Method for analyzing the cross-sectional capacity of free-flow toll roads under the influence of construction zones

By constructing a traffic characteristic data set and calculating the traffic capacity reduction coefficient, the impact of the construction area on the free-flow toll road was analyzed, the problem of reduced traffic efficiency in the construction area was solved, and a better grasp of the traffic operating status and improvement of traffic efficiency were achieved. .

CN118298643BActive Publication Date: 2024-10-22JSTI GRP CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202410716146.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2024-10-22
Estimated Expiration
2044-06-04

AI Technical Summary

Technical Problem

When there is a highway construction zone, the traffic efficiency of the free-flow toll road is significantly reduced. How to analyze the impact of the construction zone on the free-flow toll road and calculate the traffic capacity of each section, so as to take traffic congestion prevention measures in advance and improve traffic efficiency.

Method used

By constructing a traffic characteristic data set, we can obtain the traffic capacity reduction coefficient, determine the impact of the construction area on the free-flow toll road, calculate the traffic capacity of each section, and use these data to better understand the traffic operation status and take preventive measures. Specific steps include: dividing road sections, collecting traffic data, establishing traffic characteristic data sets, calculating capacity reduction coefficients, determining benchmark capacity, and correcting actual capacity.

Benefits of technology

Effectively quantify the impact of the construction area on free-flow toll roads, analyze cross-section traffic capacity, and take traffic preventive measures in advance to improve traffic efficiency and reduce traffic congestion.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118298643B_ABST
    Figure CN118298643B_ABST
Patent Text Reader

Abstract

The embodiment of the present invention discloses a method for analyzing the cross-sectional capacity of a free-flow toll road under the influence of a construction zone, which relates to the field of intelligent transportation technology, and includes constructing a cross-sectional traffic feature data set of a free-flow toll road under the influence of a construction zone; calculating the cross-sectional capacity reduction coefficient of the free-flow toll road; calculating the cross-sectional capacity reduction coefficient of the upstream and downstream roads of the construction zone; determining the lane-changing position of vehicles on the upstream and downstream roads of the construction zone; determining the baseline capacity of the free-flow toll road under the influence of the construction zone; and calculating the cross-sectional capacity of the free-flow toll road under the influence of the construction zone. The present invention can effectively quantify the impact of the construction zone on the capacity of the free-flow toll road, analyze the cross-sectional capacity of the free-flow toll road under the influence of the construction zone, better grasp the traffic operation status of the free-flow toll road, take traffic congestion prevention measures in advance, and improve the traffic efficiency of the free-flow toll road.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of intelligent transportation technology, and in particular to a method for analyzing the cross-sectional capacity of a free-flow toll road under the influence of a construction zone. Background Art

[0002] In recent years, with the increasing traffic volume on highways, vehicles often form queues and cause traffic congestion when passing through toll booths. In response, more and more toll roads have begun to adopt free-flow toll collection technology to allow passing vehicles to pay without stopping, thereby improving road traffic efficiency.

[0003] However, after installing free-flow toll collection equipment on the road, although vehicles can pay the toll without stopping, the speed of vehicles will still be reduced, thereby reducing the efficiency of road traffic. If there is a construction zone within the scope of the free-flow toll road, it will inevitably affect the traffic flow of the road to a greater extent and significantly reduce the efficiency of road traffic.

[0004] Therefore, how to analyze the traffic operation characteristics of free-flow toll roads under the influence of construction areas, and further calculate the traffic capacity of each traffic section, so as to better understand the traffic operation status of free-flow toll roads, so as to take traffic congestion prevention measures in advance and improve the traffic efficiency of free-flow toll roads, has become a topic that needs to be studied. Summary of the invention

[0005] The embodiments of the present invention provide a method for analyzing the cross-sectional capacity of a free-flow toll road under the influence of a construction zone, which can effectively quantify the impact of a construction zone on the cross-sectional capacity of a free-flow toll road, analyze the cross-sectional capacity of a free-flow toll road under the influence of a construction zone, analyze the traffic operation characteristics of a free-flow toll road under the influence of a construction zone, and further calculate the capacity of each cross-sectional capacity, so as to better grasp the traffic operation status of the free-flow toll road and improve the traffic efficiency of the free-flow toll road.

