A smart construction site data collection method and system for road construction
The smart construction site data collection method through intelligent prediction and analysis solves the low efficiency and accuracy problems of traditional construction site data collection, realizes real-time data analysis and construction plan optimization, and improves construction site management efficiency and prediction accuracy.
Patent Information
- Application Number
- CN202410939130.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-07-15
AI Technical Summary
Traditional construction site data collection relies on paper forms, resulting in low efficiency, inaccurate data, and difficulty in sharing and collaboration. It cannot effectively use data for prediction, optimization, and decision support.
A smart construction site data collection method with intelligent prediction and analysis is used to obtain real-time construction site data at preset time intervals, predict influencing factors and project progress based on environmental and mechanical equipment data, update the construction plan, and use data preprocessing and features Extract and predict models for data analysis and storage.
It improves the efficiency of construction site management, ensures the accuracy and timeliness of data, dynamically adjusts the project progress prediction model, adapts to environmental changes, reduces potential risks and delays, and optimizes resource utilization.
Smart Images

Figure CN118469354B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of smart construction sites, and in particular to a smart construction site data collection method and system for road construction. Background Art
[0002] Traditional construction site data collection relies on paper forms and records. Workers need to record their work content on paper every day, including information such as construction progress, material usage, and labor input. However, this method often leads to inefficiency due to manual data entry and is susceptible to human errors, making it difficult to ensure the accuracy and timeliness of the data. In addition, data sharing and collaboration based on paper records are also difficult, resulting in scattered and difficult to structure data, and a lack of a unified platform for analysis and visualization. This situation makes it impossible to effectively use data for prediction, optimization, and decision support.
[0003] Therefore, we urgently need to provide a smart construction site data collection method and system for road construction with intelligent prediction and analysis. Summary of the invention
[0004] The present invention aims to provide a smart construction site data collection method and system for road construction with intelligent prediction and analysis, so as to make the collection of construction site data more intelligent.
[0005] A smart construction site data collection method for road construction, comprising:
[0006] S1. Acquire real-time construction site data at the target construction site at every preset time interval, the real-time construction site data including environmental data, engineering progress data and mechanical equipment data; obtain the predicted influencing factors within the next preset time interval based on the environmental data, mechanical equipment data and the influencing factor prediction model; obtain the predicted engineering progress within the next preset time interval based on the predicted influencing factors, engineering progress data and the engineering progress prediction model; arrange the project construction plan within the next preset time interval based on the predicted engineering progress; combine the real-time construction site data and the predicted engineering progress to obtain smart construction site data, and input the smart construction site data into the smart construction site database for storage;
[0007] S2. When each I+1 piece of smart construction site data is collected in the smart construction site database, the I+1 piece of smart construction site data is judged to obtain an updated judgment result; I+1 is the number of smart construction site data extracted from the smart construction site database, and I+1 is an integer; if the update judgment result is yes, the I+1 piece of smart construction site data is used to update the project progress prediction model; otherwise, the smart construction site data collection work continues.
[0008] As a preferred technical solution of the present invention, the influencing factor prediction model in step S1 includes a data preprocessing layer, an environmental factor prediction layer, an equipment factor prediction layer, a feature extraction layer and a result output layer;
[0009] The data preprocessing layer is used to preprocess the environmental data and mechanical equipment data to obtain preprocessed environmental data and preprocessed mechanical equipment data;
[0010] The environmental factor prediction layer is used to perform prediction analysis on the pre-processed environmental data to obtain the predicted environmental data within the next preset time interval;
[0011] The equipment factor prediction layer is used to perform prediction analysis on the pre-processed mechanical equipment data to obtain the predicted mechanical equipment data within the next preset time interval;
[0012] The feature extraction layer is used to extract features from the predicted environmental data and predicted mechanical equipment data to obtain the prediction influencing factors;
[0013] The result output layer is used to output the predicted influencing factors.
[0014] As a preferred technical solution of the present invention, the specific steps of training the environmental factor prediction layer and the equipment factor prediction layer in the influencing factor prediction model include:
[0015] Collect all environmental data and all mechanical equipment data within a set time range, arrange and combine all environmental data in chronological order, and obtain an environmental factor prediction training set; the environmental data of the next preset time interval in the environmental factor prediction training set is the target value of the environmental data of the previous preset time interval, and obtain the environmental factor target value; arrange and combine all mechanical equipment data in chronological order, and obtain an equipment factor prediction training set; the mechanical equipment data of the next preset time interval in the equipment factor prediction training set is the target value of the mechanical equipment data of the previous preset time interval, and obtain the equipment factor target value;
[0016] Input the environmental factor prediction training set into the influencing factor prediction model to train the environmental factor prediction layer, and train with the environmental factor target value as the target to obtain the predicted environmental data to be evaluated; calculate the accuracy of the predicted environmental data to be evaluated and the environmental factor target value to obtain the environmental factor prediction accuracy; if the environmental factor prediction accuracy meets the preset environmental factor accuracy, output the trained environmental factor prediction layer; otherwise, continue to train the environmental factor prediction layer using the environmental factor prediction training set;
[0017] The equipment factor prediction training set is input into the influencing factor prediction model to train the equipment factor prediction layer, and the equipment factor target value is used as the target for training to obtain the mechanical equipment data to be evaluated and predicted; the accuracy of the mechanical equipment data to be evaluated and predicted and the equipment factor target value is calculated to obtain the equipment factor prediction accuracy; if the equipment factor prediction accuracy meets the preset equipment factor accuracy, the trained equipment factor prediction layer is output; otherwise, the equipment factor prediction layer is continued to be trained using the equipment factor prediction training set.
