Power equipment health assessment method, system and storage medium based on digital twin

Through digital twin technology and decision tree classification model, combined with historical operation data and real-time infrared image data, the problems of inefficient and insufficient accuracy of traditional power equipment health assessment methods are solved, and rapid and accurate equipment health assessment and early warning regulation are achieved, improving The operational safety and efficiency of power equipment.

CN118094390BActive Publication Date: 2024-11-15ANHUI XINNENG VENTURE CAPITAL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410128661.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-30
Publication Date
2024-11-15
Estimated Expiration
2044-01-30

AI Technical Summary

Technical Problem

Traditional power equipment health assessment methods are inefficient and insufficiently accurate, and cannot meet the needs of large-scale equipment monitoring, making it difficult to quickly and accurately evaluate the health status of power equipment.

Method used

Using a digital twin method, a power model is constructed by obtaining historical operation data, combining real-time infrared image data and decision tree classification model, equipment pressure point analysis and health assessment are carried out, real-time pressure distribution data are generated and early warning and regulation are carried out.

Benefits of technology

It realizes fast and accurate equipment pressure distribution analysis, and improves the accuracy of equipment healthy operation evaluation and the operation safety and efficiency of power equipment under large-scale and high-complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118094390B_ABST
    Figure CN118094390B_ABST
Patent Text Reader

Abstract

The present invention discloses a method, system and storage medium for health assessment of electric power equipment based on digital twins, constructs an electric power model based on digital twins based on the historical operation data, obtains real-time infrared image data of preset electric power equipment in real time within an analysis cycle, analyzes infrared image features of internal and external equipment in the preset electric power equipment, constructs internal classification models and external classification models based on decision trees, performs feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtains real-time pressure distribution data of the preset electric power equipment; compares the real-time pressure distribution data with the equipment pressure distribution assessment data in the equipment area, generates health assessment data, and performs early warning and regulation on the preset electric power equipment based on the health assessment data. Through the present invention, fast and accurate equipment pressure distribution analysis can be achieved, and accurate evaluation of equipment health operation under large-scale and high-complexity conditions can be achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of digital twins, and more specifically, to a health assessment method, system and storage medium for power equipment based on digital twins. Background Art

[0002] With the widespread application of new energy equipment such as wind power equipment and photovoltaic equipment, the number and complexity of power equipment are increasing, making the health monitoring and maintenance of equipment more and more difficult. Traditional power equipment health assessment methods are inefficient and inaccurate, and cannot meet the needs of large-scale equipment monitoring. Therefore, developing a method and system that can accurately and quickly assess the health status of power equipment is of great significance to improving the reliability and operating efficiency of equipment. Summary of the invention

[0003] The present invention overcomes the defects of the prior art and proposes a power equipment health assessment method, system and storage medium based on digital twins.

[0004] The first aspect of the present invention provides a method for health assessment of electric power equipment based on digital twins, comprising:

[0005] Acquire historical operation data of preset power equipment, and build a digital twin-based power model based on the historical operation data;

[0006] Acquire power demand information within an analysis period, generate operation parameter information of preset power equipment based on the power demand information, import the operation parameter information into the power model to perform operation simulation and generate equipment operation simulation data;

[0007] Performing equipment pressure point analysis based on the equipment simulation data to generate equipment pressure distribution assessment data;

[0008] Acquire real-time infrared image data of preset power equipment in real time within an analysis cycle, analyze infrared image features of internal and external equipment in the preset power equipment, build internal classification model and external classification model based on decision tree, perform feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtain real-time pressure distribution data of the preset power equipment;

[0009] The real-time pressure distribution data is compared with the equipment pressure distribution assessment data in the equipment area, and health assessment data is generated. Based on the health assessment data, early warning and regulation of the preset power equipment are carried out.

[0010] In this solution, the historical operation data of the preset power equipment is obtained, and a power model based on digital twins is constructed based on the historical operation data, specifically:

[0011] Obtain historical operation data of preset power equipment;

[0012] The historical operation data includes current, voltage, power, equipment parameters, equipment temperature, and cable temperature monitoring data of the power equipment;

[0013] Based on historical operation data, the operation analysis and equation fitting of the preset power equipment are carried out to establish multiple equipment operation simulation models;

[0014] The multiple equipment operation simulation models are integrated to form a power model based on digital twins.

[0015] In this solution, the power demand information within an analysis period is obtained, the operation parameter information of the preset power equipment is generated based on the power demand information, the operation parameter information is imported into the power model for operation simulation and the equipment operation simulation data is generated, specifically:

[0016] Obtaining power demand information within an analysis period;

[0017] Based on the power demand information, operation task planning is performed for the preset power equipment, and operation parameter information is generated;

[0018] The operating parameter information is imported into the power model to simulate the equipment operation and generate equipment operation simulation data.

[0019] In this solution, the equipment pressure point analysis is performed based on the equipment simulation data to generate equipment pressure distribution evaluation data, specifically:

[0020] According to the equipment simulation data, the working pressure point of the preset power equipment is evaluated, the evaluation position is based on the equipment and the cable, and the pressure position point is obtained;

[0021] Acquire location distribution of preset power equipment, and divide the preset power equipment into external equipment and internal equipment based on the location distribution;

[0022] A pressure point distribution analysis is performed based on the position distribution, pressure position points and equipment simulation data, and equipment pressure distribution evaluation data is generated.

