A control and management system for digital power ports for generation, storage and charging conversion

By analyzing the operating cycle sub-sequences of the charging and swapping rectifier modules in the digital power port system, abnormality evaluation indicators are constructed, which solves the problem that traditional detection algorithms are difficult to detect minor abnormalities, and improves detection accuracy and management capabilities.

CN118333584BActive Publication Date: 2024-10-11SHENYANG YULONG NEW ENERGY AUTOMOBILE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410773559.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2024-10-11
Estimated Expiration
2044-06-17

AI Technical Summary

Technical Problem

Traditional anomaly detection algorithms are difficult to accurately detect minor abnormalities in charging and swapping rectifier modules, leading to frequent misjudgments. Especially in new energy vehicle-related facilities, current data fluctuates complexly, making it difficult to distinguish between normal and abnormal states.

Method used

Using an analysis method based on operating cycle subsequences, the current data of the charging and replacing rectifier modules is acquired and analyzed through the digital power port system, and a sequence of suspected operating abnormalities, anomaly confidence and normality index are constructed, and a clustering algorithm and anomaly detection algorithm are combined to evaluate Charging and replacing the operating status of the rectifier module to improve detection accuracy.

Benefits of technology

It effectively reduces misjudgments, improves the detection accuracy of charging and swapping rectifier modules, can more accurately distinguish between normal and abnormal states, and enhances the digital power port system's management capabilities for new energy vehicle charging and swapping facilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118333584B_ABST
    Figure CN118333584B_ABST
Patent Text Reader

Abstract

The present application relates to the field of digital power port control technology, and specifically to a control and management system for a digital power port with power generation, storage, charging and conversion, the system comprising: a digital power port data acquisition module, used to obtain each operating cycle subsequence in the current data of the charging and swapping rectifier module through the digital power port system; a digital power port data analysis module, used to analyze the current data performance of the charging and swapping rectifier module in actual scenarios, and assist the digital power port system in realizing the control and management of power generation, storage and charging conversion; a digital power port control and management module, used to perform an abnormal evaluation on the operating normality index of the charging and swapping rectifier module through the digital power port system, and use the abnormal evaluation results to control and manage the charging and swapping rectifier module. The present application improves the detection accuracy and real-time performance of the digital power port system for the charging and swapping rectifier module, so as to achieve the purpose of monitoring, analyzing and calculating the real-time data of the rapid energy replenishment of the digital power port, and improving the charging and swapping efficiency of the digital power port.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of digital power port control technology, and in particular to a control and management system for a digital power port for power generation, storage, charging and conversion. Background Art

[0002] Controlling and managing digital power ports or power stations for power generation, energy storage, charging and battery replacement will have a positive impact on the development of the energy industry, environmental protection and sustainable development of the social economy. Especially with the development of new energy vehicles, various supporting facilities related to new energy vehicles have gradually begun to be set up in every corner of the city. Among the facilities related to new energy vehicles, the most widely used infrastructure is the photovoltaic breeze power station, energy storage power station, charging station, battery replacement station, etc., which provides a good power environment for various new energy vehicles. In order to better ensure the normal operation of various new energy facilities, data of various parameters of new energy facilities are usually monitored in real time and uploaded to the digital power port control and management system for control and management.

[0003] Normally, an abnormality detection algorithm is used to monitor the operation log data of the charging and swapping rectifier module in the charging and swapping equipment to determine the operating status of the charging and swapping equipment. However, when a major abnormality occurs in the charging and swapping rectifier module, such as a short circuit or open circuit, the current data will change dramatically. This situation is easy to monitor using traditional abnormality detection algorithms; and when a slight abnormality occurs in the charging and swapping rectifier module, the current data may fluctuate, or it may not be able to supply power according to the current during normal power supply. In addition, due to the different models of charging vehicles or charging behaviors of charging users, the current data of the charging and swapping rectifier module will also have a series of fluctuations, which is similar to the data when the charging and swapping rectifier module has a slight abnormality, resulting in misjudgment of the data monitoring of the charging and swapping rectifier module. Summary of the invention

[0004] In order to solve the above technical problems, the purpose of this application is to provide a control and management system for a digital power port for power generation, storage and charging conversion. The technical solutions adopted are as follows:

[0005] The present application proposes a control and management system based on a digital power port for power generation, storage and charging conversion, the system comprising:

[0006] The digital power port data acquisition module is used to obtain each operating cycle subsequence in the current data of each charging and swapping rectifier module through the digital power port system;

[0007] The digital power port data analysis module is used to analyze the current data performance of the charging and swapping rectifier module at different levels in actual scenarios, and assist the digital power port system in realizing the control and management of power generation, storage and charging conversion, specifically:

[0008] S1, according to the correlation between the operation cycle subsequences of each charging and swapping rectifier module and the changes of adjacent data points in the operation cycle subsequences, divide the operation abnormality suspect sequence of each charging and swapping rectifier module;

[0009] S2, constructing the operational abnormality confidence of each charging / swapping rectifier module according to the difference between the operational abnormality suspect sequences of each charging / swapping rectifier module and other charging / swapping rectifier modules that are adjacent in time;

[0010] S3, constructing an operation normality index of each charging and swapping rectifier module according to the current sudden change characteristics between the operation cycle subsequence of each charging and swapping rectifier module and the corresponding sequences of other charging and swapping rectifier modules, and the operational abnormality confidence of each charging and swapping rectifier module;

[0011] The digital power port control and management module is used to perform abnormal evaluation on the normal operation index of the charging and swapping rectifier module through the digital power port system, and use the abnormal evaluation result to control and manage the charging and swapping rectifier module.

[0012] Preferably, the method for acquiring the operation cycle subsequence includes:

[0013] Obtain the log data of each charging and swapping rectifier module through the digital power port system, and read the current data of the charging and swapping rectifier module in the log data; divide the data between the start and end time of each user using the charging and swapping rectifier module in the current data into each operation cycle subsequence;

[0014] The longest sequence length among all the operation cycle subsequences is used as the sequence length benchmark; and the data of all the remaining operation cycle subsequences are filled according to the sequence length benchmark.

