Risk assessment method for receiving power grid under multiple DC commutation failures
By evaluating the commutation failure probability, power loss ratio and missing energy ratio in the DC system, combined with the entropy weight method, the problem of the inability to accurately evaluate the commutation failure risk of the DC system in the existing technology is solved, and the risk of the receiving end power grid is realized. Assessment ensures the safe and stable operation of the system.
Patent Information
- Application Number
- CN202311815897.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2043-12-26
AI Technical Summary
The existing short-circuit ratio cannot accurately and comprehensively assess the risk level of commutation failure in the DC system, resulting in the inability to effectively ensure the safe and stable operation of the receiving end power grid with a high power proportion.
This paper proposes a risk assessment method for the receiving power grid in the case of multiple DC commutation failures. By obtaining the commutation failure probability of the bus in the DC system due to a three-phase grounding short-circuit fault, and the loss of the DC system due to a three-phase grounding short-circuit fault. The power ratio and the ratio of missing energy to the maximum releasable rotor kinetic energy are combined with the entropy weight method to calculate the risk, providing a more direct and accurate risk assessment.
This method can more accurately reflect the safety and stability risks caused by multiple DC commutation failures faced by the receiving-end power grid, provide a reference for the planning and operation of multiple DC feed-in receiving-end power grids, and ensure the safe and stable operation of the system.
Smart Images

Figure CN117996724B_ABST
Abstract
Description
[Technical field]
[0001] The present application relates to the field of power grid safety technology, and in particular to a risk assessment method for a receiving-end power grid in the event of multiple DC commutation failures. [Background technology]
[0002] my country's energy and load show the characteristics of reverse distribution from east to west. Both fossil energy and clean energy are mainly distributed in the western region of my country, while the load center is located in the eastern coastal area of my country. Therefore, the transmission of electricity from west to east has become an important solution to my country's energy problem. With the implementation of the West-East Power Transmission Project, the number and capacity of DC systems have increased significantly, and the power grid in the eastern coastal area has gradually evolved into a receiving-end power grid with a high power receiving ratio. Since the grid phase-commutation converter as an inverter station has the phenomenon of phase-commutation failure, the simultaneous phase-commutation failure of multiple DC has become one of the important factors threatening the safe and stable operation of the receiving-end power grid. Specifically, the simultaneous phase-commutation failure of multiple DCs will cause the system to be short-term power insufficient, destroy the balance between supply and demand, and even cause system instability. In order to ensure the safe and stable operation of the receiving-end power grid with a high power receiving ratio, it is urgent to study the severity assessment method of multiple DC phase-commutation failures.
[0003] The current common method used in engineering to evaluate commutation failure in multiple DC systems is to use the short-circuit ratio of multiple infeeds. However, the short-circuit ratio itself is an indicator of the relative strength between the AC system and the DC system, which directly reflects the static stability of the DC system, and has no direct connection with transient problems such as commutation failure. In other words, using the short-circuit ratio as a risk assessment standard for commutation failure cannot fully and accurately reflect the true risk level of commutation failure in the DC system.
[0004] Therefore, how to comprehensively and accurately assess the real risk level of commutation failure in DC systems has become a technical problem that needs to be solved urgently. [Summary of the invention]
[0005] An embodiment of the present application provides a risk assessment method for a receiving-end power grid in the event of multiple DC commutation failures, aiming to solve the technical problem in the related art that the risk level of DC system commutation failure cannot be accurately and comprehensively assessed based on the short-circuit ratio.
[0006] In a first aspect, an embodiment of the present application provides a risk assessment method for a receiving-end power grid in the event of multiple DC commutation failures, comprising:
[0007] Acquire a first ratio of each DC system of the receiving-end power grid, wherein the first ratio is used to reflect the probability of a DC commutation failure caused by a three-phase ground short circuit fault on a busbar in the DC system;
[0008] Acquire a second ratio of each bus of the receiving-end power grid, wherein the second ratio is used to reflect the situation that the DC system power of the bus is lost due to a three-phase ground short circuit fault;
[0009] Acquire a third ratio of each DC system of the receiving-end power grid, wherein the third ratio is used to reflect the proportion of missing energy when DC commutation failure occurs due to a three-phase ground short-circuit fault in each busbar of each DC system in the receiving-end power grid in the maximum releasable rotor kinetic energy of the receiving-end power grid;
[0010] The risk level of the receiving-end power grid is determined based on the first ratio, the second ratio, and the third ratio.
[0011] In one embodiment of the present application, optionally, obtaining the first ratio of each DC system of the receiving-end power grid includes:
[0012] For each DC system of the receiving-end power grid, the number of faulty buses in the DC system that have DC commutation failures due to a three-phase ground short circuit fault and the total number of buses in the DC system are obtained;
[0013] The ratio of the number of the faulty busbars to the total number of the busbars is determined as the first ratio.
[0014] In one embodiment of the present application, optionally, the obtaining the second ratio of each bus of the receiving-end power grid includes:
[0015] For each bus of the receiving power grid, the amount of DC system power lost by the bus due to a three-phase ground short circuit fault and the total amount of external DC power of the receiving power grid are obtained;
[0016] The ratio of the amount of the lost DC system power to the total amount of the external DC power is determined as the second ratio.
[0017] In one embodiment of the present application, optionally, obtaining the third ratio of each DC system of the receiving-end power grid includes:
[0018] For each DC system of the receiving-end power grid, obtaining missing power when DC commutation failure occurs in the DC system;
[0019] Based on the missing power of the DC system, determining the missing energy of each node where a three-phase ground short circuit fault may occur;
[0020] Obtain the maximum allowable released rotor kinetic energy for each DC system;
[0021] A third ratio of each DC system is determined based on a maximum allowed released rotor kinetic energy of each DC system and a maximum energy of the missing energy of each of the nodes.
[0022] In one embodiment of the present application, optionally, for each DC system of the receiving-end power grid, obtaining missing power when DC commutation failure occurs in the DC system includes:
[0023] For each DC system of the receiving-end power grid, the missing power when a DC commutation failure occurs in the DC system is determined based on the DC commutation failure duration, the DC commutation failure repair time, the initial DC power and the time-dependent transformation function of the DC power of the DC system.
[0024] In one embodiment of the present application, optionally, determining the missing energy of each node where a three-phase ground short circuit fault may occur based on the missing power of the DC system includes:
[0025] For each node where a three-phase ground short circuit fault may occur, determining a set of DC systems where a DC commutation failure occurs due to the three-phase ground short circuit fault occurring at the node;
[0026] The sum of the missing powers of the DC systems in the DC system set is determined as the missing energy of the node.
