Building facility supervision and maintenance system based on BIM

Through BIM technology, real-time monitoring of the status of building facilities and analysis of their characteristic parameters solves the problem of lack of predictability in traditional supervision, enables accurate failure risk judgment of facilities and dynamic adjustment of maintenance strategies, and improves the safety and reliability of facilities. sex.

CN118114879BActive Publication Date: 2024-10-22CCCC RAILWAY DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410297789.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-10-22
Estimated Expiration
2044-03-15

AI Technical Summary

Technical Problem

The supervision and maintenance of traditional building facilities lack pertinence and predictability, making it difficult to identify and prevent safety hazards and failure risks in a timely manner.

Method used

Adopt a BIM-based building facility supervision and maintenance system to monitor the status of facilities in real time through the monitoring and evaluation module and maintenance management module, extract the characteristic parameters of the facilities, such as aging index and operation index, conduct comprehensive analysis, determine the risk of failure, and perform corresponding maintenance Strategy.

Benefits of technology

It achieves accurate health status judgment and failure risk prediction of facilities, dynamically adjusts maintenance strategies, improves the reliability and safety of facilities, and avoids potential safety hazards and failures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118114879B_ABST
    Figure CN118114879B_ABST
Patent Text Reader

Abstract

The present invention discloses a building facility supervision and maintenance system based on BIM, which relates to the technical field of building supervision. By extracting features from the internal and external states of a facility respectively to obtain characteristic parameters of the facility, the overall state of the facility can be accurately measured, and technical support can be provided for further judging the health status of the facility, predicting failure risks, and timely implementing maintenance management strategies. By comprehensively analyzing the characteristic parameters of the facility to judge whether the facility has a failure risk, an accurate judgment of the risk status of the facility can be achieved, which helps to avoid potential safety hazards. At the same time, according to the judgment result of the failure risk, corresponding maintenance management strategies are executed, which can timely prevent the occurrence of facility failures and accidents, and improve the reliability and safety of the facility.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building supervision, and in particular to a building facility supervision and maintenance system based on BIM. Background Art

[0002] Building facilities play a vital role in the construction process, providing the infrastructure and services required for the normal operation of buildings. For example, electricity, water supply, drainage, air conditioning, HVAC and other facilities provide the necessary energy and environmental support for buildings, ensuring that the living and working environment in the building is comfortable and safe; therefore, the supervision and maintenance of building facilities is particularly important;

[0003] Traditional facility supervision and maintenance are often based on a model of regular inspection and maintenance, which has certain limitations and lacks specificity and predictability, resulting in inappropriate and in-time supervision and maintenance of building facilities, which in turn creates safety hazards. Summary of the invention

[0004] Based on this, it is necessary to provide a BIM-based building facility supervision and maintenance system to address the problems mentioned in the above background technology.

[0005] The object of the present invention can be achieved by the following technical solutions: A building facility supervision and maintenance system based on BIM, including a monitoring and evaluation module and a maintenance management module;

[0006] The monitoring and evaluation module extracts external and internal features of the facility based on the facility information and the environmental information of the environment in which the facility is located to obtain the characteristic parameters of the facility, where the characteristic parameters include the facility aging index, operation index and environmental impact factor; selects the largest facility aging index in each collection time as the aging factor of the facility, sends the aging factor to the data collection module, and sends the characteristic parameters of the facility to the maintenance management module;

[0007] The maintenance management module conducts a comprehensive analysis based on the characteristic parameters of the facility to determine whether the facility has a risk of failure and implements the corresponding maintenance strategy; the specific process is as follows:

[0008] 101: Assume that each facility has a maintenance factor, from which the maintenance factor corresponding to the facility can be obtained and recorded as Lf; substitute the facility aging index FWj, operation index NZj, environmental impact factor GHj, and maintenance factor Lf into the set formula The facility risk value PHj corresponding to each collection time is calculated, where h1, h2, and h3 are the set proportional coefficients respectively;

[0009] 102: Construct a risk value versus time curve with time as the horizontal axis and risk value as the vertical axis; draw a tangent to the curve at the risk point, use data fitting to get the tangent expression, and calculate the derivative of the risk at each risk point by taking the derivative of the tangent expression. Sum the risk derivatives greater than zero to get the risk monotonically increasing degree, recorded as A1; sum the risk derivatives less than zero and take the absolute value to get the risk monotonically decreasing degree, recorded as A2; count the number of risk derivatives equal to zero, recorded as A3; substitute the risk value PHj, the risk monotonically increasing degree A1, the risk monotonically decreasing degree A2 and the number of risk derivatives equal to zero A3 into the set formula The fault judgment index Af is calculated, where f4, f5, and f6 are respectively set proportional coefficients, and e is a natural constant; when the fault judgment index is greater than or equal to the set judgment threshold, the facility is recorded as a risk facility and a maintenance instruction is generated to control the risk facility to stop running, and the instruction is sent to the maintenance engineer's mobile terminal; when the maintenance completion instruction is received from the maintenance engineer's mobile terminal, the corresponding facility is restarted and 103 is executed;

