Joint design method of frequency control and transmission communication of virtual power plant under cloud-edge-end collaboration
Through the cloud-edge-device collaborative virtual power plant frequency control architecture, combined with routing optimization and dynamic power control of wired and wireless communications, the impact of hybrid communication networks on virtual power plant frequency control is solved, achieving more efficient frequency control accuracy and response speed. .
Patent Information
- Application Number
- CN202410994772.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-24
AI Technical Summary
In the existing technology, the impact of the hybrid communication network on the frequency control of the virtual power plant has not been fully considered, making it difficult to guarantee the real-time and accuracy of the frequency control service.
Adopting a cloud-edge-device collaborative virtual power plant frequency control architecture, combining wired and wireless communications, and using routing optimization strategies and dynamic power control strategies to reduce the impact of communication network uncertainty on the virtual power plant and ensure real-time and accuracy of frequency control.
It effectively improves the frequency control accuracy and response speed of the virtual power plant in a mixed communication environment, improves the system frequency adjustment capability, and reduces the impact of communication network problems on frequency control.
Smart Images

Figure CN118539433B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a method for jointly designing frequency control and transmission communication of a virtual power plant under cloud-edge-end collaboration, and belongs to the technical field of power system operation and control. Background Art
[0002] The increasing penetration of renewable energy has led to a decreasing synchronous inertia of the power system. In addition, the intermittent nature of renewable energy has exacerbated the challenge of frequency stability, resulting in a significant decrease in the system's flexible regulation capabilities. Therefore, more regulation resources are urgently needed to improve system frequency stability. In recent years, a large number of renewable energy and flexible distributed resources have been widely connected to the distribution network, which has brought new opportunities for system frequency regulation. However, due to the limited capacity of these resources, the use of virtual power plants to aggregate and coordinate these resources to support frequency control business has become an emerging paradigm.
[0003] At present, there are some literatures that study the use of virtual power plants to provide frequency control. These studies mainly focus on enabling virtual power plants to achieve system frequency stability through resource optimization scheduling and bidding and bidding strategies, while few studies have achieved dynamic collaborative regulation of virtual power plants. At the same time, virtual power plants participating in frequency control also require a good communication network environment. In recent years, some literatures have developed some advanced communication technologies to support virtual power plants in providing frequency control services. These studies mainly consider the impact of wireless communication environments. However, the impact of hybrid communication network issues on virtual power plant frequency control is rarely considered. Therefore, the present invention proposes a joint design method for virtual power plant frequency control and transmission communication based on cloud-edge-end collaboration in a hybrid communication environment. Summary of the invention
[0004] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a method for jointly designing frequency control and transmission communication of virtual power plants under cloud-edge-end collaboration, which effectively reduces the impact of hybrid communication network uncertainty on the frequency control service of virtual power plants and ensures the real-time and accuracy of frequency control services. To achieve the above purpose, the present invention is implemented by adopting the following technical solution, which specifically includes the following steps:
[0005] (1) Build a virtual power plant frequency control architecture for cloud-edge-end collaboration, in which the wired transmission communication used by cloud-edge collaboration and the wireless transmission communication used by edge-end collaboration form a hybrid communication environment;
[0006] (2) A joint design strategy for virtual power plant power scheduling and wired communication routing optimization under cloud-edge collaboration is proposed. That is, the impact of cloud-edge communication network uncertainty on virtual power plant power scheduling is considered and the impact is overcome by designing a routing optimization strategy.
[0007] (3) An integrated design method for dynamic power control of virtual power plants and wireless communication network performance under edge collaboration is proposed. That is, the impact of cloud-edge wireless network performance on the dynamic power control of virtual power plants is considered, and this impact is overcome by developing a dynamic power control strategy for the generalized closed loop of "collection-transmission-decision-control" of information-physical collaboration of virtual power plants.
[0008] Furthermore, the step (1) comprises:
[0009] The control architecture built involves the terminal layer, edge layer and cloud layer. The terminal layer consists of a virtual power plant that aggregates a large number of resources on the distribution network side, numerous sensors and terminal controllers. The resources here include renewable energy, such as photovoltaic power generation and wind power generation, as well as flexible distributed resources (such as plug-in electric vehicles and distributed battery energy storage systems). Sensors and terminal controllers are responsible for monitoring and controlling these resources through wireless communication networks. A large number of fusion terminals are deployed in the edge layer to aggregate, analyze and process data from the terminal side, and interact with the virtual power plant control center through a wired Ethernet network. The cloud consists of a virtual power plant control center, which is responsible for responding to the main power grid dispatch center and making decisions to support frequency control services.
