively independent bridge axis mileage coordinate system in combination with the survey control network and the design structural dimensions of the bridge tower; its definition is as follows: the longitudinal direction of the bridge is the X-axis, that is, the mileage direction, and the direction pointing to the larger mileage is the positive direction; the transverse direction of the bridge is the Y-axis, that is, the offset direction, and the direction pointing to the upstream side is the positive direction.

[0083] In the design coordinate system, the coordinates of point P are (X... P Y P ), calculate the coordinates of point P' in the bridge axis construction coordinate system as (X P’ Y P’ The formula for () is as follows:

[0084] ;

[0085] ;

[0086] In the formula:

[0087] (X) P’ Y P’ Let P be the coordinates of point P in the bridge axis coordinate system;

[0088] (X) P Y P Let P be the coordinates of point P in the design coordinate system;

[0089] (X5, Y5) are the coordinates of the center of the No. 5 pier column in the design coordinate system;

[0090] (X) 5’ Y 5’ () represents the coordinates of the center of pier #5 in the bridge axis coordinate system;

[0091] β is the difference in coordinate azimuth angle, that is, the rotation angle between the two coordinate systems.

[0092] Step 6: As-built measurement of the current tower segment:

[0093] like Figure 14 As shown, after the concrete 7 of the current segment tower is poured, a total station is used to collect the coordinates of the corner points on the top surface of the current segment tower limb, and the center data of the current segment tower limb is calculated through the corner point data; and this working condition data is used as the initial value of the center line of the current segment tower limb.

[0094] The coordinates of the corner points of the current tower segment are (X1, ..., X8; Y1, ..., Y8), and the center coordinates of the single tower segment (X-center, Y-center) are the average of the corner point coordinates, i.e.:

[0095] X_center = (J1X + J2X + J3X + J4X + J5X + J6X + J7X + J8X) / 8;

[0096] Y center = (J1Y+J2Y+J3Y+J4Y+J5Y+J6Y+J7Y+J8Y) / 8;

[0097] Step 7: Initial data acquisition for the current segment monitoring prism:

[0098] like Figure 7 As shown, during the same time period of the completion measurement of the current segment of the tower, a total station is set up on the measurement base point 8 under the tower in four directions of the bridge tower, aiming at the center of the single prism lens 4, to obtain the center data of the monitoring prism, and using this data as the initial value of the monitoring prism.

[0099] Step 8: Determine the distance and direction data between the two monitoring points using two coordinates:

[0100] like Figure 15 As shown, during observation, given the high distance measurement accuracy of the total station, each tower limb monitoring prism only takes the distance direction value from the prism center to the measurement base point (8) at the bottom of the tower as the basis, and the distance direction of every two monitoring points connects the longitudinal and transverse directions of the tower limb; among them, the X-axis of tower limb 1 is the distance direction data of monitoring point L1, and the Y value is the distance direction data of monitoring point L2; the rest are analogous; the definition of its number is: the prefix of the tower limb corner point number is j, and the prefix of the monitoring prism number is L.

[0101] The measurement of the initial value of the prism monitoring should be completed simultaneously with the final measurement of the tower limbs to avoid tower limb deformation due to asynchronous observation times, which would lead to errors in the initial calculation of the tower limb shape.

[0102] Step 9: Calculation of the spatial alignment of the tower limbs:

[0103] After the initial data acquisition is completed, the monitoring prisms at different heights on the outside of the tower limb are measured according to different working conditions. The change value between the current monitoring prism data and the initial monitoring prism data is calculated. This change value is then substituted into the initial value data of the tower limb center to obtain the tower limb center data at different segment heights under different working conditions. This achieves the goal of accurately grasping the spatial attitude of the tower limb and provides parameters for subsequent construction.

[0104] For example, the formula for calculating the spatial alignment data of the center of tower leg No. 1 under different working conditions is as follows:

[0105] X1 center = X1 initial value + (LX1 - LX1 initial value);

[0106] Y1 center = Y1 initial value + (LY2 - LY1 initial value);

[0107] In the formula:

[0108] The initial values ​​of X1 and Y1 are the X and Y coordinates of the center of the segment tower under the completed working condition, which are the average values ​​of the coordinates of the 8 corner points.