[0006] To achieve the above object, the embodiments of the present invention adopt the following technical solutions:

[0007] A traffic characteristic data set is constructed for a target road, wherein the target road is a free-flow toll road with a construction area; a capacity reduction coefficient of the target road is obtained according to the traffic characteristic data set, and the capacity reduction coefficient corresponding to the construction area is determined; a baseline capacity of the target road under the influence of the construction area is determined; and an actual capacity of the target road under the influence of the construction area is determined using the capacity reduction coefficient corresponding to the construction area and the baseline capacity.

[0008] Specifically, the traffic characteristic data set is constructed for the target road, wherein the target road is a free-flow toll road with a construction area, including: dividing the target road into sections, collecting traffic data of each section; extracting traffic data of the sections of the upstream and downstream roads of the construction area, and establishing a traffic characteristic data set. Thus, the free-flow toll road and the construction area are divided into sections, and then the relevant traffic data of each section are collected, and the traffic characteristic data set of the free-flow toll road section and the traffic characteristic data set of the sections of the upstream and downstream roads of the construction area are respectively constructed.

[0009] The target road is divided into sections and traffic data of each section is collected, including: collecting traffic data of the upstream section of the free-flow toll road in the target road according to the spacing Divide the road sections; then, establish the traffic characteristics dataset of the road sections of the free-flow toll roads ,in, , Free-flow toll roads The period passes Section The instantaneous speed and headway of the vehicle, i, s, n are all positive integers;

[0010] The extraction of traffic data of the upstream and downstream sections of the construction area includes: Divide the road sections; then, establish the traffic characteristic dataset of the road sections in the construction area: ,in, , The construction area roads are The period passes Section The instantaneous speed and headway of the vehicles, , They are respectively the upstream and downstream sections of the construction area. The period passes Section The location of the lane-changing diversion point and the merging point of the vehicle (the distance from the upstream starting point and downstream end section of the construction area).

[0011] Specifically, the method of obtaining the capacity reduction coefficient of the target road and determining the capacity reduction coefficient corresponding to the construction area according to the traffic characteristic data set includes: determining the speed range to which the traffic flow belongs in each time period by the average speed of all vehicles passing through the section in each time period, wherein the instantaneous speed of vehicles in the reference section of the free-flow toll road and the instantaneous speed of vehicles in the reference section of the construction area road are determined by the traffic characteristic data set; calculating the average speed and critical headway of vehicles passing through each section corresponding to each speed range and time period; and calculating the capacity reduction coefficient of the free-flow toll road section and the construction area road section corresponding to each speed range.

[0012] The determination of the instantaneous vehicle speed of the reference section of the free-flow toll road and the instantaneous vehicle speed of the reference section of the construction zone road includes: taking the most upstream section of the free-flow toll road as the reference section; The reference section is used to calculate the average speed of vehicles passing through the reference section in each period. , determine the speed range to which the average speed of each period belongs The calculation corresponds to the average speed and critical headway of vehicles passing through each section in each speed interval and time period, including: calculating the average speed of vehicles passing through each section in all time periods of each speed interval , and sort the headway distances of vehicles passing through the same section in all periods within the same speed range from large to small, among which the first Headroom As the critical headway.

[0013] The determining of the instantaneous vehicle speed of the reference section of the free-flow toll road and the instantaneous vehicle speed of the reference section of the construction zone road includes: calculating the capacity reduction coefficient of the free-flow toll road section corresponding to each speed interval, including: ,in, , is the number of effective lanes in the section, Indicates the capacity of the free-flow toll road section corresponding to each speed range. Indicates the capacity of the base section of the free-flow toll road corresponding to each speed range; calculates the capacity reduction factor of the construction zone road section corresponding to each speed range, including: ,in, , is the number of effective lanes in the section, Indicates the capacity of the road section in the construction area corresponding to each speed range. Indicates the capacity of the reference section of the construction area road corresponding to each speed range.