[0027] In one embodiment of the present application, optionally, obtaining the maximum allowable released rotor kinetic energy of each DC system includes:
[0028] For each DC system, the maximum allowable released rotor kinetic energy of the DC system is determined based on the rated speed of the unit, the minimum allowable speed of the unit and the rotational inertia of the unit, wherein:
[0029]
[0030] W eg i is the maximum allowable released rotor kinetic energy of the ith DC system, J i is the moment of inertia of the i-th DC system, ω0 is the rated speed of the i-th DC system, ω min is the minimum allowable speed of the unit in the i-th DC system.
[0031] In one embodiment of the present application, optionally, determining the third proportion of the receiving-end power grid based on the maximum allowable released rotor kinetic energy of each DC system and the maximum energy of the missing energy of each node includes:
[0032] Based on the maximum allowable released rotor kinetic energy of each DC system, determining the sum of the maximum allowable released rotor kinetic energy of all units of the receiving-end power grid;
[0033] The ratio of the maximum energy to the sum of the maximum allowable released rotor kinetic energies of all the units is determined as the third ratio.
[0034] In one embodiment of the present application, optionally, determining the risk level of the receiving-end power grid based on the first ratio, the second ratio, and the third ratio includes:
[0035] Based on the first ratio, the second ratio and the third ratio, respectively determine the indicator values of the three risk indicators of the receiving-end power grid;
[0036] Obtaining a normalized value of each DC system of the receiving-end power grid under each risk index;
[0037] Determining the entropy value of each risk indicator based on the normalized value of each DC system under each risk indicator;
[0038] Determining a first weight coefficient of each risk indicator based on the entropy value of each risk indicator;
[0039] Determining a third weight coefficient for each risk indicator based on the first weight coefficient and a predetermined second weight coefficient;
[0040] Based on the third weight coefficient of each risk indicator, the indicator values of the risk indicators of the receiving-end power grid are weighted and summed to obtain the risk of the receiving-end power grid.
[0041] In one embodiment of the present application, optionally, determining the respective indicator values of the three risk indicators of the receiving-end power grid based on the first ratio, the second ratio, and the third ratio respectively includes:
[0042] Determine the maximum value of the first ratio of each DC system of the receiving-end power grid as the indicator value of the first risk indicator;
[0043] Determine the maximum value of the second ratio of each bus of the receiving-end power grid as the indicator value of the second risk indicator;
[0044] The maximum value of the third ratios of each DC system of the receiving-end power grid is determined as an indicator value of the third risk indicator.
[0045] In one embodiment of the present application, optionally, determining the entropy value of each risk indicator based on the normalized value of each DC system under each risk indicator includes:
[0046] For each risk index, the entropy value of the risk index is determined based on the normalized value of each DC system of the receiving power grid under the risk index and the sum of the normalized values of all DC systems of the receiving power grid under the risk index, wherein:
[0047]
[0048] Among them, D j is the entropy value of the j-th risk index, j is 1, 2 or 3, q ij is the ratio of the normalized value of the i-th DC system of the receiving power grid under the j-th risk index to the sum of the normalized values of all DC systems of the receiving power grid under the j-th risk index, n is the total number of DC systems of the receiving power grid, and m is the product of n and the total number of risk indicators.
[0049] In one embodiment of the present application, optionally, determining the first weight coefficient of each risk indicator based on the entropy value of each risk indicator includes:
[0050] For each risk indicator, determining a numerator parameter and a denominator parameter of the entropy value of the risk indicator;
[0051] The ratio of the numerator parameter to the denominator parameter is determined as the first weight coefficient of the risk index, wherein:
[0052]
[0053] w j ″ is the first weight coefficient of the j-th risk index, D j is the entropy value of the j-th risk index, 1-D j is the molecular parameter of the j-th risk index, is the denominator parameter, representing the sum of the entropy values of all risk indicators of the receiving-end power grid.
[0054] In one embodiment of the present application, optionally, determining the third weight coefficient of each risk indicator based on the first weight coefficient and a predetermined second weight coefficient includes:
[0055] Obtaining a square root of a product of the first weight coefficient and a predetermined second weight coefficient;
[0056] For each risk indicator, the ratio of the square root value corresponding to the risk indicator to the sum of the square roots corresponding to all risk indicators is determined as the third weight coefficient.
[0057] In a second aspect, an embodiment of the present application provides a risk assessment device for a receiving-end power grid in the event of multiple DC commutation failures, comprising:
[0058] A first ratio acquisition unit, used for acquiring a first ratio of each DC system of the receiving-end power grid, wherein the first ratio is used for reflecting the probability of a DC commutation failure caused by a three-phase ground short circuit fault on a busbar in the DC system;
[0059] A second ratio acquisition unit, used to acquire a second ratio of each bus of the receiving-end power grid, wherein the second ratio is used to reflect the situation that the DC system power of the bus is lost due to a three-phase ground short circuit fault;
[0060] A third ratio acquisition unit is used to acquire a third ratio of each DC system of the receiving-end power grid, wherein the third ratio is used to reflect the proportion of missing energy when DC commutation failure occurs due to a three-phase ground short-circuit fault on each busbar of each DC system in the receiving-end power grid in the maximum releasable rotor kinetic energy of the receiving-end power grid;
[0061] A risk determination unit is used to determine the risk of the receiving-end power grid based on the first ratio, the second ratio and the third ratio.
[0062] In one embodiment of the present application, optionally, the first ratio acquisition unit is used to:
[0063] For each DC system of the receiving-end power grid, the number of faulty busbars in the DC system that have DC commutation failure due to a three-phase ground short-circuit fault and the total number of buses in the DC system are obtained; and the ratio of the number of faulty busbars to the total number of buses is determined as the first ratio.
[0064] In one embodiment of the present application, optionally, the second ratio acquisition unit is used to:
[0065] For each bus of the receiving power grid, the amount of DC system power lost by the bus due to a three-phase ground short-circuit fault and the total amount of external DC power of the receiving power grid are obtained; and the ratio of the amount of lost DC system power to the total amount of external DC power is determined as the second ratio.
[0066] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0067] For each DC system of the receiving-end power grid, the missing power when DC commutation failure occurs in the DC system is obtained; based on the missing power of the DC system, the missing energy of each node where a three-phase ground short circuit fault may occur is determined; the maximum allowable released rotor kinetic energy of each DC system is obtained; and based on the maximum energy of the maximum allowable released rotor kinetic energy of each DC system and the missing energy of each node, the third ratio of each DC system is determined.
[0068] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0069] For each DC system of the receiving-end power grid, the missing power when a DC commutation failure occurs in the DC system is determined based on the DC commutation failure duration, the DC commutation failure repair time, the initial DC power and the time-dependent transformation function of the DC power of the DC system.
[0070] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0071] For each node where a three-phase ground short circuit fault may occur, a set of DC systems where DC commutation failure occurs due to the three-phase ground short circuit fault at the node is determined; and the sum of the missing powers of each DC system in the set of DC systems is determined as the missing energy of the node.
