A vertical water well

By setting up multi-stage energy dissipation channels in the water drop well, using water flow diversion and hedging mechanisms to consume water flow energy, the problem of insufficient consumption of water flow energy in the existing technology is solved, and the energy dissipation effect of the vertical shaft and the impact resistance of the structure are improved. .

CN118128153BActive Publication Date: 2024-11-26JILIANG FUTURE WATER TECH (SHENZHEN) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410467454.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-18
Publication Date
2024-11-26
Estimated Expiration
2044-04-18

AI Technical Summary

Technical Problem

In existing water drop wells, water flow energy cannot be completely consumed in water conservancy projects that deal with large flow and large drops, resulting in the structure being subjected to impact pressure. The existing technology needs to enhance the strength of the structure to resist the impact of the water flow, and there is a lack of effective energy dissipation measures.

Method used

A water drop shaft was designed, and a multi-stage energy dissipation channel was set up in the well body, including slope stairs and reverse slope stairs. The water flow was divided into two parts in the diversion. After hedging the energy dissipation pool and the force dissipation trough, the water flow was consumed step by step. Energy, ensuring that only potential energy remains in the next level and no energy superposition.

Benefits of technology

It effectively consumes water flow energy, reduces the kinetic energy of water flow, avoids energy superposition, improves the energy dissipation effect of the shaft, and suppresses cavitation and cavitation in local areas. It is suitable for drainage pipelines and water conservancy projects with large flow and large drops.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118128153B_ABST
    Figure CN118128153B_ABST
Patent Text Reader

Abstract

The present invention discloses a vertical drop shaft, which is mainly composed of a shaft body, a water inlet pipe, a water outlet pipe, a stepped ramp, an energy dissipation pool, an energy dissipation sill, and a drop water arranged in the shaft body. A multi-stage energy dissipation channel is arranged in the shaft, and the water flow is divided into two parts. The energy dissipation of the stepped ramp, the energy dissipation pool, and the energy dissipation sill, the water flow diffusion zone at the bottom of the water jump and the surface tumbling zone, the aeration effect, and the turbulent diffusion effect of the water cushion layer in the energy dissipation pool are used to reduce the flow velocity of the downstream water flow, improve the energy dissipation effect of the shaft, and effectively inhibit cavitation and erosion in the local area of ​​the shaft. The remaining energy of the two water flows is offset, and the flow rates of the two water flows are equal in size and opposite in direction. The offset mutually offsets the kinetic energy of the water flow, so that the energy of the water flow is exhausted, and the energy falling into the next level only has the potential energy relative to the next level, and there is no energy superposition and accumulation. It is suitable for use in drainage pipes, water conservancy projects with large drop heights, and other projects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a vertical drop shaft and to a hydraulic energy dissipation structure of a drainage project and a water conservancy project. Background Art

[0002] With the development of cities, large-scale construction and land hardening have increased surface runoff and the designed flow rate of drainage pipes. However, the existing drainage pipe system downstream cannot bear such a large flow rate, causing waterlogging in some areas. In order to solve the problem of waterlogging, drainage pits are used as facilities for storing rainwater during off-peak hours in some large cities. Rainwater is discharged into the pits during heavy rains, and drainage equipment is used to discharge the stored water after the rainstorms. The depth of the drainage pit is deep and is set under various underground pipelines in the city. The depth of the drainage pit is generally more than 10m, and the drop can even reach 20m or more. When the drainage pipe is connected to the pit, a waterfall device needs to be installed. The so-called vertical shaft is a shaft with a depth greater than the width or diameter of the plane. Some energy dissipation structures are set in the shaft to prevent the water from directly falling and damaging the shaft. In water conservancy projects, flood discharge tunnels and diversion tunnels also have large drops, and energy dissipation facilities are also required.

[0003] Most of the existing waterfall wells use stepped waterfalls, rotating waterfalls, return waterfalls, multi-stage waterfalls, etc., which use the lengthened water flow path to consume the energy of the water flow step by step. However, the water flow energy of the previous level is not completely consumed. The remaining energy is superimposed on the water flow energy of the next level. The water flow still has a large amount of energy when it falls to the lowest level. Although it consumes a lot of water flow energy compared to direct waterfalls, the existing waterfall structure still needs to resist the impact of water flow by strengthening the strength of the structure when used for ultra-deep waterfall structures. Summary of the invention

[0004] .The purpose of the present invention is to provide a vertical drop shaft, which is suitable for large flow and large drop energy dissipation structures in drainage pipes and water conservancy projects. It is mainly composed of a well body, a water inlet pipe, a water outlet pipe and an energy dissipation channel arranged in the well body. The water flow entering the well body is divided into two parts. Through the energy dissipation of the stepped ramp, the energy dissipation pool and the energy dissipation ridge, the remaining energy of the two water flows offsets each other. The flow rates of the two water flows are equal in size and opposite in direction. The offset offsets the kinetic energy of the water flow, so that the energy of the water flow is exhausted, and the energy that falls into the next level only has the potential energy relative to the next level, and there is no energy superposition and accumulation.