[0018] As a preferred technical solution of the present invention, the project progress prediction model in step S1 includes a progress data preprocessing layer, a prediction analysis layer and a result output layer;
[0019] The progress data preprocessing layer is used to preprocess the project progress data to obtain preprocessed project progress data;
[0020] The prediction analysis layer is used to perform prediction analysis based on prediction influencing factors and pre-processed engineering progress data to obtain the predicted engineering progress;
[0021] The result output layer is used to output the predicted project progress.
[0022] As a preferred technical solution of the present invention, the specific steps of constructing a project progress prediction model include:
[0023] Get all model training real-time construction site data P within the preset time range j , j=1, 2, ..., J-1; J is the number of all model training real-time construction site data within the preset time range; model training real-time construction site data P j Contains model training environment data Q j , model training project progress data W j and model training mechanical equipment data R j ; The model training environment data Q j and model training mechanical equipment data R j Perform feature extraction to obtain the model training influencing factor U j ;
[0024] The model training project progress data W of adjacent preset time intervals j , Model training influencing factors U j+1 and model training project progress data W j+1 A set of engineering progress prediction training samples is formed, and the model training engineering progress data W j+1 as the training target value of a group of engineering progress prediction training samples; combining J-1 groups of engineering progress prediction training samples to obtain the engineering progress prediction training set;
[0025] The engineering progress prediction training set is input into the engineering progress prediction initial model, and the model is trained with the training target value as the target to obtain the prediction result of the engineering progress prediction training set; the mean square error between the prediction result of the engineering progress prediction training set and the training target value is calculated to obtain the prediction evaluation error; if the prediction evaluation error is within the error standard range, the trained engineering progress prediction initial model is output, and the engineering progress prediction initial model is used as the engineering progress prediction model; otherwise, the engineering progress prediction training set is used to continue the model training.
[0026] As a preferred technical solution of the present invention, the specific steps of step S2 include:
[0027] S21. Obtain the first I+1 pieces of smart construction site data and extract the project progress data X from the smart construction site data i and predicted project progress Y i , i=1,2,…,I; the project progress data X i+1 and predicted project progress Y i Combining to obtain a set of engineering progress prediction verification data, combining I sets of engineering progress prediction verification data to obtain an engineering progress prediction verification data set;
[0028] S22. Perform a posterior error ratio calculation based on the engineering progress prediction verification data set to obtain the posterior error ratio of the engineering progress prediction model; if the posterior error ratio of the engineering progress prediction model exceeds the error standard range, and the update judgment result is yes, use the first I+1 smart construction site data to update the engineering progress prediction model; otherwise, continue the smart construction site data collection work.
[0029] As a preferred technical solution of the present invention, the specific steps of updating the project progress prediction model using the first I+1 smart construction site data in step S22 include:
[0030] Construct K hyperparameter individuals H k , k=1, 2, ..., K; K is the number of hyperparameter individuals; each hyperparameter individual H k contains a set of hyperparameters for adjusting the project progress prediction model; k Combine to obtain the hyperparameter iteration population; set the maximum number of iterations;
[0031] Extract the real-time construction site data L from the first I+1 smart construction site data i , real-time construction site data L i Environmental data in Z i and mechanical equipment data D i Input into the influencing factor prediction model to obtain the predicted influencing factor G i , all engineering progress data X i and predicted influencing factors Gi Combine to obtain the engineering progress update data set;
[0032] According to the hyperparameter iteration population, the hyperparameter individuals H k The project progress update data set is simulated and calculated to obtain the project progress update prediction data set; the posterior difference ratio is calculated based on the project progress update data set and the project progress update prediction data set to obtain the updated posterior difference ratio; the inverse of the updated posterior difference ratio is used as the hyperparameter individual H k The fitness S k ;
[0033] Based on all hyperparameters individual H k The fitness S k Select, reorganize and mutate the hyperparameter iteration population, and update all hyperparameter iteration populations;
[0034] When the maximum number of iterations is reached, the hyperparameter individual H corresponding to the maximum fitness is output k , which is the optimal hyperparameter individual. The engineering progress prediction model is updated according to the adjusted hyperparameters in the optimal hyperparameter individual to obtain a new engineering progress prediction model.