[0010] 103: Obtain the time when the maintenance instruction is generated, and record it as the start time of the maintenance; obtain the time when the maintenance completion instruction is received, and record it as the end time of the maintenance; thereby, the number of maintenance times in the historical maintenance record of the facility and the maintenance start time and maintenance end time corresponding to each maintenance can be obtained, and the maintenance factor is obtained by performing cumulative analysis of the historical maintenance record, and it is updated to 101 and the data acquisition module.

[0011] In some embodiments, the specific steps of performing maintenance accumulation analysis based on historical maintenance records to obtain maintenance factors are:

[0012] Mark the maintenance times on the horizontal axis of time according to the corresponding maintenance time to obtain the maintenance trajectory diagram of the facility; calculate the interval between two adjacent maintenances to obtain the maintenance interval, and calculate the average of all maintenance intervals to obtain the average maintenance interval length, recorded as L2; ​​take the maintenance start time and maintenance end time of any maintenance to calculate the time difference to obtain the maintenance time, calculate the time difference between the maintenance time to which the maintenance time belongs and the current time of the system to obtain the relevant maintenance time; take the reciprocal of the relevant time corresponding to each maintenance time, and multiply it by the corresponding maintenance time to obtain the maintenance time related value corresponding to each maintenance time; then calculate the average of the maintenance time related values ​​corresponding to each maintenance time to obtain the maintenance time related mean, recorded as L1;

[0013] Substitute the average maintenance interval length L2 and the maintenance duration related average value L1 into the set formula The maintenance factor Lf is calculated and updated to step 1 and the data acquisition module, where f7 and f8 are the set proportional coefficients respectively.

[0014] In some embodiments, a data acquisition module and a BIM database are also included;

[0015] The building area is divided into several monitoring areas, each of which is equipped with several sensors. The data acquisition module determines the latest collection interval of each monitoring area by conducting demand analysis on the facilities in each monitoring area, and obtains the generation time of the latest collection instruction of each monitoring area from the current time of the system, and calculates the time difference between it and the current time of the system to obtain the actual interval length of each monitoring area. When the actual interval length of each monitoring area is equal to the latest collection interval of the corresponding monitoring area, the sensors connected to it are controlled to collect facility information and environmental information to obtain the facility information and environmental information of each monitoring area, and send them to the BIM database for storage.

[0016] In some embodiments, the specific steps of demand analysis are:

[0017] Obtain the workload, work frequency, and startup and shutdown times of the facilities in the monitoring area; calculate the time difference between the startup and shutdown times corresponding to each work to obtain the working time of each work;

[0018] When the working time is greater than the maximum value in the set time interval, one overtime work is accumulated; when the working time is within the set time interval, one medium-time work is accumulated; when the working time is less than the minimum value in the set time interval, one low-time work is accumulated; the number of overtime work, medium-time work and low-time work is counted respectively; the working time corresponding to overtime work, medium-time work and low-time work will be summed up to obtain the overtime time, medium-time time and low-time time respectively;

[0019] Substitute the workload S1, the number of overtime work S2, the number of medium-time work S3, the number of low-time work S4, the overtime duration S5, the medium-time duration S6 and the low-time duration S7 into the set formula The negative demand value Sd is calculated, where d1, d2, and d3 are respectively the set proportional coefficients, and d1>d2>d3, and e is a natural constant; thus, the negative demand value of each facility in the monitoring area can be obtained, and the average value of the negative demand in the monitoring area can be calculated;

[0020] It is assumed that each facility corresponds to a maintenance factor and an aging factor, thereby obtaining the maintenance factor and aging factor corresponding to each facility in the monitoring area, and calculating their mean values ​​to obtain the mean values ​​of the maintenance factors and aging factors of the facilities in the monitoring area;

[0021] The average negative demand in the monitoring area Substitute the maintenance factor mean Ga and the aging factor mean La into the set formula The latest acquisition interval LS is calculated, where d5 and d6 are respectively the set proportional coefficients, and δ is the set time conversion coefficient.