[0014] Specifically, determining the benchmark capacity of the target road under the influence of the construction area includes: determining the benchmark section of the free-flow toll road under the influence of the construction area. ;

[0015] Determine the speed range of free-flow toll road traffic under the influence of the construction zone, where the time period Internal through reference section The mean speed of all vehicles is , Speed ​​range ; Calculate the capacity of the base section of the free-flow toll road under the influence of the construction zone ,in, , Indicates time period The first section of all vehicles passing through the free-flow toll road under the influence of the construction area Headroom.

[0016] The actual capacity of the target road under the influence of the construction area is determined by using the capacity reduction coefficient corresponding to the construction area and the benchmark capacity, including: calculating the capacity reduction coefficient of the free flow toll road section under the influence of the construction area ; Calculate the correction coefficient of the road construction impact area on the road section capacity , among which, and equal , is the road width, It is the distance between the reference section of the free-flow toll road and the section where the free-flow toll equipment is arranged. , are the width and length of the construction area, , The actual traffic capacity of the target road under the influence of the construction area is .

[0017] In this embodiment, by constructing a traffic feature dataset of the free-flow toll road section under the influence of the construction zone; calculating the capacity reduction coefficient of the free-flow toll road section; calculating the capacity reduction coefficient of the upstream and downstream roads of the construction zone; determining the lane change position of the vehicles on the upstream and downstream roads of the construction zone; determining the baseline capacity of the free-flow toll road under the influence of the construction zone; and calculating the capacity of the free-flow toll road section under the influence of the construction zone, the impact of the construction zone on the capacity of the free-flow toll road is effectively quantified, the capacity of the free-flow toll road section under the influence of the construction zone is analyzed, the traffic operation status of the free-flow toll road is better understood, traffic congestion prevention measures are taken in advance, and the traffic efficiency of the free-flow toll road is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0019] Figure 1 A schematic diagram of a method flow chart provided by an embodiment of the present invention;

[0020] Figure 2 A schematic diagram of vehicle traffic operation characteristics of a free-flow toll road section in step 1) of an embodiment of the present invention;

[0021] Figure 3 The vehicle traffic operation characteristics of the road section in the construction area in step 1) of the embodiment provided in the embodiment of the present invention;

[0022] Figure 4 A schematic diagram of determining a reference section of a free-flow toll road under the influence of a construction zone in step 5) of an embodiment of the present invention;

[0023] Figure 5 A schematic diagram of vehicle traffic operation characteristics on a free-flow toll road under the influence of a construction zone provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0024] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. The embodiments of the present invention will be described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be interpreted as limiting the present invention. It can be understood by those skilled in the art that, unless specifically stated, the singular forms "one", "one", "said" and "the" used herein may also include plural forms. It should be further understood that the term "including" used in the specification of the present invention refers to the presence of the features, integers, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or their groups. It should be understood that when we say that an element is "connected" or "coupled" to another element, it can be directly connected or coupled to other elements, or there may also be intermediate elements. In addition, the "connection" or "coupling" used here may include wireless connection or coupling. The term "and / or" used herein includes any unit and all combinations of one or more associated listed items. It can be understood by those skilled in the art that, unless otherwise defined, all terms (including technical terms and scientific terms) used herein have the same meaning as generally understood by those skilled in the art in the field to which the present invention belongs. It should also be understood that terms such as those defined in general dictionaries should be understood to have meanings consistent with the meanings in the context of the prior art, and will not be interpreted with idealized or overly formal meanings unless defined as herein.

[0025] The embodiment of the present invention provides a method for analyzing the cross-sectional capacity of a free-flow toll road under the influence of a construction zone, such as Figure 1 As shown, including:

[0026] 1) Construct a traffic characteristic dataset of free-flow toll roads under the influence of construction zones;

[0027] Divide the free-flow toll roads and road construction areas into sections, collect relevant traffic data for each section, and construct traffic characteristic datasets for free-flow toll roads and upstream and downstream roads in construction areas;

[0028] For the upstream section of the free-flow toll road, Divide the road sections and construct a traffic characteristic dataset of free-flow toll road sections ,in, , Free-flow toll roads The period passes Section The instantaneous speed and headway of the vehicles, such as Figure 2 As shown;

[0029] The distance between the upstream and downstream sections of the construction area is Divide the road sections and construct the traffic characteristics dataset of the construction area road sections ,in, , The construction area roads are The period passes Section The instantaneous speed and headway of the vehicles, , They are the upstream and downstream sections of the construction area. The period passes Section The location of the lane-changing and merging points of the vehicles (the distance from the upstream starting point and downstream end section of the construction area), such as Figure 3 shown.