[0023] In this solution, the real-time infrared image data of the preset power equipment is obtained in real time within one analysis cycle, the infrared image features of the internal and external equipment in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, including:

[0024] Acquire first standard infrared image data of external equipment in preset power equipment under different environmental parameters;

[0025] The environmental parameters include external temperature, humidity, and climate parameters;

[0026] Obtaining an external pressure area and an internal pressure area according to the equipment pressure distribution evaluation data;

[0027] Based on the external pressure area, corresponding area feature extraction is performed on the first standard infrared image data, wherein the feature extraction is based on color and contour features to obtain infrared feature data and contour feature data of each pressure area;

[0028] Performing feature fusion on the infrared feature data and the contour feature data of each pressure area based on a pyramid fusion algorithm to form fused feature data;

[0029] Build an external classification model based on decision trees;

[0030] Generate feature judgment nodes based on fused feature data of each pressure area;

[0031] According to the feature judgment nodes and the CART heuristic algorithm, the root nodes and child nodes of the external classification model are determined, and a complete decision tree is constructed to obtain a complete external classification model.

[0032] In this solution, the real-time infrared image data of the preset power equipment is obtained in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, and also includes:

[0033] Acquire second standard infrared image data of external equipment in preset power equipment under different internal environmental parameters;

[0034] Based on the internal pressure area, corresponding area feature extraction is performed on the second standard infrared image data, the feature extraction is based on color and contour features, infrared feature data and contour feature data of each pressure area are obtained, and the infrared feature data and contour feature data are subjected to feature fusion based on a pyramid fusion algorithm to obtain fused feature data of each pressure area;

[0035] Build an internal classification model based on decision trees;

[0036] Generate feature judgment nodes based on fused feature data of each pressure area;

[0037] According to the feature judgment nodes and CART heuristic algorithm, the root nodes and child nodes of the internal classification model are determined, and a complete decision tree is constructed to obtain a complete internal classification model.

[0038] In this solution, the real-time infrared image data of the preset power equipment is obtained in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, and also includes:

[0039] Acquire infrared images of preset power equipment in real time within an analysis cycle to obtain real-time infrared image data;

[0040] Based on the preset power equipment, the real-time infrared image data is divided into external equipment images and internal equipment images;

[0041] Divide the external device image into grid areas to form multiple image sub-areas;

[0042] Extract color and contour features from image data in each image sub-region to obtain identification features;

[0043] Import the identification features into the external classification model for feature classification and equipment pressure point analysis to obtain pressure assessment information based on infrared feature analysis;

[0044] Analyze the pressure evaluation information of each image sub-region and perform overall pressure distribution evaluation on the entire external device image to obtain external pressure distribution data;

[0045] Performing regional division and image feature classification and recognition based on internal equipment images, the classification and recognition is based on an internal classification model, and obtaining internal pressure distribution data;

[0046] The real-time pressure distribution data includes external pressure distribution data and internal pressure distribution data.

[0047] In this solution, the real-time pressure distribution data and the equipment pressure distribution assessment data are compared in the equipment area, and health assessment data is generated. Based on the health assessment data, early warning and regulation of the preset power equipment are carried out, specifically:

[0048] Compare the real-time pressure distribution data with the equipment pressure distribution assessment data based on the internal and external equipment area pressures, mark the areas where the pressure points exceed the expected range, and generate real-time health assessment data for the preset power equipment through comparative analysis;

[0049] The health assessment data is sent to a preset terminal device, and a real-time early warning is given to the power equipment based on the health assessment data.

[0050] The second aspect of the present invention further provides a power equipment health assessment system based on digital twins, the system comprising: a memory, a processor, the memory comprising a power equipment health assessment program based on digital twins, the power equipment health assessment program based on digital twins when executed by the processor implements the following steps:

[0051] Acquire historical operation data of preset power equipment, and build a digital twin-based power model based on the historical operation data;

[0052] Acquire power demand information within an analysis period, generate operation parameter information of preset power equipment based on the power demand information, import the operation parameter information into the power model to perform operation simulation and generate equipment operation simulation data;

[0053] Performing equipment pressure point analysis based on the equipment simulation data to generate equipment pressure distribution assessment data;

[0054] Acquire real-time infrared image data of preset power equipment in real time within an analysis cycle, analyze infrared image features of internal and external equipment in the preset power equipment, build internal classification model and external classification model based on decision tree, perform feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtain real-time pressure distribution data of the preset power equipment;

[0055] The real-time pressure distribution data is compared with the equipment pressure distribution assessment data in the equipment area, and health assessment data is generated. Based on the health assessment data, early warning and regulation of the preset power equipment are carried out.

[0056] The third aspect of the present invention also provides a computer-readable storage medium, which includes a digital twin-based power equipment health assessment program. When the digital twin-based power equipment health assessment program is executed by a processor, the steps of the digital twin-based power equipment health assessment method as described in any one of the above items are implemented.

[0057] The present invention discloses a method, system and storage medium for health assessment of electric power equipment based on digital twins, constructs an electric power model based on digital twins based on the historical operation data, obtains real-time infrared image data of preset electric power equipment in real time within an analysis cycle, analyzes infrared image features of internal and external equipment in the preset electric power equipment, constructs internal classification models and external classification models based on decision trees, performs feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtains real-time pressure distribution data of the preset electric power equipment; compares the real-time pressure distribution data with the equipment pressure distribution assessment data in the equipment area, generates health assessment data, and performs early warning and regulation on the preset electric power equipment based on the health assessment data. Through the present invention, fast and accurate equipment pressure distribution analysis can be achieved, and accurate evaluation of equipment health operation under large-scale and high-complexity conditions can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] Figure 1 A flowchart of a method for health assessment of electric power equipment based on digital twins of the present invention is shown;

[0059] Figure 2 The flowchart of constructing the power model of the present invention is shown;

[0060] Figure 3 A block diagram of a digital twin-based power equipment health assessment system of the present invention is shown. DETAILED DESCRIPTION

[0061] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0062] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Therefore, the protection scope of the present invention is not limited to the specific embodiments disclosed below.

[0063] Figure 1 A flow chart of a method for health assessment of electric power equipment based on digital twins of the present invention is shown.

