A fender system for an upper module of an offshore platform and a manufacturing method thereof
By adopting detachable connection and electromagnetic suction devices in the fender system of the upper block of the offshore platform, the complex and cost problems of traditional fender systems are solved, flexible installation and reuse are achieved, and construction difficulty and cost are reduced.
Patent Information
- Application Number
- CN202410351613.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-26
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-03-26
AI Technical Summary
The fender system of the upper block of the traditional offshore platform is complex and costly during the installation and dismantling process, and is not conducive to reuse, making it difficult to meet the needs of large offshore converter stations.
The fender support platform is used to be integrated fixed connection with the circumferential side of the conduit frame, and the rubber compression block is detachable connection with the fender plate. Combined with electromagnetic suction device and chain stopper, the fender system is flexible to be installed and removed, reducing the Construction difficulty and cost.
It effectively reduces the difficulty of onshore construction of large marine platforms, improves system utilization, reduces the amount of steel used, and improves the installation efficiency and cost control of the upper blocks of offshore platforms.
Smart Images

Figure CN118087480B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of marine engineering technology, and in particular to a fender system for an upper module of an offshore platform, and a method for manufacturing the fender system. Background Art
[0002] As the scale of wind farms and the distance from shore increase, large offshore converter stations will gradually be used to meet the large-capacity transmission needs of offshore wind power. Drawing on the installation experience of offshore oil and gas platforms, there are usually two methods for offshore installation of platform modules: hoisting and floating. However, due to the hoisting capacity of the crane ship and the requirements for installation economy, hoisting installation is only applicable to the installation of light-weight and small-sized platform modules; while floating method can be applied to the installation of large platform modules. Therefore, for large offshore converter stations with heavy weight and large volume, floating method is a more suitable choice.
[0003] Offshore wind power construction accounts for a large proportion of the cost. When the traditional floating method is used to install the upper modules of large offshore platforms, the fenders, rubber compression blocks and jacket fender support platforms of the traditional fender system need to be built and fixedly installed on the jacket as auxiliary components during the onshore production stage of the jacket, which makes it inconvenient to dismantle and recycle them later. At the same time, the traditional fender system only plays a role in installation and dismantling during the entire life cycle of the offshore booster station or converter station. In addition, the processing process of the traditional fender system is complicated and the amount of steel used is high, which is not conducive to cost control. Summary of the invention
[0004] In order to solve the above technical problems, the present invention provides a fender system for an upper module of an offshore platform which can reduce the construction difficulty and construction cost.
[0005] The present invention adopts the following technical solution:
[0006] The present invention provides a fender system for an upper assembly of an offshore platform, comprising a fender support platform, a rubber compression block and a fender plate. The fender support platform is fixedly connected to the circumferential side of a conductor frame in an integrated manner, one lateral end of the rubber compression block is detachably vertically connected to the fender support platform, and the other lateral end is fixedly vertically connected to the fender plate. The fender support platform extends a chain on both lateral sides of the rubber compression block, and both ends of each chain are detachably connected to the fender plate at vertical intervals.
[0007] Preferably, an electromagnetic suction device is also included. A remote-controlled power supply is provided inside the rubber compression block. The electromagnetic suction device is arranged at one lateral end of the rubber compression block and is electrically connected to the power supply. The electromagnetic suction device is electromagnetically adsorbed on the fender support platform.
[0008] Preferably, it also includes a chain stopper, four chain stoppers are arranged in a rectangular pattern on the fender, both ends of each chain are respectively inserted into two chain stoppers arranged vertically at intervals, and a power-off unlocking lock is installed on the chain stopper, which is electrically connected to the power supply in the rubber compression block and locks the chain on the chain stopper.
[0009] The present invention also provides a method for manufacturing the fender system of the above-mentioned offshore platform upper module, comprising the following steps:
[0010] S1: During the onshore construction phase, the fender, chain stopper, locker, rubber compression block and electromagnetic suction device are installed as an integrated fender component, and the chain, fender support platform and conductor frame are installed as an integrated frame component;
[0011] S2: Install the frame integrated component at sea, and remotely control the power supply in the rubber compression block to energize the electromagnetic suction device, so that the fender integrated component is magnetically connected with the frame integrated component;
[0012] S3: The two ends of each chain are respectively passed through two chain stoppers vertically spaced apart on the integrated fender component, and the locker is energized by the power supply in the remotely controlled rubber compression block, so that the chain is locked on the chain stopper by the locker.