[0010] Furthermore, the step (2) comprises:
[0011] According to the maximum output power value of each controllable resource and the output power value of the scheduling plan, the regulation capacity of a single controllable resource is calculated:
[0012] (1)
[0013] in, and Respectively Moment The power of a controllable resource is adjusted upward and downward. express Moment The maximum output power of a controllable resource, express Moment The output power of the controllable resource scheduling plan, and Respectively represent the set of all controllable resources and time; in a single virtual power plant, its regulation capacity is calculated as:
[0014] (2)
[0015] in, and Respectively Moment The upward and downward aggregation regulation of the virtual power plant, and They represent the collection of all controllable resources and all virtual power plants in a single virtual power plant respectively; based on the aggregate regulation capability of a single virtual power plant, the aggregate regulation capability of all virtual power plants is calculated:
[0016] (3)
[0017] in, and Respectively The sum of the upward and downward aggregated regulation powers of all virtual power plants at the moment;
[0018] Based on the regulation capability of the virtual power plant, the virtual power plant control center The adjustment tasks undertaken at all times It can be calculated as:
[0019] (4)
[0020] in, express The regulation power required by the main power grid dispatching center at all times;
[0021] The control center allocates the regulation tasks to each virtual power plant in proportion based on their respective regulation capabilities, which can be expressed as:
[0022] (5)
[0023] in, express Moment The regulation tasks assigned to each virtual power plant;
[0024] Based on The regulation tasks assigned to the virtual power plant and path decision factor , the actual regulation task undertaken by the calculation :
[0025] (6)
[0026] (7)
[0027] in, Represents variables A function of and is the parameter of the function;
[0028] According to the central controller in the software-defined network control architecture, the topological structure and historical network characteristic information of the communication network are obtained, in which a connected undirected graph is used. Represents the network topology, where and They represent the collection of all nodes and links in the network topology respectively. The network characteristic information obtained includes delay, throughput and packet loss rate;
[0029] Based on the obtained data information, the gate recursive unit neural network model is used to predict the node network characteristics. Specifically, the network parameter matrix generated by the node characteristic information is used as the input of the gate recursive unit neural network model after minimum-maximum normalization. The main calculation process is as follows:
[0030] Model reset gate used to control the degree to which the system structure ignores previous state information Calculated as
[0031] (8)
[0032] Model update gate used to control the extent to which previous state information is moved to the current state Calculated as
[0033] (9)
[0034] According to the obtained weights, the candidate hidden states and the current hidden state The calculation formula is
[0035] (10)
[0036] (11)
[0037] Finally, the predicted output of the GRE neural network model is It can be calculated according to formula (12):
[0038] (12)
[0039] in, express function, express An input sequence of time instants, After normalization, The network node network features, represents element-wise multiplication, , , , , , , They represent the weight matrix parameters respectively, , , , denote the deviation vector parameters, is the hyperbolic tangent function;
[0040] The multi-index entropy decision is used to measure the reliability of the routing path. The main steps are as follows: Normalize each decision factor
[0041] (13)
[0042] in, Indicates network features, Indicates The influence coefficient of each network feature is and Respectively represent the number of network topology nodes and characteristic indicators;
[0043] Network characteristics The entropy value The calculation formula is:
[0044] (14)
[0045] in, For Node Network characteristics The ratio is:
[0046] (15)
[0047] Then, according to the entropy theory, we divide the network features The entropy weight is defined as ,Right now:
[0048] (16)
[0049] Finally, according to the entropy weight and normalized value, the characteristic of the routing path is calculated Path decision factors for suitability ,Right now:
[0050] (17)
[0051] Next, the central controller Sort all candidate paths and then adopt The lowest path As output decision, namely:
[0052] (18)
[0053] in, Represents a set of candidate paths.
[0054] Furthermore, the step (3) comprises:
[0055] The first-order lag function is used to characterize the active dynamic transfer characteristics of a single renewable energy source. The model is:
[0056] (19)
[0057] in, Indicates Regulating power output of renewable energy sources, and Respectively represent control signals and time constants for renewable energy sources;
[0058] Similarly, the dynamic model of a single distributed resource is
[0059] (20)
[0060] in, Indicates The regulated power output of distributed resources, and Respectively represent Control signals and time constants for each distributed resource;
[0061] The clustering-based solution is used to establish a dynamic model of virtual power plant aggregation. The main steps are as follows:
[0062] By using the maximum and minimum normalization method, the parameters of various renewable energy sources are normalized to within the range.