[0035] A smart construction site data collection system for road construction, comprising:
[0036] The smart construction site data acquisition module is used to obtain real-time construction site data at the target construction site at preset time intervals. The real-time construction site data includes environmental data, project progress data and mechanical equipment data;
[0037] The smart construction site data analysis module is used to deploy the influencing factor prediction model and the project progress prediction model. Based on the environmental data, mechanical equipment data and the influencing factor prediction model, the predicted influencing factors within the next preset time interval are obtained; based on the predicted influencing factors, the project progress data and the project progress prediction model, the predicted project progress within the next preset time interval is obtained; based on the predicted project progress, the project construction plan within the next preset time interval is arranged;
[0038] A smart construction site data storage module is used to combine real-time construction site data and predicted project progress to obtain smart construction site data, and input the smart construction site data into a smart construction site database for storage;
[0039] The smart construction site data update module is used to judge the I+1 smart construction site data every time it collects I+1 smart construction site data in the smart construction site database to obtain an update judgment result; I+1 is the number of smart construction site data extracted from the smart construction site database, and I+1 is an integer; if the update judgment result is yes, the I+1 smart construction site data is used to update the project progress prediction model; otherwise, the smart construction site data collection work continues.
[0040] The present invention has the following advantages:
[0041] 1. The present invention can help managers to timely understand the current status of the construction site and make more accurate decisions by acquiring real-time construction site data at preset time intervals, including environment, project progress, mechanical equipment data, etc.; through these real-time data, managers can quickly respond to changes on site and improve construction site management efficiency; using environmental data, mechanical equipment data and influencing factor prediction models to predict influencing factors and project progress within the next preset time interval can effectively help plan and adjust project construction plans, avoid potential risks and delays, and ensure that the project proceeds as planned; by evaluating each new smart construction site data collected, the project progress prediction model is updated in a timely manner to ensure that the project progress prediction model is always kept up to date and improve the accuracy of the prediction; this dynamic adjustment can allow the model to adapt to environmental changes and actual site conditions, making the prediction results more reliable.
[0042] 2. The present invention continuously improves the prediction accuracy of the project progress prediction model by establishing and iteratively calculating the hyperparameter population, and ensures that the data relied on by the project progress prediction model for updating is both comprehensive and timely by comprehensively and real-time collecting site data, thereby significantly enhancing the ability of the project progress prediction model to reflect reality; in addition, by dynamically adjusting the hyperparameters, the project progress prediction model is more adaptable to the ever-changing site conditions and needs; by calculating the posterior difference ratio between the updated data set and the predicted data set, and taking its inverse as the fitness, the effectiveness of the adjustment of the project progress prediction model is guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 This is a schematic diagram of the structure of a smart construction site data collection system for road construction adopted in an embodiment of the present invention. DETAILED DESCRIPTION
[0044] In order to enable persons skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0045] A smart construction site data collection method for road construction, comprising:
[0046] S1. Acquire real-time construction site data at the target construction site at every preset time interval, the real-time construction site data including environmental data, engineering progress data and mechanical equipment data; obtain the predicted influencing factors within the next preset time interval based on the environmental data, mechanical equipment data and the influencing factor prediction model; obtain the predicted engineering progress within the next preset time interval based on the predicted influencing factors, engineering progress data and the engineering progress prediction model; arrange the project construction plan within the next preset time interval based on the predicted engineering progress; combine the real-time construction site data and the predicted engineering progress to obtain smart construction site data, and input the smart construction site data into the smart construction site database for storage;
[0047] The preset time interval is set by professional technicians based on actual conditions. The environmental data and mechanical equipment data in the real-time construction site data are obtained from sensors at the road construction site. The project progress data in the real-time construction site data is obtained by professional technicians after measurement using professional equipment.
[0048] By collecting real-time site data at preset time intervals, project managers can be kept up to date with the latest project environment, progress and equipment status. By using the project progress prediction model, project progress can be predicted more accurately to ensure that the project proceeds as planned and reduce the probability of delays. The status and use of mechanical equipment can be tracked in real time to optimize the deployment and use of equipment, reduce equipment idle time, and improve resource utilization efficiency. By analyzing the project progress and arranging the project construction plan within the next preset time interval based on the predicted project progress, personnel arrangements can be optimized, construction efficiency can be improved, and labor costs can be reduced.