[0064] like Figure 1 As shown, the first aspect of the present invention provides a method for health assessment of power equipment based on digital twins, comprising:

[0065] S102, obtaining historical operation data of preset power equipment, and constructing a digital twin-based power model based on the historical operation data;

[0066] S104, acquiring power demand information within an analysis period, generating operation parameter information of preset power equipment based on the power demand information, importing the operation parameter information into a power model to perform operation simulation and generate equipment operation simulation data;

[0067] S106, performing equipment pressure point analysis based on the equipment simulation data to generate equipment pressure distribution evaluation data;

[0068] S108, acquiring real-time infrared image data of a preset power device in real time within an analysis cycle, analyzing infrared image features of internal and external devices in the preset power device, building an internal classification model and an external classification model based on a decision tree, and performing feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model to obtain real-time pressure distribution data of the preset power device;

[0069] S110, comparing the real-time pressure distribution data with the equipment pressure distribution assessment data in the equipment area, and generating health assessment data, and performing early warning and regulation on the preset power equipment based on the health assessment data.

[0070] Figure 2 The flowchart of building the power model of the present invention is shown.

[0071] According to an embodiment of the present invention, the step of obtaining historical operation data of a preset power device and constructing a digital twin-based power model based on the historical operation data is specifically as follows:

[0072] S202, obtaining historical operation data of preset power equipment;

[0073] S204, the historical operation data includes current, voltage, power, equipment parameters, equipment temperature, and cable temperature monitoring data of the power equipment;

[0074] S206, based on historical operation data, performing operation analysis and equation fitting on preset power equipment, and establishing multiple equipment operation simulation models;

[0075] S208, integrating the multiple device operation simulation models to form a digital twin-based power model.

[0076] It should be noted that the preset power equipment includes internal equipment and external equipment. The historical operation data is obtained by real-time data collection and data integration through various sensors of the power equipment. By analyzing the historical data, the operating parameters of the power equipment and the working power data are fitted with corresponding equations, and a corresponding simulation model (i.e., equipment operation simulation model) can be formed. Each power equipment corresponds to a simulation model, and a power model based on digital twins is formed through model integration. Through the power model, the power equipment can be simulated and operated, and the corresponding parameters can be input to obtain the simulated working state of the power equipment, which is used to evaluate the operation of the power equipment.

[0077] According to an embodiment of the present invention, the power demand information within an analysis period is obtained, the operation parameter information of the preset power equipment is generated based on the power demand information, and the operation parameter information is imported into the power model for operation simulation and generation of equipment operation simulation data, specifically:

[0078] Obtaining power demand information within an analysis period;

[0079] Based on the power demand information, operation task planning is performed for the preset power equipment, and operation parameter information is generated;

[0080] The operating parameter information is imported into the power model to simulate the equipment operation and generate equipment operation simulation data.

[0081] It should be noted that the power demand information includes the power generation and transmission demand data of the power equipment, and the operating parameter information includes the equipment operation setting parameters, operation mode, operation time and other information. The equipment pressure distribution assessment data is obtained by simulation analysis and assessment based on the existing power demand and digital twin technology, and is used for subsequent real-time comparison and health assessment.

[0082] The preset power equipment includes wind power equipment, photovoltaic power equipment and other power equipment.

[0083] According to an embodiment of the present invention, the device pressure point analysis is performed based on the device simulation data to generate device pressure distribution evaluation data, specifically:

[0084] According to the equipment simulation data, the working pressure point of the preset power equipment is evaluated, the evaluation position is based on the equipment and the cable, and the pressure position point is obtained;

[0085] Acquire location distribution of preset power equipment, and divide the preset power equipment into external equipment and internal equipment based on the location distribution;

[0086] A pressure point distribution analysis is performed based on the position distribution, pressure position points and equipment simulation data, and equipment pressure distribution evaluation data is generated.

[0087] It should be noted that the pressure points are load points that may appear during the operation of equipment (transformers, circuit breakers, insulators, etc.), cables, etc. Due to the continuous operation of the equipment, the temperature of the load points will rise. By subsequently analyzing the temperature changes of the pressure points, the pressure distribution can be effectively analyzed comprehensively, which is reflected in the infrared image as changes in color and contour features, thereby achieving accurate equipment health assessment during operation. The external equipment and internal equipment are mainly for outdoor and indoor equipment. For example, photovoltaic power equipment, its power generation device receives light in the outdoor environment, and the power storage system equipment is set in the indoor control room. The external and internal environments are different, and the infrared image analysis process of its equipment is also different.

[0088] According to an embodiment of the present invention, the real-time infrared image data of a preset power device is acquired in real time within an analysis cycle, infrared image features of internal and external devices in the preset power device are analyzed, an internal classification model and an external classification model are constructed based on a decision tree, and feature classification and equipment pressure point analysis are performed on the real-time infrared image data based on the internal classification model and the external classification model to obtain real-time pressure distribution data of the preset power device, including:

[0089] Acquire first standard infrared image data of external equipment in preset power equipment under different environmental parameters;

[0090] The environmental parameters include external temperature, humidity, and climate parameters;

[0091] Obtaining an external pressure area and an internal pressure area according to the equipment pressure distribution evaluation data;

[0092] Based on the external pressure area, corresponding area feature extraction is performed on the first standard infrared image data, wherein the feature extraction is based on color and contour features to obtain infrared feature data and contour feature data of each pressure area;

[0093] Performing feature fusion on the infrared feature data and the contour feature data of each pressure area based on a pyramid fusion algorithm to form fused feature data;

[0094] Build an external classification model based on decision trees;

[0095] Generate feature judgment nodes based on fused feature data of each pressure area;

[0096] According to the feature judgment nodes and the CART heuristic algorithm, the root nodes and child nodes of the external classification model are determined, and a complete decision tree is constructed to obtain a complete external classification model.

[0097] It should be noted that the standard infrared image data is historically collected infrared image data under different environmental parameter states, and is used as training data for the decision tree. The external pressure region and the internal pressure region each include at least one region, and correspond to an external device and an internal device, respectively.