[0063] The Ng-Jordan-Weiss spectral clustering method is used to classify renewable energy sources into different categories based on normalization parameters.
[0064] The aggregation parameters of the virtual power plant are calculated according to the geometric center of the same group of renewable energy sources, namely:
[0065] (twenty one)
[0066] (twenty two)
[0067] in, Indicates The collection of renewable energy sources in a virtual power plant, Indicates The inertia coefficient of a virtual power plant, and Respectively represent A virtual power plant and The regulation cost coefficient of renewable energy, and Respectively represent A virtual power plant and renewable energy capacity;
[0068] Based on the above aggregation parameters, the dynamic aggregation model of the virtual power plant with renewable energy is as follows:
[0069] (twenty three)
[0070] in, Indicates A virtual power plant with renewable energy aggregates and regulates power output. Indicates The control signal of a virtual power plant with renewable energy; the aggregate dynamic model of a virtual power plant with distributed resources is as follows:
[0071] (twenty four)
[0072] in, Indicates A virtual power plant with distributed resources aggregates and regulates power output. and Respectively represent Control signals and time constants for a virtual power plant with distributed resources;
[0073] According to the above virtual power plant aggregation dynamic model, the continuous state space model of the entire system can be expressed as
[0074] (25)
[0075] in,
[0076] ,
[0077] , ,
[0078] ;
[0079] The continuous-time model (25) can be discretized as
[0080] (26)
[0081] in, , Indicates sampling time;
[0082] The connection between sensors and virtual power plants is defined as
[0083] (27)
[0084] in, For vector No. elements;
[0085] In the downlink, During the control period, the virtual power plant receives the control signal from the terminal controller. for
[0086] (28)
[0087] in, represents the attenuation gain of the downlink, is Gaussian white noise;
[0088] In the uplink, During the control period, the state estimator receives the sensor Measurements for
[0089] (29)
[0090] in, represents the attenuation gain of the uplink, is Gaussian white noise, For sensor Parameters based on specific multiple access protocols;
[0091] The terminal controller uses the observed noise Generate control signals. However, signal attenuation in the wireless communication network may cause the measured value received by the controller to be inconsistent with the actual power state. Therefore, it is considered to add a state estimation module to the controller to estimate the actual power state. x k The estimation of Precise design.
[0092] In summary, by combining formulas (26) and (28), the generalized closed-loop dynamic model of the virtual power plant is:
[0093] (30)
[0094] The power tracking control problem P1 of the virtual power plant can be described as
[0095] (31)
[0096] in, is the power tracking control strategy, To control the number of stages, is the weight factor, is the target power curve, represents a noisy observation history, is the target power dynamic characteristic, The reward function for each stage is defined as
[0097] (32)
[0098] in, and is the weight coefficient matrix;
[0099] The above problem P1 is decomposed into the following two aspects: estimation problem P2 and control problem P3, which are described as follows:
[0100] (33)
[0101] in, and is the estimated state and power control signal sequence;
[0102] (34)
[0103] in, is the feedback control gain, that is:
[0104] (35)
[0105] in, , is a solution to the following equation:
[0106] (36)
[0107] in, ,
[0108] Therefore, to solve P1, a state estimator is first designed to solve the estimation problem (P2) based on the sensor measurements, using a regularized least squares based solution to estimate the power state ,Right now:
[0109] (37)
[0110] in,
[0111] (38)
[0112] State Estimation Set ,in, is the state estimation threshold, yes The cardinality of
[0113] On this basis, by using the optimal solution obtained by solving (34) To design a controller to solve the control problem (P3), namely:
[0114] (39)
[0115] Among them, an online learning algorithm based on stochastic approximation theory is used to determine the unknown variables in formula (39) , the specific process is as follows:
[0116] Formula (36) can be expressed as ,in
[0117] (40)
[0118] (41)
[0119] According to the stochastic approximation theory, the estimated root is updated using the following formula: Come find The root is:
[0120] (42)
[0121] in, Represents a step sequence.
[0122] An electronic device comprises: a processor; a memory for storing instructions executable by the processor; wherein the processor is configured to execute the instructions to implement the joint design method of frequency control and transmission communication of a virtual power plant under cloud-edge-end collaboration.
[0123] A computer-readable storage medium having computer instructions stored thereon, which, when executed by a processor, implement the steps of the method for jointly designing frequency control and transmission communication of a virtual power plant under cloud-edge-end collaboration.