[0072] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0073] For each DC system, the maximum allowable released rotor kinetic energy of the DC system is determined based on the rated speed of the unit, the minimum allowable speed of the unit and the rotational inertia of the unit, wherein:
[0074]
[0075] W eg i is the maximum allowable released rotor kinetic energy of the ith DC system, J i is the moment of inertia of the i-th DC system, ω0 is the rated speed of the i-th DC system, ω min is the minimum allowable speed of the unit in the i-th DC system.
[0076] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0077] Based on the maximum allowable released rotor kinetic energy of each DC system, the sum of the maximum allowable released rotor kinetic energy of all units of the receiving power grid is determined; and the ratio of the maximum energy to the sum of the maximum allowable released rotor kinetic energy of all units is determined as the third ratio.
[0078] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0079] Based on the first ratio, the second ratio and the third ratio, respectively determine the indicator values of the three risk indicators of the receiving power grid; obtain the normalized value of each DC system of the receiving power grid under each risk indicator; based on the normalized value of each DC system under each risk indicator, determine the entropy value of each risk indicator; based on the entropy value of each risk indicator, determine the first weight coefficient of each risk indicator; based on the first weight coefficient and the predetermined second weight coefficient, determine the third weight coefficient of each risk indicator; based on the third weight coefficient of each risk indicator, perform weighted summation of the indicator values of each risk indicator of the receiving power grid to obtain the risk of the receiving power grid.
[0080] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0081] The maximum value among the first ratios of each DC system of the receiving power grid is determined as the index value of the first risk index; the maximum value among the second ratios of each bus of the receiving power grid is determined as the index value of the second risk index; the maximum value among the third ratios of each DC system of the receiving power grid is determined as the index value of the third risk index.
[0082] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0083] For each risk index, the entropy value of the risk index is determined based on the normalized value of each DC system of the receiving power grid under the risk index and the sum of the normalized values of all DC systems of the receiving power grid under the risk index, wherein:
[0084]
[0085] Among them, D j is the entropy value of the j-th risk index, j is 1, 2 or 3, q ij is the ratio of the normalized value of the i-th DC system of the receiving power grid under the j-th risk index to the sum of the normalized values of all DC systems of the receiving power grid under the j-th risk index, n is the total number of DC systems of the receiving power grid, and m is the product of n and the total number of risk indicators.
[0086] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0087] For each risk index, determine the numerator parameter and denominator parameter of the entropy value of the risk index; determine the ratio of the numerator parameter to the denominator parameter as the first weight coefficient of the risk index, wherein,
[0088]
[0089] w j ″ is the first weight coefficient of the j-th risk index, D j is the entropy value of the j-th risk index, 1-D j is the molecular parameter of the j-th risk index, is the denominator parameter, representing the sum of the entropy values of all risk indicators of the receiving-end power grid.
[0090] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0091] Obtain the square root of the product of the first weight coefficient and a predetermined second weight coefficient; for each risk indicator, determine the ratio of the square root corresponding to the risk indicator to the sum of the square roots corresponding to all risk indicators as the third weight coefficient.
[0092] In a third aspect, an embodiment of the present application provides a computer device, comprising: at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are configured to execute the method described in the first aspect above.
[0093] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium storing computer-executable instructions, wherein the computer-executable instructions are used to execute the method described in the first aspect above.
[0094] The above technical scheme aims at the technical problem that the risk level of DC system commutation failure cannot be accurately and comprehensively evaluated based on the short-circuit ratio in the related technology. A multi-DC commutation failure severity evaluation index system for the receiving-end power grid with a high power receiving ratio is established, which includes three risk indicators: the proportion of short-circuit faults causing DC commutation failure, the proportion of DC power loss caused by short-circuit faults, and the ratio of missing energy of commutation failure to the maximum releasable kinetic energy. Finally, the three risk indicators are processed based on the entropy weight method to obtain the risk of the receiving-end power grid, which is used to evaluate the severity of multi-DC commutation failure. Therefore, compared with the existing power grid hazard evaluation method based on the short-circuit ratio as the evaluation basis, it can more directly and accurately reflect the risk level of the receiving-end power grid, effectively reflect the safety and stability risks brought by multi-DC commutation failures faced by the receiving-end power grid, and can provide a reference for the planning and operation of multi-DC fed-in receiving-end power grids to ensure the safe and stable operation of the system.
Brief Description of the Drawings
[0095] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0096] Figure 1 A flow chart showing a method for risk assessment of a receiving-end power grid in the event of multiple DC commutation failures according to an embodiment of the present application is shown;
[0097] Figure 2 A schematic diagram showing a power curve during a commutation failure and a recovery process of a DC system according to an embodiment of the present application;
[0098] Figure 3 A schematic diagram showing a situation of receiving power from outside the area through direct current in an actual scenario according to an embodiment of the present application;
[0099] Figure 4 A block diagram of a computer device according to an embodiment of the present application is shown;
[0100] Figure 5 A block diagram of a computer device according to an embodiment of the present application is shown. [Specific implementation method]
[0101] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0102] Figure 1 A flow chart of a method for risk assessment of a receiving-end power grid in the event of multiple DC commutation failures according to an embodiment of the present application is shown.
[0103] like Figure 1 As shown, according to an embodiment of the present application, the process of the risk assessment method of the receiving-end power grid in the case of multiple DC commutation failures includes:
[0104] Step 102: Acquire a first ratio of each DC system of the receiving-end power grid, wherein the first ratio is used to reflect the probability of a DC commutation failure caused by a three-phase ground short circuit fault on a busbar in the DC system.
[0105] Among them, for each DC system of the receiving-end power grid, the number of faulty busbars in the DC system where DC commutation failure occurs due to a three-phase ground short circuit fault and the total number of buses of the DC system are obtained; and the ratio of the number of faulty busbars to the total number of buses is determined as the first ratio.
[0106] Specifically, if a bus causes a commutation failure in a DC system at the moment of a three-phase ground short-circuit fault, then the bus is considered to be a commutation failure-related bus in the DC system. The ratio of all commutation failure-related buses in a DC system to the total number of grid buses reflects the proportion of commutation failures caused by three-phase ground short-circuit faults in the DC system, and can be used as a first risk indicator for the adaptability assessment of the receiving grid to the DC system. The size of the first risk indicator can be used to measure the scope of commutation failures in the DC system caused by short-circuit faults. The larger the index value of the first risk indicator, the larger the fault range, and the more likely the DC system will have a commutation failure, which can reflect the adaptability of the AC system grid structure to the DC system. The first risk indicator is as follows:
[0107]
[0108] Among them, n fail N represents the number of faulty buses in a single DC system of the receiving-end power grid where DC commutation failure occurs due to a three-phase ground short circuit fault, sum Indicates the total number of buses in the single DC system, K fail Represents the ratio of the number of faulty buses to the total number of buses in the single DC system.
[0109] Step 104: Acquire a second ratio of each bus of the receiving-end power grid, wherein the second ratio is used to reflect the situation where the DC system power of the bus is lost due to a three-phase ground short-circuit fault.