[0049] The influencing factor prediction model in step S1 includes a data preprocessing layer, an environmental factor prediction layer, an equipment factor prediction layer, a feature extraction layer and a result output layer;
[0050] The data preprocessing layer is used to preprocess the environmental data and mechanical equipment data to obtain preprocessed environmental data and preprocessed mechanical equipment data;
[0051] The environmental factor prediction layer is used to perform prediction analysis on the pre-processed environmental data to obtain the predicted environmental data within the next preset time interval;
[0052] The equipment factor prediction layer is used to perform prediction analysis on the pre-processed mechanical equipment data to obtain the predicted mechanical equipment data within the next preset time interval;
[0053] The feature extraction layer is used to extract features from the predicted environmental data and predicted mechanical equipment data to obtain the prediction influencing factors;
[0054] The result output layer is used to output the predicted influencing factors;
[0055] The data preprocessing layer preprocesses environmental data and mechanical equipment data, cleans and organizes the original data, eliminates noise, improves the quality and accuracy of the data, and lays a solid foundation for subsequent prediction and analysis; the environmental factor prediction layer predicts and analyzes the preprocessed environmental data, and can accurately estimate the environmental changes within the next preset time interval; the equipment factor prediction layer predicts and analyzes the preprocessed mechanical equipment data, and can timely discover potential failures and performance changes of the equipment; the feature extraction layer integrates the predicted environmental data and mechanical equipment data, extracts key features, and provides comprehensive information support for accurately predicting the project progress within the next time interval;
[0056] The specific steps of training the environmental factor prediction layer and the equipment factor prediction layer in the influencing factor prediction model include:
[0057] Collect all environmental data and all mechanical equipment data within a set time range, arrange and combine all environmental data in chronological order, and obtain an environmental factor prediction training set; the environmental data of the next preset time interval in the environmental factor prediction training set is the target value of the environmental data of the previous preset time interval, and obtain the environmental factor target value; arrange and combine all mechanical equipment data in chronological order, and obtain an equipment factor prediction training set; the mechanical equipment data of the next preset time interval in the equipment factor prediction training set is the target value of the mechanical equipment data of the previous preset time interval, and obtain the equipment factor target value;
[0058] Input the environmental factor prediction training set into the influencing factor prediction model to train the environmental factor prediction layer, and train with the environmental factor target value as the target to obtain the predicted environmental data to be evaluated; calculate the accuracy of the predicted environmental data to be evaluated and the environmental factor target value to obtain the environmental factor prediction accuracy; if the environmental factor prediction accuracy meets the preset environmental factor accuracy, output the trained environmental factor prediction layer; otherwise, continue to train the environmental factor prediction layer using the environmental factor prediction training set;
[0059] Input the equipment factor prediction training set into the influencing factor prediction model to train the equipment factor prediction layer, and train with the equipment factor target value as the target to obtain the mechanical equipment data to be evaluated and predicted; calculate the accuracy of the mechanical equipment data to be evaluated and predicted and the equipment factor target value to obtain the equipment factor prediction accuracy; if the equipment factor prediction accuracy meets the preset equipment factor accuracy, output the trained equipment factor prediction layer; otherwise, continue to train the equipment factor prediction layer using the equipment factor prediction training set;
[0060] The LSTM model is used as the basic model of the environmental factor prediction layer and the equipment factor prediction layer. The time range, the accuracy of the preset environmental factors and the accuracy of the preset equipment factors are set by professional technicians according to the actual situation.
[0061] The project progress prediction model in step S1 includes a progress data preprocessing layer, a prediction analysis layer and a result output layer;
[0062] The progress data preprocessing layer is used to preprocess the project progress data to obtain preprocessed project progress data;
[0063] The prediction analysis layer is used to perform prediction analysis based on prediction influencing factors and pre-processed engineering progress data to obtain the predicted engineering progress;
[0064] The result output layer is used to output the predicted project progress;
[0065] The prediction and analysis layer uses pre-processed progress data and prediction influencing factors for comprehensive analysis, which can more accurately predict the future progress of the project. Accurate progress prediction can reveal the changing trends of resource demand and construction arrangements in advance, allowing the construction team to more reasonably plan the allocation of human resources, materials and other resources, avoid resource waste or shortage, and ensure the efficient advancement of the project. The continuously updated project progress prediction results can serve as an important reference for project control and supervision, helping the supervision team to adjust the supervision focus and methods in a timely manner to ensure that the road construction project is steadily advanced as planned.