[0030] 2) Calculate the reduction coefficient of the cross-section capacity of free-flow toll roads;

[0031] Using the instantaneous speed of vehicles on the benchmark section of the free-flow toll road, calculate the average speed of all vehicles passing through the section in each time period, and determine the speed range to which the traffic belongs in each time period; calculate the average speed and critical headway of vehicles passing through the road section in each speed range and each time period; calculate the capacity of the free-flow toll road section and its reduction factor in each speed range.

[0032] Specifically: 2-1) Determine the speed range of traffic on free-flow toll roads at different time periods.

[0033] The most upstream section of the free-flow toll road is the reference section (the distance between the reference section and the section where the free flow charging equipment is arranged is , generally 5-10 kilometers), calculate the average speed of vehicles passing through the benchmark section in each period , determine the speed range to which the average speed of each period belongs (Speed ​​interval , generally 5-10 km / h).

[0034] 2-2) Calculate the average vehicle speed and critical headway distance of the free-flow toll road section in each speed range.

[0035] Calculate the average speed of each section in all time periods of each speed interval , sort the headway distances of vehicles passing the same section in all periods within the same speed range from large to small, and sort them by the first Headroom (generally 85%-95%) As the critical headway.

[0036] 2-3) Calculate the reduction coefficient of the cross-section capacity of free-flow toll roads in each speed range.

[0037] Calculate the capacity of each speed range and each section ,in, is the number of effective lanes in the section; calculate the reduction coefficient of traffic capacity in each speed range and each section .

[0038] 3) Calculate the reduction coefficient of the road section capacity upstream and downstream of the construction area.

[0039] Using the instantaneous speed of vehicles at the reference section of the construction area road, calculate the average speed of all vehicles passing through the section in each time period, and determine the speed range to which the traffic belongs in each time period; calculate the average speed and critical headway of vehicles passing through each section in each speed range and each time period; calculate the traffic capacity and reduction factor of the construction area road section in each speed range.

[0040] Specifically:

[0041] 3-1) Determine the speed ranges for traffic flow on the construction area roads at different time periods.

[0042] The upstream section of the construction area road is the reference section (the distance between the reference section and the upstream starting section of the construction area is , generally 3-5 kilometers), calculate the average speed of the benchmark section in each period , determine the speed range of traffic flow in each period .

[0043] 3-2) Calculate the average vehicle speed and critical headway distance of the road section in the construction area for each speed range.

[0044] Calculate the average speed of each section in all time periods of each speed interval , sort the headway distances of vehicles passing through the same section in all periods of the same speed range from large to small, and sort them by the first Headroom (generally 85%-95%) As the critical headway.

[0045] 3-3) Calculate the reduction factor of the road section capacity in the construction area for each speed range.

[0046] Calculate the capacity of each speed range and each section ,in, is the number of effective lanes in the section; calculate the reduction coefficient of traffic capacity in each speed range and each section .

[0047] 4) Determine the lane-changing positions for vehicles on the upstream and downstream roads of the construction area.

[0048] Using the lane-changing position data of vehicles on the upstream and downstream roads of the construction area, the diverging and merging lane-changing positions of vehicles on the upstream and downstream sections of the construction area are calculated for each speed range and time period.

[0049] Specifically:

[0050] 4-1) Determine the vehicle diversion and lane-changing locations on the upstream roads of the construction area for each speed range.

[0051] Calculate the average of the vehicle diversion and lane-changing positions on the upstream road of the construction zone in all time periods of each speed interval as the vehicle diversion and lane-changing position on the upstream road of the construction zone in this speed interval. ;.

[0052] 4-2) Determine the merging and lane-changing positions for vehicles on the downstream road of the construction area in each speed range.