[0110] Among them, for each bus of the receiving power grid, the amount of DC system power lost by the bus due to a three-phase ground short-circuit fault and the total amount of external DC power of the receiving power grid are obtained; and the ratio of the lost DC system power to the total amount of external DC power is determined as the second ratio.
[0111] Specifically, K in the previous article failThe indicator is to select the DC system as the research object and measure the scope of the short-circuit fault that causes the DC commutation failure of the DC system. In addition, the problem of simultaneous commutation failure of multiple DCs is also one of the factors affecting the safety of the receiving power grid. In a multi-input DC transmission system, the inverter stations are coupled to each other through the receiving AC system, and the electrical distance is relatively close. When the AC system fault is serious or the AC system strength is weak, a DC commutation failure occurs in the DC system, which will lead to continuous commutation failure of multiple DCs and threaten the power supply reliability of the entire AC / DC hybrid system. Especially for large-capacity and long-distance DC transmission systems, it is not easy to recover after a fault, and it is easy to cause large power fluctuations. Commutation failure or DC lockout is enough to destroy the safe and stable operation of the receiving power grid.
[0112] If a busbar causes commutation failure in multiple conventional DC systems due to a three-phase ground short circuit fault, and the DC power is lost due to the commutation failure, the severity of the short circuit fault of the busbar can be defined as the second risk index. The index value of the second risk index is calculated as follows:
[0113]
[0114] Among them, P los It represents the amount of DC system power lost due to a three-phase ground short circuit fault on a single busbar of the receiving power grid, P sum Indicates the total amount of external DC power in the receiving grid, K los Represents the ratio of the amount of lost DC system power of the single bus to the total amount of external DC power.
[0115] Step 106: Obtain a third ratio of each DC system of the receiving power grid, wherein the third ratio is used to reflect the proportion of missing energy of each busbar of each DC system in the receiving power grid when DC commutation fails due to a three-phase ground short circuit fault in the maximum releasable rotor kinetic energy of the receiving power grid.
[0116] First, for each DC system of the receiving-end power grid, the missing power when the DC system fails to commutate is obtained. For each DC system of the receiving-end power grid, the missing power when the DC system fails to commutate is determined based on the duration of the DC commutation failure of the DC system, the time taken to repair the DC commutation failure, the initial DC power, and the time-dependent transformation function of the DC power.
[0117] Specifically, the second ratio in the previous article analyzes the severity of DC commutation failure from the perspective of power. In addition to the amount of power loss, the duration of commutation failure is also one of the factors that affect the safety of the receiving power grid. For a UHV DC system, if a commutation failure occurs under a short circuit fault and the rated power cannot be restored for a long time, it will undoubtedly have a huge impact on the voltage stability and frequency stability of the AC system. In order to obtain the impact of the duration of DC commutation failure, a method for calculating the missing energy of commutation failure can be given from the perspective of energy, so as to comprehensively measure the impact of DC commutation failure from two aspects: power and duration. Among them, the power curves of the DC system during the commutation failure and the recovery process are as follows: Figure 2 As shown. Figure 2 In the example, it is assumed that the DC power of the DC system initially runs at P0. When the DC commutation failure occurs, the DC power drops to 0. Then the missing power of the DC system when the DC commutation failure occurs is:
[0118]
[0119] Among them, E i lack is the missing power when the DC commutation failure occurs in the i-th DC system of the receiving power grid, P0 is the initial DC power of the i-th DC system, P dc (t) is the time-dependent transformation function of the DC power, TF is the duration of the DC commutation failure of the i-th DC system, and TR is the time consumed for repairing the DC commutation failure of the i-th DC system.
[0120] Next, based on the missing power of the DC system, the missing energy of each node where a three-phase ground short circuit fault may occur is determined. Specifically, for each node where a three-phase ground short circuit fault may occur, a set of DC systems where DC commutation failure occurs due to the three-phase ground short circuit fault at the node is determined; and the sum of the missing power of each DC system in the set of DC systems is determined as the missing energy of the node.
[0121] Specifically, for a receiving-end power grid with multiple DC feed-ins, a single short-circuit fault usually causes multiple DC commutation failures at the same time. Therefore, for a short-circuit fault at the jth node, the missing energy caused by it should be the sum of the missing energies of each DC commutation failure, as shown in the following formula:
[0122]
[0123] Among them, E j B represents the missing energy of the jth node, i ∈ j indicates that the three-phase ground short circuit fault at the jth node will cause the DC commutation failure of the i-th DC system.
[0124] Furthermore, the maximum allowable released rotor kinetic energy of each DC system is obtained, and based on the maximum allowable released rotor kinetic energy of each DC system and the maximum energy of the missing energy of each node, the third proportion of each DC system is determined.
[0125] Specifically, for each DC system, the maximum allowable released rotor kinetic energy of the DC system is determined based on the rated speed of the unit, the minimum allowable speed of the unit and the rotational inertia of the unit, wherein:
[0126]
[0127] W eg i is the maximum allowable released rotor kinetic energy of the ith DC system, J i is the moment of inertia of the i-th DC system, ω0 is the rated speed of the i-th DC system, ω min is the minimum allowable speed of the unit in the i-th DC system.
[0128] On this basis, based on the maximum allowable released rotor kinetic energy of each DC system, the sum of the maximum allowable released rotor kinetic energy of all units of the receiving power grid is determined; and the ratio of the maximum energy to the sum of the maximum allowable released rotor kinetic energy of all units is determined as the third ratio.
[0129] Specifically, the missing energy can reflect the severity of the DC commutation failure in the DC system, E j B The larger the E is, the greater the energy impact on the DC system due to DC commutation failure. However, under the same amount of missing energy, the threat to large-scale power systems is much smaller than that to small-scale power systems. As an absolute quantity, E j B The size of cannot directly reflect the relationship between missing energy and system scale. Therefore, the following third risk index is used to replace missing energy:
[0130]
[0131] Among them, K eg is the third ratio of the i-th DC system of the receiving grid, E B Represents the maximum energy among the missing energies of all nodes, W eg i is the maximum allowable released rotor kinetic energy of the i-th DC system.
[0132] Step 108: Determine the risk level of the receiving-end power grid based on the first ratio, the second ratio, and the third ratio.
[0133] Specifically, firstly, based on the first ratio, the second ratio and the third ratio, the index values of the three risk indicators of the receiving power grid are determined respectively. Among them, the maximum value of the first ratio of each DC system of the receiving power grid is determined as the index value of the first risk indicator; the maximum value of the second ratio of each bus of the receiving power grid is determined as the index value of the second risk indicator; the maximum value of the third ratio of each DC system of the receiving power grid is determined as the index value of the third risk indicator.