[0066] The specific steps of building a project progress prediction model include:
[0067] Get all model training real-time construction site data P within the preset time range j , j=1, 2, ..., J-1; J is the number of all model training real-time construction site data within the preset time range; model training real-time construction site data P j Contains model training environment data Q j , model training project progress data W j and model training mechanical equipment data R j ; The model training environment data Q j and model training mechanical equipment data R j Perform feature extraction to obtain the model training influencing factor U j ;
[0068] The model training project progress data W of adjacent preset time intervals j , Model training influencing factors U j+1 and model training project progress data W j+1 A set of engineering progress prediction training samples is formed, and the model training engineering progress data W j+1 as the training target value of a group of engineering progress prediction training samples; combining J-1 groups of engineering progress prediction training samples to obtain the engineering progress prediction training set;
[0069] Input the engineering progress prediction training set into the engineering progress prediction initial model, and perform model training with the training target value as the target, to obtain the prediction result of the engineering progress prediction training set; calculate the mean square error between the prediction result of the engineering progress prediction training set and the training target value, and obtain the prediction evaluation error; if the prediction evaluation error is within the error standard range, output the trained engineering progress prediction initial model, and use the engineering progress prediction initial model as the engineering progress prediction model; otherwise, continue to perform model training using the engineering progress prediction training set;
[0070] The preset time range is set by professional technicians based on actual conditions, using the BP neural network model as the basic model of the project progress prediction model;
[0071] By acquiring real-time construction site data within a preset time range for model training, including model training environment data, model training project progress data, and model training mechanical equipment data, this real-time nature enables the prediction model to be analyzed based on the latest data, thereby improving the accuracy of the prediction; by deploying influencing factor prediction models and project progress prediction models, these models can predict the influencing factors and project progress within the next preset time interval based on real-time data. This integrated prediction model can provide a more comprehensive prediction of the construction site status. By predicting possible delays and problems, construction site project managers can formulate response strategies in advance, thereby reducing project risks; accurate progress predictions can help construction site project managers allocate resources more effectively, such as manpower, materials, and equipment , ensuring that resources are used in the right place at the right time; the prediction model provides a clear schedule and cost forecast, which helps to improve project transparency and enhance the confidence of site project managers; the prediction model can reduce unnecessary waiting time and resource waste and improve the efficiency of the entire project; for example, when it is predicted that there may be bad weather in the next preset time interval, the site project manager can adjust the project plan in time and complete the outdoor work project in advance to avoid the bad weather affecting the progress of the project; when it is predicted that the mechanical equipment may suffer serious wear and tear in the next preset time interval, the site project manager can overhaul the mechanical equipment in advance, or prepare multiple mechanical equipment in advance in the next preset time interval to deal with emergencies;
[0072] S2. When I+1 pieces of smart construction site data are collected in the smart construction site database, the I+1 pieces of smart construction site data are judged to obtain an updated judgment result; I+1 is the number of smart construction site data extracted from the smart construction site database, and I+1 is an integer; if the update judgment result is yes, the project progress prediction model is updated using the I+1 pieces of smart construction site data; otherwise, the smart construction site data collection work continues;
[0073] By continuously acquiring new site data and comparing it with the predicted values, the model can verify and calibrate its accuracy, thereby providing more accurate project progress predictions in actual applications. Based on the calculation of the posterior difference ratio, the model automatically updates and adjusts when the prediction model accuracy does not meet the error range, which enables the model to self-optimize to adapt to changing data patterns. The updated and verified prediction model provides a powerful decision-making support tool for site management, helping construction project managers to better plan resources and adjust progress.
[0074] The specific steps of step S2 include:
[0075] S21. Obtain the first I+1 pieces of smart construction site data and extract the project progress data X from the smart construction site data i and predicted project progress Y i , i=1,2,…,I; the project progress data X i+1 and predicted project progress Y i Combining to obtain a set of engineering progress prediction verification data, combining I sets of engineering progress prediction verification data to obtain an engineering progress prediction verification data set;
[0076] S22. Calculate the posterior difference ratio based on the engineering progress prediction verification data set to obtain the posterior difference ratio of the engineering progress prediction model; if the posterior difference ratio of the engineering progress prediction model exceeds the error standard range, the update judgment result is yes, then use the first I+1 smart construction site data to update the engineering progress prediction model; otherwise, continue to collect smart construction site data;
[0077] Using the formula: Calculate the posterior error ratio, P represents the posterior error ratio of the project progress prediction model, Represents all the engineering progress data X in the engineering progress prediction validation dataset i+1 The sum of the average values, X i+1 and Y i Represents a set of engineering progress data X in the engineering progress prediction verification data set i+1 and predicted project progress Y i ; The error standard range is set by professional technicians based on actual conditions. The smaller the value of the posterior error ratio of the project progress prediction model, the more accurate the prediction of the project progress prediction model;
[0078] The specific steps of updating the project progress prediction model using the first I+1 smart construction site data in step S22 include:
[0079] Construct K hyperparameter individuals H k , k=1, 2, ..., K; K is the number of hyperparameter individuals; each hyperparameter individual H kcontains a set of hyperparameters for adjusting the project progress prediction model; k Combine to obtain the hyperparameter iteration population; set the maximum number of iterations;
[0080] Extract the real-time construction site data L from the first I+1 smart construction site data i , real-time construction site data L i Environmental data in Z i and mechanical equipment data D i Input into the influencing factor prediction model to obtain the predicted influencing factor G i , all engineering progress data X i and predicted influencing factors G i Combine to obtain the engineering progress update data set;