[0022] In some embodiments, the specific process of extracting features based on facility information and environmental information of the environment in which the facility is located is:

[0023] 501: Based on the facility appearance diagram, quantitative analysis is performed on the facility appearance aging to obtain the corrosion value and the crack value, the time when the facility is put into use is retrieved, and the time difference between the time difference and the current time of the system is calculated to obtain the use time, and the time difference is comprehensively analyzed with the corrosion value and the crack value to obtain the facility aging index, thereby obtaining the facility aging index corresponding to each collection time, selecting the maximum facility aging index as the facility aging factor, and sending it to the data collection module;

[0024] 502: retrieve the facility temperature, facility vibration value and energy consumption at each collection time, and compare them with the standard operation parameters to obtain the standard temperature, standard vibration value and standard energy consumption corresponding to each collection time; the facility temperature Tj, facility vibration value Zj, energy consumption Nj, standard temperature BT, standard vibration value BZ and standard energy consumption BN are calculated by the set formula Calculate and obtain the operation index NZj corresponding to each collection moment, where f1, f2, and f3 are respectively the set proportional coefficients; j = 1, 2, 3, ... J, where J is a positive integer, J represents the total number of collection moments, and j represents the sequence number of any collection moment;

[0025] 503: Perform environmental impact analysis based on the environmental information of the environment in which the facility is located to obtain the environmental impact factor corresponding to each collection time; record the facility aging index, operation index and environmental impact factor as characteristic parameters of the facility, and send the characteristic parameters to the maintenance management module.

[0026] In some embodiments, the specific process of quantitatively analyzing the aging of the facility appearance based on the facility appearance diagram to obtain the corrosion value and the crack value is as follows:

[0027] The convolutional neural network model is used to identify the appearance of the facility to obtain the corrosion parts and crack parts, and the area of ​​each corrosion part and crack part is calculated to obtain the corrosion area and crack area respectively. The corrosion area and crack area corresponding to each corrosion part and crack part are summed up to obtain the total corrosion value and the total number of cracks, which are recorded as Fz and Wz respectively.

[0028] The corrosion area is compared with the set corrosion interval to divide the corrosion area into high corrosion area, medium corrosion area and low corrosion area. The number of high corrosion area, medium corrosion area and low corrosion area is counted respectively and recorded as F1, F2 and F3 respectively. Fz, F1, F2 and F3 are substituted into the set formula The corrosion value is calculated, where a1, a2, and a3 are respectively set proportional coefficients, and a1>a2>a3>0;

[0029] The crack area is compared with the set crack interval to divide the crack area into primary crack area, secondary crack area and tertiary crack area. The number of primary crack area, secondary crack area and tertiary crack area is counted respectively and recorded as W1, W2 and W3 respectively; Wz, W1, W2 and W3 are substituted into the set formula to calculate the crack value a4, a5, and a6 are respectively set proportional coefficients, and a4>a5>a6>0.

[0030] In some embodiments, the specific process of environmental impact analysis is:

[0031] Retrieve the environmental information at each collection time, where the environmental information includes environmental temperature, environmental humidity and environmental pressure, and record them as GTj, GSj and GYj respectively; set each facility to correspond to an optimal environmental parameter, where the optimal environmental parameters include optimal environmental temperature, optimal environmental humidity and optimal environmental pressure, and record them as HT, HS and HY respectively; through the set formula The environmental impact factor GHj corresponding to each collection moment is calculated, where b1, b2, and b3 are respectively set proportional coefficients.

[0032] Compared with the prior art, the present invention has the following beneficial effects:

[0033] 1. Through real-time monitoring of the facilities in each monitoring area and dynamically adjusting the collection interval according to the actual working conditions of the facilities, a highly automated and intelligent data collection module is realized; facility information and environmental information can be collected more accurately. This method is more flexible and efficient than traditional periodic inspections, and can provide technical support for timely discovery and response to changes in facilities;

[0034] 2. By extracting the characteristics of the internal and external states of the facility to obtain the characteristic parameters of the facility, the overall state of the facility can be accurately measured, providing technical support for further judging the health status of the facility, predicting the risk of failure, and timely implementing maintenance management strategies;

[0035] 3. By comprehensively analyzing the characteristic parameters of the facility to determine whether the facility has a risk of failure, an accurate judgment of the risk status of the facility can be achieved, which helps to avoid potential safety hazards. At the same time, according to the judgment results of the failure risk, the corresponding maintenance management strategy is implemented, which can timely prevent the occurrence of facility failures and accidents and improve the reliability and safety of the facility. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the conventional technology, the drawings required for use in the embodiments or the conventional technology descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0037] Figure 1 It is a principle block diagram of the present invention. DETAILED DESCRIPTION