[0134] Specifically, set e j is the jth index value of the ith DC system, and is calculated as follows:
[0135]
[0136] Next, obtain the normalized value of each DC system of the receiving power grid under each risk index. Because the calculation results of different risk indicators vary greatly in units and values, when analyzing various indicators comprehensively, the calculation results of each risk indicator should be normalized first to make them at the same level to improve the calculation accuracy. Specifically, the following normalization formula is adopted:
[0137]
[0138] In the formula, R j max is the upper limit of the value allowed for the j-th risk index in the DC system, R j min is the lower limit of the value allowed for the j-th risk index in the DC system, R ij represents the original value of the jth risk index under the i-th DC system, and r ij YesR ij The normalized value of .
[0139] Then, based on the normalized value of each DC system under each risk index, the entropy value of each risk index is determined. The entropy weight method is a weighting method that determines the weight according to the discrete degree of the index value. The greater the discrete degree of the index value, the greater the entropy, the more useful information it has, and the index weighting should be larger, and vice versa.
[0140] For each risk index, the entropy value of the risk index is determined based on the normalized value of each DC system of the receiving power grid under the risk index and the sum of the normalized values of all DC systems of the receiving power grid under the risk index, wherein,
[0141]
[0142] Among them, D j is the entropy value of the j-th risk index, j is 1, 2 or 3, q ij is the ratio of the normalized value of the i-th DC system of the receiving power grid under the j-th risk index to the sum of the normalized values of all DC systems of the receiving power grid under the j-th risk index, n is the total number of DC systems of the receiving power grid, and m is the product of n and the total number of risk indicators.
[0143] Further, based on the entropy value of each risk indicator, a first weight coefficient of each risk indicator is determined. Specifically, for each risk indicator, a numerator parameter and a denominator parameter of the entropy value of the risk indicator are determined; and a ratio of the numerator parameter to the denominator parameter is determined as the first weight coefficient of the risk indicator, wherein:
[0144]
[0145] w j ″ is the first weight coefficient of the j-th risk index, D j is the entropy value of the j-th risk index, 1-D j is the molecular parameter of the j-th risk index, is the denominator parameter, representing the sum of the entropy values of all risk indicators of the receiving-end power grid.
[0146] Next, based on the first weight coefficient and the predetermined second weight coefficient, the third weight coefficient of each risk indicator is determined. In order to make the comprehensive weight as unbiased as possible to any one of the subjective and objective weights, the minimum discriminant information principle is used to establish an optimization model to determine the comprehensive weight, as shown in the following formula:
[0147]
[0148] Solving this equation, we get:
[0149]
[0150] That is, the square root of the product of the first weight coefficient and the predetermined second weight coefficient is obtained; for each risk indicator, the ratio of the square root corresponding to the risk indicator to the sum of the square roots corresponding to all risk indicators is determined as the third weight coefficient.
[0151] Among them, w j ′ is the second weight coefficient of the j-th risk index, which is a preset constant, and w j ″ is the first weight coefficient of the j-th risk index, w jis the third weight coefficient of the j-th risk indicator, and j is 1, 2 or 3.
[0152] Finally, based on the third weight coefficient of each risk indicator, the indicator values of each risk indicator of the receiving-end power grid are weighted and summed to obtain the risk of the receiving-end power grid, as shown in the following formula:
[0153]
[0154] Where s is the risk of the receiving-end power grid, ranging from 0 to 1. The closer it is to 1, the more likely the receiving-end power grid is to become unstable due to DC commutation failure. j is the third weight coefficient of the j-th risk index, e j is the jth index value of the i-th DC system.
[0155] The following analysis is based on the 2025 Jiangsu power grid planning data to verify the correctness of the proposed method. In 2025, the installed capacity of synchronous generators in Jiangsu Province will reach 128,000MW, and the installed capacity of wind power will reach about 30,000MW. In addition, Jiangsu will absorb 39,000MW of external power through UHV DC projects. The situation of Jiangsu power grid receiving external power through DC is as follows: Figure 3 shown.
[0156] Six typical operation modes of Jiangsu power grid are selected, including summer peak, summer underestimate, winter peak, winter underestimate, flood season peak and flood season underestimate. The comprehensive evaluation index s of the severity of multi-DC commutation failure is calculated under different operation modes. The results are shown in Table 1.
[0157] Table 1
[0158]
[0159]
[0160] In Table 1, the closer the comprehensive evaluation index s is to 1, the greater the threat to the power grid from the commutation failure of the DC system, and the more unfavorable it is to the safe and stable operation of the power grid.
[0161] As can be seen from Table 1, the highest comprehensive evaluation index is in the summer peak, when the DC system is basically in full transmission and the load is relatively heavy. After the phase change failure occurs, many DC systems cannot recover quickly after the fault is cleared, thereby increasing the missing energy. In addition to the summer peak, the system is most threatened by phase change failure in the flood season valley operation mode. This is because the DC is basically in full transmission, but due to the light load, a large number of units in the Jiangsu power grid are not turned on, which reduces the system strength and expands the impact of phase change failure.
[0162] The above technical scheme establishes a multi-DC commutation failure severity assessment index system for a high-power receiving ratio receiving-end power grid, which includes three risk indicators: the proportion of short-circuit faults that cause DC commutation failures, the proportion of DC power loss caused by short-circuit faults, and the ratio of missing energy due to commutation failure to the maximum releasable kinetic energy. Finally, the three risk indicators are processed based on the entropy weight method to obtain the risk of the receiving-end power grid, which is used to evaluate the severity of multi-DC commutation failures. Therefore, compared with the existing power grid hazard assessment method based on the short-circuit ratio as the evaluation basis, it can more directly and accurately reflect the risk level of the receiving-end power grid, and effectively reflect the safety and stability risks brought by multi-DC commutation failures faced by the receiving-end power grid. It can provide a reference for the planning and operation of multi-DC fed-in receiving-end power grids and ensure the safe and stable operation of the system.
[0163] The embodiment of the present application provides a risk assessment device for a receiving-end power grid in the event of multiple DC commutation failures, comprising:
[0164] A first ratio acquisition unit, used for acquiring a first ratio of each DC system of the receiving-end power grid, wherein the first ratio is used for reflecting the probability of a DC commutation failure caused by a three-phase ground short circuit fault on a busbar in the DC system;
[0165] A second ratio acquisition unit, used to acquire a second ratio of each bus of the receiving-end power grid, wherein the second ratio is used to reflect the situation that the DC system power of the bus is lost due to a three-phase ground short circuit fault;
[0166] A third ratio acquisition unit is used to acquire a third ratio of each DC system of the receiving-end power grid, wherein the third ratio is used to reflect the proportion of missing energy when DC commutation failure occurs due to a three-phase ground short-circuit fault on each busbar of each DC system in the receiving-end power grid in the maximum releasable rotor kinetic energy of the receiving-end power grid;
[0167] A risk determination unit is used to determine the risk of the receiving-end power grid based on the first ratio, the second ratio and the third ratio.