[0081] According to the hyperparameter iteration population, the hyperparameter individuals H k The project progress update data set is simulated and calculated to obtain the project progress update prediction data set; the posterior difference ratio is calculated based on the project progress update data set and the project progress update prediction data set to obtain the updated posterior difference ratio; the inverse of the updated posterior difference ratio is used as the hyperparameter individual H k The fitness S k ;
[0082] The steps of simulation calculation are:
[0083] According to the hyperparameter individual H k The engineering progress prediction model is adjusted by adjusting the hyperparameters in to obtain a simulated engineering progress prediction model, and the engineering progress update data set is input into the simulated engineering progress prediction model to obtain an engineering progress update prediction data set; the engineering progress update data set is matched with the data in the engineering progress update prediction data set to obtain an engineering progress update prediction verification set; the posterior difference ratio is calculated for the data in the engineering progress prediction update verification set to obtain an updated posterior difference ratio;
[0084] Based on all hyperparameters individual H k The fitness S k Select, reorganize and mutate the hyperparameter iteration population, and update all hyperparameter iteration populations;
[0085] The selection operation is to select the hyperparameter individual H k The fitness S k Based on this, the roulette wheel selection algorithm is used to select the hyperparameter individuals H in the hyperparameter iteration population. k Select and choose the better hyperparameter individual H k Form a new hyperparameter iteration population;
[0086] The recombination operation is to perform two random hyperparameter individuals H in the hyperparameter iteration population k Perform multi-point crossover changes, that is, randomly select multiple positions and cross-exchange the elements of two random hyperparameter individuals at the selected multiple positions, such as exchanging any parameters in the two sets of adjustment hyperparameters;
[0087] The mutation operation is to iterate each hyperparameter individual H in the hyperparameter population k , randomly generate a set of values for adjusting hyperparameters. If the values of the generated hyperparameters meet the mutation conditions, randomly select the value position of the hyperparameters and change the hyperparameter individual H k Perform mutation at the selected numerical location of the tuning hyperparameter;
[0088] When the maximum number of iterations is reached, the hyperparameter individual H corresponding to the maximum fitness is output k , that is, the optimal hyperparameter individual, the engineering progress prediction model is updated according to the adjusted hyperparameters in the optimal hyperparameter individual to obtain a new engineering progress prediction model; the algorithm for updating the engineering progress prediction model using the first I+1 smart construction site data in step S22 is a genetic algorithm;
[0089] By constructing a hyperparameter population and performing iterative calculations, the model can continuously optimize its prediction capabilities and strive to achieve higher accuracy; the comprehensive collection of real-time site data ensures that the data basis for model updates is comprehensive and real-time, greatly improving the ability of the prediction model to reflect the actual situation; the application of genetic algorithms enables dynamic adjustment of hyperparameters, which makes the model more in line with the ever-changing on-site environment and needs; the calculation of the posterior difference ratio between the update data set and the prediction data set, and its reciprocal as the fitness, effectively verifies the effectiveness of each model adjustment; the use of genetic algorithms introduces the selection, crossover and mutation mechanisms in biological evolution, which increases the probability of finding the optimal hyperparameter solution;
[0090] After collecting a certain amount of smart construction site data, the project progress prediction model is calculated by the posterior difference ratio to determine whether the model needs to be updated. This model update mechanism based on actual data helps to improve the prediction accuracy and adaptability of the model; in the model update process, hyperparameter optimization technology is used to construct hyperparameter individuals and iterative populations, and select, reorganize and mutate operations to find the optimal hyperparameter configuration. This hyperparameter optimization method can improve the performance and prediction accuracy of the model; when training the influencing factor prediction model and the project progress prediction model, the system evaluates the accuracy of the model by calculating the prediction accuracy and mean square error. This accuracy evaluation helps to ensure the reliability of the model and guide the further optimization of the model; for example, when the predicted project progress is always faster than the actual project progress, the project plan may be seriously inconsistent with the actual progress, which will affect the construction progress. Therefore, the project progress prediction model needs to be updated to improve the accuracy of the prediction, so that the predicted progress is closer to the actual progress, so as to more accurately adjust the project construction plan.
[0091] A smart construction site data collection system for road construction, see Figure 1 As shown, including:
[0092] The smart construction site data acquisition module is used to obtain real-time construction site data at the target construction site at preset time intervals. The real-time construction site data includes environmental data, project progress data and mechanical equipment data;
[0093] The smart construction site data analysis module is used to deploy the influencing factor prediction model and the project progress prediction model. Based on the environmental data, mechanical equipment data and the influencing factor prediction model, the predicted influencing factors within the next preset time interval are obtained; based on the predicted influencing factors, the project progress data and the project progress prediction model, the predicted project progress within the next preset time interval is obtained; based on the predicted project progress, the project construction plan within the next preset time interval is arranged;
[0094] A smart construction site data storage module is used to combine real-time construction site data and predicted project progress to obtain smart construction site data, and input the smart construction site data into a smart construction site database for storage;
[0095] The smart construction site data update module is used to judge the I+1 smart construction site data every time when the smart construction site database collects I+1 smart construction site data, and obtain an update judgment result; I+1 is the number of smart construction site data extracted from the smart construction site database, and I+1 is an integer; if the update judgment result is yes, the project progress prediction model is updated using the I+1 smart construction site data; otherwise, the smart construction site data collection work continues;
[0096] The smart construction site data storage module combines and stores real-time construction site data and predicted project progress, while the data update module dynamically updates the prediction model based on the collected data. This dynamic update mechanism ensures that the model can adapt to changes in site conditions and maintain the accuracy of the prediction.