[0053] Calculate the average of the merging and lane-changing positions of vehicles on the downstream road of the construction zone in all time periods of each speed interval as the merging and lane-changing position of vehicles on the downstream road of the construction zone in this speed interval. .

[0054] 5) Determine the baseline capacity of free-flow toll roads under the influence of construction areas.

[0055] The section further upstream among the free-flow toll road reference section and the construction area road reference section is used as the free-flow toll road reference section under the influence of the construction area; the average speed of vehicles passing through the reference section within a certain period of time is calculated to determine the speed range to which the traffic belongs; the reference capacity is calculated with the help of the average vehicle speed and critical headway of the reference section.

[0056] Specifically,

[0057] 5-1) Determine the reference section of the free-flow toll road affected by the construction area.

[0058] Compare the benchmark sections of free-flow toll roads and construction zone roads , , with a section further upstream As its road reference section, Figure 4 shown.

[0059] 5-2) Determine the speed range of free-flow toll road traffic under the influence of the construction zone.

[0060] Calculation period The average speed of all vehicles passing through the reference section of the free-flow toll road under the influence of the construction zone , determine the average speed Speed ​​range .

[0061] 5-3) Calculate the base section capacity of the free-flow toll road under the influence of the construction area.

[0062] Calculation period The first section of all vehicles passing through the free-flow toll road under the influence of the construction area Headroom (Sort by largest to smallest) to calculate the capacity of the base section of the free-flow toll road under the influence of the construction zone .

[0063] 6) Calculate the cross-sectional capacity of free-flow toll roads under the influence of construction areas.

[0064] The road section capacity reduction coefficient is calculated using the free-flow toll road section and the construction zone road section capacity reduction coefficient in the speed range of the free-flow toll road under the influence of the construction zone; the road construction influence area is calculated using the upstream and downstream lane change positions of the construction zone in its belonging speed range and the construction zone area, and the correction coefficient of the road construction influence area on the section capacity is calculated; the section capacity of the free-flow toll road under the influence of the construction zone is calculated.

[0065] Specifically,

[0066] 6-1) Calculate the reduction factor of the cross-section capacity of the free-flow toll road under the influence of the construction area.

[0067] The reduction coefficient of the cross-section capacity of the free-flow toll road and the construction zone road corresponding to the speed range of the free-flow toll road under the influence of the construction zone is used , , calculate the reduction coefficient of the cross-section capacity of the free-flow toll road under the influence of the construction area .

[0068] 6-2) Calculate the correction factor of the road section capacity affected by the road construction area.

[0069] The vehicle divergence and merging positions on the upstream and downstream roads of the construction area corresponding to the speed range of the free-flow toll road under the influence of the construction area , , calculate the road construction impact area ,in , are the width and length of the construction area respectively, and further calculate the correction coefficient of the section capacity affected by the road construction area ,in, is the road width, It is the distance between the base section of the free-flow toll road and the section where the free-flow toll equipment is arranged.

[0070] 6-3) Calculate the cross-sectional capacity of free-flow toll roads under the influence of construction areas.

[0071] Taking into account the reduction of road section capacity and the correction of the construction impact area, the cross-section capacity of the free-flow toll road under the influence of the construction area is calculated.

[0072] A possible embodiment in practical application is listed below.

[0073] The method for calculating the cross-sectional capacity of a free-flow toll road under the influence of a construction zone of the present invention is further explained by an example. Figure 5 The figure shows the Zhejiang Hangzhou-Shaoxing-Ningbo Expressway with six lanes in both directions, with a design speed of 120 km / h. The following is a specific step of the method for calculating the cross-section capacity of a free-flow toll road under the influence of a construction zone of the present invention to calculate and determine the cross-section capacity of a target road.