[0015] Preferably, the process of dividing the operation abnormality suspect sequence includes:

[0016] For each operating cycle subsequence of the charging and swapping rectifier module, obtain the fitting curve of any operating cycle subsequence, and calculate the slope value of each data point in any operating cycle subsequence on the fitting curve corresponding to the operating cycle subsequence to which it belongs;

[0017] According to the change difference of adjacent data points in any operation cycle subsequence, the correlation between any operation cycle subsequence and the other operation cycle subsequences of the charging and swapping rectifier module in which it is located, and the slope difference, the operation quality coefficient of any operation cycle subsequence is constructed;

[0018] The operation quality coefficients of all operation cycle subsequences in each charging and swapping rectifier module are taken as input, and a clustering algorithm is used to output a number of clusters, which are respectively recorded as operation status clusters;

[0019] The mean of the good operation coefficient of each operation condition cluster is calculated, and all the operation cycle subsequences in the operation condition cluster with the smallest mean of the good operation coefficient are respectively used as the operation abnormality questionable sequences.

[0020] Preferably, the method for constructing the operation excellence coefficient includes:

[0021] The sum of the correlations between any one of the operation cycle subsequences and the remaining operation cycle subsequences of the charging / swapping rectifier module in which it is located is taken as the numerator, the accumulation of the absolute values ​​of the differences between the slope values ​​of all data points in any one of the operation cycle subsequences and the slope values ​​of the corresponding data points of all other operation cycle subsequences of the charging / swapping rectifier module in which it is located is taken as the denominator, and the ratio of the numerator to the denominator is calculated as the first fusion term;

[0022] Taking the average of the absolute values ​​of the differences between all adjacent data points in any operation cycle subsequence as the second fusion item;

[0023] According to the first fusion item and the second fusion item of any operation cycle subsequence, the operation excellence coefficient of any operation cycle subsequence is determined; wherein the operation excellence coefficient of any operation cycle subsequence is positively correlated with the first fusion item and the second fusion item of any operation cycle subsequence, respectively.

[0024] Preferably, the method for constructing the operational abnormality confidence comprises:

[0025] For any suspicious operation abnormality sequence of each charging / swapping rectifier module, the suspicious operation abnormality sequences of all other charging / swapping rectifier modules that have an intersection with the data points in any suspicious operation abnormality sequence are respectively used as abnormal comparison sequences of any suspicious operation abnormality sequence;

[0026] Constructing an operation abnormality determination coefficient of any sequence with suspected operation abnormality according to the distance difference and operation good coefficient difference between any sequence with suspected operation abnormality and its abnormal comparison sequence;

[0027] The average of the operation abnormality determination coefficients of all operation abnormality doubtful sequences in each charging and swapping rectifier module is used as the operation abnormality certainty of each charging and swapping rectifier module.

[0028] Preferably, the method for constructing the operation abnormality determination coefficient includes:

[0029] The sum of the distances between any of the suspected operation abnormality sequences and all of its abnormal comparison sequences is used as the third fusion term, and the sum of the absolute values ​​of the differences between the operation good coefficient of any of the suspected operation abnormality sequences and the operation good coefficients of all of its abnormal comparison sequences is used as the fourth fusion term;

[0030] The third fusion item and the fourth fusion item of any of the operation abnormality doubtful sequences are added, and the result of the addition is used as the operation abnormality determination coefficient of any of the operation abnormality doubtful sequences.

[0031] Preferably, the process of constructing the operation normality index includes:

[0032] According to the distribution of the number of mutation points in each operating cycle subsequence of each charging and swapping rectifier module, the abnormal suspected subsequence of each charging and swapping rectifier module is screened, and the mutation time value of each mutation point is determined;

[0033] For the position of the operation cycle subsequence corresponding to any suspicious abnormal subsequence in each charging / swapping / rectifying module in the charging / swapping / rectifying module, the operation cycle subsequences of other charging / swapping / rectifying modules at the position are taken as the corresponding sequence of any suspicious abnormal subsequence;

[0034] According to the degree of synchronization between any suspected abnormal subsequence and all its corresponding sequences in each charging and swapping rectifier module, as well as the difference in the value, position, and quantity distribution of the mutation points, the operating state approximate index and the operating current mutation difference index of any suspected abnormal subsequence in each charging and swapping rectifier module are constructed;

[0035] The ratio of the operating state approximation index of any abnormal suspected subsequence in each charging and swapping rectifier module to the operating current mutation difference index is used as the operating stability coefficient;

[0036] The operation normality index of each charging and swapping rectifier module is determined based on the operation stability coefficient and operation abnormality certainty of all abnormal suspicious subsequences in each charging and swapping rectifier module; wherein, the operation normality index of each charging and swapping rectifier module is positively correlated with the cumulative sum of the operation stability coefficients of all abnormal suspicious subsequences in each charging and swapping rectifier module, and is negatively correlated with the operation abnormality certainty of each charging and swapping rectifier module.

[0037] Preferably, the screening process of the abnormal suspicious subsequence and the method for determining the mutation time value include:

[0038] Each operating cycle subsequence of each charging and swapping rectifier module is used as the input of the mutation point detection algorithm, and the mutation point of each operating cycle subsequence is output;

[0039] The total number of mutation points in each operating cycle subsequence is counted, and the total number of mutation points in all operating cycle subsequences is used as the input of the clustering algorithm, and several clusters are output, which are respectively recorded as mutation point number clusters;

[0040] Calculate the average value of the total number of mutation points of each mutation point number cluster, and record all the operation cycle subsequences corresponding to the mutation point number cluster with the largest average value of the total number of mutation points as abnormal and suspicious subsequences;

[0041] The sampling time position of each mutation point in the abnormal suspicious subsequence is used as the mutation time value corresponding to each mutation point.

[0042] Preferably, the process of constructing the operating state approximation index and the operating current mutation difference index includes:

[0043] The absolute value of the difference between the total number of mutation points of any suspected abnormal subsequence and its corresponding sequence is used as the first denominator; the PLV value between any suspected abnormal subsequence and its corresponding sequence is used as the first numerator; the ratio of the first numerator to the first denominator is calculated as the fifth fusion term of any suspected abnormal subsequence;

[0044] The average of the fifth fusion terms between any suspected abnormal subsequence and the corresponding sequences of all other charging / swapping rectifier modules is used as the running state approximation index of any suspected abnormal subsequence;

[0045] The absolute value of the difference between the mean of the mutation point data in any suspected abnormal subsequence and its corresponding sequence is taken as the mutation point value difference; the sum of the distances between the mutation time values ​​of all corresponding mutation points in any suspected abnormal subsequence and its corresponding sequence is taken as the mutation time value difference; the sum of the mutation point value difference and the mutation time value difference of any suspected abnormal subsequence is calculated;

[0046] The average value of the sum results between any suspected abnormal subsequence and all its corresponding sequences is used as the running current mutation difference index of any suspected abnormal subsequence.