[0038] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0039] like Figure 1 As shown, the BIM-based building facility supervision and maintenance system includes: data acquisition module, BIM database, monitoring and evaluation module and maintenance management module;

[0040] The building area is divided into several monitoring areas, each of which is equipped with several sensors. The data acquisition module determines the latest collection interval of each monitoring area by performing demand analysis on the facilities in each area, and obtains the generation time of the latest collection instruction of each monitoring area from the current time of the system, and calculates the time difference between it and the current time of the system to obtain the actual interval length of each monitoring area. When the actual interval length of each monitoring area is equal to the latest collection interval of the corresponding monitoring area, the sensors connected to it are controlled to collect facility information and environmental information to obtain the facility information and environmental information of each monitoring area, and send them to the BIM database for storage; the specific steps of demand analysis are as follows:

[0041] Obtain the workload of the facilities in the monitoring area and record it as S1, the number of work, and the start-up time and shutdown time corresponding to each work; calculate the time difference between the start-up time and the shutdown time corresponding to each work to obtain the working time of each work, and compare the working time with the set time interval. When the working time is greater than the maximum value in the set time interval, an overtime work is accumulated; when the working time is within the set time interval, a medium-time work is accumulated; when the working time is less than the minimum value in the set time interval, a low-time work is accumulated; count the number of overtime work, medium-time work and low-time work respectively, and record them as S2, S3 and S4 respectively; sum the working time corresponding to overtime work, medium-time work and low-time work to obtain the overtime time, medium-time time and low-time time, and record them as S5, S6 and S7 respectively; use the set formula The negative demand value Sd is calculated, where d1, d2, and d3 are respectively the set proportional coefficients, and d1>d2>d3, and e is a natural constant; it should be noted that the negative demand value is a value that measures the importance of facilities in buildings. The larger the negative demand value, the higher the frequency of use of the facility in the building facilities, the more load it carries, and the more important it is in the building facilities, the larger the negative demand value; thus, the negative demand value of each facility in the monitoring area can be obtained, and the average value is calculated to obtain the average negative demand value in the monitoring area, which is recorded as Sd;

[0042] Assume that each facility corresponds to a maintenance factor and an aging factor, thus the maintenance factor and aging factor corresponding to each facility in the monitoring area can be obtained, and the mean values ​​of the maintenance factor and aging factor of the facilities in the monitoring area are calculated respectively, and recorded as Ga and La respectively; using the set formula The latest collection interval LS is calculated, where d5 and d6 are the set proportional coefficients, and δ is the set time conversion coefficient; thus, the minimum collection interval of each monitoring area can be obtained;

[0043] By real-time monitoring of the facilities in each monitoring area and dynamically adjusting the collection interval according to the actual working conditions of the facilities, a highly automated and intelligent data collection module is realized; facility information and environmental information can be collected more accurately. This method is more flexible and efficient than traditional periodic inspections, and can provide technical support for timely detection and response to changes in facilities.

[0044] The monitoring and evaluation module analyzes the internal and external status of each facility by analyzing the facility information and environmental information of each facility in the monitoring area to evaluate its status characteristics and obtain status characteristic parameters, specifically:

[0045] Internal status analysis: retrieve facility information at each collection time, including facility appearance, commissioning time, facility temperature, facility vibration value, and energy consumption value;

[0046] The convolutional neural network model is used to identify the appearance of the facility to obtain the corrosion parts and crack parts, where the corrosion parts refer to the corrosion phenomena such as fading, mottled, paint peeling, damage and discoloration caused by oxidation on the surface of the facility; the number of corrosion parts and crack parts is counted respectively, and the area of ​​each corrosion part and crack part is calculated to obtain the corrosion area and crack area respectively, and the corrosion area and crack area corresponding to each corrosion part and crack part are summed up to obtain the total corrosion value and the total number of cracks, which are recorded as Fz and Wz respectively;

[0047] The corrosion area is compared with the set corrosion interval. When the corrosion area is greater than the maximum value in the set corrosion interval, the corrosion area is recorded as a high corrosion area; when the corrosion area is within the set corrosion interval, the corrosion area is recorded as a moderate corrosion area; when the corrosion area is less than the minimum value in the set corrosion interval, the corrosion area is recorded as a low corrosion area; the number of high corrosion areas, moderate corrosion areas and low corrosion areas is counted respectively, and they are recorded as F1, F2 and F3 respectively; using the set formula The corrosion value is calculated, where a1, a2, and a3 are respectively set proportional coefficients, and a1>a2>a3>0;