[0013] Compared with the prior art, the present invention has the following beneficial effects:
[0014] The fender system of the upper module of the offshore platform of the present invention changes the fixed connection between the rubber compression block and the fender support platform, and the fixed connection between the chain on the fender support platform and the fender plate into a detachable connection, so that the components other than the fender support platform and the chain can be installed and removed more conveniently, thereby effectively reducing the difficulty of onshore construction of large-scale offshore platforms, and allowing the components other than the fender support platform and the chain to be reused in the installation of the upper module of the large-scale offshore platform, thereby improving the utilization rate of the system, reducing waste, and reducing the amount of steel used.
[0015] The method for manufacturing the fender system of the upper module of the offshore platform of the present invention can realize the effective installation of the fender system of the upper module of the offshore platform. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the use status of the fender system of the upper module of the offshore platform in an embodiment of the present invention.
[0017] Figure 2 It is a side view of the installation state of the fender system of the upper module of the offshore platform in an embodiment of the present invention.
[0018] The reference numerals are described as follows:
[0019] 1. Fender support platform 6. Barge
[0020] 2. Rubber compression block 7. Ship fender
[0021] 3. Fender 8. Electromagnetic suction device
[0022] 4. Guide tube frame 9. Chain stopper
[0023] 5. Chain 10. Lock DETAILED DESCRIPTION
[0024] The specific embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. These embodiments are only used to illustrate the present invention, but not to limit the present invention.
[0025] In the description of the present invention, it should be noted that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0026] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0027] Furthermore, in the description of the present invention, unless otherwise specified, “plurality” means two or more.
[0028] See also Figure 1 and Figure 2 The present embodiment provides a fender system for an upper assembly of an offshore platform, comprising a fender support platform 1, a rubber compression block 2 and a fender plate 3. The fender support platform 1 is fixedly connected to the circumferential side of a conductor frame 4 in an integral manner. One lateral end of the rubber compression block 2 is detachably vertically connected to the fender support platform 1, and the other lateral end is fixedly vertically connected to the fender plate 3. The fender support platform 1 extends a chain 5 on both lateral sides of the rubber compression block 2, and both ends of each chain 5 are detachably connected to the fender plate 3 at vertical intervals.
[0029] The fender system of the upper module of the offshore platform of the present embodiment changes the fixed connection between the rubber compression block 2 and the fender support platform 1, and the fixed connection between the chain 5 on the fender support platform 1 and the fender plate 3 into a detachable connection, so that the components other than the fender support platform 1 and the chain 5 can be installed and removed more conveniently, thereby effectively reducing the difficulty of onshore construction of large offshore platforms, and allowing the components other than the fender support platform 1 and the chain 5 to be reused in the installation of the upper module of the large offshore platform, thereby improving the system utilization rate, reducing waste, and reducing the amount of steel used.
[0030] See also Figure 1 After the installation of the fender system of the upper module of the offshore platform of this embodiment is completed, the use status is the same as that of the traditional fender system, that is, the fender plate 3 contacts the ship fender plate 7 on the barge 6, and the fender purpose is achieved by the elastic buffering of the rubber compression block 2.
[0031] Preferably, see Figure 1 and Figure 2 The fender system of the upper assembly of the offshore platform of this embodiment also includes an electromagnetic suction device 8. A remote-controlled power supply is provided inside the rubber compression block 2. The electromagnetic suction device 8 is arranged at one lateral end of the rubber compression block 2 and is electrically connected to the power supply. The electromagnetic suction device 8 is electromagnetically adsorbed on the fender support platform 1.
[0032] The setting of the electromagnetic suction device 8 allows the installer to power the electromagnetic suction device 8 through the remote control power supply, and use the electromagnetic force to adsorb and fix the rubber compression block 2 on the fender support platform 1 to achieve the installation of the fender system; and after the fender purpose is completed, the power supply to the electromagnetic suction device 8 can also be cut off by the remote control power supply, thereby completing the separation between the rubber compression block 2 and the fender support platform 1.
[0033] Preferably, see Figure 2 The fender system of the upper module of the offshore platform of this embodiment also includes a chain stopper 9. Four chain stoppers 9 are arranged on the fender board 3 in a rectangular manner. The two ends of each chain 5 are respectively inserted into two chain stoppers 9 arranged vertically at intervals. A power-off unlocking lock 10 is installed on the chain stopper 9. The lock 10 is electrically connected to the power supply in the rubber compression block 2 and locks the chain 5 on the chain stopper 9.
[0034] The arrangement of the chain stopper 9 and the locker 10 enables the installer to power the locker 10 through the remote control power supply, thereby locking the chain 5 passing through the chain stopper 9, and strengthening the connection effect between the fender 3 and the fender supporting platform 1 through the tensioned chain 5; and after the fender purpose is completed, the power supply to the locker 10 can also be cut off through the remote control power supply, thereby releasing the connection between the chain 5 and the fender 3.