[0005] The present invention is realized by the following technologies: a vertical water drop shaft mainly comprises a shaft body 1, a water inlet pipe 2 and a water outlet pipe 3. The shaft body 1 is in a circular shape, and a maintenance passage 4 which is concentric with the shaft body 1 is arranged at the center of the shaft body 1. Based on the direction of water flow in and out of the shaft body 1, one end of the water inlet pipe 2 is the rear end, and one end of the water outlet pipe 3 is the front end. The water inlet pipe 2 is connected from the upper part of the rear end of the shaft body 1, and the water outlet pipe 3 is led out from the lower part of the front end of the shaft body 1. Several levels of energy dissipation channels are arranged between the water inlet pipe 2 and the water outlet pipe 3 in the well body 1. The energy dissipation channels include downslope steps 5 and reverse slope steps 6 based on the flow direction of water in the well body 1. The starting point of the downslope steps 5 of the top energy dissipation channel is the diversion area 7, which is connected to the water inlet pipe 2. The downslope steps 5 and the reverse slope steps 6 are divided into two semicircular rings and are arranged between the inspection channel 4 and the well body 1 to the front end of the well body 1. The junction of the downslope steps 5 and the reverse slope steps 6 is the valley bottom area 8, which serves as an energy dissipation pool, and the junction of the reverse slope steps 6 on both sides is the hedge area 9. The reverse slope steps 6 and valley bottom area 8 are provided with guide plates 10 between the inspection channel 4 and the counter-hedging area 9, which are used to guide the water flow to the counter-hedging area 9. A drop outlet 11 is provided between the outer wall of the inspection channel 4 and the counter-hedging area 9 and the guide plates 10. The bottom surface of the counter-hedging area 9 slopes toward the drop outlet 11. Below the drop outlet 11 is the diversion area 7 of the next energy dissipation channel. The diversion area 7 of the next energy dissipation channel is connected to the down-slope steps 5 on both sides. The down-slope steps 5 and the reverse slope steps 6 are divided into two semicircular rings in the return direction and are arranged between the inspection channel 4 and the well body 1 to the rear end of the well body 1. The junction of the reverse slope steps 6 on both sides is the counter-hedging area 9, and the bottom plate of the counter-hedging area 9 slopes toward the drop outlet 11. This is repeated to the flow channel 12 below the drop outlet 11 of the lowest energy dissipation channel, and the flow channel 12 is connected to the outlet pipe 3.

[0006] The energy dissipation working condition of the described waterfall shaft is as follows: water flows into the well body 1 from the water inlet pipe 2, and is diverted to the downslope steps 5 on both sides in the diversion area 7. The water flow is divided into two and the flow rate is halved. The water flow rate of the downslope steps 5 on both sides is the same. The width of the water-passing section increases as the flow rate decreases, so that the water depth flowing into the downslope steps 5 decreases. The water flows to the front end of the well body 1, and uses the bottom flow to dissipate energy. The water flows along the downslope steps 5 step by step to generate turbulence, so that the water flow cannot flow smoothly, thereby reducing the energy of the water flow; when the water flows to the valley bottom area 8, the valley bottom area 8 is equivalent to an energy dissipation pool. When the water flow transitions from the rapid flow of the downslope steps 5 to the slow flow of the valley bottom area 8, the water surface suddenly rises and a water jump is generated locally. The water jump includes the water flow diffusion area at the bottom and the surface vortex area. The range of the water jump includes the valley bottom area 8 and the reverse slope step 6. The surface vortex area of ​​the water jump is mixed with a large number of bubbles to prevent the movement of water molecules. The water cushion layer in the water flow diffusion area and the surface vortex area Aeration forms turbulent diffusion effect, reducing the flow rate of the downstream water flow; at the junction of the valley bottom area 8 and the reverse slope step 6, the reverse slope step 6 is equivalent to the energy dissipation sill. When the water flows to the valley bottom area 8 and flows toward the reverse slope step 6, it is blocked by the step facade of the reverse slope step 6 and consumes energy again. A part of the water flows in the opposite direction and forms a counter-attack with the water flow of the downslope step 5, consuming a part of the energy. Under the impetus of the water flow of the downslope step 5, it continues to flow to the counter-attack area 9 under the guidance of the guide plate 10. The two water flows of the reverse slope steps 6 on both sides of the counter-attack area 9 have equal flow sizes and opposite directions to form a counter-attack, which offsets each other's energy; the water flows to the drop outlet 11 and falls to the diversion area 7 of the next level of energy dissipation channel, where there is only kinetic energy converted from the potential energy of the drop height difference, and there is no superposition of water flow energy; the water flow repeatedly counter-attacks and falls to the drop outlet 11 of the lowest energy dissipation channel in the same way, and the water flow falls to the flow trough 12 and is discharged from the outlet pipe 3.

[0007] The bottom of the well body 1 is a bottom plate 13 , and the top is a cover plate 14 .

[0008] The inspection channel 4 is provided with a diverter weir 15 at a position opposite to the water inlet pipe 2 to guide the water flowing into the diverter area 7 to flow along the slope steps 5 on both sides.

[0009] The width B of the energy dissipation channel composed of the downslope step 5 and the reverse slope step 6 is 1 to 2 times the diameter D of the water inlet pipe 2, and the length W of the energy dissipation channel is equal to the length L of the downslope step 5 and the length L of the water jump. j The hydraulic jump range includes the valley bottom area 8 and the reverse slope step 6. The length of the valley bottom area 8 is the hydraulic jump length L j The interlayer drop Z from the hedging area 9 to the next level diversion area 7 is (0.4~0.6) times, and the interlayer drop Z from the hedging area 9 to the next level diversion area 7 is 1~2 meters.

[0010] The valley bottom area 8 is provided with a drainage hole 16 for draining the accumulated water in the valley bottom area 8 .

[0011] A passage door 17 is provided at the bottom of the inspection passage 4. An observation port 18 is provided above the position of the inspection passage 4 corresponding to the valley bottom area 8 of the energy dissipation passage.

[0012] The calculation method of the shaft structure size of the water drop shaft is to determine the number of energy dissipation channels, the drop difference of each energy dissipation channel, the width of the energy dissipation channel, and the diameter of the shaft 1 according to the flow rate and the height difference between the water inlet pipe 2 and the water outlet pipe 3:

[0013] Step 1: Determine the energy dissipation channel level m according to the height difference H between the inlet pipe 2 and the outlet pipe 3, where m is an integer, the interlayer drop Z from the flushing area 9 to the next level diversion area 7, Z is 1~2 meters, and the diameter of the outlet pipe 3 is D. Calculate the drop X of each level of energy dissipation channel, H=m(X+Z)+D, and the drop X of each level of energy dissipation channel=[H-(mZ+D)] / m.