[0048] The crack area is compared and analyzed with the set crack interval. When the crack area is greater than the maximum value in the set crack interval, the crack area is recorded as the primary crack area; when the crack area is within the set crack interval, the crack area is recorded as the secondary crack area; when the crack area is less than the minimum value in the set crack interval, the crack area is recorded as the tertiary crack area; the number of primary crack areas, secondary crack areas and tertiary crack areas is counted respectively, and they are recorded as W1, W2 and W3 respectively, and the crack value is calculated using the set formula a4, a5, and a6 are respectively set proportional coefficients, and a4>a5>a6>0;

[0049] The time when the facility is put into use is retrieved, and the time difference between it and the current time of the system is calculated to obtain the use time, which is recorded as F4. The facility aging index FW is calculated using the set formula FW=ea7×Fa+a8×Wa+a9×F4, where a7, a8, and a9 are respectively the set proportional coefficients, and e is a natural constant; thus, the facility aging index of each facility in the monitoring area is recorded as FWj, where j=1, 2, 3...J, and J is a positive integer, J represents the total number of collection moments, and j represents the sequence number of any collection moment;

[0050] The facility temperature, facility vibration value and energy consumption at each collection time are retrieved and recorded as Tj, Zj and Nj respectively; a standard operating parameter is set for each facility, wherein the standard operating parameter includes a standard temperature range, a standard vibration range and a standard energy consumption range; it should be noted that the standard operating parameter is usually determined based on the design requirements of the facility, the manufacturer's recommendations, industry standards and actual operating experience, so different facilities correspond to a standard operating parameter; the facility temperature at each collection time is compared and analyzed with the standard temperature range, when the facility temperature is greater than the maximum value in the set standard temperature range, the upper limit in the standard temperature range is used as the standard temperature at the collection time; when the facility temperature is within the set standard temperature range, the facility temperature at the collection time is used as the standard temperature at the collection time; when the facility temperature is less than the minimum value in the set standard temperature range, the lower limit in the standard temperature range is used as the standard temperature at the collection time;

[0051] Compare and analyze the facility vibration value at each collection time with the standard vibration range. When the facility vibration value is greater than the maximum value in the set standard vibration range, the upper limit in the standard vibration range is used as the standard vibration value at the collection time; when the facility vibration value is within the set standard vibration range, the facility vibration value at the collection time is used as the standard vibration value at the collection time; when the facility temperature is less than the minimum value in the set standard vibration range, the lower limit in the standard vibration range is used as the standard vibration value at the collection time;

[0052] Compare and analyze the facility energy consumption at each collection time with the standard energy consumption range. When the facility energy consumption is greater than the maximum value in the set standard energy consumption range, the upper limit in the standard energy consumption range is used as the standard energy consumption value at the collection time; when the facility energy consumption is within the set standard energy consumption range, the facility energy consumption at the collection time is used as the standard energy consumption at the collection time; when the facility energy consumption is less than the minimum value in the set standard energy consumption range, the lower limit in the standard energy consumption range is used as the standard energy consumption at the collection time;

[0053] Thus, the standard temperature, standard vibration value and standard energy consumption corresponding to each acquisition time can be obtained, and they are recorded as BT, BZ and BN respectively; using the set formula The operation index NZj corresponding to each collection time is calculated, where f1, f2, and f3 are the set proportional coefficients respectively; it can be seen from the formula that when the facility temperature, facility vibration value, and energy consumption at each collection time are closer to the standard temperature, standard vibration value, and standard energy consumption, the operation status of the facility is more normal, and the operation index will be larger if the facility is within the range of the standard operation parameter requirements; on the contrary, if the temperature, vibration value, or energy consumption of the facility deviates from the standard value, the operation status of the facility will be more abnormal, and the operation index will be smaller accordingly;

[0054] External state analysis: retrieve the environmental information at each acquisition time, including environmental temperature, environmental humidity and environmental pressure, and record them as GTj, GSj and GYj respectively; it should be noted that the working environment of the equipment will directly affect its wear and aging degree; for example, harsh environments such as humidity, corrosion, high temperature and high pressure will accelerate the wear and aging of the equipment, causing the performance of the facility to decline; set each facility to correspond to an optimal environmental parameter, including optimal environmental temperature, optimal environmental humidity and optimal environmental pressure, and record them as HT, HS and HY respectively; the optimal environmental parameter means that the facility is relatively less worn and aged under certain specific environmental conditions, so that it can maintain better performance and life; the optimal environmental parameters usually include optimal environmental temperature (HT), optimal environmental humidity (HS) and optimal environmental pressure (HY). Different types of facilities may have different requirements for these environmental parameters, so the corresponding optimal environmental conditions are usually different; use the set formula The environmental impact factor GHj corresponding to each collection moment is calculated, where b1, b2, and b3 are the set proportional coefficients respectively; it can be seen from the formula that when the ambient temperature, ambient humidity, and ambient pressure are closer to the optimal environmental parameters, the smaller the environmental impact factor is, indicating that the negative impact of environmental conditions on the facility is smaller;