[0074] S1: Construct a traffic characteristic dataset of the free-flow toll road section under the influence of the construction zone; With the help of actual survey data, a traffic characteristic dataset of the free-flow toll road section is constructed. Specifically, the road section is divided into 10m intervals 10km upstream of the free-flow toll device on the Hangzhou-Shaoxing-Ningbo Expressway. The first section closest to the free-flow toll device is numbered 1, and so on. The operation data of all vehicles for 30 consecutive days from November 1, 2023 to November 30, 2023 are collected, which are the free-flow toll road sections, sections 10m and 10km upstream of the free-flow toll device on the Hangzhou-Shaoxing-Ningbo Expressway, and sections 10m and 10km upstream of the free-flow toll device on the Hangzhou-Shaoxing-Ningbo Expressway. The period passes Section The instantaneous speed of the vehicle ( ) and headway ( ), the information is shown in Table 1 (partial data is listed).

[0075] Table 1

[0076]

[0077] With the help of field surveys and vehicle GPS data, a traffic characteristic dataset of road sections in the construction area was constructed. In the 5km sections upstream and downstream of the construction area of ​​the Hangzhou-Shaoxing-Ningbo Expressway, the road sections were divided into 10m intervals, and the first section closest to the construction area was numbered 1, and so on. The operation data of all vehicles for 30 consecutive days from November 1, 2023 to November 30, 2023 were collected, and they were respectively the first, second, and third sections of the construction area roads. The period passes Section The instantaneous speed of the vehicle ( ) and headway ( ), the information is shown in Table 2 (listing some data), and the upstream and downstream sections of the construction area The period passes Section The position of the lane change diversion point of the vehicle ( ) and the confluence point location ( ), the information is shown in Table 3 (partial data is listed).

[0078] Table 2

[0079]

[0080] Table 3

[0081]

[0082] S2: Calculate the reduction coefficient of the cross-section capacity of the free-flow toll road.

[0083] S21: Taking the most upstream section of the free-flow toll road as the reference section, calculate the average speed of vehicles passing through the reference section in each time period, and determine the speed range to which the average speed of each time period belongs, with a speed range interval of 10 km / h, as shown in Table 4.

[0084] Table 4

[0085]

[0086] S22: Calculate the average vehicle speed and critical headway distance of the free-flow toll road section in each speed interval.

[0087] The average instantaneous speed of vehicles passing through the same section in all time periods is taken, and they are classified according to the speed range of S21 to obtain the average speed of vehicles passing through each section in all time periods in each speed range. The headway between vehicles passing through the same section in all time periods in the same speed range is sorted from large to small, and the 85th position is taken as the critical headway. Some results are shown in Table 5.

[0088] Table 5

[0089]

[0090] S23: Calculate the cross-sectional capacity and reduction coefficient of the free-flow toll road in each speed range, as shown in Table 6 below.

[0091] Table 6

[0092]

[0093] S3: Calculate the reduction coefficient of the road section capacity upstream and downstream of the construction area.

[0094] S31: Take the most upstream section of the construction area road as the reference section, calculate the average vehicle speed of the reference section in each time period, and determine the speed range to which the average vehicle speed in each time period belongs, with a speed interval of 10 km / h, as shown in Table 7.

[0095] Table 7

[0096]

[0097] S32: Calculate the average vehicle speed and critical headway of the road section in the construction area in each speed interval.

[0098] The average instantaneous speed of vehicles passing through the same section in all time periods is taken, and they are classified according to the speed range of S31 to obtain the average speed of vehicles passing through each section in all time periods in each speed range. The headway between vehicles passing through the same section in all time periods in the same speed range is sorted from large to small, and the 85th position is taken as the critical headway. Some results are shown in Table 8.

[0099] Table 8

[0100]

[0101] S33: Calculate the road section capacity and reduction coefficient in each speed range of the construction area, as shown in Table 9.

[0102] Table 9

[0103]

[0104] S4: Determine the lane-changing position of vehicles on the upstream and downstream roads of the construction area.

[0105] The average of the vehicle diverging and merging positions on the upstream road and the downstream road in the construction area in all time periods is taken as the vehicle diverging and merging position on the upstream road and the downstream road in the construction area in this speed range, as shown in Table 10.

[0106] Table 10

[0107]

[0108] S5: Determine the baseline capacity of the free-flow toll road affected by the construction zone.