[0014] Step 2: Plan the width B of the energy dissipation channel, B is 1~2 times the diameter D of the water inlet pipe 2, determine the inner diameter φ of the maintenance channel 4, φ is 0.7~1 meters, the wall thickness δ of the maintenance channel 4 is 0.2~0.3 meters, and the outer diameter of the maintenance channel 4 is φ+2δ.

[0015] Step 3: Calculate the center length W of the energy dissipation channel. The length of the diversion area 7 is 0.7D, and the length of the impact area 9 is D. Then: W=[(φ+2δ)π-(0.7D+D)] / 2.

[0016] Step 4: The length L of the downslope step 5 is 0.5~0.7 times W, and the height difference Y between the diversion area 7 and the valley bottom area 8 is 1.2~1.5 times the drop difference X of the energy dissipation channel.

[0017] Step 5: Determine the length of the valley bottom area 8 and the length of the reverse slope step 6. The sum of the length of the valley bottom area 8 and the length of the reverse slope step 6 is the hydraulic jump length L j , L j =WL, the length of valley area 8 is (0.4~0.6)L j , the length of the reverse slope step 6 is L j Reduce the length of the valley area by 8.

[0018] Step 6: Calculate the inner diameter N of the well body 1, N=φ+2δ+2B.

[0019] Step 7: Perform hydraulic calculations on the energy dissipation channel and determine the L and Y values ​​according to Xie Caimanning's flow formula:

[0020] Q=(1 / n)R 2 / 3 I 1 / 2 A

[0021] Among them: n is the roughness coefficient, R is the hydraulic radius, I is the water surface slope, and A is the effective water-passing cross-sectional area. The hydraulic radius of the downslope step 5 is R=2h1+B, h1 is the water depth before the water jump of the downslope step 5, B is the width of the downslope step 5, the water surface slope I is calculated according to the slope of the downslope step 5, I=Y / L, Y is the height difference between the diversion area 7 and the valley bottom area 8, the step length L of the downslope step 5 is calculated based on the center line of the arc-shaped energy dissipation channel, the water-passing cross-sectional area A=Bh1, the flow rate of the water inlet pipe 2 is Q, and the flow rate diverted to the downslope step 5 on one side is Q / 2, then the flow formula can be rewritten as: Q=2(1 / n)(2h1+B) 2 / 3 (Y / L) 1 / 2 Bh 1, The least square method is used to solve h1. The bottom roughness coefficient n of the downslope step 5 is set to 0.05~0.1. The single-width flow rate of the energy dissipation channel on each side is q=Q / 2B. Substitute q and h1 into the water jump equation to calculate the water depth h2 after the jump: h2=(h1 / 2)[(1+8q 2 / g(h1) 3 )-1] 1 / 2 , h1 and h2 are a pair of conjugate water depths, g is the gravitational acceleration; according to the empirical formula of water jump length, based on the conjugate water depths h1 and h2, the water jump length L is calculated j :L j =6.9(h2-h1).

[0022] Step 8: Based on the proposed L and calculated L j , compared with the center length W of the energy dissipation channel, if L+L j >1.1W, reduce L and increase Y, and repeat steps 7 to 8; if L+L j <0.9W, increase L and decrease Y, and repeat steps 7 to 8.

[0023] If the comparison result of step eight has a large deviation, re-determine the energy dissipation channel width B and repeat steps two to eight.

[0024] The beneficial effects of the present invention are as follows: a multi-stage energy dissipation channel is set in the shaft, and the water flow is divided into two parts, the flow in the energy dissipation channel is reduced, the water-passing section is widened and the water depth is shallow, the stepped bottom surface has a large friction resistance, the water jump generated by the water flow has a water flow diffusion area at the bottom and a surface tumbling area, the aeration effect and the turbulent diffusion effect of the water cushion layer of the energy dissipation pool, which reduce the flow velocity of the downstream water flow, improve the energy dissipation effect of the shaft, and effectively inhibit cavitation and erosion in the local area of ​​the shaft. It overcomes the defects of the existing waterfall structure that the residual energy of the water flow is continuously superimposed and the height of the waterfall is limited. The energy of the water flow is reduced by the action of the water flow itself, and there is no energy superposition and accumulation. It is suitable for use in drainage pipes, water conservancy projects with large heights, and other projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a top plan view of the present invention;

[0026] Figure 2 The vertical cross-section of the well body ( Figure 1 AA section);

[0027] Figure 3 This is the vertical cross-section of the well body energy dissipation channel ( Figure 1 A'-A' section);

[0028] Figure 4 The plan view of the top energy dissipation channel ( Figure 2 BB profile);

[0029] Figure 5 is the plan view of the energy dissipation channel in the middle layer ( Figure 2 CC profile);

[0030] Figure 6 The plan view of the energy dissipation channel on the bottom floor ( Figure 2 DD profile);

[0031] Figure 7 is the bottom chute plan ( Figure 2 EE profile);

[0032] Figure 8 Schematic diagram of water flow in the energy dissipation channel.

[0033] In the figure: 1-well body, 2-water inlet pipe, 3-water outlet pipe, 4-maintenance passage, 5-downslope steps, 6-reverse slope steps, 7-diversion area, 8-valley bottom area, 9-hedge area, 10-guide plate, 11-water drop, 12-flow chute, 13-bottom plate, 14-cover plate, 15-diversion weir, 16-sluice hole, 17-passage door, 18-observation port, 19-wellbore, 20-well cover. DETAILED DESCRIPTION

[0034] In order for those skilled in the art to better understand the present invention, Figures 1 to 8 To further illustrate the present invention, in the present description, the orientations or positional relationships indicated by “upper”, “lower”, “inside” and “outside” are based on the orientations or positional relationships shown in the accompanying drawings, or are orientations or positional relationships commonly understood by those skilled in the art. They are only simplified descriptions for the convenience of describing the present invention, and do not indicate or imply that the structure referred to must have a specific orientation, be constructed and operated in a specific orientation. The structural proportional relationships shown in the drawings are only for illustration, and do not indicate or imply the necessary proportional relationships of the structures referred to. The contents mentioned in the implementation modes are not limitations of the present invention.