[0047] Preferably, the abnormality assessment process includes:

[0048] The normal operation indexes of all charging and swapping rectifier modules are input into the digital power port system. The digital power port system uses an abnormality detection algorithm to perform abnormality detection on the normal operation indexes of all charging and swapping rectifier modules, obtains the abnormality score of the normal operation index of each charging and swapping rectifier module, and normalizes the abnormality score;

[0049] An abnormal threshold is set; when the normalized value of the abnormal score of the normal operation index of the charging and swapping rectifier module is greater than or equal to the abnormal threshold, it is determined that the charging and swapping rectifier module has an abnormal situation; otherwise, it is determined that the charging and swapping rectifier module is operating normally.

[0050] In the above scheme, this application aims to explore the prominence between each operating cycle subsequence and other relatively normal operating cycle subsequences in the charging and swapping rectifier module based on the periodic regular characteristics of the user charging data in the charging and swapping rectifier module as a whole, and construct an operating excellence coefficient of the operating cycle subsequence to evaluate the abnormal conditions of the operating cycle subsequence relative to other operating cycle subsequences, which can effectively analyze the current data fluctuation differences that appear for different charging and swapping equipment models. At the same time, the impact of the slight abnormal state of the charging and swapping rectifier module on the periodic changes of the current data is considered to reduce the impact of normal current data on abnormal judgment. This application aims to analyze the abnormal conditions of users using charging and swapping equipment to charge at the same time, and conduct an abnormal analysis of the charging state by combining the similar characteristics of the actual charging behavior of users at the same time in actual scenarios, that is, considering the abnormal conditions of different charging and swapping equipment from the same time dimension, it can explore the characteristics of the current data abnormalities caused by the abnormal conditions of the charging and swapping equipment itself, and add a multi-level analysis for evaluating the abnormal conditions of the current data. The present application aims to analyze the current sudden change characteristics between the operating cycle subsequence of each charging and swapping rectifier module and the corresponding sequences of other charging and swapping rectifier modules, and use the differences in cycle characteristics that do not conform to the normal state to analyze the user's charging status in actual scenarios. It can more accurately distinguish between current data changes caused by user behavior and current data changes caused by abnormalities in the charging and swapping rectifier module, and more accurately distinguish between charging and swapping equipment that is operating normally and charging and swapping equipment that is operating abnormally, avoiding misjudgment of the actual state of the charging and swapping equipment caused by a single analysis level, and solving the problem that it is difficult to distinguish charging and swapping rectifier modules with minor abnormal problems when monitoring the operating current data of charging and swapping equipment using traditional abnormality detection algorithms, thereby improving the detection accuracy of the digital power port system for charging and swapping rectifier modules. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present application or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0052] Figure 1 A flow chart of a control and management system for a digital power port for power generation, storage and charging conversion provided by an embodiment of the present application;

[0053] Figure 2 A schematic diagram of a specific process of data analysis in a digital power port data analysis module provided in one embodiment of the present application;

[0054] Figure 3A flowchart for constructing indicators for determining whether there is an abnormal situation in a charging and swapping rectifier module provided in one embodiment of the present application. DETAILED DESCRIPTION

[0055] In order to further explain the technical means and effects adopted by this application to achieve the predetermined invention purpose, the following, in combination with the accompanying drawings and preferred embodiments, describes in detail the specific implementation method, structure, features and effects of a control and management system for a digital power port for power generation, storage and charging conversion proposed in accordance with this application. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. In addition, specific features, structures or characteristics in one or more embodiments may be combined in any suitable form.

[0056] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.

[0057] The following is a detailed description of a specific solution for a control and management system for a digital power port for power generation, storage and charging conversion provided by the present application in conjunction with the accompanying drawings.

[0058] See also Figure 1 , which shows a flow chart of a control and management system for a digital power port for power generation, storage and charging conversion provided by an embodiment of the present application, the system includes: a digital power port data acquisition module, a digital power port data analysis module and a digital power port control and management module. The specific contents of each module are:

[0059] The digital power port data acquisition module is used to obtain each operating cycle subsequence in the current data of each charging and swapping rectifier module through the digital power port system.

[0060] Charging and swapping equipment is a device used to charge and replenish electric vehicles such as electric vehicles and hybrid vehicles, while the charging and swapping rectifier module is a subsystem within the charging and swapping equipment, which is mainly used to convert AC power into DC power so as to supply power to charge the battery of the electric vehicle. The charging and swapping rectifier module usually includes components such as a rectifier and a control circuit. When the power battery is connected to the charging and swapping equipment rectifier module, the charging and swapping rectifier module will convert the power from the mains or other AC power source into DC power through the rectifier to charge the electric vehicle battery. The control circuit will monitor the battery charging status and adjust parameters such as output current and voltage as needed.

[0061] Therefore, the charging and swapping rectifier module plays a key role in the charging and swapping equipment and is one of the important components to achieve the rapid energy replenishment function of the power battery of new energy vehicles. The design and performance of the charging and swapping rectifier module directly affect the efficiency, safety and speed of the power battery replenishment.

[0062] In one embodiment of the present application, the digital power port system is used to obtain the log data of the rectifier module in each charging and swapping device within the past three days, and then read the current data of the rectifier module at each moment in the log data. The number of days for obtaining historical log data can be set by the implementer according to actual conditions.

[0063] Preferably, in order to avoid data loss during data transmission, an embodiment of the present application uses a linear interpolation algorithm to fill the data, and then uses a wavelet denoising algorithm to denoise the data. Among them, the linear interpolation and wavelet denoising algorithms are both well-known technologies, and the present application will not repeat the process.

[0064] Normally, the current of the charging and swapping rectifier module is mainly divided into three change processes, namely the pre-charging period, the constant current period and the constant voltage period, until the final charge is fully charged and the current returns to the initial state until the next power battery is charged. Therefore, the change state of the current has a certain periodicity.