[0109] S51: Figure 5 The free-flow toll road under the influence of the construction area shown in the figure is taken as the research object. Its road reference section is determined in combination with the layout location of the free-flow toll equipment, and its reference section position is determined in combination with the location of the construction area. Through comparison, the reference section of the free-flow toll road is determined as the reference section of the free-flow toll road under the influence of the construction area.

[0110] S52: Determine the speed range to which the traffic on the free-flow toll road belongs under the influence of the construction zone.

[0111] The average speed of all vehicles passing through the benchmark section of the free-flow toll road under the influence of the construction area from 8:00 to 9:00 on December 4, 2023 is calculated to be 74km / h, which is within the speed range of 70km / h-80km / h.

[0112] S53: Calculate the capacity of the base section of the free-flow toll road under the influence of the construction area.

[0113] The headway distances of vehicles passing through the benchmark section of the free-flow toll road under the influence of the construction zone in all time periods are sorted from large to small, and the 85th position is taken as the critical headway distance, which is 187m. The traffic capacity of the benchmark section of the free-flow toll road under the influence of the construction zone is calculated to be 1425 vehicles / h.

[0114] S6: Calculate the capacity of the free-flow toll road section under the influence of the construction zone.

[0115] S61: Calculate the reduction coefficient of the cross-section capacity of the free-flow toll road under the influence of the construction area. The results are shown in Table 11.

[0116] Table 11

[0117]

[0118] S62: Calculate the correction coefficient of the road construction impact area on the road section traffic capacity.

[0119] According to the field survey data, the length of the construction area is 720m, the width is 3.5m, and the vehicle speed range is 70km / h-80km / h. The upstream road vehicle diversion and downstream road vehicle merging and changing lanes are 484.4m and 389.6m respectively. The road construction affected area is 4049.5m. 2 The distance between the reference section of the free-flow toll road and the section where the free-flow toll equipment is arranged is 10 km. The width of a single lane of the expressway is 3.75 m, the total road width is 11.25 m, and the overall area of ​​the free-flow toll road is 112,500 m. 2 , then the correction coefficient of the section capacity affected by the road construction area is 0.0360.

[0120] S63: Calculate the cross-sectional capacity of the free-flow toll road under the influence of the construction area. The results are shown in Table 12.

[0121] Table 12

[0122]