[0035] The vertical water drop shaft of the present invention mainly comprises a shaft body 1, a water inlet pipe 2, and a water outlet pipe 3. The shaft body 1 is annular, and a maintenance passage 4 which is concentric with the shaft body 1 is provided at the center of the shaft body 1. The plan view of the present application is shown in FIG. Figure 1 , Figure 1 This is a top view of the well 1. Based on the direction of water flow in and out of the well 1, the end of the water inlet pipe 2 is the rear end (left side in the figure), and the end of the water outlet pipe 3 is the front end (right side in the figure). The water inlet pipe 2 is connected from the upper part of the rear end of the well 1, and the water outlet pipe 3 is led out from the lower part of the front end of the well 1. Figure 2 , Figure 2 yes Figure 1 AA section view, cut along the center line of the water inlet pipe 2 and the water outlet pipe 3. The diameters of the water inlet pipe 2 and the water outlet pipe 3 are equal. Several levels of energy dissipation channels are set between the water inlet pipe 2 and the water outlet pipe 3 in the well body 1. The energy dissipation channels include downslope steps 5 and reverse slope steps 6, based on the flow direction of the water flow in the well body 1. The starting point of the downslope steps 5 of the uppermost energy dissipation channel is the diversion area 7, which is connected to the water inlet pipe 2. The outer wall of the maintenance channel 4 is provided with a diversion weir 15 at a position facing the water inlet pipe 2, which guides the water flowing into the diversion area 7 to flow along the slope steps 5 on both sides, as shown in FIG. Figure 1 The down-slope step 5 and the reverse-slope step 6 are divided into two semicircular rings and arranged between the inspection channel 4 and the well body 1 to the front end of the well body 1. The connection between the down-slope step 5 and the reverse-slope step 6 is the valley bottom area 8, which serves as an energy dissipation pool. The reverse-slope step 6 is equivalent to a force dissipation sill. The connection between the reverse-slope steps 6 on both sides is the counter-attack area 9. A guide plate 10 is provided between the reverse-slope step 6 and the valley bottom area 8 between the inspection channel 4 and the counter-attack area 9, which serves to guide the water flow to the counter-attack area 9. There is a drop outlet 11 between the outer wall of the inspection channel 4 and the counter-attack area 9 and the guide plate 10. The guide plate 10 also serves to isolate the reverse-slope step 6 and the drop outlet 11. The bottom surface of the counter-attack area 9 slopes toward the drop outlet 11, and below the drop outlet 11 is the diversion area 7 of the next energy dissipation channel. The interlayer drop difference Z from the counter-attack area 9 to the next diversion area 7 is preferably 1 to 2 meters. The vertical section of the energy dissipation channel is shown in Figure 3 , Figure 3 yes Figure 1 The A'-A' section is cut along the center of the energy dissipation channel and then turns to the turning section of the drop outlet 11 and the impact zone 9.

[0036] The diversion area 7 of the next energy dissipation channel is connected to the downslope steps 5 on both sides. The downslope steps 5 and the reverse slope steps 6 are divided into two semicircular rings in the return direction and arranged between the maintenance channel 4 and the well body 1 to the rear end of the well body 1. The connection between the reverse slope steps 6 on both sides is the hedging area 9, and the bottom plate of the hedging area 9 slopes toward the drop outlet 11; this is repeated to the flow channel 12 below the drop outlet 11 of the lowest energy dissipation channel, and the flow channel 12 is connected to the outlet pipe 3. Figure 2 , Figure 3 .

[0037] Figure 2 , Figure 3 The three-level energy dissipation channel is shown for illustration only. The energy dissipation channel of the present invention is not limited to three levels, and should be determined according to the actual height difference H between the water inlet pipe 2 and the water outlet pipe 3 and the energy dissipation needs. The energy dissipation channel level m is preferably an odd number, so that the water inlet pipe 2 is connected from one end of the well body 1 and the water outlet pipe 3 is led out from the other end of the well body 1. If the direction of the water outlet pipe 3 is not the same as that of the water inlet pipe 2, the flow channel 12 can be used at the bottom of the well body 1 to turn to a suitable position for leading out.

[0038] The bottom of the well body 1 is a bottom plate 13, the top is a cover plate 14, the inspection channel 4 is set between the bottom plate 13 and the cover plate 14, the cover plate 14 is provided with holes, the upper part is built with a well shaft 19 to the ground, and a well cover 20 is installed on the ground. A ladder is set in the inspection channel 4 for maintenance personnel to go down to the well. A channel door 17 is set at the bottom of the inspection channel 4, and an observation port 18 is set above the position of the inspection channel 4 corresponding to the valley area 8 of the energy dissipation channel. Figure 2 The width B of the energy dissipation channel formed by the downslope step 5 and the reverse slope step 6 is 1 to 2 times the diameter D of the water inlet pipe 2, and the length W of the energy dissipation channel is equal to the length L of the downslope step 5 and the length L of the water jump. j The hydraulic jump range includes the valley bottom area 8 and the reverse slope step 6. The length of the valley bottom area 8 is the hydraulic jump length L j (0.4~0.6) times. This application is used for rainwater pipes. After rainfall, the valley bottom area 8 will retain water. It is used for diversion tunnels, flood discharge tunnels and other projects of water conservancy projects. When not in operation, the valley bottom area 8 will retain water. The valley bottom area 8 is provided with a drainage hole 16 to drain the water in the valley bottom area 8. Figure 1 , Figure 3 .