[0065] Since charging and swapping equipment is not used by users all the time, in order to prevent the impact of data when the charging and swapping equipment is idle on abnormal analysis, the Digital Power Port Big Data Platform obtains user usage data from the log data of the charging and swapping rectifier module of each charging and swapping equipment, specifically the start and end time of each time the user uses the charging and swapping equipment. The data between the start and end time of the user's use is divided into various operating cycle sub-sequences. In this way, the idle current data in the current data of the charging and swapping rectifier module can be eliminated in combination with the user's usage data.

[0066] At the same time, the sequence length of each operation cycle subsequence is calculated, and the operation cycle subsequence with the longest sequence length is used as the sequence length benchmark. The remaining operation cycle subsequences are filled with data using the mean filling method to ensure that the sequence length of each operation cycle subsequence is the same. Among them, the mean filling method is a well-known technology, and this application will not repeat its process.

[0067] At this point, the above method can be used to obtain each operating cycle subsequence in the current data of each charging and swapping rectifier module in the digital power port system.

[0068] The digital power port data analysis module is used to analyze the current data performance of the charging and swapping rectifier module at different levels in actual scenarios, and assist the digital power port system in realizing the control and management of power generation, storage and charging conversion, specifically:

[0069] (1) Based on the correlation between the operating cycle subsequences of each charging and swapping rectifier module and the changes in adjacent data points in the operating cycle subsequences, the operating abnormality suspected sequence of each charging and swapping rectifier module is divided.

[0070] For each operating cycle subsequence in each charging and swapping rectifier module, each operating cycle subsequence is used as input, and a linear regression curve fitting algorithm is used to output a fitting curve for each operating cycle subsequence. The slope value of each data point in the operating cycle subsequence on the fitting curve corresponding to the operating cycle subsequence to which it belongs is calculated. Among them, the linear regression curve fitting algorithm and the slope calculation method are both well-known technologies, and this application will not repeat the process.

[0071] Since the user charging data in the charging and swapping rectifier module generally presents periodic regular characteristics, if there is abnormal current data, such abnormal data will be more prominent than the data under normal circumstances. Based on the difference between each operating cycle subsequence and other operating cycle subsequences of the charging and swapping rectifier module, it is possible to explore whether each operating cycle subsequence is abnormal relative to the whole.

[0072] Based on this, this embodiment analyzes the i-th operation cycle subsequence in each charging and swapping rectifier module, constructs the operation excellence coefficient of the i-th operation cycle subsequence, and is used to evaluate the abnormality of the i-th operation cycle subsequence relative to other operation cycle subsequences, specifically:

[0073] First, the sum of the correlations between the i-th operating cycle subsequence and the rest of the operating cycle subsequences of the charging and swapping rectifier module in which it is located is taken as the numerator, the cumulative result of the absolute value of the difference between the slope values ​​of all data points in the i-th operating cycle subsequence and the slope values ​​of the corresponding data points of all other operating cycle subsequences of the charging and swapping rectifier module in which it is located is taken as the denominator, and the ratio of the numerator to the denominator is calculated as the first fusion term; the mean of the absolute values ​​of the differences between all adjacent data points in the i-th operating cycle subsequence is taken as the second fusion term;

[0074] Among them, the operation quality coefficient of the i-th operation cycle subsequence is positively correlated with the first fusion item and the second fusion item of the i-th operation cycle subsequence respectively.

[0075] In one embodiment of the present application, an exponential function with a natural constant as the base and the second fusion term of the i-th operation cycle subsequence as the exponent is calculated, and the sum of the first fusion term of the i-th operation cycle subsequence and the calculation result of the exponential function is taken as the operation excellence coefficient of the i-th operation cycle subsequence.

[0076] In other embodiments of the present application, other suitable positive correlations between the first fusion item and the second fusion item of the i-th operation cycle subsequence may be calculated to obtain the operation quality coefficient of the i-th operation cycle subsequence.

[0077] It can be understood that a positive correlation means that the dependent variable will increase as the independent variable increases, and the dependent variable will decrease as the independent variable decreases. The specific relationship can be a multiplication relationship, an addition relationship, or the idempotence of an exponential function, which is determined by actual application and is not specifically limited in this application.

[0078] It should be noted that, in order to prevent the denominator from being zero when calculating the first fusion term, this embodiment uses the sum of a very small positive number greater than zero and the denominator as a new denominator.

[0079] It should be understood that the greater the cosine similarity between the i-th operating cycle subsequence and the remaining operating cycle subsequences of the charging and swapping rectifier module in which it is located, the smaller the difference between the slope values ​​of all data points in the operating cycle subsequence, and the smaller the change in adjacent data in the i-th operating cycle subsequence, it means that the degree of similarity between the operating cycle subsequence and the remaining operating cycle subsequences in the charging and swapping rectifier module is higher, the higher the regularity is, and the less likely it is that anomalies exist.

[0080] Preferably, in one embodiment of the present application, cosine similarity is used for calculation when calculating correlation, and in other embodiments of the present application, other correlation calculation methods such as Pearson correlation coefficient may also be used for calculation. Among them, the calculation of cosine similarity is a well-known technology and will not be repeated here.

[0081] The operation quality coefficients of all operation cycle subsequences in each charging and swapping rectifier module are used as input, and a clustering algorithm is used to output several clusters, which are recorded as operation status clusters. The mean of the operation quality coefficient of each operation status cluster is calculated, and all the operation cycle subsequences in the operation status cluster with the smallest mean of the operation quality coefficient are respectively used as the operation abnormality suspected sequence.

[0082] Preferably, one embodiment of the present application adopts a DPC clustering algorithm, which is a well-known technology and the present application will not repeat its process. In other embodiments of the present application, other clustering algorithms such as density clustering and k-nearest neighbor clustering can also be used for clustering.

[0083] At this point, the above method can be used to divide the suspicious operation abnormality sequence of each charging and swapping rectifier module.

[0084] This application aims to explore the prominence between each operating cycle subsequence and other relatively normal operating cycle subsequences in the charging and swapping rectifier module based on the periodic regular characteristics of user charging data in the charging and swapping equipment, and construct an operating excellence coefficient for the operating cycle subsequence to evaluate the abnormality of the operating cycle subsequence relative to other operating cycle subsequences. It can effectively analyze the current data fluctuation differences that appear for different charging and swapping equipment models. At the same time, the impact of the slight abnormal state of the charging and swapping rectifier module on the periodic change of the current data is considered to reduce the impact of normal current data on abnormal judgment.