[0109] The initial value of LX1 is the distance and direction data of the monitoring prism at point L1 of each tower segment observed under the completed construction condition.

[0110] The initial value of LY2 is the distance and direction data of the monitoring prism at point L2 of each tower segment observed under the completed working condition.

[0111] LX1 represents the distance and direction data of the monitoring prism at point L1 of each tower segment observed under the current operating conditions.

[0112] LY2 represents the distance and direction data of the monitoring prism at point L2 of each tower segment observed under the current operating conditions.

[0113] The same applies to the rest.

[0114] Step 10, Calculation of pre-offset of the tower segment:

[0115] like Figure 16 As shown, considering the two parts of deformation during the bridge tower construction stage, namely the deformation caused by the self-weight of concrete and the deformation caused during the later bridge completion stage, the reverse deformation value needs to be used as the pre-deflection of the plane for the construction formwork before the bridge tower is measured.

[0116] Therefore, when measuring and laying out the X and Y directions at the top of the current segment of the tower, the displacement increment value is superimposed on that of the adjacent segments to ensure that it reaches the design position in the completed bridge state.

[0117] For the bottom of a segment, its template is consistent with that of the completed segment, and the pre-bias is zero.

[0118] Compared with the prior art, the beneficial effects achieved by the present invention are:

[0119] The method for monitoring the full prism alignment of four-tower bridge segments in offshore space according to the present invention is simple, intuitive, and easy to implement. It can monitor the deformation of each bridge segment and avoid the error caused by estimation.

[0120] When installing the monitoring point, the top surface of the embedded part can be kept flush with the concrete surface. With the length of the prism connecting rod 3 known, the center line of each completed bridge tower segment can be directly calculated by monitoring the center data of the prism, so as to more accurately grasp the spatial attitude of the bridge tower.

[0121] Meanwhile, by completing the alignment monitoring and the final measurement of the bridge tower segments in the same time period, the deformation error caused by the time difference between the two measurements is avoided. It also allows for monitoring of the deformation between different tower segments, solving the problem of asynchronous deformation caused by inconsistent temperature or load on the four-tower bridge segments, and improving the construction accuracy of the bridge tower.

[0122] Furthermore, by utilizing the high distance measurement accuracy of total stations, the problem of limited measurement base points for bridge towers in water was solved. By using the fewest possible measurement base points, monitoring accuracy was ensured while avoiding the cumbersome construction of adding measurement base point platforms in the water, thus saving time and money.

[0123] The present invention has been described above by way of example with reference to the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-described manner. Any non-substantial improvements made using the inventive concept and technical solution of the present invention, or the direct application of the inventive concept and technical solution of the present invention to other occasions without modification, are all within the protection scope of the present invention.