[0168] In one embodiment of the present application, optionally, the first ratio acquisition unit is used to:
[0169] For each DC system of the receiving-end power grid, the number of faulty busbars in the DC system that have DC commutation failure due to a three-phase ground short-circuit fault and the total number of buses in the DC system are obtained; and the ratio of the number of faulty busbars to the total number of buses is determined as the first ratio.
[0170] In one embodiment of the present application, optionally, the second ratio acquisition unit is used to:
[0171] For each bus of the receiving power grid, the amount of DC system power lost by the bus due to a three-phase ground short-circuit fault and the total amount of external DC power of the receiving power grid are obtained; and the ratio of the amount of lost DC system power to the total amount of external DC power is determined as the second ratio.
[0172] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0173] For each DC system of the receiving-end power grid, the missing power when DC commutation failure occurs in the DC system is obtained; based on the missing power of the DC system, the missing energy of each node where a three-phase ground short circuit fault may occur is determined; the maximum allowable released rotor kinetic energy of each DC system is obtained; and based on the maximum energy of the maximum allowable released rotor kinetic energy of each DC system and the missing energy of each node, the third ratio of each DC system is determined.
[0174] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0175] For each DC system of the receiving-end power grid, the missing power when a DC commutation failure occurs in the DC system is determined based on the DC commutation failure duration, the DC commutation failure repair time, the initial DC power and the time-dependent transformation function of the DC power of the DC system.
[0176] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0177] For each node where a three-phase ground short circuit fault may occur, a set of DC systems where DC commutation failure occurs due to the three-phase ground short circuit fault at the node is determined; and the sum of the missing powers of each DC system in the set of DC systems is determined as the missing energy of the node.
[0178] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0179] For each DC system, the maximum allowable released rotor kinetic energy of the DC system is determined based on the rated speed of the unit, the minimum allowable speed of the unit and the rotational inertia of the unit, wherein:
[0180]
[0181] W eg i is the maximum allowable released rotor kinetic energy of the ith DC system, J i is the moment of inertia of the i-th DC system, ω0 is the rated speed of the i-th DC system, ω minis the minimum allowable speed of the unit in the i-th DC system.
[0182] In one embodiment of the present application, optionally, the third ratio acquisition unit is used to:
[0183] Based on the maximum allowable released rotor kinetic energy of each DC system, the sum of the maximum allowable released rotor kinetic energy of all units of the receiving power grid is determined; and the ratio of the maximum energy to the sum of the maximum allowable released rotor kinetic energy of all units is determined as the third ratio.
[0184] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0185] Based on the first ratio, the second ratio and the third ratio, respectively determine the indicator values of the three risk indicators of the receiving power grid; obtain the normalized value of each DC system of the receiving power grid under each risk indicator; based on the normalized value of each DC system under each risk indicator, determine the entropy value of each risk indicator; based on the entropy value of each risk indicator, determine the first weight coefficient of each risk indicator; based on the first weight coefficient and the predetermined second weight coefficient, determine the third weight coefficient of each risk indicator; based on the third weight coefficient of each risk indicator, perform weighted summation of the indicator values of each risk indicator of the receiving power grid to obtain the risk of the receiving power grid.
[0186] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0187] The maximum value among the first ratios of each DC system of the receiving power grid is determined as the index value of the first risk index; the maximum value among the second ratios of each bus of the receiving power grid is determined as the index value of the second risk index; the maximum value among the third ratios of each DC system of the receiving power grid is determined as the index value of the third risk index.
[0188] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0189] For each risk index, the entropy value of the risk index is determined based on the normalized value of each DC system of the receiving power grid under the risk index and the sum of the normalized values of all DC systems of the receiving power grid under the risk index, wherein:
[0190]
[0191] Among them, D j is the entropy value of the j-th risk index, j is 1, 2 or 3, q ijis the ratio of the normalized value of the i-th DC system of the receiving power grid under the j-th risk index to the sum of the normalized values of all DC systems of the receiving power grid under the j-th risk index, n is the total number of DC systems of the receiving power grid, and m is the product of n and the total number of risk indicators.
[0192] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0193] For each risk index, determine the numerator parameter and denominator parameter of the entropy value of the risk index; determine the ratio of the numerator parameter to the denominator parameter as the first weight coefficient of the risk index, wherein,
[0194]
[0195] w j ″ is the first weight coefficient of the j-th risk index, D j is the entropy value of the j-th risk index, 1-D j is the molecular parameter of the j-th risk index, is the denominator parameter, representing the sum of the entropy values of all risk indicators of the receiving-end power grid.
[0196] In one embodiment of the present application, optionally, the risk determination unit is used to:
[0197] Obtain the square root of the product of the first weight coefficient and a predetermined second weight coefficient; for each risk indicator, determine the ratio of the square root corresponding to the risk indicator to the sum of the square roots corresponding to all risk indicators as the third weight coefficient.
[0198] The risk assessment device for the receiving-end power grid in the case of multiple DC commutation failures uses any of the solutions in the above embodiments, and therefore has all the above technical effects, which will not be repeated here.
[0199] In addition, in one embodiment, the present application provides a computer device, which may be a server, and its internal structure diagram may be as shown in FIG. Figure 4As shown. The computer device includes a processor, a memory, a network interface and a database connected via a system bus. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile and / or volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The network interface of the computer device is used to communicate with an external client via a network connection. When the computer program is executed by the processor, the risk assessment method of the receiving-end power grid in the case of multi-DC commutation failure described in any of the above embodiments can be implemented.
[0200] In one embodiment, the present application further provides a computer device, which may be a client, and its internal structure diagram may be as follows: Figure 5 As shown. The computer device includes a processor, a memory, a network interface, a display screen and an input device connected via a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The network interface of the computer device is used to communicate with an external server via a network connection. When the computer program is executed by the processor, the risk assessment method of the receiving-end power grid in the case of multi-DC commutation failure described in any of the above embodiments can be implemented.
[0201] Any of the above-mentioned computer devices in the embodiments of the present application may exist in various forms, including but not limited to:
[0202] (1) Mobile communication devices: These devices are characterized by their mobile communication functions and their main purpose is to provide voice and data communications. These terminals include: smart phones (such as iPhone), multimedia phones, functional phones, and low-end phones.
[0203] (2) Ultra-mobile personal computer devices: These devices fall into the category of personal computers, have computing and processing capabilities, and generally also have mobile Internet access features. These terminals include: PDA, MID and UMPC devices, such as iPad.
[0204] (3) Portable entertainment devices: These devices can display and play multimedia content. They include audio and video players (such as iPods), handheld game consoles, e-books, as well as smart toys, wearable devices, and portable car navigation devices.
[0205] (4) Server: A device that provides computing services. The server consists of a processor, hard disk, memory, system bus, etc. The server is similar to a general computer architecture, but because it needs to provide highly reliable services, it has higher requirements in terms of processing power, stability, reliability, security, scalability, and manageability.
[0206] (5) Other electronic devices with data interaction functions.