[0039] The water flows downward by gravity. Figure 1 to Figure 7 The water flow counteracting and energy dissipation working conditions of the present invention are described layer by layer. Water flows into the well body 1 from the water inlet pipe 2, Figure 2 , Figure 3 , Figure 4 At point a, the water flows to the downslope steps 5 on both sides in the diversion area 7, and the water flow is divided into two and the flow rate is halved. The flow rate of the downslope steps 5 on both sides is the same, and the water flows to the front end of the well body 1. Figure 4 After the water flow is divided, the flow on both sides decreases, and the width of the water-passing section increases, so that the water depth flowing into the downslope step 5 decreases, and the water flows to the front end of the well body 1. Using the bottom flow to dissipate energy, the water flows along the downslope step 5 step by step to generate turbulence, making the water flow unable to flow smoothly, thereby reducing the energy of the water flow; when the water flows to the valley bottom area 8, Figure 2 , Figure 3 , Figure 4At point b, the valley bottom area 8 is equivalent to an energy dissipation pool. When the water flow transitions from the rapid flow of the downslope step 5 to the slow flow of the valley bottom area 8, the water surface suddenly rises and a hydraulic jump is generated locally. The hydraulic jump includes the water flow diffusion area at the bottom and the surface vortex area. The surface vortex area is mixed with a large number of bubbles to prevent the movement of water molecules. The water cushion layer in the water flow diffusion area and the air in the surface vortex area form a turbulent diffusion effect, which reduces the flow rate of the downstream water flow. At the junction of the valley bottom area 8 and the reverse slope step 6, the reverse slope step 6 is equivalent to an energy dissipation pool. When the water flows to the valley bottom area 8 and flows toward the reverse slope step 6, it is blocked by the step facade of the reverse slope step 6 and consumes energy again. A part of the water flows in the opposite direction and forms a counterattack with the water flow on the downslope step 5, which consumes another part of the energy. Figure 3 Under the push of the water flow on the downslope step 5, the water flow continues to flow to the counter-flow area 9 under the guidance of the guide plate 10. The two water flows on the reverse slope steps 6 on both sides of the counter-flow area 9 have equal flow rates and opposite directions, forming a counter-flow, which offsets the energy of the water flow. Figure 3 , Figure 4 The water flows to the drop outlet 11 and falls to the diversion area 7 of the next energy dissipation channel. Figure 3 At point d, there is only the kinetic energy converted from the potential energy of the interlayer drop difference Z, and there is no superposition of water flow energy. At point d, the diversion area 7 diverts the water flow to the downslope steps 5 on both sides, and the water flow is divided into two and the flow rate is halved. The flow rate of the downslope steps 5 on both sides is the same, and the water flows to the rear end of the well body 1. Figure 5 The water flow passes through the bottom flow energy dissipation, energy dissipation pool, energy dissipation sill, and water flow counter-energy dissipation in the same way as above, and reaches point f. Figure 3 , Figure 5 The water flows to the drop outlet 11 and falls to the diversion area 7 of the next level energy dissipation channel. Figure 3 At point g, the diversion area 7 diverts the water flow to the downslope steps 5 on both sides, and the water flow is divided into two and the flow rate is halved. The flow rate of the downslope steps 5 on both sides is the same and flows to the front end of the well body 1. Figure 3 , Figure 6 The water flows to the drop outlet 11 and falls to the drop outlet 11 of the lowest energy dissipation channel. The water flows to the flow channel 12 and is discharged from the outlet pipe 3. Figure 3 , Figure 7 The energy dissipation channel described above is three-level, but it is not limited to three-level in actual application. It should be determined according to the height difference H between the water inlet pipe 2 and the water outlet pipe 3 and the energy dissipation needs. Regardless of the number of energy dissipation channels, the water flow repeatedly rushes and falls in the same way to the drop outlet 11 of the lowest energy dissipation channel, and the water flow falls to the flow channel 12 and is discharged from the water outlet pipe 3.

[0040] When implementing the present invention, the structural dimensions of the well body 1 should be determined according to the diameter and drop of the upstream and downstream pipelines, and the wall thickness of the well body 1 should be calculated according to the depth of the well body 1 and the surrounding soil conditions. If the bearing capacity of the base foundation of the well body 1 cannot meet the requirements of the energy dissipation structure, it should be treated by filling with stone chips. The well body 1 and all the internal structures are cast with reinforced concrete. The slope steps 5, reverse slope steps 6, diversion area 7, valley bottom area 8, and counter-attack area 9 of the energy dissipation channel are fixed on the inner wall of the well body 1 on one side and on the outer wall of the maintenance channel 4 on the other side. The steel bars should be anchored in the wellbore 1 and the maintenance channel 4. In actual engineering, if the energy dissipation structure is deep and the support excavation is difficult, the well body 1 can be designed as a caisson, and the reverse method is used for sinking construction. After the bottom is sealed, the bottom plate 7 is constructed. When the caisson is prefabricated, the anchor steel bars of the slope steps 5, reverse slope steps 6, diversion area 7, valley bottom area 8, and counter-attack area 9 should be reserved. After all structures in the well body 1 such as the cover plate 14 are completed, reinforced concrete is poured. The well shaft 19 on the cover plate 14 is made of brick or concrete, and a well cover 20 is installed on the ground. A ladder is set in the well shaft 19. The staff can enter the inspection channel 4 through the well shaft 19, check the status of the energy dissipation channel from the observation port 18, and go down to the bottom through the channel door 17 to check the status of the flow channel 12 and the outlet pipe 3. Figure 2 , Figure 7 .