[0055] The facility aging index FWj, the operation index NZj and the environmental impact factor GHj are recorded as the characteristic parameters of the facility, and the largest facility aging index corresponding to each collection time of each facility in the monitoring area is selected as the aging factor FWmax of each facility in the monitoring area, and sent to the data acquisition module;

[0056] By extracting features from the internal and external states of the facility respectively to obtain the characteristic parameters of the facility, the overall state of the facility can be accurately measured, providing technical support for further judging the health status of the facility, predicting failure risks, and timely implementing maintenance management strategies.

[0057] The maintenance management module comprehensively analyzes various parameters to determine the risk of facility failure, and implements corresponding maintenance management strategies to achieve timely maintenance management of building facilities, improve the reliability and safety of facilities, and effectively prevent accidents; specifically:

[0058] Step 1: Assume that each facility has a maintenance factor, thereby obtaining the maintenance factor corresponding to the facility and recording it as Lf; the facility aging index FWj, operation index NZj, environmental impact factor GHj, and maintenance factor Lf are calculated by the formula The facility risk value PHj corresponding to each collection time is calculated, where h1, h2, and h3 are the set proportional coefficients respectively;

[0059] Step 2: Construct a two-dimensional rectangular coordinate system with time as the horizontal axis and risk value as the vertical axis; input the risk value into the coordinate axis according to the corresponding collection time, and record the position of the risk value in the coordinate axis as the risk point; use a smooth curve to connect the risk points in sequence to obtain a curve relationship diagram of the risk value changing with time; draw a tangent to the curve at the risk point, use data fitting to obtain the tangent expression, and derive the tangent expression to obtain the risk derivative of each risk point. The risk derivatives greater than zero are summed up to obtain the risk monotonic increase degree, which is recorded as A1, and the risk derivatives less than zero are summed up and the absolute value is taken to obtain the risk monotonic decrease degree, which is recorded as A2. The number of risk derivatives equal to zero is recorded as A3, and the set formula is used. The fault judgment index Af is calculated, where f4, f5, and f6 are respectively the set proportional coefficients, and e is a natural constant; the fault judgment index is compared and analyzed with the set judgment threshold. When the fault judgment index is greater than or equal to the set judgment threshold, it indicates that the facility has a greater safety risk and needs safety maintenance. The facility is recorded as a risk facility and a maintenance instruction is generated to control the risk facility to stop running. The instruction is sent to the maintenance engineer's mobile terminal to promptly notify the maintenance engineer to perform safety maintenance; when the maintenance completion instruction is received from the maintenance engineer's mobile terminal, the corresponding facility is restarted, and step three is executed to perform fault accumulation analysis;

[0060] Step 3: Get the time when the maintenance instruction is generated, and record it as the start time of the maintenance; get the time when the maintenance completion instruction is received, and record it as the end time of the maintenance; thus, the number of maintenances in the historical maintenance record of the facility and the corresponding maintenance start time and maintenance end time of each maintenance can be obtained; mark the number of maintenances on the horizontal axis of time according to the corresponding maintenance time (maintenance start time and maintenance end time) to obtain the maintenance trajectory diagram of the facility; take the maintenance end time of the previous maintenance and the maintenance start time of the next maintenance in two adjacent maintenances to calculate the time difference to obtain the maintenance interval length, and calculate the average of all maintenance interval lengths to obtain the average maintenance interval length and record it as L2; ​​take the maintenance start time and maintenance end time of any maintenance to calculate the time difference Calculate the maintenance duration; sort the maintenance interval durations according to the maintenance time to which they belong (maintenance start time and maintenance end time), and calculate the time difference between the maintenance time to which they belong and the current system time to obtain the relevant duration of the maintenance duration. It should be noted that the larger the relevant duration corresponding to the maintenance duration, the farther the maintenance duration is from the current system time according to the maintenance time to which it belongs, and the smaller the impact of the maintenance duration on the current time; take the reciprocal of the relevant duration corresponding to each maintenance duration, and multiply it by the corresponding maintenance duration to obtain the relevant value of the maintenance duration corresponding to each maintenance duration, and then calculate the average of the relevant values ​​of the maintenance duration corresponding to each maintenance duration to obtain the relevant mean of the maintenance duration, and record it as L1; use the set formula Calculate and obtain the maintenance factor Lf, and update the maintenance factor to step 1 and the data acquisition module; wherein f7 and f8 are respectively the set proportional coefficients;

[0061] By comprehensively analyzing the characteristic parameters of the facility to determine whether the facility has a risk of failure, an accurate judgment of the risk status of the facility can be achieved, which helps to avoid potential safety hazards; at the same time, according to the judgment results of the failure risk, the corresponding maintenance management strategy can be implemented to prevent the occurrence of facility failures and accidents in a timely manner, and improve the reliability and safety of the facility. Such a maintenance management module can effectively ensure the normal operation of the facility, reduce the losses caused by failures and accidents, and improve the overall efficiency of the facility.

