The invention relates to the technical field of
mining engineering, in particular to an extra-thick
coal seam fully mechanized caving face bearing pressure distribution
simulation analysis method which comprises the steps of S1, bearing stability analysis; s2, crack analysis; s3, analyzing the influence of the
topping operation; s4, evaluating feasibility of roof
cutting roadway protection; according to the method, the stress data of the
coal pillar are collected and analyzed to obtain the bearing stability of the
coal pillar, the crack propagation speed is analyzed through
image acquisition, so that the crack severity degree of the top plate is obtained, and the effect evaluation coefficient of the coal seam roof
cutting operation is obtained according to the pressure
parameter analysis of the coal seam working face after the roof
cutting operation. The roadway deformation amount and the surrounding rock stability are obtained through
video recording analysis, and then the feasibility of roof cutting roadway protection is obtained through analysis, so that the coal seam fully mechanized caving face bearing pressure influence evaluation index is comprehensively analyzed, targeted measures can be better taken to guarantee
operation safety, the mining technology and process can be optimized, and the mining efficiency is improved.