[0123] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment. The above is only a specific implementation method of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or replacements that can be easily thought of by any technician familiar with the technical field within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A method for analyzing the cross-sectional capacity of a free-flow toll road under the influence of a construction zone, characterized in that: include: Constructing a traffic feature dataset for a target road, wherein the target road is a free-flow toll road with a construction zone; According to the traffic characteristic data set, obtaining the capacity reduction coefficient of the target road, and determining the capacity reduction coefficient corresponding to the construction area; Determine the baseline capacity of the target road under the influence of the construction area; determine the lane change position of vehicles on the upstream and downstream roads of the construction area; Determine the actual capacity of the target road under the influence of the construction area by using the capacity reduction coefficient corresponding to the construction area and the benchmark capacity; The construction of a traffic characteristic data set for the target road includes: dividing the target road into sections and collecting traffic data of each section; extracting traffic data of sections of upstream and downstream roads in the construction area and establishing a traffic characteristic data set; According to the traffic characteristic data set, the capacity reduction coefficient of the target road is obtained, and the capacity reduction coefficient corresponding to the construction area is determined, including: determining the speed range to which the traffic flow belongs in each time period through the average speed of all vehicles passing through the section in each time period, wherein the instantaneous speed of vehicles in the reference section of the free-flow toll road and the instantaneous speed of vehicles in the reference section of the construction area road are determined through the traffic characteristic data set; the average speed and critical headway of vehicles passing through each section corresponding to each speed range and time period are calculated; the capacity reduction coefficient of the free-flow toll road section and the construction area road section corresponding to each speed range is calculated; the determination of the instantaneous speed of vehicles in the reference section of the free-flow toll road and the instantaneous speed of vehicles in the reference section of the construction area road includes: taking the most upstream section of the free-flow toll road as the average speed of the vehicles passing through the reference section of the construction area road The reference section is used to calculate the average speed of vehicles passing through the reference section in each period. , determine the speed range to which the average speed of each period belongs The calculation corresponds to the average speed and critical headway of vehicles passing through each section in each speed range and time period, including: calculating the average speed of vehicles passing through each section in all time periods of each speed range , and sort the headway distances of vehicles passing through the same section in all periods within the same speed range from large to small, among which the first Headroom As the critical headway; the instantaneous speed of the vehicle in the reference section of the free-flow toll road and the instantaneous speed of the vehicle in the reference section of the construction zone road include: Calculate the capacity reduction factor of the free-flow toll road section corresponding to each speed range, including: ,in, , is the number of effective lanes in the section, Indicates the capacity of the free-flow toll road section corresponding to each speed range. Indicates the capacity of the reference section of the free-flow toll road corresponding to each speed range; Calculate the capacity reduction factor of the construction area road section corresponding to each speed range, including: ,in, , is the number of effective lanes in the section, Indicates the capacity of the road section in the construction area corresponding to each speed range. Indicates the capacity of the reference section of the construction area road corresponding to each speed range. It represents the average speed of each section in all time periods of each speed interval. Indicates the critical headway; Determining the benchmark capacity of the target road under the influence of the construction area includes: determining the benchmark section of the free-flow toll road under the influence of the construction area ; Determine the speed range of free-flow toll road traffic under the influence of the construction zone, where the time period Internal through reference section The mean speed of all vehicles is , Speed ​​range ; Calculate the capacity of the base section of the free-flow toll road under the influence of the construction zone ,in, , Indicates time period The first section of all vehicles passing through the free-flow toll road under the influence of the construction area Headroom; The actual capacity of the target road under the influence of the construction area is determined by using the capacity reduction coefficient corresponding to the construction area and the benchmark capacity, including: calculating the capacity reduction coefficient of the free flow toll road section under the influence of the construction area ; Calculate the correction coefficient of the road construction impact area on the road section capacity ,in, Indicates the area affected by road construction and equal , is the road width, It is the distance between the reference section of the free-flow toll road and the section where the free-flow toll equipment is arranged. , are the width and length of the construction area, , The diverging lane changing position and merging lane changing position of the vehicles are respectively; wherein the actual traffic capacity of the target road under the influence of the construction area is .

2. The method according to claim 1, characterized in that The target road is divided into sections and traffic data of each section is collected, including: collecting traffic data of the upstream section of the free-flow toll road in the target road according to the spacing Divide the road sections; then, establish the traffic characteristics dataset of the road sections of the free-flow toll roads ,in, , Free-flow toll roads The period passes Section The instantaneous speed and headway of the vehicle, i, s, n are all positive integers; The extraction of traffic data of the upstream and downstream sections of the construction area includes: Divide the road sections; then, establish the traffic characteristic dataset of the road sections in the construction area: ,in, , The construction area roads are The period passes Section The instantaneous speed and headway of the vehicles, , They are respectively the upstream and downstream sections of the construction area. The period passes Section The vehicle's lane change divergence point and merging point position.

3. The method according to claim 1, characterized in that Before determining the actual traffic capacity of the target road under the influence of the construction area by using the traffic capacity reduction coefficient corresponding to the construction area and the benchmark traffic capacity, the method further includes: Calculate the average of the vehicle diversion and lane-changing positions on the upstream road of the construction zone in all time periods of each speed interval as the vehicle diversion and lane-changing position on the upstream road of the construction zone in this speed interval. ; Calculate the average of the merging and lane-changing positions of vehicles on the downstream road of the construction zone in all time periods of each speed interval as the merging and lane-changing position of vehicles on the downstream road of the construction zone in this speed interval. .

Citation Information

Patent Citations

  • Computing method for improving degree of fitting of traffic capacity model of intersection occupying-road construction area

    CN110070720A

  • Method for calculating traffic capacity of adjacent lanes of harbor bus stops at peak hours

    CN110232821A

  • Urban road traffic flow overrun evaluation method

    CN115034570A

  • Method and system for predicting traffic volume of expressway under construction road occupation scene

    CN117116062A

  • Method for displaying service level of highway capacity analysis

    KR1020180046547A