[0124] Compared with the prior art, the method for jointly designing frequency control and transmission communication of a virtual power plant based on cloud-edge-end collaboration in a hybrid communication environment provided by an embodiment of the present invention has the following beneficial effects:
[0125] (1) The cloud-edge-end collaborative virtual power plant coordinated frequency control architecture proposed in this invention can effectively tap the regulation potential of the massive power load resources on the distribution network side aggregated by the virtual power plant to support the frequency control needs of the power system.
[0126] (2) In view of the fact that the impact of hybrid communication network problems on the frequency control of virtual power plants has not been considered in current studies, this paper proposes a joint design strategy for virtual power plant power scheduling and wired communication routing optimization under cloud-edge collaboration. This strategy can not only effectively reduce the impact of wired network problems on the power scheduling of virtual power plants, but also ensure the real-time response of virtual power plants to frequency control.
[0127] (3) The present invention proposes an integrated design of dynamic power control of virtual power plants and wireless communication network performance under edge collaboration to reduce the impact of wireless network problems on power tracking control, effectively improving the accuracy of frequency control services provided by virtual power plants. BRIEF DESCRIPTION OF THE DRAWINGS
[0128] Figure 1 It is a flow chart of a method for joint design of frequency control and transmission communication of a virtual power plant under cloud-edge-end collaboration provided by an embodiment of the present invention;
[0129] Figure 2 This is a diagram of a frequency control architecture of a virtual power plant in cloud-edge-end collaboration provided by an embodiment of the present invention;
[0130] Figure 3 This is a graph showing the performance comparison of node feature prediction of different models provided by an embodiment of the present invention;
[0131] Figure 4 is a comparison result diagram of the path performance experienced by each virtual power plant under different routing methods provided in an embodiment of the present invention;
[0132] Figure 5 It is a comparison result diagram of power tracking control under different methods provided in the embodiments of the present invention. DETAILED DESCRIPTION
[0133] The present invention will be further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.
[0134] Example: Figure 1 As shown, this embodiment provides a method for jointly designing frequency control and transmission communication of a virtual power plant under cloud-edge-end collaboration, including:
[0135] (1) Build a virtual power plant frequency control architecture for cloud-edge-end collaboration, in which the wired transmission communication used by cloud-edge collaboration and the wireless transmission communication used by edge-end collaboration form a hybrid communication environment;
[0136] (2) A joint design strategy for virtual power plant power scheduling and wired communication routing optimization under cloud-edge collaboration is proposed. That is, the impact of cloud-edge communication network uncertainty on virtual power plant power scheduling is considered and the impact is overcome by designing a routing optimization strategy.
[0137] (3) An integrated design method for dynamic power control of virtual power plants and wireless communication network performance under edge collaboration is proposed. That is, the impact of cloud-edge wireless network performance on the dynamic power control of virtual power plants is considered, and this impact is overcome by developing a dynamic power control strategy for the generalized closed loop of "collection-transmission-decision-control" of information-physical collaboration of virtual power plants.
[0138] The specific steps include:
[0139] Step 1: Build a virtual power plant frequency control architecture for cloud-edge-end collaboration, in which the wired transmission communication used by cloud-edge collaboration and the wireless transmission communication used by edge-end collaboration form a hybrid communication environment. In this embodiment, Figure 2 The frequency control architecture diagram of a virtual power plant under cloud-edge collaboration is shown in the figure. The control architecture involves the terminal layer, edge layer, and cloud layer. The terminal layer consists of a virtual power plant that aggregates a large number of resources on the distribution network side, numerous sensors, and terminal controllers. The resources here include renewable energy, such as photovoltaic power generation and wind power generation, as well as flexible distributed resources (such as plug-in electric vehicles and distributed battery energy storage systems). Sensors and terminal controllers are responsible for monitoring and controlling these resources through wireless communication networks. A large number of fusion terminals are deployed in the edge layer to aggregate, analyze, and process data from the terminal side, and interact with the virtual power plant control center through a wired Ethernet network. The cloud consists of a virtual power plant control center, which is responsible for responding to the main power grid dispatch center and making decisions to support frequency control services.
[0140] Step 2: Propose a joint design strategy for virtual power plant power scheduling and wired communication routing optimization under cloud-edge collaboration, that is, considering the impact of cloud-edge communication network uncertainty on virtual power plant power scheduling, and overcoming this impact by designing a routing optimization strategy.