[0062] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0063] The above-mentioned embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. The BIM-based building facility supervision and maintenance system is characterized by: include: Data collection module, monitoring and evaluation module and maintenance management module; The monitoring and evaluation module extracts external and internal features of the facility based on the facility information and the environmental information of the facility environment to obtain the characteristic parameters of the facility, where the characteristic parameters include the facility aging index, operation index and environmental impact factor; selects the largest facility aging index in each collection time as the facility aging factor, sends the aging factor to the data collection module, and sends the characteristic parameters of the facility to the maintenance management module; the details are as follows: 501: Based on the facility appearance diagram, quantitative analysis is performed on the facility appearance aging to obtain the corrosion value and the crack value, the time when the facility is put into use is retrieved, and the time difference between the time difference and the current time of the system is calculated to obtain the use time, and the time difference is comprehensively analyzed with the corrosion value and the crack value to obtain the facility aging index, thereby obtaining the facility aging index corresponding to each collection time, selecting the maximum facility aging index as the facility aging factor, and sending it to the data collection module; 502: retrieve the facility temperature, facility vibration value and energy consumption at each collection time, and compare them with the standard operation parameters to obtain the standard temperature, standard vibration value and standard energy consumption corresponding to each collection time; the facility temperature Tj, facility vibration value Zj, energy consumption Nj, standard temperature BT, standard vibration value BZ and standard energy consumption BN are calculated by the set formula The operation index NZj corresponding to each acquisition moment is calculated, where f1, f2, and f3 are respectively the set proportional coefficients; j=1, 2, 3...J, J represents the total number of acquisition moments, and j represents the sequence number of any one of the acquisition moments; 503: Perform environmental impact analysis based on the environmental information of the environment in which the facility is located to obtain the environmental impact factor corresponding to each collection time; record the facility aging index, operation index and environmental impact factor as characteristic parameters of the facility, and send the characteristic parameters to the maintenance management module; The maintenance management module conducts a comprehensive analysis based on the characteristic parameters of the facility to determine whether the facility has a risk of failure and implements the corresponding maintenance strategy; the specific process is as follows: 101: Assume that each facility has a maintenance factor, thereby obtaining the maintenance factor corresponding to the facility; perform formula calculation and analysis on the facility aging index, operation index, environmental impact factor and maintenance factor to obtain the facility risk value PHj corresponding to each collection time; 102: construct a risk value versus time curve relationship diagram with time as the horizontal axis and risk value as the vertical axis; draw a tangent line at the risk point, obtain the tangent expression by data fitting, and calculate the risk derivative of each risk point by taking the derivative of the tangent expression; sum the risk derivatives greater than zero to obtain the risk monotonically increasing degree; sum the risk derivatives less than zero and take the absolute value to obtain the risk monotonically decreasing degree; count the number of risk derivatives equal to zero; and calculate and analyze the risk value, the risk monotonically increasing degree, the risk monotonically decreasing degree, and the number of risk derivatives equal to zero by formulating and analyzing to obtain the fault judgment index; when the fault judgment index is greater than or equal to the set judgment threshold, the facility is recorded as a risk facility and a maintenance instruction is generated to control the risk facility to stop running, and the instruction is sent to the maintenance engineer's mobile terminal; when the maintenance completion instruction is received from the maintenance engineer's mobile terminal, the corresponding facility is restarted and 103 is executed; 103: Obtain the time when the maintenance instruction is generated, and record it as the maintenance start time; obtain the time when the maintenance completion instruction is received, and record it as the maintenance end time; thereby, the number of maintenance times in the facility's historical maintenance record and the maintenance start time and maintenance end time corresponding to each maintenance can be obtained, and the maintenance factor is obtained by performing maintenance cumulative analysis based on the historical maintenance record, and it is updated to 101 and the data acquisition module; the details are as follows: Mark the maintenance times on the horizontal axis of time according to the corresponding maintenance time to obtain the maintenance trajectory diagram of the facility; calculate the interval between two adjacent maintenances to obtain the maintenance interval, and calculate the average of all maintenance intervals to obtain the average maintenance interval; take the maintenance start time and maintenance end time of any maintenance to calculate the time difference to obtain the maintenance time, calculate the time difference between the maintenance time to which the maintenance time belongs and the current time of the system to obtain the relevant maintenance time; take the reciprocal of the relevant time corresponding to each maintenance time, and multiply it by the corresponding maintenance time to obtain the maintenance time related value corresponding to each maintenance time; then calculate the average of the maintenance time related values ​​corresponding to each maintenance time to obtain the maintenance time related mean; The maintenance factor is obtained by formulating and analyzing the average length of the maintenance interval and the related average value of the maintenance duration, and the maintenance factor is updated to 101 and the data acquisition module.