[0098] It is worth mentioning that in the digital twin power analysis of the prior art, simple data is often used to compare and monitor the health status of power equipment, such as the comparison of temperature values. The effect is often relatively simple, and it is difficult to reasonably evaluate large-scale and highly complex power systems. The present invention uses digital twin technology to analyze the external and internal pressure points of power equipment. Based on different pressure points and pressure areas, the infrared image features of the equipment often show a high degree of correlation and regularity. Further, this embodiment constructs a recognition model when making a decision, and the decision tree uses the fused infrared features in different environments as judgment nodes to construct a recognition classification model with a high pressure feature recognition capability. In addition, based on the different environmental characteristics of internal and external equipment, two corresponding models are constructed for separate identification. Through the classification model, the pressure point features of the infrared image data collected in real time can be quickly judged, and the pressure distribution can be accurately judged in different environments and the classification results of the features can be obtained, so as to realize fast and accurate equipment pressure analysis and temperature control distribution analysis, thereby improving the accurate evaluation of the healthy operation of equipment under large-scale and high complexity, and improving the operation safety and efficiency of power equipment. In addition, the decision tree classification model can dynamically correct the classification decision by the imported training data, so as to adapt to the monitoring needs of different power equipment systems.

[0099] According to an embodiment of the present invention, the real-time infrared image data of the preset power equipment is acquired in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, and further includes:

[0100] Acquire second standard infrared image data of external equipment in preset power equipment under different internal environmental parameters;

[0101] Based on the internal pressure area, corresponding area feature extraction is performed on the second standard infrared image data, the feature extraction is based on color and contour features, infrared feature data and contour feature data of each pressure area are obtained, and the infrared feature data and contour feature data are subjected to feature fusion based on a pyramid fusion algorithm to obtain fused feature data of each pressure area;

[0102] Build an internal classification model based on decision trees;

[0103] Generate feature judgment nodes based on fused feature data of each pressure area;

[0104] According to the feature judgment nodes and CART heuristic algorithm, the root nodes and child nodes of the internal classification model are determined, and a complete decision tree is constructed to obtain a complete internal classification model.

[0105] It should be noted that the internal environmental parameters are the environmental parameters of the internal power equipment in a certain closed space, including temperature, humidity, etc., such as the equipment environment of a container or an ordinary room. The present invention includes internal and external classification models, and the construction process of the two is roughly the same, but the model data is completely different, which is different from the external and internal environmental parameters, different pressure areas, and different fusion feature data. The standard infrared image data is the collected data or simulated data under normal operation.

[0106] According to an embodiment of the present invention, the real-time infrared image data of the preset power equipment is acquired in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, and further includes:

[0107] Acquire infrared images of preset power equipment in real time within an analysis cycle to obtain real-time infrared image data;

[0108] Based on the preset power equipment, the real-time infrared image data is divided into external equipment images and internal equipment images;

[0109] Divide the external device image into grid areas to form multiple image sub-areas;

[0110] Extract color and contour features from image data in each image sub-region to obtain identification features;

[0111] Import the identification features into the external classification model for feature classification and equipment pressure point analysis to obtain pressure assessment information based on infrared feature analysis;

[0112] Analyze the pressure evaluation information of each image sub-region and perform overall pressure distribution evaluation on the entire external device image to obtain external pressure distribution data;

[0113] Performing regional division and image feature classification and recognition based on internal equipment images, the classification and recognition is based on an internal classification model, and obtaining internal pressure distribution data;

[0114] The real-time pressure distribution data includes external pressure distribution data and internal pressure distribution data.

[0115] According to an embodiment of the present invention, the real-time pressure distribution data and the equipment pressure distribution assessment data are compared in the equipment area, and health assessment data is generated, and early warning regulation of the preset power equipment is performed based on the health assessment data, specifically:

[0116] Compare the real-time pressure distribution data with the equipment pressure distribution assessment data based on the internal and external equipment area pressures, mark the areas where the pressure points exceed the expected range, and generate real-time health assessment data for the preset power equipment through comparative analysis;

[0117] The health assessment data is sent to a preset terminal device, and a real-time early warning is given to the power equipment based on the health assessment data.

[0118] According to an embodiment of the present invention, it also includes:

[0119] Get real-time health assessment data;

[0120] Acquire a pressure abnormality point of a preset power device based on the real-time health assessment data;

[0121] Acquire power transmission layout information of preset power equipment, and obtain transmission line data based on the power transmission layout information;

[0122] According to the transmission line data, the transmission line is used as the path and the abnormal pressure point is used as the path point. The shortest path planning analysis is performed based on the Floyd algorithm, and the abnormal impact path is generated.

[0123] Through the abnormal impact path, the power equipment on the corresponding path is analyzed and marked as abnormal impact equipment;

[0124] An operation and maintenance plan is analyzed based on the abnormal impact path and the abnormal impact equipment, and an operation and maintenance plan for the power system is obtained.

[0125] It should be noted that the pressure abnormal point is generally a temperature control abnormal point, and the infrared characteristics show abnormal conditions beyond the normal range. The power transmission layout information includes the equipment transmission circuit routes of power storage, power supply, transmission and other links. Through the interconnection line environment of the circuit route, combined with the analysis of abnormal pressure points, it is possible to evaluate the transmission impact of the abnormal point and generate an impact route. Equipment maintenance work is performed based on the impact route, thereby effectively improving the safety operation and maintenance efficiency of power equipment. The power system operation and maintenance plan includes operation and maintenance plans for system equipment such as equipment and cables.

[0126] Figure 3 A block diagram of a digital twin-based power equipment health assessment system of the present invention is shown.