[0097] It should be understood that those skilled in the art can make improvements or changes based on the above description, and all such improvements and changes should fall within the scope of protection of the appended claims of the present invention. Parts not described in detail in this specification belong to the prior art known to those skilled in the art.
Claims
1. A smart construction site data collection method for road construction, characterized in that: include: S1. Acquire real-time construction site data at the target construction site at every preset time interval, the real-time construction site data including environmental data, engineering progress data and mechanical equipment data; obtain the predicted influencing factors within the next preset time interval based on the environmental data, mechanical equipment data and the influencing factor prediction model; obtain the predicted engineering progress within the next preset time interval based on the predicted influencing factors, engineering progress data and the engineering progress prediction model; arrange the project construction plan within the next preset time interval based on the predicted engineering progress; combine the real-time construction site data and the predicted engineering progress to obtain smart construction site data, and input the smart construction site data into the smart construction site database for storage; S2. When I+1 pieces of smart construction site data are collected in the smart construction site database, the I+1 pieces of smart construction site data are judged to obtain an updated judgment result; I+1 is the number of smart construction site data extracted from the smart construction site database, and I+1 is an integer; if the update judgment result is yes, the project progress prediction model is updated using the I+1 pieces of smart construction site data; otherwise, the smart construction site data collection work continues; The influencing factor prediction model in step S1 includes a data preprocessing layer, an environmental factor prediction layer, an equipment factor prediction layer, a feature extraction layer and a result output layer; The data preprocessing layer is used to preprocess the environmental data and mechanical equipment data to obtain preprocessed environmental data and preprocessed mechanical equipment data; The environmental factor prediction layer is used to perform prediction analysis on the pre-processed environmental data to obtain the predicted environmental data within the next preset time interval; The equipment factor prediction layer is used to perform prediction analysis on the pre-processed mechanical equipment data to obtain the predicted mechanical equipment data within the next preset time interval; The feature extraction layer is used to extract features from the predicted environmental data and predicted mechanical equipment data to obtain the prediction influencing factors; The result output layer is used to output the predicted influencing factors; The project progress prediction model in step S1 includes a progress data preprocessing layer, a prediction analysis layer and a result output layer; The progress data preprocessing layer is used to preprocess the project progress data to obtain preprocessed project progress data; The prediction analysis layer is used to perform prediction analysis based on prediction influencing factors and pre-processed engineering progress data to obtain the predicted engineering progress; The result output layer is used to output the predicted project progress; The specific steps of step S2 include: S21. Obtain the first I+1 pieces of smart construction site data and extract the project progress data X from the smart construction site data i and predicted project progress Y i , i=1,2,…,I; the project progress data X i+1 and predicted project progress Y i Combining to obtain a set of engineering progress prediction verification data, combining I sets of engineering progress prediction verification data to obtain an engineering progress prediction verification data set; S22. Calculate the posterior difference ratio based on the engineering progress prediction verification data set to obtain the posterior difference ratio of the engineering progress prediction model; if the posterior difference ratio of the engineering progress prediction model exceeds the error standard range, the update judgment result is yes, then use the first I+1 smart construction site data to update the engineering progress prediction model; otherwise, continue to collect smart construction site data; The specific steps of updating the project progress prediction model using the first I+1 smart construction site data in step S22 include: Construct K hyperparameter individuals H k , k=1, 2, ..., K; K is the number of hyperparameter individuals; each hyperparameter individual H k contains a set of hyperparameters for adjusting the project progress prediction model; k Combine to obtain the hyperparameter iteration population; set the maximum number of iterations; Extract the real-time construction site data L from the first I+1 smart construction site data i , real-time construction site data L i Environmental data in Z i and mechanical equipment data D i Input into the influencing factor prediction model to obtain the predicted influencing factor G i , all engineering progress data X i and predicted influencing factors G i Combine to obtain the engineering progress update data set; According to the hyperparameter iteration population, the hyperparameter individuals H k The project progress update data set is simulated and calculated to obtain the project progress update prediction data set; the posterior difference ratio is calculated based on the project progress update data set and the project progress update prediction data set to obtain the updated posterior difference ratio; the inverse of the updated posterior difference ratio is used as the hyperparameter individual H k The fitness S k ; Based on all hyperparameters individual H k The fitness S k Select, reorganize and mutate the hyperparameter iteration population, and update all hyperparameter iteration populations; When the maximum number of iterations is reached, the hyperparameter individual H corresponding to the maximum fitness is output k , which is the optimal hyperparameter individual. The engineering progress prediction model is updated according to the adjusted hyperparameters in the optimal hyperparameter individual to obtain a new engineering progress prediction model.