Claims

1. A monitoring method for a full prism linear monitoring system for a four-tower bridge in a remote space, wherein the four-tower bridge is formed by pouring concrete (7) from a bridge tower template (5), and multiple uniformly distributed single prism lenses (4) are set on the four outer sides of the four-tower bridge from bottom to top; at a distance from the center of the bottom of the four sides of the four-tower bridge, a tower monitoring base point (8) is set on each tower, and a total station is set on each tower monitoring base point (8); CP3 embedded parts (1) are installed in the bridge tower concrete (7); in the state without the single prism lens (4) installed, the threaded part of the clamping bolt (2) is passed through the template opening (6) on the bridge tower template (5) and screwed into the threaded hole of the CP3 embedded part (1) to clamp the clamping bolt (2) and the bridge tower template (5); in the state with the single prism lens (4) installed, the threaded end of the prism connecting rod (3) is screwed into the threaded hole of the CP3 embedded part (1); the single prism lens (4) is installed on the outward end of the prism connecting rod (3); characterized in that The monitoring method includes the following steps: Step 1: Drill holes in the bridge tower template (5); Step 2, Install CP3 embedded parts (1); Step 3, Remove the clamping bolts (2); Step 4: Install the standard monitoring prism connecting rod (3) and single prism lens (4); Step 5: Establishing the bridge axis coordinate system; Step 6: As-built measurement of the current tower segment; Step 7: Initial data acquisition for the current segment monitoring prism; Step 8: Determine the distance and direction data between the two monitoring points using two coordinates; Step 9: Calculation of the spatial alignment of the tower limbs; Step 10: Calculation of pre-deflection of the tower segment; The first step is to drill holes at appropriate positions on the template surface in the direction of the corresponding tower monitoring base point (8) before the bridge tower template (5) is hoisted in sections, and to drill template openings (6). The diameter of the template openings (6) is consistent with the major diameter of the threaded hole of the CP3 embedded part (1). The second step is to install the CP3 embedded part (1) inside the bridge tower template (5) before assembling the bridge tower template (5), and screw the clamping bolt (2) into the threaded hole of the CP3 embedded part (1) through the template opening (6) on the outside of the bridge tower template (5), and tighten the clamping bolt (2) so that the clamping bolt (2) and the CP3 embedded part (1) are completely clamped on the template (5); In the third step, the posture of the bridge tower formwork (5) is adjusted and the bridge tower concrete (7) is poured. After the bridge tower concrete (7) is poured, before it reaches a certain strength and before the bridge tower formwork (5) is removed, the clamping bolts (2) on the outer side of the bridge tower formwork (5) are removed. The fourth step is to install the single prism lens (4) on the outer end of the prism connecting rod (3) during the as-built measurement and alignment monitoring after the bridge tower template (5) is removed, and screw the single prism lens (4) into the threaded hole of the pre-embedded CP3 pre-embedded part (1). In step 5, to facilitate bridge tower construction surveying and make the survey data results more intuitive and clear, before the survey, the design coordinate system is transformed into a relatively independent bridge axis mileage coordinate system in conjunction with the survey control network and the bridge tower design structural dimensions; its definition is as follows: the longitudinal direction of the bridge is the X-axis, that is, the mileage direction, and the direction pointing to the larger mileage is positive; the transverse direction of the bridge is the Y-axis, that is, the offset direction, and the direction pointing to the upstream side is positive. In step 6, after the concrete (7) of the current segment tower is poured, a total station is used to collect the coordinates of the corner points on the top surface of the current segment tower and to calculate the center data of the current segment tower using the corner point data; and this working condition data is used as the initial value of the center line of the current segment tower. The seventh step is to set up a total station on the monitoring base point (8) under the tower in the four directions of the bridge tower during the same time period as the completion measurement of the current tower segment, aim at the center of the single prism (4), obtain the center data of the monitoring prism, and use this data as the initial value of the monitoring prism. The 8th step is as follows: During observation, given the high distance measurement accuracy of the total station, each tower limb monitoring prism only takes the distance direction value from the prism center to the monitoring base point (8) at the bottom of the tower as the basis, and the distance direction of every two monitoring points connects the longitudinal and transverse directions of the tower limb; among them, the X-axis of tower limb 1 is the distance direction data of monitoring point L1, and the Y value is the distance direction data of monitoring point L2; the rest are similar; the definition of its number is: the prefix of the tower limb corner point number is j, and the prefix of the monitoring prism number is L; The 9th step involves, after completing the initial data acquisition, measuring the monitoring prisms at different heights on the outside of the tower limb according to different working conditions, calculating the change value between the current monitoring prism data and the initial monitoring prism data, and substituting this change value into the initial value data of the tower limb center. This allows the acquisition of tower limb center data at different segment heights under different working conditions, achieving the goal of accurately grasping the spatial attitude of the tower limb and providing parameters for subsequent construction. In step 10, considering the two parts of deformation during the bridge tower construction stage (deformation due to the self-weight of concrete and deformation during the later bridge completion stage), the reverse deformation value needs to be used as the pre-deflection of the plane for the construction formwork before the bridge tower is measured.

Citation Information

Patent Citations

  • Control method for synchronous construction survey of pylons and beams of cable-stayed bridge

    CN102251478A

  • Ultrahigh-space diamond-shaped four-tower-limb cable bent tower and construction method thereof

    CN114717939A