[0127] The second aspect of the present invention further provides a power equipment health assessment system 3 based on digital twins, the system comprising: a memory 31, a processor 32, the memory comprising a power equipment health assessment program based on digital twins, the power equipment health assessment program based on digital twins when executed by the processor implements the following steps:

[0128] Acquire historical operation data of preset power equipment, and build a digital twin-based power model based on the historical operation data;

[0129] Acquire power demand information within an analysis period, generate operation parameter information of preset power equipment based on the power demand information, import the operation parameter information into the power model to perform operation simulation and generate equipment operation simulation data;

[0130] Performing equipment pressure point analysis based on the equipment simulation data to generate equipment pressure distribution assessment data;

[0131] Acquire real-time infrared image data of preset power equipment in real time within an analysis cycle, analyze infrared image features of internal and external equipment in the preset power equipment, build internal classification model and external classification model based on decision tree, perform feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtain real-time pressure distribution data of the preset power equipment;

[0132] The real-time pressure distribution data is compared with the equipment pressure distribution assessment data in the equipment area, and health assessment data is generated. Based on the health assessment data, early warning and regulation of the preset power equipment are carried out.

[0133] According to an embodiment of the present invention, the step of obtaining historical operation data of a preset power device and constructing a digital twin-based power model based on the historical operation data is specifically as follows:

[0134] Obtain historical operation data of preset power equipment;

[0135] The historical operation data includes current, voltage, power, equipment parameters, equipment temperature, and cable temperature monitoring data of the power equipment;

[0136] Based on historical operation data, the operation analysis and equation fitting of the preset power equipment are carried out to establish multiple equipment operation simulation models;

[0137] The multiple equipment operation simulation models are integrated to form a power model based on digital twins.

[0138] It should be noted that the preset power equipment includes internal equipment and external equipment. The historical operation data is obtained by real-time data collection and data integration through various sensors of the power equipment. By analyzing the historical data, the operating parameters of the power equipment and the working power data are fitted with corresponding equations, and a corresponding simulation model (i.e., equipment operation simulation model) can be formed. Each power equipment corresponds to a simulation model, and a power model based on digital twins is formed through model integration. Through the power model, the power equipment can be simulated and operated, and the corresponding parameters can be input to obtain the simulated working state of the power equipment, which is used to evaluate the operation of the power equipment.

[0139] According to an embodiment of the present invention, the power demand information within an analysis period is obtained, the operation parameter information of the preset power equipment is generated based on the power demand information, and the operation parameter information is imported into the power model for operation simulation and generation of equipment operation simulation data, specifically:

[0140] Obtaining power demand information within an analysis period;

[0141] Based on the power demand information, operation task planning is performed for the preset power equipment, and operation parameter information is generated;

[0142] The operating parameter information is imported into the power model to simulate the equipment operation and generate equipment operation simulation data.

[0143] It should be noted that the power demand information includes the power generation and transmission demand data of the power equipment, and the operating parameter information includes the equipment operation setting parameters, operation mode, operation time and other information. The equipment pressure distribution assessment data is obtained by simulation analysis and assessment based on the existing power demand and digital twin technology, and is used for subsequent real-time comparison and health assessment.

[0144] The preset power equipment includes wind power equipment, photovoltaic power equipment and other power equipment.

[0145] According to an embodiment of the present invention, the device pressure point analysis is performed based on the device simulation data to generate device pressure distribution evaluation data, specifically:

[0146] According to the equipment simulation data, the working pressure point of the preset power equipment is evaluated, the evaluation position is based on the equipment and the cable, and the pressure position point is obtained;

[0147] Acquire location distribution of preset power equipment, and divide the preset power equipment into external equipment and internal equipment based on the location distribution;

[0148] A pressure point distribution analysis is performed based on the position distribution, pressure position points and equipment simulation data, and equipment pressure distribution evaluation data is generated.

[0149] It should be noted that the pressure points are load points that may appear during the operation of equipment (transformers, circuit breakers, insulators, etc.), cables, etc. Due to the continuous operation of the equipment, the temperature of the load points will rise. By subsequently analyzing the temperature changes of the pressure points, the pressure distribution can be effectively analyzed comprehensively, which is reflected in the infrared image as changes in color and contour features, thereby achieving accurate equipment health assessment during operation. The external equipment and internal equipment are mainly for outdoor and indoor equipment. For example, photovoltaic power equipment, its power generation device receives light in the outdoor environment, and the power storage system equipment is set in the indoor control room. The external and internal environments are different, and the infrared image analysis process of its equipment is also different.

[0150] According to an embodiment of the present invention, the real-time infrared image data of a preset power device is acquired in real time within an analysis cycle, infrared image features of internal and external devices in the preset power device are analyzed, an internal classification model and an external classification model are constructed based on a decision tree, and feature classification and equipment pressure point analysis are performed on the real-time infrared image data based on the internal classification model and the external classification model to obtain real-time pressure distribution data of the preset power device, including:

[0151] Acquire first standard infrared image data of external equipment in preset power equipment under different environmental parameters;

[0152] The environmental parameters include external temperature, humidity, and climate parameters;

[0153] Obtaining an external pressure area and an internal pressure area according to the equipment pressure distribution evaluation data;

[0154] Based on the external pressure area, corresponding area feature extraction is performed on the first standard infrared image data, wherein the feature extraction is based on color and contour features to obtain infrared feature data and contour feature data of each pressure area;

[0155] Performing feature fusion on the infrared feature data and the contour feature data of each pressure area based on a pyramid fusion algorithm to form fused feature data;

[0156] Build an external classification model based on decision trees;

[0157] Generate feature judgment nodes based on fused feature data of each pressure area;

[0158] According to the feature judgment nodes and the CART heuristic algorithm, the root nodes and child nodes of the external classification model are determined, and a complete decision tree is constructed to obtain a complete external classification model.

[0159] It should be noted that the standard infrared image data is historically collected infrared image data under different environmental parameter states, and is used as training data for the decision tree. The external pressure region and the internal pressure region each include at least one region, and correspond to an external device and an internal device, respectively.