[0085] (2) According to the difference between each charging / swapping rectifier module and the suspected operation abnormality sequences of other charging / swapping rectifier modules that are adjacent in time, the operation abnormality certainty of each charging / swapping rectifier module is constructed.

[0086] For abnormal situations in which users use charging and swapping equipment to charge at the same time, if the charging and swapping equipment itself is abnormal, it is easy to cause the normal situation to be misidentified as an abnormal situation when only the charging and swapping rectifier module is analyzed; at the same time, combined with the characteristics that the actual charging behaviors of users in the adjacent time range of each sequence of suspected abnormal operation are similar, this embodiment takes the rth charging and swapping rectifier module as an example for analysis:

[0087] Preferably, in this embodiment, the operation abnormality questionable sequences of all other charging and swapping rectifier modules whose data points intersect with the data points in the yth operation abnormality questionable sequence in the rth charging and swapping rectifier module are used as abnormal comparison sequences of the yth operation abnormality questionable sequence in the rth charging and swapping rectifier module.

[0088] According to the distance difference and the difference in excellent operation coefficient between the yth operation abnormality suspect sequence and its abnormal comparison sequence in the rth charging and swapping rectifier module, the operation abnormality determination coefficient of the yth operation abnormality suspect sequence in the rth charging and swapping rectifier module is constructed. Taking the operation abnormality determination coefficient of the yth operation abnormality suspect sequence in the rth charging and swapping rectifier module as an example, the specific construction method is as follows:

[0089] First, the sum of the distances between the yth operation abnormality suspect sequence in the rth charging and swapping rectifier module and all its abnormal comparison sequences is taken as the third fusion term, and the sum of the absolute values ​​of the differences between the operation good coefficient of the yth operation abnormality suspect sequence in the rth charging and swapping rectifier module and the operation good coefficient of all its abnormal comparison sequences is taken as the fourth fusion term;

[0090] Then, the third fusion term and the fourth fusion term of the yth operation abnormality doubtful sequence in the rth charging and swapping rectifier module are added, and the result of the addition is used as the operation abnormality determination coefficient of the yth operation abnormality doubtful sequence in the rth charging and swapping rectifier module.

[0091] It should be noted that the calculation method of the operation excellence coefficient of the abnormal comparison sequence is the same as the calculation method of the operation excellence coefficient of the operation period subsequence.

[0092] Preferably, in one embodiment of the present application, DTW distance is used to calculate the distance between sequences, and in other embodiments of the present application, other methods such as Euclidean distance can also be used to calculate the distance. Among them, DTW distance is a well-known technology, and the present application will not repeat its calculation process.

[0093] It should be understood that the more dissimilar the yth abnormality suspect sequence in the rth charging and swapping rectifier module is from all its abnormal comparison sequences, and the greater the difference between their operating excellence coefficients, the more special the abnormal situation of the operating abnormality suspect sequence is, and the more likely it is that the current data abnormality is caused by the abnormal situation of the rth charging and swapping rectifier module itself.

[0094] Furthermore, the average of the operation abnormality determination coefficients of all operation abnormality questionable sequences in the r-th charging and swapping rectifier module is taken as the operation abnormality certainty of the r-th charging and swapping rectifier module.

[0095] It should be understood that, the greater the certainty of the operating abnormality of the rth charging and swapping rectifier module, the greater the possibility that the charging and swapping rectifier module has an abnormality.

[0096] At this point, the operational abnormality certainty of each charging and swapping rectifier module can be obtained through the above method.

[0097] This application aims to analyze the abnormal situations when users use charging and swapping equipment to charge at the same time. By combining the similar characteristics of users' actual charging behaviors at the same time in actual scenarios, the charging status is analyzed abnormally, that is, the abnormal situations of different charging and swapping rectifier modules are considered from the same time dimension. The characteristics of current data abnormalities caused by the abnormal situations of the charging and swapping equipment itself can be explored, and a multi-level analysis for evaluating abnormal situations in current data can be added.

[0098] (3) Based on the current sudden change characteristics between the operating cycle subsequence of each charging and swapping rectifier module and the corresponding sequences of other charging and swapping rectifier modules, as well as the operational abnormality certainty of each charging and swapping rectifier module, the operational normality index of each charging and swapping rectifier module is constructed.

[0099] However, in actual applications of charging and swapping equipment, some users may need to charge for a shorter period of time, or when they need to leave in a hurry, they will turn off the power and leave after using the charging and swapping equipment for a period of time. Therefore, the change in current will not necessarily follow the cyclic changes of the pre-charging period, constant current period and constant voltage period. When only relying on the above method to judge the abnormal operation of the charging and swapping equipment, the actual state of the charging and swapping equipment may be misjudged. Therefore, further analysis is needed for this situation.

[0100] In addition, when a user stops using a charging and swapping device, the current of the charging and swapping rectifier module will drop rapidly in a short period of time. Before the next user starts using it, the current will remain in a standby state, and the time of each stoppage will be uncertain according to the user's wishes. When there is an abnormality in the charging and swapping rectifier module and the current changes significantly, the change is gradual and does not only affect a certain moment.

[0101] Compared with the current data of the charging and swapping rectifier module that has completed charging normally, the above two situations have more changes, and the most obvious feature is that the number of mutation points in the current data has increased significantly. Based on this, this embodiment takes the rth charging and swapping rectifier module as an example for analysis:

[0102] According to the distribution of the number of mutation points in each operating cycle subsequence of each charging and swapping rectifier module, the abnormal suspicious subsequence of each charging and swapping rectifier module is screened, and the mutation time value of each mutation point is determined; specifically:

[0103] First, each operation cycle subsequence of the rth charging and swapping rectifier module is used as the input of the mutation point detection algorithm, and the mutation point of each operation cycle subsequence is output; the total number of mutation points of each operation cycle subsequence is counted, and the total number of mutation points of all operation cycle subsequences is used as the input of the clustering algorithm, and several clustering clusters are output, which are respectively recorded as mutation point number clustering clusters; the average value of the total number of mutation points of each mutation point number clustering cluster is calculated, and all operation cycle subsequences corresponding to the mutation point number clustering cluster with the largest average value of the total number of mutation points are recorded as abnormal suspicious subsequences;

[0104] Then, the sampling time position of each mutation point in the abnormal suspicious subsequence is used as the mutation time value corresponding to each mutation point.