2. A smart construction site data collection method for road construction according to claim 1, characterized in that: The specific steps of training the environmental factor prediction layer and the equipment factor prediction layer in the influencing factor prediction model include: Collect all environmental data and all mechanical equipment data within a set time range, arrange and combine all environmental data in chronological order, and obtain an environmental factor prediction training set; the environmental data of the next preset time interval in the environmental factor prediction training set is the target value of the environmental data of the previous preset time interval, and obtain the environmental factor target value; arrange and combine all mechanical equipment data in chronological order, and obtain an equipment factor prediction training set; the mechanical equipment data of the next preset time interval in the equipment factor prediction training set is the target value of the mechanical equipment data of the previous preset time interval, and obtain the equipment factor target value; Input the environmental factor prediction training set into the influencing factor prediction model to train the environmental factor prediction layer, and train with the environmental factor target value as the target to obtain the predicted environmental data to be evaluated; calculate the accuracy of the predicted environmental data to be evaluated and the environmental factor target value to obtain the environmental factor prediction accuracy; if the environmental factor prediction accuracy meets the preset environmental factor accuracy, output the trained environmental factor prediction layer; otherwise, continue to train the environmental factor prediction layer using the environmental factor prediction training set; The equipment factor prediction training set is input into the influencing factor prediction model to train the equipment factor prediction layer, and the equipment factor target value is used as the target for training to obtain the mechanical equipment data to be evaluated and predicted; the accuracy of the mechanical equipment data to be evaluated and predicted and the equipment factor target value is calculated to obtain the equipment factor prediction accuracy; if the equipment factor prediction accuracy meets the preset equipment factor accuracy, the trained equipment factor prediction layer is output; otherwise, the equipment factor prediction layer is continued to be trained using the equipment factor prediction training set.
3. A smart construction site data collection method for road construction according to claim 2, characterized in that: The specific steps of building a project progress prediction model include: Get all model training real-time construction site data P within the preset time range j , j=1, 2, ..., J-1; J is the number of all model training real-time construction site data within the preset time range; model training real-time construction site data P j Contains model training environment data Q j , model training project progress data W j and model training mechanical equipment data R j ; The model training environment data Q j and model training mechanical equipment data R j Perform feature extraction to obtain the model training influencing factor U j ; The model training project progress data W of adjacent preset time intervals j , Model training influencing factors U j+1 and model training project progress data W j+1 A set of engineering progress prediction training samples is formed, and the model training engineering progress data W j+1 as the training target value of a group of engineering progress prediction training samples; combining J-1 groups of engineering progress prediction training samples to obtain the engineering progress prediction training set; The engineering progress prediction training set is input into the engineering progress prediction initial model, and the model is trained with the training target value as the target to obtain the prediction result of the engineering progress prediction training set; the mean square error between the prediction result of the engineering progress prediction training set and the training target value is calculated to obtain the prediction evaluation error; if the prediction evaluation error is within the error standard range, the trained engineering progress prediction initial model is output, and the engineering progress prediction initial model is used as the engineering progress prediction model; otherwise, the engineering progress prediction training set is used to continue the model training.
4. A smart construction site data collection system for road construction, characterized in that: The system applies a smart construction site data collection method for road construction as described in any one of claims 1 to 3, including: The smart construction site data acquisition module is used to obtain real-time construction site data at the target construction site at preset time intervals. The real-time construction site data includes environmental data, project progress data and mechanical equipment data; The smart construction site data analysis module is used to deploy the influencing factor prediction model and the project progress prediction model. Based on the environmental data, mechanical equipment data and the influencing factor prediction model, the predicted influencing factors within the next preset time interval are obtained; based on the predicted influencing factors, the project progress data and the project progress prediction model, the predicted project progress within the next preset time interval is obtained; based on the predicted project progress, the project construction plan within the next preset time interval is arranged; A smart construction site data storage module is used to combine real-time construction site data and predicted project progress to obtain smart construction site data, and input the smart construction site data into a smart construction site database for storage; The smart construction site data update module is used to judge the I+1 smart construction site data every time it collects I+1 smart construction site data in the smart construction site database to obtain an update judgment result; I+1 is the number of smart construction site data extracted from the smart construction site database, and I+1 is an integer; if the update judgment result is yes, the I+1 smart construction site data is used to update the project progress prediction model; otherwise, the smart construction site data collection work continues.