[0207] In addition, an embodiment of the present application provides a computer-readable storage medium storing computer-executable instructions, wherein the computer-executable instructions are used to perform the following steps:
[0208] Acquire a first ratio of each DC system of the receiving-end power grid, wherein the first ratio is used to reflect the probability of a DC commutation failure caused by a three-phase ground short circuit fault on a busbar in the DC system;
[0209] Acquire a second ratio of each bus of the receiving-end power grid, wherein the second ratio is used to reflect the situation that the DC system power of the bus is lost due to a three-phase ground short circuit fault;
[0210] Acquire a third ratio of each DC system of the receiving-end power grid, wherein the third ratio is used to reflect the proportion of missing energy when DC commutation failure occurs due to a three-phase ground short-circuit fault in each busbar of each DC system in the receiving-end power grid in the maximum releasable rotor kinetic energy of the receiving-end power grid;
[0211] The risk level of the receiving-end power grid is determined based on the first ratio, the second ratio, and the third ratio.
[0212] It should be noted that the above functions or steps that can be implemented by the computer-readable storage medium or computer device can refer to the relevant description in the aforementioned method embodiment. In order to avoid repetition, they will not be described one by one here.
[0213] The technical solution of the present application is described in detail above in conjunction with the accompanying drawings. Through the technical solution of the present application, a multi-DC commutation failure severity assessment index system for a high power receiving ratio receiving-end power grid is established, including three risk indicators: the proportion of short-circuit faults causing DC commutation failures, the proportion of DC power loss caused by short-circuit faults, and the ratio of missing energy of commutation failure to the maximum releasable kinetic energy. Finally, the three risk indicators are processed based on the entropy weight method to obtain the risk of the receiving-end power grid, which is used to evaluate the severity of multi-DC commutation failures. Therefore, compared with the existing power grid hazard assessment method based on the short-circuit ratio as the evaluation basis, it can more directly and accurately reflect the risk level of the receiving-end power grid, effectively reflect the safety and stability risks brought by multi-DC commutation failures faced by the receiving-end power grid, and can provide a reference for the planning and operation of multi-DC fed-in receiving-end power grids to ensure the safe and stable operation of the system.
[0214] It should be understood that, although the terms first, second, etc. may be used to describe ratios in the embodiments of the present application, these ratios should not be limited to these terms. These terms are only used to distinguish ratios from each other. For example, without departing from the scope of the embodiments of the present application, the first ratio may also be referred to as the second ratio, and similarly, the second ratio may also be referred to as the first ratio.
[0215] The word "if" as used herein may be interpreted as "at the time of" or "when" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrases "if it is determined" or "if (stated condition or event) is detected" may be interpreted as "when it is determined" or "in response to determining" or "when detecting (stated condition or event)" or "in response to detecting (stated condition or event)", depending on the context.
[0216] The terms used in the embodiments of the present application are only for the purpose of describing specific embodiments, and are not intended to limit the present application. The singular forms "a", "said" and "the" used in the embodiments of the present application and the appended claims are also intended to include plural forms, unless the context clearly indicates other meanings.
[0217] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0218] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of hardware plus software functional units.
[0219] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application can include non-volatile and / or volatile memory. Non-volatile memory can include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory can include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
[0220] The embodiments described above are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention, and should all be included in the protection scope of the present invention.
Claims
1. A risk assessment method for a receiving-end power grid under the condition of multiple DC commutation failures, characterized in that: include: Acquire a first ratio of each DC system of the receiving-end power grid, wherein the first ratio is used to reflect the probability of a DC commutation failure caused by a three-phase ground short circuit fault on a busbar in the DC system; Acquire a second ratio of each bus of the receiving-end power grid, wherein the second ratio is used to reflect the situation that the DC system power of the bus is lost due to a three-phase ground short circuit fault; Obtaining a third ratio of each DC system of the receiving power grid, wherein the third ratio is used to reflect the proportion of the maximum energy of all missing energies of nodes in each busbar of a single DC system in the receiving power grid where a three-phase ground short circuit fault may occur in the sum of the maximum allowable released rotor kinetic energies of all DC systems in the receiving power grid; Determining the risk level of the receiving-end power grid based on the first ratio, the second ratio and the third ratio; The obtaining of the first ratio of each DC system of the receiving-end power grid includes: For each DC system of the receiving-end power grid, the number of faulty buses in the DC system that have DC commutation failures due to a three-phase ground short circuit fault and the total number of buses in the DC system are obtained; Determine the ratio of the number of the faulty busbars to the total number of the busbars as the first ratio; The obtaining of the second ratio of each bus of the receiving-end power grid includes: For each bus of the receiving power grid, the amount of DC system power lost by the bus due to a three-phase ground short circuit fault and the total amount of external DC power of the receiving power grid are obtained; Determining the ratio of the amount of the lost DC system power to the total amount of the external DC power as the second ratio; The determining the risk level of the receiving-end power grid based on the first ratio, the second ratio, and the third ratio includes: Based on the first ratio, the second ratio and the third ratio, respectively determine the index values of the first risk index, the second risk index and the third risk index of the receiving-end power grid; Obtaining a normalized value of each DC system of the receiving-end power grid under each risk index; Determining the entropy value of each risk indicator based on the normalized value of each DC system under each risk indicator; Determining a first weight coefficient of each risk indicator based on the entropy value of each risk indicator; Determining a third weight coefficient for each risk indicator based on the first weight coefficient and the second weight coefficient, wherein the second weight coefficient is a preset constant; Based on the third weight coefficient of each risk indicator, weighted sum of the indicator values of each risk indicator of the receiving-end power grid is performed to obtain the risk of the receiving-end power grid; The determining, based on the first ratio, the second ratio and the third ratio, respectively the indicator values of the first risk index, the second risk index and the third risk index of the receiving-end power grid, comprises: Determine the maximum value of the first ratios of each DC system of the receiving-end power grid as the indicator value of the first risk indicator; Determine the maximum value of the second ratio of each bus of the receiving-end power grid as the indicator value of the second risk indicator; Determine the maximum value of the third ratios of each DC system of the receiving-end power grid as the indicator value of the third risk indicator; The determining, based on the first weight coefficient and the second weight coefficient, a third weight coefficient of each risk indicator comprises: Obtaining a square root of a product of the first weight coefficient and the second weight coefficient; For each risk indicator, the ratio of the square root value corresponding to the risk indicator to the sum of the square roots corresponding to all risk indicators is determined as the third weight coefficient.
2. The risk assessment method for the receiving-end power grid under the condition of multiple DC commutation failure according to claim 1 is characterized in that: The obtaining of the third ratio of each DC system of the receiving-end power grid includes: For each DC system of the receiving-end power grid, obtaining missing power when DC commutation failure occurs in the DC system; Based on the missing power of the DC system, determining the missing energy of each node where a three-phase ground short circuit fault may occur; Obtain the maximum allowable released rotor kinetic energy for each DC system; A third ratio of each DC system is determined based on a maximum allowed released rotor kinetic energy of each DC system and a maximum energy among the missing energies of all the nodes.