[0105] Preferably, in one embodiment of the present application, the Pettitt mutation point detection algorithm and the DPC clustering algorithm are used. The Pettitt mutation point detection algorithm and the DPC clustering algorithm are both well-known technologies, and the present application will not repeat the process. In other embodiments of the present application, other mutation point detection algorithms and clustering algorithms may also be used, which are not limited here.

[0106] Furthermore, for the position of the operating cycle subsequence corresponding to the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module in the charging and swapping rectifier module where it is located, the operating cycle subsequences of other charging and swapping rectifier modules at the said position are used as the corresponding sequences of the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module.

[0107] In order to facilitate subsequent analysis, the calculation methods of the mutation points, mutation time values, etc. of the corresponding sequences involved in the subsequent calculation process are the same as the calculation methods of the mutation points, mutation time values, etc. in the abnormal suspicious subsequence.

[0108] According to the degree of synchronization between any suspicious abnormal subsequence and all its corresponding sequences in each charging and swapping rectifier module, as well as the difference in the value, position, and quantity distribution of the mutation points, the operating state approximation index and the operating current mutation difference index of any suspicious abnormal subsequence in each charging and swapping rectifier module are constructed; specifically:

[0109] Among them, taking the operating state approximate index of the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module as an example, the specific construction process is:

[0110] Then, the absolute value of the difference between the total number of mutation points of the u-th abnormal suspicious subsequence and its corresponding sequence in the r-th charging and swapping rectifier module is used as the first denominator; the PLV value between the u-th abnormal suspicious subsequence and its corresponding sequence in the r-th charging and swapping rectifier module is used as the first numerator; the ratio of the first numerator to the first denominator is calculated as the fifth fusion item of the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module;

[0111] Next, the average of the fifth fusion term between the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module and the corresponding sequences of all other charging and swapping rectifier modules is taken as the approximate operating status index of the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module.

[0112] It should be noted that, in order to prevent the first denominator from being zero in the process of calculating the fifth fusion term, this embodiment uses the sum of a very small positive number greater than zero and the first denominator as the new first denominator.

[0113] The calculation of the PLV value is a well-known technique, and the present application will not describe the process in detail.

[0114] It should be understood that, when the difference in the total number of mutation points between the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module and its corresponding sequence is smaller, and the PLV value between the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module and the corresponding sequences of the remaining charging and swapping rectifier modules is larger, it means that the operating condition of the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module is closer to the normal operating state, and the generated mutation points are more likely to be caused by user behavior under normal operating conditions.

[0115] Among them, taking the operating current mutation difference index of the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module as an example, the specific construction process is:

[0116] First, the absolute value of the difference between the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module and the mean of the mutation point data in its corresponding sequence is taken as the mutation point numerical difference; the sum of the distances between the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module and the mutation time values ​​of all corresponding mutation points in its corresponding sequence is taken as the mutation time value difference; the sum of the mutation point numerical difference and the mutation time value difference of the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module is calculated;

[0117] Then, the average value of the sum result between the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module and all its corresponding sequences is taken as the operating current mutation difference index of the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module.

[0118] It should be noted that when calculating the sum of the distances between the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module and the mutation time values ​​of all corresponding mutation points in its corresponding sequence, the distance is calculated using the DTW distance in one embodiment of the present application. The calculation process of the DTW distance is a well-known technology and will not be repeated here. In other embodiments of the present application, other distance calculation methods can also be used for calculation.

[0119] It should be understood that the greater the difference between the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module and the mutation point value in its corresponding sequence, and the greater the difference in the corresponding mutation time values, the greater the difference between the current data characteristics in the u-th abnormal suspected subsequence in the r-th charging and swapping rectifier module and the current data characteristics of the charging and swapping rectifier module under normal operating conditions, and the more likely it is that there is an abnormality in the charging and swapping rectifier module.

[0120] Finally, the ratio of the operating state approximation index of the u-th abnormal suspicious subsequence in the r-th charging and swapping rectifier module to the operating current mutation difference index is used as the operating stability coefficient;

[0121] Among them, the operation normality index of the rth charging and swapping rectifier module is positively correlated with the cumulative sum of the operation stability coefficients of all abnormal suspicious subsequences in the rth charging and swapping rectifier module, and is negatively correlated with the operation abnormality certainty of the rth charging and swapping rectifier module.

[0122] It can be understood that a positive correlation means that the dependent variable will increase as the independent variable increases, and the dependent variable will decrease as the independent variable decreases. The specific relationship can be a multiplication relationship, an addition relationship, or the power of an exponential function, which is determined by actual application and is not specifically limited in this application. A negative correlation means that the dependent variable will decrease as the independent variable increases, and the dependent variable will increase as the independent variable decreases. It can be a subtraction relationship, a division relationship, etc., which is determined by actual application.

[0123] It should be understood that the larger the operating normality index of the rth charging and swapping rectifier module is, the more it indicates that the change conditions of the current data of the charging and swapping rectifier module are the changing characteristics of the normal operation of the charging and swapping rectifier module, and the better the operating status of the charging and swapping rectifier module is.

[0124] In one embodiment of the present application, the ratio of the cumulative sum of the operating stability coefficients of all abnormal suspicious subsequences in the rth charging and swapping rectifier module to the operating abnormality certainty of the rth charging and swapping rectifier module is used as the operating normality index of the rth charging and swapping rectifier module.

[0125] In other embodiments of the present application, the difference between the cumulative sum of the operating stability coefficients of all abnormal suspicious subsequences in the rth charging and swapping rectifier module and the operating abnormality certainty of the rth charging and swapping rectifier module can also be used as the operating normality index of the rth charging and swapping rectifier module.

[0126] At this point, the normal operation index of each charging and swapping rectifier module can be calculated through the above method.

[0127] The present application aims to analyze the current sudden change characteristics between the operating cycle subsequence of each charging and swapping rectifier module and the corresponding sequences of other charging and swapping rectifier modules, and use the differences in cycle characteristics that do not conform to the normal state to analyze the user's charging status in actual scenarios. It can more accurately distinguish between current data changes caused by user behavior and current data changes caused by abnormalities in the charging and swapping rectifier module, and more accurately distinguish between charging and swapping equipment that is operating normally and charging and swapping equipment that is operating abnormally, avoiding misjudgment of the actual state of the charging and swapping equipment caused by a single analysis level, and solving the problem that it is difficult to distinguish charging and swapping rectifier modules with minor abnormal problems when monitoring the operating current data of the rectifier modules of charging and swapping equipment using traditional abnormality detection algorithms, thereby improving the detection accuracy of the digital power port system for charging and swapping rectifier modules.