[0160] It is worth mentioning that in the digital twin power analysis of the prior art, simple data is often used to compare and monitor the health status of power equipment, such as the comparison of temperature values. The effect is often relatively simple, and it is difficult to reasonably evaluate large-scale and highly complex power systems. The present invention uses digital twin technology to analyze the external and internal pressure points of power equipment. Based on different pressure points and pressure areas, the infrared image features of the equipment often show a high degree of correlation and regularity. Further, this embodiment constructs a recognition model when making a decision, and the decision tree uses the fused infrared features in different environments as judgment nodes to construct a recognition classification model with a high pressure feature recognition capability. In addition, based on the different environmental characteristics of internal and external equipment, two corresponding models are constructed for separate identification. Through the classification model, the pressure point features of the infrared image data collected in real time can be quickly judged, and the pressure distribution can be accurately judged in different environments and the classification results of the features can be obtained, so as to realize fast and accurate equipment pressure analysis and temperature control distribution analysis, thereby improving the accurate evaluation of the healthy operation of equipment under large-scale and high complexity, and improving the operation safety and efficiency of power equipment. In addition, the decision tree classification model can dynamically correct the classification decision by the imported training data, so as to adapt to the monitoring needs of different power equipment systems.

[0161] According to an embodiment of the present invention, the real-time infrared image data of the preset power equipment is acquired in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, and further includes:

[0162] Acquire second standard infrared image data of external equipment in preset power equipment under different internal environmental parameters;

[0163] Based on the internal pressure area, corresponding area feature extraction is performed on the second standard infrared image data, the feature extraction is based on color and contour features, infrared feature data and contour feature data of each pressure area are obtained, and the infrared feature data and contour feature data are subjected to feature fusion based on a pyramid fusion algorithm to obtain fused feature data of each pressure area;

[0164] Build an internal classification model based on decision trees;

[0165] Generate feature judgment nodes based on fused feature data of each pressure area;

[0166] According to the feature judgment nodes and CART heuristic algorithm, the root nodes and child nodes of the internal classification model are determined, and a complete decision tree is constructed to obtain a complete internal classification model.

[0167] It should be noted that the internal environmental parameters are the environmental parameters of the internal power equipment in a certain closed space, including temperature, humidity, etc., such as the equipment environment of a container or an ordinary room. The present invention includes internal and external classification models, and the construction process of the two is roughly the same, but the model data is completely different, which is different from the external and internal environmental parameters, different pressure areas, and different fusion feature data. The standard infrared image data is the collected data or simulated data under normal operation.

[0168] According to an embodiment of the present invention, the real-time infrared image data of the preset power equipment is acquired in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, and further includes:

[0169] Acquire infrared images of preset power equipment in real time within an analysis cycle to obtain real-time infrared image data;

[0170] Based on the preset power equipment, the real-time infrared image data is divided into external equipment images and internal equipment images;

[0171] Divide the external device image into grid areas to form multiple image sub-areas;

[0172] Extract color and contour features from image data in each image sub-region to obtain identification features;

[0173] Import the identification features into the external classification model for feature classification and equipment pressure point analysis to obtain pressure assessment information based on infrared feature analysis;

[0174] Analyze the pressure evaluation information of each image sub-region and perform overall pressure distribution evaluation on the entire external device image to obtain external pressure distribution data;

[0175] Performing regional division and image feature classification and recognition based on internal equipment images, the classification and recognition is based on an internal classification model, and obtaining internal pressure distribution data;

[0176] The real-time pressure distribution data includes external pressure distribution data and internal pressure distribution data.

[0177] According to an embodiment of the present invention, the real-time pressure distribution data and the equipment pressure distribution assessment data are compared in the equipment area, and health assessment data is generated, and early warning regulation of the preset power equipment is performed based on the health assessment data, specifically:

[0178] Compare the real-time pressure distribution data with the equipment pressure distribution assessment data based on the internal and external equipment area pressures, mark the areas where the pressure points exceed the expected range, and generate real-time health assessment data for the preset power equipment through comparative analysis;

[0179] The health assessment data is sent to a preset terminal device, and a real-time early warning is given to the power equipment based on the health assessment data.

[0180] According to an embodiment of the present invention, it also includes:

[0181] Get real-time health assessment data;

[0182] Acquire a pressure abnormality point of a preset power device based on the real-time health assessment data;

[0183] Acquire power transmission layout information of preset power equipment, and obtain transmission line data based on the power transmission layout information;

[0184] According to the transmission line data, the transmission line is used as the path and the abnormal pressure point is used as the path point. The shortest path planning analysis is performed based on the Floyd algorithm, and the abnormal impact path is generated.

[0185] Through the abnormal impact path, the power equipment on the corresponding path is analyzed and marked as abnormal impact equipment;

[0186] An operation and maintenance plan is analyzed based on the abnormal impact path and the abnormal impact equipment, and an operation and maintenance plan for the power system is obtained.

[0187] It should be noted that the pressure abnormal point is generally a temperature control abnormal point, and the infrared characteristics show abnormal conditions beyond the normal range. The power transmission layout information includes the equipment transmission circuit routes of power storage, power supply, transmission and other links. Through the interconnection line environment of the circuit route, combined with the analysis of abnormal pressure points, it is possible to evaluate the transmission impact of the abnormal point and generate an impact route. Equipment maintenance work is performed based on the impact route, thereby effectively improving the safety operation and maintenance efficiency of power equipment. The power system operation and maintenance plan includes operation and maintenance plans for system equipment such as equipment and cables.

[0188] The third aspect of the present invention also provides a computer-readable storage medium, which includes a digital twin-based power equipment health assessment program. When the digital twin-based power equipment health assessment program is executed by a processor, the steps of the digital twin-based power equipment health assessment method as described in any one of the above items are implemented.