[0041] See also Figure 1 Floor plan, Figure 3 Energy dissipation channel vertical section and Figure 8 Schematic diagram of water flow in the energy dissipation channel. The calculation method of the well body structural dimensions of the waterfall shaft of the present invention is as follows:

[0042] Step 1: Determine the energy dissipation channel level m according to the height difference H between the inlet pipe 2 and the outlet pipe 3, where m is an integer, the interlayer drop Z from the flushing area 9 to the next level diversion area 7, Z is 1~2 meters, and the diameter of the outlet pipe 3 is D. Calculate the drop X of each level of energy dissipation channel, H=m(X+Z)+D, and the drop X of each level of energy dissipation channel=[H-(mZ+D)] / m.

[0043] Step 2: Plan the width B of the energy dissipation channel, B is 1~2 times the diameter of the water inlet pipe 2, determine the inner diameter φ of the maintenance channel 4, φ is 0.7~1m, the wall thickness δ of the maintenance channel 4 is 0.2~0.3m, and the outer diameter of the maintenance channel 4 is φ+2δ.

[0044] .Step 3: Calculate the center length W of the energy dissipation channel, take the length of the diversion area 7 as 0.7D, and the length of the counter-flow area 9 as D, then:

[0045] W = [(φ + 2δ)π - (0.7D + D)] / 2;

[0046] Step 4: The length L of the downslope step 5 is 0.5~0.7 times W, and the height difference Y between the diversion area 7 and the valley bottom area 8 is 1.2~1.5 times the drop difference X of the energy dissipation channel.

[0047] Step 5: Determine the length of the valley bottom area 8 and the length of the reverse slope step 6. The sum of the length of the valley bottom area 8 and the length of the reverse slope step 6 is the hydraulic jump length L j , L j =WL, the length of valley area 8 is (0.4~0.6)L j , the length of the reverse slope step 6 is L j Reduce the length of the valley area by 8.

[0048] Step 6: Calculate the inner diameter N of the well body 1, N=φ+2δ+2B.

[0049] Step 7: Perform hydraulic calculations on the energy dissipation channel and determine the L and Y values ​​according to Xie Caimanning's flow formula:

[0050] Q=(1 / n)R 2 / 3 I 1 / 2 A;

[0051] Among them: n is the roughness coefficient, R is the hydraulic radius, I is the water surface slope, and A is the effective water-passing cross-sectional area. The hydraulic radius of the downslope step 5 is R=2h1+B, h1 is the water depth before the water jump of the downslope step 5, B is the width of the downslope step 5, the water surface slope I is calculated according to the slope of the downslope step 5, I=Y / L, Y is the height difference between the diversion area 7 and the valley bottom area 8, the step length L of the downslope step 5 is calculated based on the center line of the arc-shaped energy dissipation channel, the water-passing cross-sectional area A=Bh1, the flow rate of the water inlet pipe 2 is Q, and the flow rate diverted to the downslope step 5 on one side is Q / 2, then the flow formula can be rewritten as: Q=2(1 / n)(2h1+B) 2 / 3 (Y / L) 1 / 2 Bh1;

[0052] The least square method is used to solve h1. The bottom roughness coefficient n of the downslope step 5 is set to 0.05~0.1. The single-width flow rate of the energy dissipation channel on each side is q=Q / 2B. Substitute q and h1 into the water jump equation to calculate the water depth h2 after the jump: h2=(h1 / 2)[(1+8q 2 / g(h1) 3 )-1] 1 / 2 ;

[0053] h1 and h2 are a pair of conjugate water depths, g is the gravitational acceleration; according to the empirical formula of water jump length, the water jump length L is calculated based on the conjugate water depths h1 and h2. j :L j =6.9(h2-h1).

[0054] Step 8: Based on the proposed L and calculated L j , compared with the center length W of the energy dissipation channel, if L+L j>1.1W (water jump enters the hedge zone 9), reduce L and increase Y, and repeat steps 7 to 8; if L+L j <0.9W (water jump) Increase L and decrease Y, and repeat steps 7 to 8.

[0055] If the comparison result of step eight has a large deviation, re-determine the energy dissipation channel width B and repeat steps two to eight.

[0056] In step eight, if L+L j >1.1W, indicating that the water jumps into the counter-flow area 9, and the water flow is not consumed in the downslope step 5, the valley bottom area 8, and the reverse slope step 6; if L+L j <0.9W, which means that the water flow energy is consumed prematurely and the size of the energy dissipation channel is too large.

[0057] After determining the structural dimensions of the energy dissipation channel, the wall thickness of the well body 1, the step height and width of the downslope step 5 and the reverse slope step 6, and the plate thickness of the diversion area 7, the valley bottom area 8, and the hedge area 9 need to be determined through structural calculations.

[0058] In the embodiment, the diameter of the water inlet pipe 2 and the water outlet pipe 3 is 2000mm (2m), and the height difference H between the water inlet pipe 2 and the water outlet pipe 3 is 14m. According to H, the energy dissipation channel level m is determined to be 3 levels, and the interlayer drop Z from the hedging area 9 to the next level of diversion area 7 is 1.5m. The drop of each level of energy dissipation channel is calculated:

[0059] X=[H-(mZ+D)] / m=[14-(3×1.5)+2)] / 3=2.5. The width B of the energy dissipation channel is 1.5D, which is 3m. The inner diameter of the maintenance channel 4 is 1m. The wall thickness δ of the maintenance channel 4 is 0.25m. The outer diameter of the maintenance channel 4 is φ+2δ=1.5m. The center length of the energy dissipation channel is W, the length of the diversion area 7 is 0.7D, and the length of the counter-flow area 9 is D. Then:

[0060] W = [(φ + 2δ)π - (0.7D + D)] / 2 = (4.5π - 3.4) / 2 = 5.365m. The length of the 5th step L along the slope is 0.6W, which is 3.219m. The length of the hydraulic jump is L j =WL=2.146, the length of valley area 8 is 0.5 times L j is 1.073m, and the length of the reverse slope step 6 is the water jump length L j The length of the valley-reducing area 8 is 1.073m. The height difference Y between the diversion area 7 and the valley-reducing area 8 is 1.4 times the drop difference X of the energy dissipation channel, and Y is 3.5m. The inner diameter N of the well body 1 is N=φ+2δ+2B=1+2×0.25+2×3=7.5m. After verification, L+L j<0.8W, re-plan the width of the energy dissipation channel B=1.2D=2.4m, the inter-layer drop Z=1.5m and the drop X=2.5m of each level of the energy dissipation channel remain unchanged, Y is 1.3 times the drop X of the energy dissipation channel, Y=3.25m. Calculate the center length of the energy dissipation channel W=4.423m, the length of the 5th step L along the slope is 0.65W, which is 2.875m, and the water jump length L j =1.548, the length of valley area 8 is 0.5 times L j The length of the reverse slope step 6 is 0.774m. The inner diameter N of the well body 1 is N=1.5+2×2.4=6.3m, and the dimensions of the well body 1 and the energy dissipation channel are reduced.

[0061] The description and drawings of this application are only a specific implementation method and are not restrictive. Under the guidance of this application, technicians in this field can make many forms without departing from the scope of protection of the purpose of this application, all of which are within the scope of protection of this application.

Claims

1. A vertical water drop shaft, mainly comprising a shaft body (1), a water inlet pipe (2), and a water outlet pipe (3), wherein the shaft body (1) is in the shape of a ring, and a maintenance passage (4) which is concentric with the shaft body (1) is provided at the center of the shaft body (1), and based on the direction of water flow in and out of the shaft body (1), one end of the water inlet pipe (2) is the rear end, and one end of the water outlet pipe (3) is the front end, the water inlet pipe (2) is connected from the upper part of the rear end of the shaft body (1), and the water outlet pipe (3) is led out from the lower part of the front end of the shaft body (1), wherein: A plurality of energy dissipation channels are arranged between the water inlet pipe (2) and the water outlet pipe (3) in the well body (1). The energy dissipation channels include a downslope step (5) and a reverse slope step (6) based on the flow direction of water in the well body (1). The starting point of the downslope step (5) of the uppermost energy dissipation channel is a diversion area (7). The diversion area (7) is connected to the water inlet pipe (2). The downslope step (5) and the reverse slope step (6) are divided into two semicircular rings and arranged between the inspection channel (4) and the well body (1) to the front end of the well body (1). The connection between the downslope step (5) and the reverse slope step (6) is as follows: The valley bottom area (8) is located at the valley bottom area (8), and the valley bottom area (8) functions as an energy dissipation pool. The connection between the reverse slope steps (6) on both sides is the counter-attack area (9). A guide plate (10) is provided between the reverse slope steps (6) and the valley bottom area (8) between the inspection channel (4) and the counter-attack area (9), and the guide plate (10) functions to guide water flow to the counter-attack area (9). A water drop (11) is located between the outer wall of the inspection channel (4) and the counter-attack area (9) and the guide plate (10). The bottom surface of the counter-attack area (9) slopes toward the water drop (11), and below the water drop (11) is the diversion area (7) of the next energy dissipation channel. The diversion area (7) of the next energy dissipation channel is connected to the downslope steps (5) on both sides. The downslope steps (5) and the reverse slope steps (6) are divided into two semicircular rings in the return direction and arranged between the inspection channel (4) and the well body (1) to the rear end of the well body (1). The connection between the reverse slope steps (6) on both sides is the hedging area (9), and the bottom plate of the hedging area (9) slopes towards the drop outlet (11); this is repeated to the flow channel (12) below the drop outlet (11) of the lowest energy dissipation channel, and the flow channel (12) is connected to the outlet pipe (3); The energy dissipation working condition of the vertical drop shaft is as follows: water flows into the well body (1) from the water inlet pipe (2), and is diverted to the downslope steps (5) on both sides at the diversion area (7). The water flow is divided into two and the flow rate is halved. The flow rate of water in the downslope steps (5) on both sides is the same. The width of the water flow section increases as the flow rate decreases, so that the depth of water flowing into the downslope steps (5) decreases. The water flows to the front end of the well body (1), and uses the bottom flow to dissipate energy. The water flows along the downslope steps (5) step by step to generate turbulence, so that the water flow cannot flow smoothly, thereby reducing the energy of the water flow; when the water flows to the valley bottom area (8), the valley bottom area (8) is equivalent to an energy dissipation pool. When the water flow transitions from the rapid flow of the downslope steps (5) to the slow flow of the valley bottom area (8), the water surface suddenly rises and a hydraulic jump is generated locally. The hydraulic jump includes the water flow diffusion area at the bottom and the surface vortex area. The range of the hydraulic jump includes the valley bottom area (8) ) and the reverse slope step (6), a large number of bubbles are mixed in the tumbling zone on the surface of the water jump to prevent the movement of water molecules, and the water cushion layer in the water diffusion zone and the air mixed in the surface tumbling zone form a turbulent diffusion effect, thereby reducing the flow rate of the downstream water flow; at the junction of the valley bottom zone (8) and the reverse slope step (6), the reverse slope step (6) is equivalent to a force dissipation sill, and when the water flows to the valley bottom zone (8) and flows toward the reverse slope step (6), it is blocked by the step facade of the reverse slope step (6) and consumes energy again, and a part of the water flows in the reverse direction and forms an offset with the water flow of the downslope step (5), consuming a part of the energy, and under the impetus of the water flow of the downslope step (5), it continues to flow toward the offset zone (9) under the guidance of the guide plate (10), and the two water flows of the reverse slope steps (6) on both sides of the offset zone (9) have equal flow sizes and opposite directions to form an offset, thereby offsetting the energy of the water flow; The water flows to the drop outlet (11) and falls to the diversion area (7) of the next energy dissipation channel. Here, there is only kinetic energy converted from the potential energy of the drop height difference, and there is no superposition of water flow energy. The water flows repeatedly collide and fall in the same way to the drop outlet (11) of the lowest energy dissipation channel, and the water flows to the flow channel (12) and is discharged from the outlet pipe (3). The width B of the energy dissipation channel formed by the downslope step (5) and the reverse slope step (6) is 1 to 2 times the diameter D of the water inlet pipe (2), and the length W of the energy dissipation channel is equal to the length L of the downslope step (5) and the length L of the water jump. j The hydraulic jump range includes the valley bottom area (8) and the reverse slope step (6). The length of the valley bottom area (8) is the hydraulic jump length L j The interlayer drop Z from the hedging area (9) to the next level diversion area (7) is 1~2 meters.