3. The risk assessment method for the receiving-end power grid in the case of multiple DC commutation failures according to claim 2 is characterized in that: The step of obtaining, for each DC system of the receiving-end power grid, missing power when a DC commutation failure occurs in the DC system includes: For each DC system of the receiving-end power grid, the missing power when a DC commutation failure occurs in the DC system is determined based on the DC commutation failure duration, the DC commutation failure repair time, the initial DC power and the time-dependent transformation function of the DC power of the DC system.
4. The risk assessment method for the receiving-end power grid in the case of multiple DC commutation failures according to claim 3 is characterized in that: The determining, based on the missing power of the DC system, the missing energy of each node where a three-phase ground short circuit fault may occur comprises: For each node where a three-phase ground short circuit fault may occur, determining a set of DC systems where a DC commutation failure occurs due to the three-phase ground short circuit fault occurring at the node; The missing energy of the node is determined based on the sum of the missing powers of the DC systems in the DC system set.
5. The risk assessment method for the receiving-end power grid in the case of multiple DC commutation failures according to claim 2 is characterized in that: The obtaining of the maximum allowable released rotor kinetic energy of each DC system comprises: For each DC system, the maximum allowable released rotor kinetic energy of the DC system is determined based on the rated speed of the unit, the minimum allowable speed of the unit and the rotational inertia of the unit, wherein: W eg i is the maximum allowable released rotor kinetic energy of the ith DC system, J i is the moment of inertia of the i-th DC system, ω0 is the rated speed of the i-th DC system, ω min is the minimum allowable speed of the unit in the i-th DC system.
6. The risk assessment method for the receiving-end power grid in the case of multiple DC commutation failures according to claim 2 is characterized in that: The determining the third ratio of the receiving-end power grid based on the maximum allowable released rotor kinetic energy of each DC system and the maximum energy of the missing energy of each node comprises: Based on the maximum allowable released rotor kinetic energy of each DC system, determining the sum of the maximum allowable released rotor kinetic energy of all DC systems of the receiving-end power grid; The ratio of the maximum energy to the sum of the maximum allowable released rotor kinetic energies of all the DC systems is determined as the third ratio.
7. The risk assessment method for the receiving-end power grid in the case of multiple DC commutation failures according to claim 1 is characterized in that: Determining the entropy value of each risk indicator based on the normalized value of each DC system under each risk indicator includes: For each risk index, the entropy value of the risk index is determined based on the normalized value of each DC system of the receiving power grid under the risk index and the sum of the normalized values of all DC systems of the receiving power grid under the risk index, wherein: Among them, D j is the entropy value of the j-th risk index, j is 1, 2 or 3, q ij is the ratio of the normalized value of the i-th DC system of the receiving power grid under the j-th risk index to the sum of the normalized values of all DC systems of the receiving power grid under the j-th risk index, n is the total number of DC systems of the receiving power grid, and m is the product of n and the total number of risk indicators.
8. The risk assessment method for the receiving-end power grid in the case of multiple DC commutation failures according to claim 1 is characterized in that: The step of determining a first weight coefficient of each risk indicator based on the entropy value of each risk indicator comprises: For each risk indicator, determining a numerator parameter and a denominator parameter of the entropy value of the risk indicator; The ratio of the numerator parameter to the denominator parameter is determined as the first weight coefficient of the risk index, wherein: w j ″ is the first weight coefficient of the j-th risk index, D j is the entropy value of the j-th risk index, 1-D j is the molecular parameter of the j-th risk index, is the denominator parameter, representing the sum of the entropy values of all risk indicators of the receiving-end power grid.
9. A risk assessment device for a receiving-end power grid in the case of multiple DC commutation failures, characterized in that: include: A first ratio acquisition unit, used for acquiring a first ratio of each DC system of the receiving-end power grid, wherein the first ratio is used for reflecting the probability of a DC commutation failure caused by a three-phase ground short circuit fault on a busbar in the DC system; A second ratio acquisition unit, used to acquire a second ratio of each bus of the receiving-end power grid, wherein the second ratio is used to reflect the situation that the DC system power of the bus is lost due to a three-phase ground short circuit fault; A third ratio acquisition unit is used to acquire a third ratio of each DC system of the receiving-end power grid, wherein the third ratio is used to reflect the proportion of the maximum energy of all missing energies of nodes in each busbar of a single DC system in the receiving-end power grid where a three-phase ground short circuit fault may occur in the sum of the maximum allowable released rotor kinetic energies of all DC systems in the receiving-end power grid; a risk determination unit, configured to determine the risk of the receiving-end power grid based on the first ratio, the second ratio and the third ratio; The first ratio acquisition unit is used for: For each DC system of the receiving-end power grid, the number of faulty buses in the DC system that have DC commutation failure due to a three-phase ground short circuit fault and the total number of buses in the DC system are obtained; and the ratio of the number of faulty buses to the total number of buses is determined as the first ratio; The second ratio acquisition unit is used for: For each bus of the receiving-end power grid, the amount of DC system power lost by the bus due to a three-phase ground short circuit fault and the total amount of external DC power of the receiving-end power grid are obtained; and the ratio of the amount of lost DC system power to the total amount of external DC power is determined as the second ratio; The risk determination unit is used to: Based on the first ratio, the second ratio and the third ratio, respectively determine the index values of the first risk index, the second risk index and the third risk index of the receiving power grid; obtain the normalized value of each DC system of the receiving power grid under each risk index; based on the normalized value of each DC system under each risk index, determine the entropy value of each risk index; based on the entropy value of each risk index, determine the first weight coefficient of each risk index; based on the first weight coefficient and the second weight coefficient, determine the third weight coefficient of each risk index, the second weight coefficient being a preset constant; based on the third weight coefficient of each risk index, perform weighted summation of the index values of each risk index of the receiving power grid to obtain the risk of the receiving power grid; The risk determination unit is also used for: Determine the maximum value of the first ratio of each DC system of the receiving power grid as the index value of the first risk index; determine the maximum value of the second ratio of each bus of the receiving power grid as the index value of the second risk index; determine the maximum value of the third ratio of each DC system of the receiving power grid as the index value of the third risk index; The risk determination unit is also used for: Obtain the square root of the product of the first weight coefficient and the second weight coefficient; for each risk indicator, determine the third weight coefficient as the ratio of the square root corresponding to the risk indicator to the sum of the square roots corresponding to all risk indicators.
10. A computer device, characterized in that: include: at least one processor; and, a memory communicatively coupled to the at least one processor; The memory stores instructions executable by the at least one processor, wherein the instructions are configured to execute the method according to any one of claims 1 to 8.
11. A computer-readable storage medium, characterized in that: Computer executable instructions are stored, and the computer executable instructions are used to execute the method according to any one of claims 1 to 8.