[0189] The present invention discloses a method, system and storage medium for health assessment of electric power equipment based on digital twins, constructs an electric power model based on digital twins based on the historical operation data, obtains real-time infrared image data of preset electric power equipment in real time within an analysis cycle, analyzes infrared image features of internal and external equipment in the preset electric power equipment, constructs internal classification models and external classification models based on decision trees, performs feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtains real-time pressure distribution data of the preset electric power equipment; compares the real-time pressure distribution data with the equipment pressure distribution assessment data in the equipment area, generates health assessment data, and performs early warning and regulation on the preset electric power equipment based on the health assessment data. Through the present invention, fast and accurate equipment pressure distribution analysis can be achieved, and accurate evaluation of equipment health operation under large-scale and high-complexity conditions can be achieved.

[0190] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. The device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as: multiple units or components can be combined, or can be integrated into another system, or some features can be ignored or not executed. In addition, the coupling, direct coupling, or communication connection between the components shown or discussed can be through some interfaces, and the indirect coupling or communication connection of the devices or units can be electrical, mechanical or other forms.

[0191] The units described above as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units; they may be located in one place or distributed on multiple network units; some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0192] In addition, all functional units in the embodiments of the present invention may be integrated into one processing unit, or each unit may be separately used as a unit, or two or more units may be integrated into one unit; the above-mentioned integrated units may be implemented in the form of hardware or in the form of hardware plus software functional units.

[0193] Those skilled in the art can understand that: all or part of the steps of implementing the above method embodiments can be completed by hardware related to program instructions, and the aforementioned program can be stored in a computer-readable storage medium. When the program is executed, it executes the steps of the above method embodiments; and the aforementioned storage medium includes: mobile storage devices, read-only memories (ROM, Read-Only Memory), random access memories (RAM, Random Access Memory), disks or optical disks, and other media that can store program codes.

[0194] Alternatively, if the above-mentioned integrated unit of the present invention is implemented in the form of a software function module and sold or used as an independent product, it can also be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the embodiment of the present invention can be essentially or partly reflected in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the methods described in each embodiment of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as mobile storage devices, ROM, RAM, magnetic disks or optical disks.

[0195] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A power equipment health assessment method based on digital twins, characterized in that: include: Acquire historical operation data of preset power equipment, and build a digital twin-based power model based on the historical operation data; Acquire power demand information within an analysis period, generate operation parameter information of preset power equipment based on the power demand information, import the operation parameter information into the power model to perform operation simulation and generate equipment operation simulation data; Performing equipment pressure point analysis based on the equipment operation simulation data to generate equipment pressure distribution evaluation data; Acquire real-time infrared image data of preset power equipment in real time within an analysis cycle, analyze infrared image features of internal and external equipment in the preset power equipment, build internal classification model and external classification model based on decision tree, perform feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtain real-time pressure distribution data of the preset power equipment; Compare the real-time pressure distribution data with the equipment pressure distribution assessment data for the equipment area, and generate health assessment data, and perform early warning and regulation on the preset power equipment based on the health assessment data; Among them, the real-time infrared image data of the preset power equipment is obtained in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, specifically: Acquire first standard infrared image data of external equipment in preset power equipment under different environmental parameters; The environmental parameters include external temperature, humidity, and climate parameters; Obtaining an external pressure area and an internal pressure area according to the equipment pressure distribution evaluation data; Based on the external pressure area, corresponding area feature extraction is performed on the first standard infrared image data, wherein the feature extraction is based on color and contour features to obtain infrared feature data and contour feature data of each pressure area; Performing feature fusion on the infrared feature data and the contour feature data of each pressure area based on a pyramid fusion algorithm to form fused feature data; Build an external classification model based on decision trees; Generate feature judgment nodes based on fused feature data of each pressure area; According to the feature judgment node and CART heuristic algorithm, the root node and child nodes of the external classification model are determined, and a complete decision tree is constructed to obtain a complete external classification model; Acquire second standard infrared image data of external equipment in preset power equipment under different internal environmental parameters; Based on the internal pressure area, corresponding area feature extraction is performed on the second standard infrared image data, the feature extraction is based on color and contour features, infrared feature data and contour feature data of each pressure area are obtained, and the infrared feature data and contour feature data are subjected to feature fusion based on a pyramid fusion algorithm to obtain fused feature data of each pressure area; Build an internal classification model based on decision trees; Generate feature judgment nodes based on fused feature data of each pressure area; According to the feature judgment node and CART heuristic algorithm, the root node and child nodes of the internal classification model are determined, and a complete decision tree is constructed to obtain a complete internal classification model; Acquire infrared images of preset power equipment in real time within an analysis cycle to obtain real-time infrared image data; Based on the preset power equipment, the real-time infrared image data is divided into external equipment images and internal equipment images; Divide the external device image into grid areas to form multiple image sub-areas; Extract color and contour features from image data in each image sub-region to obtain identification features; Import the identification features into the external classification model for feature classification and equipment pressure point analysis to obtain pressure assessment information based on infrared feature analysis; Analyze the pressure evaluation information of each image sub-region and perform overall pressure distribution evaluation on the entire external device image to obtain external pressure distribution data; Performing regional division and image feature classification and recognition based on internal equipment images, the classification and recognition is based on an internal classification model, and obtaining internal pressure distribution data; The real-time pressure distribution data includes external pressure distribution data and internal pressure distribution data.

2. According to claim 1, a method for health assessment of electric power equipment based on digital twins is characterized in that: The obtaining of historical operation data of preset power equipment and constructing a digital twin-based power model based on the historical operation data is specifically as follows: Obtain historical operation data of preset power equipment; The historical operation data includes current, voltage, power, equipment parameters, equipment temperature, and cable temperature monitoring data of the power equipment; Based on historical operation data, the operation analysis and equation fitting of the preset power equipment are carried out to establish multiple equipment operation simulation models; The multiple equipment operation simulation models are integrated to form a power model based on digital twins.