2. The vertical drop shaft according to claim 1, characterized in that: The bottom of the well body (1) is a bottom plate (13), and the top is a cover plate (14).

3. The vertical drop shaft according to claim 1, characterized in that: A diversion weir (15) is provided at a position of the inspection channel (4) directly opposite to the water inlet pipe (2) to guide the water flowing into the diversion area (7) to flow along the slope steps (5) on both sides.

4. The vertical drop shaft according to claim 1, characterized in that: The valley bottom area (8) is provided with a drainage hole (16) for draining the accumulated water in the valley bottom area (8).

5. The vertical drop shaft according to claim 1, characterized in that: A passage door (17) is provided at the bottom of the inspection passage (4).

6. The vertical drop shaft according to claim 1, characterized in that: The inspection passage (4) is provided with an observation port (18) above a position corresponding to the valley bottom area (8) of the energy dissipation passage.

7. A method for calculating the structural dimensions of a vertical drop shaft according to claim 1, characterized in that: The method for determining the number of energy dissipation channels, the drop difference of each energy dissipation channel, the width of the energy dissipation channel, and the diameter of the wellbore is as follows: Step 1: Determine the number m of energy dissipation channels according to the height difference H between the water inlet pipe (2) and the water outlet pipe (3), where m is an integer, the interlayer drop difference Z from the flushing area (9) to the next level of diversion area (7), where Z is 1 to 2 meters, and the diameter D of the water outlet pipe (3). Calculate the drop difference X of each level of energy dissipation channel, where H=m(X+Z)+D, and the drop difference X of each level of energy dissipation channel=[H-(mZ+D)] / m; Step 2: Determine the width B of the energy dissipation channel, where B is 1 to 2 times the diameter D of the water inlet pipe (2), determine the inner diameter φ of the maintenance channel (4), where φ is 0.7 to 1 m, the wall thickness δ of the maintenance channel (4) is 0.2 to 0.3 m, and the outer diameter of the maintenance channel (4) is φ+2δ; Step 3: Calculate the central length W of the energy dissipation channel. The length of the diversion area (7) is 0.7D, and the length of the counter-flow area (9) is D. Then: W = [(φ + 2δ)π - (0.7D + D)] / 2; Step 4: The step length L of the downslope step (5) is set to 0.5 to 0.7 times W, and the height difference Y between the diversion area (7) and the valley bottom area (8) is set to 1.2 to 1.5 times the drop difference X of the energy dissipation channel; Step 5: Determine the length of the valley bottom area (8) and the length of the reverse slope step (6). The sum of the length of the valley bottom area (8) and the length of the reverse slope step (6) is the hydraulic jump length L. j , L j =WL, the length of the valley area (8) is (0.4~0.6)L j , the length of the reverse slope step (6) is L j minus the length of the valley area (8); Step 6: Calculate the inner diameter N of the well body (1), N=φ+2δ+2B; Step 7: Perform hydraulic calculations on the energy dissipation channel and determine the L and Y values ​​according to Xie Caimanning's flow formula: Q=(1 / n)R 2 / 3 I 1 / 2 A; Where: n is the roughness coefficient, R is the hydraulic radius, I is the water surface slope, and A is the effective water-passing cross-sectional area; the hydraulic radius of the downslope step (5) R=2h1+B, h1 is the water depth before the hydraulic jump of the downslope step (5), B is the width of the downslope step (5), the water surface slope I is calculated according to the slope of the downslope step (5), I=Y / L, Y is the height difference between the diversion area (7) and the valley bottom area (8), the step length L of the downslope step (5) is measured based on the center line of the arc-shaped energy dissipation channel, the water-passing cross-sectional area A=Bh1, the flow rate of the water inlet pipe (2) is Q, and the flow rate diverted to the downslope step (5) on one side is Q / 2, then the flow rate formula can be rewritten as: Q=2(1 / n)(2h1+B) 2 / 3 (Y / L) 1 / 2 Bh1; The least square method is used to solve h1. The bottom roughness coefficient n of the downslope step (5) is set to 0.05~0.

1. The single-width flow rate of the energy dissipation channel on each side is q=Q / 2B. Substitute q and h1 into the water jump equation to calculate the water depth h2 after the jump: h2=(h1 / 2)[(1+8q 2 / g(h1) 3 )-1] 1 / 2 ; h1 and h2 are a pair of conjugate water depths, g is the gravitational acceleration; according to the empirical formula of water jump length, the water jump length L is calculated based on the conjugate water depths h1 and h2. j :L j =6.9(h2-h1); Step 8: Based on the proposed L and calculated L j , compared with the center length W of the energy dissipation channel, if L+L j >1.1W, reduce L and increase Y, and repeat steps 7 to 8; if L+L j <0.9W, increase L and decrease Y, and repeat steps 7 to 8; If the comparison result of step eight has a large deviation, re-determine the energy dissipation channel width B and repeat steps two to eight.