[0035] Preferably, in this embodiment, the power source inside the rubber compression block 2 is electrically connected to the electromagnetic suction device 8 and the locker 10 via wires extending from the rubber compression block 2 .
[0036] Obviously, the fender system of the upper module of the offshore platform of this embodiment is able to control the on and off of the power supply through the remote control device by arranging a remote-controlled power supply inside the rubber compression block 2. When the power is turned on, the electromagnetic suction device 8 is adsorbed on the fender support platform 1, and the locker 10 drives the chain stopper 9 to clamp the chain 5, thereby completing the installation of the fender system of the upper module of the offshore platform; when the power is cut off, the electromagnetic suction device 8 and the locker 10 are powered off synchronously, the locker 10 stops working and releases the chain stopper 9, the chain 5 is released, and the electromagnetic suction device 8 also loses its magnetism and disconnects from the fender support platform 1, thereby completing the removal of the components of the fender system of the upper module of the offshore platform except for the fender support platform 1 and the chain 5.
[0037] This embodiment also provides a method for manufacturing the fender system of the upper module of the offshore platform, Figure 1 and Figure 2 , including the following steps:
[0038] S1: During the onshore construction phase, the fender 3, the chain stopper 9, the locker 10, the rubber compression block 2 and the electromagnetic suction device 8 are installed as an integrated fender component, and the chain 5, the fender support platform 1 and the conductor frame 4 are installed as an integrated frame component;
[0039] S2: Install the frame integrated component at sea, and remotely control the power supply in the rubber compression block 2 to energize the electromagnetic suction device 8, so that the fender integrated component is magnetically connected to the frame integrated component;
[0040] S3: The two ends of each chain 5 are respectively passed through two chain stoppers 9 vertically spaced apart on the integrated fender component, and the locker 10 is energized by the power supply in the remotely controlled rubber compression block 2, so that the chain 5 is locked on the chain stopper 9 by the locker 10.
[0041] The method for manufacturing the fender system of the upper module of the offshore platform according to the present embodiment can realize the effective installation of the fender system of the upper module of the offshore platform.
[0042] The fender system of the upper module of the offshore platform of this embodiment can be applied to the floating installation of upper components of large offshore platforms such as offshore booster stations, converter stations and offshore oil platforms. It can be used in a wide range of scenarios with few restrictions, helping offshore wind power to move to the deep sea on a large scale and reduce costs and improve construction efficiency.
[0043] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A fender system for an upper module of an offshore platform, characterized in that: The invention comprises a fender support platform (1), a rubber compression block (2), a fender plate (3), an electromagnetic suction device (8) and a chain stopper (9), wherein the fender support platform (1) is integrally fixedly connected to the circumferential side of a pipe frame (4), one lateral end of the rubber compression block (2) is detachably vertically connected to the fender support platform (1), and the other lateral end is fixedly vertically connected to the fender plate (3), and the fender support platform (1) extends a chain (5) on both lateral sides of the rubber compression block (2), and both ends of each chain (5) are detachably connected to the fender plate (3) at a vertical interval; the rubber compression block (2) A remote-controlled power supply is provided inside the rubber compression block (2); the electromagnetic suction device (8) is arranged at one lateral end of the rubber compression block (2) and is electrically connected to the power supply; the electromagnetic suction device (8) is electromagnetically adsorbed on the fender support platform (1); four chain stoppers (9) are arranged at intervals in a rectangular shape on the fender plate (3); the two ends of each chain (5) are respectively inserted into two chain stoppers (9) arranged at intervals in a vertical direction; a power-off unlocking type locker (10) is installed on the chain stopper (9); the locker (10) is electrically connected to the power supply in the rubber compression block (2) and locks the chain (5) on the chain stopper (9).
2. A method for manufacturing a fender system for an upper module of an offshore platform according to claim 1, characterized in that: The following steps are involved: S1: During the onshore construction phase, the fender plate (3), the chain stopper (9), the locker (10), the rubber compression block (2) and the electromagnetic suction device (8) are installed as an integrated fender component, and the chain (5), the fender support platform (1) and the conductor frame (4) are installed as an integrated frame component; S2: installing the frame integrated component at sea, and remotely controlling the power supply in the rubber compression block (2) to energize the electromagnetic suction device (8), so that the fender integrated component is magnetically connected to the frame integrated component; S3: The two ends of each chain (5) are respectively inserted into two chain stoppers (9) vertically spaced apart on the integrated fender component, and the locker (10) is powered by remotely controlling the power supply in the rubber compression block (2), so that the chain (5) is locked on the chain stopper (9).
Citation Information