3. According to a method for health assessment of electric power equipment based on digital twins according to claim 1, it is characterized in that: The obtaining of power demand information within an analysis period, generating operation parameter information of preset power equipment based on the power demand information, importing the operation parameter information into the power model for operation simulation and generating equipment operation simulation data, specifically includes: Obtaining power demand information within an analysis period; Based on the power demand information, operation task planning is performed for the preset power equipment, and operation parameter information is generated; The operating parameter information is imported into the power model to simulate the equipment operation and generate equipment operation simulation data.

4. According to claim 1, a method for health assessment of electric power equipment based on digital twins is characterized in that: The equipment pressure point analysis is performed based on the equipment operation simulation data to generate equipment pressure distribution evaluation data, specifically: According to the equipment operation simulation data, the working pressure point of the preset power equipment is evaluated, the evaluation position is based on the equipment and the cable, and the pressure position point is obtained; Acquire location distribution of preset power equipment, and divide the preset power equipment into external equipment and internal equipment based on the location distribution; A pressure point distribution analysis is performed based on the position distribution, pressure position points and equipment operation simulation data, and equipment pressure distribution evaluation data is generated.

5. According to a method for health assessment of electric power equipment based on digital twins according to claim 1, it is characterized in that: The real-time pressure distribution data is compared with the equipment pressure distribution assessment data for the equipment area, and health assessment data is generated, and early warning and control of the preset power equipment are performed based on the health assessment data, specifically: Compare the real-time pressure distribution data with the equipment pressure distribution assessment data based on the internal and external equipment area pressures, mark the areas where the pressure points exceed the expected range, and generate real-time health assessment data for the preset power equipment through comparative analysis; The health assessment data is sent to a preset terminal device, and a real-time early warning is given to the power equipment based on the health assessment data.

6. A power equipment health assessment system based on digital twins, characterized in that: The system includes: a memory and a processor, wherein the memory includes a power equipment health assessment program based on digital twins, and when the power equipment health assessment program based on digital twins is executed by the processor, the following steps are implemented: Acquire historical operation data of preset power equipment, and build a digital twin-based power model based on the historical operation data; Acquire power demand information within an analysis period, generate operation parameter information of preset power equipment based on the power demand information, import the operation parameter information into the power model to perform operation simulation and generate equipment operation simulation data; Performing equipment pressure point analysis based on the equipment operation simulation data to generate equipment pressure distribution evaluation data; Acquire real-time infrared image data of preset power equipment in real time within an analysis cycle, analyze infrared image features of internal and external equipment in the preset power equipment, build internal classification model and external classification model based on decision tree, perform feature classification and equipment pressure point analysis on the real-time infrared image data based on the internal classification model and the external classification model, and obtain real-time pressure distribution data of the preset power equipment; Compare the real-time pressure distribution data with the equipment pressure distribution assessment data for the equipment area, and generate health assessment data, and perform early warning and regulation on the preset power equipment based on the health assessment data; Among them, the real-time infrared image data of the preset power equipment is obtained in real time within one analysis cycle, the infrared image features of the internal and external devices in the preset power equipment are analyzed, the internal classification model and the external classification model are constructed based on the decision tree, and the real-time infrared image data is subjected to feature classification and equipment pressure point analysis based on the internal classification model and the external classification model to obtain the real-time pressure distribution data of the preset power equipment, specifically: Acquire first standard infrared image data of external equipment in preset power equipment under different environmental parameters; The environmental parameters include external temperature, humidity, and climate parameters; Obtaining an external pressure area and an internal pressure area according to the equipment pressure distribution evaluation data; Based on the external pressure area, corresponding area feature extraction is performed on the first standard infrared image data, wherein the feature extraction is based on color and contour features to obtain infrared feature data and contour feature data of each pressure area; Performing feature fusion on the infrared feature data and the contour feature data of each pressure area based on a pyramid fusion algorithm to form fused feature data; Build an external classification model based on decision trees; Generate feature judgment nodes based on fused feature data of each pressure area; According to the feature judgment node and CART heuristic algorithm, the root node and child nodes of the external classification model are determined, and a complete decision tree is constructed to obtain a complete external classification model; Acquire second standard infrared image data of external equipment in preset power equipment under different internal environmental parameters; Based on the internal pressure area, corresponding area feature extraction is performed on the second standard infrared image data, the feature extraction is based on color and contour features, infrared feature data and contour feature data of each pressure area are obtained, and the infrared feature data and contour feature data are subjected to feature fusion based on a pyramid fusion algorithm to obtain fused feature data of each pressure area; Build an internal classification model based on decision trees; Generate feature judgment nodes based on fused feature data of each pressure area; According to the feature judgment node and CART heuristic algorithm, the root node and child nodes of the internal classification model are determined, and a complete decision tree is constructed to obtain a complete internal classification model; Acquire infrared images of preset power equipment in real time within an analysis cycle to obtain real-time infrared image data; Based on the preset power equipment, the real-time infrared image data is divided into external equipment images and internal equipment images; Divide the external device image into grid areas to form multiple image sub-areas; Extract color and contour features from image data in each image sub-region to obtain identification features; Import the identification features into the external classification model for feature classification and equipment pressure point analysis to obtain pressure assessment information based on infrared feature analysis; Analyze the pressure evaluation information of each image sub-region and perform overall pressure distribution evaluation on the entire external device image to obtain external pressure distribution data; Performing regional division and image feature classification and recognition based on internal equipment images, the classification and recognition is based on an internal classification model, and obtaining internal pressure distribution data; The real-time pressure distribution data includes external pressure distribution data and internal pressure distribution data.

7. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a digital twin-based power equipment health assessment program. When the digital twin-based power equipment health assessment program is executed by a processor, the steps of the digital twin-based power equipment health assessment method as described in any one of claims 1 to 5 are implemented.