[0128] In one embodiment of the present application, a schematic diagram of the specific process of data analysis in the digital power port data analysis module is shown in FIG. Figure 2 shown.

[0129] The digital power port control and management module is used to perform abnormal evaluation on the normal operation index of the charging and swapping rectifier module through the digital power port system, and use the abnormal evaluation result to control and manage the charging and swapping rectifier module.

[0130] The calculated operating normality index of each charging and swapping rectifier module is input into the digital power port system for power generation, storage and charging conversion. The digital power port system then uses the anomaly detection algorithm to perform anomaly detection on the operating normality index of all charging and swapping rectifier modules, outputs the anomaly score of the operating normality index of each charging and swapping rectifier module, and normalizes the anomaly score of the operating normality index, normalizing its value range to between [0,1] to facilitate the judgment of the degree of abnormality.

[0131] In one embodiment of the present application, the LOF anomaly detection algorithm is used to calculate the anomaly score. The LOF anomaly detection algorithm is a well-known technology and the present application will not repeat its process. In other embodiments of the present application, other anomaly detection algorithms such as isolation forest can also be used for anomaly detection.

[0132] Set an abnormal threshold. In this embodiment, the abnormal threshold is 0.85. The larger the value of the abnormal threshold, the stricter the requirement for judging the abnormal state of the charging and swapping rectifier module. The implementer can set it according to actual needs.

[0133] When the abnormal score of the normal operation index of the charging and swapping rectifier module is greater than or equal to the abnormal threshold, it is determined that there is an abnormal situation in the charging and swapping rectifier module. The digital power port system sends the specific location of the charging and swapping rectifier module to the communication equipment of the relevant maintenance personnel through the information transmission module, and the relevant maintenance personnel then arrive at the location of the charging and swapping rectifier module for maintenance; otherwise, it is determined that the charging and swapping rectifier module is operating normally.

[0134] In one embodiment of the present application, the indicator construction flow chart for judging whether there is an abnormality in the charging and swapping rectifier module is as follows: Figure 3 shown.

[0135] In other embodiments of the present application, the charging and swapping rectifier module in the digital power port system can also be adjusted based on parameters such as the output voltage of the charging and swapping rectifier module in the charging and swapping equipment regarding the charging status of the battery. At the same time, the operating status of the charging and swapping rectifier module can be auxiliary analyzed in combination with the real-time temperature changes and charging rate of the charging and swapping equipment.

[0136] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.

[0137] It should be noted that, unless otherwise specified and limited, terms such as "include", "comprises" or any other variants thereof are intended to cover non-exclusive inclusion, so that a circuit structure, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such article or device. In the absence of further restrictions, an element defined by the sentence "including one..." does not exclude the existence of other identical elements in the article or device including the element. In addition, the term "and\or" used herein includes any and all combinations of one or more related listed items.

[0138] Those skilled in the art will readily appreciate other embodiments of the present application after considering the specification and practicing the invention herein. The present application is intended to cover any variations, uses or adaptations of the present application, which follow the general principles of the present application and include common knowledge or customary technical means in the art that are not invented by the present application.

[0139] It will be appreciated that the present application is not limited to the exact construction that has been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof.

Claims

1. A control and management system for digital power ports for power generation, storage and charging conversion. It is characterized in that The system comprises: The digital power port data acquisition module is used to obtain each operating cycle subsequence in the current data of each charging and swapping rectifier module through the digital power port system; The method for obtaining the operation cycle subsequence includes: obtaining the log data of each charging and swapping rectifier module through the digital power port system, and reading the current data of the charging and swapping rectifier module in the log data; dividing the data between the start and end time of each user using the charging and swapping rectifier module in the current data into each operation cycle subsequence; taking the longest sequence length in all the operation cycle subsequences as the sequence length benchmark; and filling the data of all the remaining operation cycle subsequences according to the sequence length benchmark; The digital power port data analysis module is used to analyze the current data performance of the charging and swapping rectifier module at different levels in actual scenarios, and assist the digital power port system in realizing the control and management of power generation, storage and charging conversion, specifically: S1, according to the correlation between the operation cycle subsequences of each charging and swapping rectifier module and the changes of adjacent data points in the operation cycle subsequences, divide the operation abnormality suspect sequence of each charging and swapping rectifier module; S2, constructing the operational abnormality confidence of each charging / swapping rectifier module according to the difference between the operational abnormality suspect sequences of each charging / swapping rectifier module and other charging / swapping rectifier modules that are adjacent in time; S3, constructing an operation normality index of each charging and swapping rectifier module according to the current sudden change characteristics between the operation cycle subsequence of each charging and swapping rectifier module and the corresponding sequences of other charging and swapping rectifier modules, and the operational abnormality confidence of each charging and swapping rectifier module; A digital power port control and management module is used to perform an abnormal evaluation on the normal operation index of the charging and swapping rectifier module through the digital power port system, and control and manage the charging and swapping rectifier module using the abnormal evaluation result; The process of dividing the operation abnormality and suspicious sequence includes: For each operating cycle subsequence of the charging and swapping rectifier module, obtain the fitting curve of any operating cycle subsequence, and calculate the slope value of each data point in any operating cycle subsequence on the fitting curve corresponding to the operating cycle subsequence to which it belongs; According to the change difference of adjacent data points in any operation cycle subsequence, the correlation between any operation cycle subsequence and the other operation cycle subsequences of the charging and swapping rectifier module in which it is located, and the slope difference, the operation quality coefficient of any operation cycle subsequence is constructed; The operation quality coefficients of all operation cycle subsequences in each charging and swapping rectifier module are taken as input, and a clustering algorithm is used to output a number of clusters, which are respectively recorded as operation status clusters; Calculate the mean of the good operation coefficient of each operation condition cluster, and take all the operation cycle subsequences in the operation condition cluster with the smallest mean of the good operation coefficient as the operation abnormality questionable sequence; The method for constructing the operational abnormality confidence comprises: For any suspicious operation abnormality sequence of each charging / swapping rectifier module, the suspicious operation abnormality sequences of all other charging / swapping rectifier modules that have an intersection with the data points in any suspicious operation abnormality sequence are respectively used as abnormal comparison sequences of any suspicious operation abnormality sequence; Constructing an operation abnormality determination coefficient of any sequence with suspected operation abnormality according to the distance difference and operation good coefficient difference between any sequence with suspected operation abnormality and its abnormal comparison sequence; The average of the operation abnormality determination coefficients of all operation abnormality doubtful sequences in each charging and swapping rectifier module is used as the operation abnormality certainty of each charging and swapping rectifier module; The process of constructing the operational normality index includes: According to the distribution of the number of mutation points in each operating cycle subsequence of each charging and swapping rectifier module, the abnormal suspected subsequence of each charging and swapping rectifier module is screened, and the mutation time value of each mutation point is determined; For the position of the operation cycle subsequence corresponding to any suspicious abnormal subsequence in each charging / swapping / rectifying module in the charging / swapping / rectifying module, the operation cycle subsequences of other charging / swapping / rectifying modules at the position are taken as the corresponding sequence of any suspicious abnormal subsequence; According to the degree of synchronization between any suspected abnormal subsequence and all its corresponding sequences in each charging and swapping rectifier module, as well as the difference in the value, position, and quantity distribution of the mutation points, the operating state approximate index and the operating current mutation difference index of any suspected abnormal subsequence in each charging and swapping rectifier module are constructed; The ratio of the operating state approximation index of any abnormal suspected subsequence in each charging and swapping rectifier module to the operating current mutation difference index is used as the operating stability coefficient; The operation normality index of each charging and swapping rectifier module is determined based on the operation stability coefficient and operation abnormality certainty of all abnormal suspicious subsequences in each charging and swapping rectifier module; wherein, the operation normality index of each charging and swapping rectifier module is positively correlated with the cumulative sum of the operation stability coefficients of all abnormal suspicious subsequences in each charging and swapping rectifier module, and is negatively correlated with the operation abnormality certainty of each charging and swapping rectifier module.