2. The BIM-based building facility supervision and maintenance system according to claim 1 is characterized in that: It also includes a BIM database; The building area is divided into several monitoring areas, each of which is equipped with several sensors. The data acquisition module determines the latest collection interval of each monitoring area by conducting demand analysis on the facilities in each monitoring area, and obtains the generation time of the latest collection instruction of each monitoring area from the current time of the system, and calculates the time difference between it and the current time of the system to obtain the actual interval length of each monitoring area. When the actual interval length of each monitoring area is equal to the latest collection interval of the corresponding monitoring area, the sensors connected to it are controlled to collect facility information and environmental information to obtain the facility information and environmental information of each monitoring area, and send them to the BIM database for storage.

3. The BIM-based building facility supervision and maintenance system according to claim 2 is characterized in that: The specific steps of demand analysis are: Obtain the workload, work frequency, and startup and shutdown times of the facilities in the monitoring area; calculate the time difference between the startup and shutdown times corresponding to each work to obtain the working time of each work; When the working time is greater than the maximum value in the set time interval, one overtime work is accumulated; when the working time is within the set time interval, one medium-time work is accumulated; when the working time is less than the minimum value in the set time interval, one low-time work is accumulated; the number of overtime work, medium-time work and low-time work is counted respectively; the working time corresponding to overtime work, medium-time work and low-time work will be summed up to obtain the overtime time, medium-time time and low-time time respectively; The workload, the number of overtime work, the number of medium-time work, the number of low-time work, the length of overtime, the length of medium-time and the length of low-time are calculated and analyzed by formula to obtain the negative demand value; thus, the negative demand value of each facility in the monitoring area can be obtained, and the average value is calculated to obtain the average negative demand value in the monitoring area; It is assumed that each facility corresponds to a maintenance factor and an aging factor, thereby obtaining the maintenance factor and aging factor corresponding to each facility in the monitoring area, and calculating their mean values ​​to obtain the mean values ​​of the maintenance factors and aging factors of the facilities in the monitoring area; The average negative demand, maintenance factor and aging factor in the monitoring area are calculated and analyzed by formulating and analyzing to obtain the latest collection interval.

4. The BIM-based building facility supervision and maintenance system according to claim 1, characterized in that: The specific process of quantitatively analyzing the aging of the facility appearance based on the facility appearance diagram to obtain the corrosion value and crack value is as follows: The convolutional neural network model is used to identify the appearance of the facility to obtain the corrosion parts and crack parts, and the area of ​​each corrosion part and crack part is calculated to obtain the corrosion area and crack area respectively. The corrosion area and crack area corresponding to each corrosion part and crack part are summed up to obtain the total corrosion value and the total number of cracks. Compare and analyze the corrosion area with the set corrosion interval to divide the corrosion area into high corrosion area, medium corrosion area and low corrosion area, count the number of high corrosion area, medium corrosion area and low corrosion area respectively, and calculate and analyze the corrosion value with the total corrosion value in a formula; The crack area is compared with the set crack interval to divide the crack area into primary crack area, secondary crack area and tertiary crack area. The number of primary crack area, secondary crack area and tertiary crack area is counted respectively, and the crack value is obtained by formulating and analyzing them with the total crack value.

5. The BIM-based building facility supervision and maintenance system according to claim 4 is characterized in that: The specific process of environmental impact analysis is as follows: Retrieve the environmental information at each collection time, including the environmental temperature, environmental humidity and environmental pressure, and record them as GTj, GSj and GYj respectively; set each facility to correspond to an optimal environmental parameter, including the optimal environmental temperature, optimal environmental humidity and optimal environmental pressure, and record their values ​​as HT, HS and HY respectively; through the set formula The environmental impact factor GHj corresponding to each collection moment is calculated, where b1, b2, and b3 are respectively set proportional coefficients.