2. A control and management system for a digital power port for power generation, storage and charging conversion as claimed in claim 1, It is characterized in that The method for constructing the operation excellence coefficient includes: The sum of the correlations between any one of the operation cycle subsequences and the remaining operation cycle subsequences of the charging / swapping rectifier module in which it is located is taken as the numerator, the accumulation of the absolute values ​​of the differences between the slope values ​​of all data points in any one of the operation cycle subsequences and the slope values ​​of the corresponding data points of all other operation cycle subsequences of the charging / swapping rectifier module in which it is located is taken as the denominator, and the ratio of the numerator to the denominator is calculated as the first fusion term; Taking the average of the absolute values ​​of the differences between all adjacent data points in any operation cycle subsequence as the second fusion item; According to the first fusion item and the second fusion item of any operation cycle subsequence, the operation excellence coefficient of any operation cycle subsequence is determined; wherein the operation excellence coefficient of any operation cycle subsequence is positively correlated with the first fusion item and the second fusion item of any operation cycle subsequence, respectively.

3. A control and management system for a digital power port for power generation, storage and charging conversion as claimed in claim 1, It is characterized in that The method for constructing the operation abnormality determination coefficient includes: The sum of the distances between any of the suspected operation abnormality sequences and all of its abnormal comparison sequences is used as the third fusion term, and the sum of the absolute values ​​of the differences between the operation good coefficient of any of the suspected operation abnormality sequences and the operation good coefficients of all of its abnormal comparison sequences is used as the fourth fusion term; The third fusion item and the fourth fusion item of any of the operation abnormality doubtful sequences are added, and the result of the addition is used as the operation abnormality determination coefficient of any of the operation abnormality doubtful sequences.

4. A control and management system for a digital power port for power generation, storage and charging conversion as claimed in claim 1, It is characterized in that The screening process of the abnormal suspicious subsequence and the method for determining the mutation time value include: Each operating cycle subsequence of each charging and swapping rectifier module is used as the input of the mutation point detection algorithm, and the mutation point of each operating cycle subsequence is output; The total number of mutation points in each operating cycle subsequence is counted, and the total number of mutation points in all operating cycle subsequences is used as the input of the clustering algorithm, and several clusters are output, which are respectively recorded as mutation point number clusters; Calculate the average value of the total number of mutation points of each mutation point number cluster, and record all the operation cycle subsequences corresponding to the mutation point number cluster with the largest average value of the total number of mutation points as abnormal and suspicious subsequences; The sampling time position of each mutation point in the abnormal suspicious subsequence is used as the mutation time value corresponding to each mutation point.

5. A control and management system for a digital power port for power generation, storage and charging conversion as claimed in claim 4, It is characterized in that The process of constructing the operating state approximation index and the operating current mutation difference index includes: The absolute value of the difference between the total number of mutation points of any suspected abnormal subsequence and its corresponding sequence is used as the first denominator; the PLV value between any suspected abnormal subsequence and its corresponding sequence is used as the first numerator; the ratio of the first numerator to the first denominator is calculated as the fifth fusion term of any suspected abnormal subsequence; The average of the fifth fusion terms between any suspected abnormal subsequence and the corresponding sequences of all other charging / swapping rectifier modules is used as the running state approximation index of any suspected abnormal subsequence; The absolute value of the difference between the mean of the mutation point data in any suspected abnormal subsequence and its corresponding sequence is taken as the mutation point value difference; the sum of the distances between the mutation time values ​​of all corresponding mutation points in any suspected abnormal subsequence and its corresponding sequence is taken as the mutation time value difference; the sum of the mutation point value difference and the mutation time value difference of any suspected abnormal subsequence is calculated; The average value of the sum results between any suspected abnormal subsequence and all its corresponding sequences is used as the running current mutation difference index of any suspected abnormal subsequence.

6. A control and management system for a digital power port for power generation, storage and charging conversion as claimed in claim 1, It is characterized in that The abnormality assessment process includes: The normal operation indexes of all charging and swapping rectifier modules are input into the digital power port system. The digital power port system uses an abnormality detection algorithm to perform abnormality detection on the normal operation indexes of all charging and swapping rectifier modules, obtains the abnormality score of the normal operation index of each charging and swapping rectifier module, and normalizes the abnormality score; An abnormal threshold is set; when the normalized value of the abnormal score of the normal operation index of the charging and swapping rectifier module is greater than or equal to the abnormal threshold, it is determined that the charging and swapping rectifier module has an abnormal situation; otherwise, it is determined that the charging and swapping rectifier module is operating normally.