[0141] According to the maximum output power value of each controllable resource and the output power value of the scheduling plan, the regulation capacity of a single controllable resource is calculated:
[0142] (1)
[0143] in, and Respectively Moment The power of a controllable resource is adjusted upward and downward. express Moment The maximum output power of a controllable resource, express Moment The output power of the controllable resource scheduling plan, and Respectively represent the set of all controllable resources and moments;
[0144] In a single virtual power plant, its regulation capacity is calculated as:
[0145] (2)
[0146] in, and Respectively Moment The upward and downward aggregation regulation of the virtual power plant, and They represent the set of all controllable resources in a single virtual power plant and all virtual power plants respectively;
[0147] Based on the aggregate regulation capacity of a single virtual power plant, the aggregate regulation capacity of all virtual power plants is calculated:
[0148] (3)
[0149] in, and Respectively The sum of the upward and downward aggregated regulation powers of all virtual power plants at the moment;
[0150] Based on the regulation capability of the virtual power plant, the virtual power plant control center The adjustment tasks undertaken at all times It can be calculated as:
[0151] (4)
[0152] in, express The regulation power required by the main power grid dispatching center at all times;
[0153] The control center allocates the regulation tasks to each virtual power plant in proportion based on their respective regulation capabilities, which can be expressed as:
[0154] (5)
[0155] in, express Moment The regulation tasks assigned to each virtual power plant;
[0156] Based on The regulation tasks assigned to the virtual power plant and path decision factor , the actual regulation task undertaken by the calculation :
[0157] (6)
[0158] (7)
[0159] in, Represents variables A function of and is the parameter of the function;
[0160] According to the central controller in the software-defined network control architecture, the topological structure and historical network characteristic information of the communication network are obtained, in which a connected undirected graph is used. Represents the network topology, where and They represent the collection of all nodes and links in the network topology respectively. The network characteristic information obtained includes delay, throughput and packet loss rate;
[0161] Based on the obtained data information, the gate recursive unit neural network model is used to predict the node network characteristics. Specifically, the network parameter matrix generated by the node characteristic information is used as the input of the gate recursive unit neural network model after minimum-maximum normalization. The main calculation process is as follows:
[0162] Model reset gate used to control the degree to which the system structure ignores previous state information Calculated as
[0163] (8)
[0164] Model update gate used to control the extent to which previous state information is moved to the current state Calculated as
[0165] (9)
[0166] According to the obtained weights, the candidate hidden states and the current hidden state The calculation formula is
[0167] (10)
[0168] (11)
[0169] Finally, the predicted output of the GRE neural network model is It can be calculated according to formula (12):
[0170] (12)
[0171] in, express function, express An input sequence of time instants, After normalization, The network node network features, represents element-wise multiplication, , , , , , , They represent the weight matrix parameters respectively, , , , denote the deviation vector parameters, is the hyperbolic tangent function.
[0172] In this embodiment, the construction, training and testing of the gate recurrent unit neural network model are completed by software MATLAB. In order to verify the effectiveness of the proposed gate recurrent unit neural network model in node network feature prediction, three benchmark models of multi-layer perceptron (MLP), convolutional neural network (CNN) and long and short-term memory neural network (LSTM) are established for comparison. Figure 3 The prediction performance results of different models were compared, and the following two commonly used indicators were used to evaluate the prediction model performance: root mean square error (RMSE) and mean absolute error (MAE). Figure 3 It can be seen that the performance indicators of the proposed gated recurrent unit neural network model are better than those of other benchmark models, and it has a higher accuracy in predicting node network features.
[0173] Multi-index entropy decision-making is used to measure the reliability of routing paths. The main steps are as follows:
[0174] Normalize each decision factor
[0175] (13)
[0176] in, Indicates network features, Indicates The influence coefficient of each network feature is and Respectively represent the number of network topology nodes and characteristic indicators; network characteristics The entropy value The calculation formula is:
[0177] (14)
[0178] in, For Node Network characteristics The ratio is:
[0179] (15)
[0180] Then, according to the entropy theory, we divide the network features The entropy weight is defined as ,Right now:
[0181] (16)
[0182] Finally, according to the entropy weight and normalized value, the characteristic of the routing path is calculated Path decision factors for suitability ,Right now:
[0183] (17)
[0184] Next, the central controller Sort all candidate paths and then adopt The lowest path As output decision, namely:
[0185] (18)
[0186] in, Represents a set of candidate paths.
[0187] In this embodiment, by Figure 4 The path performance comparison results experienced by each virtual power plant in the simulation verified the effectiveness of the proposed routing optimization strategy based on adaptive prediction and multi-index decision-making. The hop-based routing method (comparison method 1) and the Dijkstra-based routing method (comparison method 2) were used to compare the proposed routing optimization strategy based on adaptive prediction and multi-index decision-making. Figure 4As shown, it can be seen that the path optimization method based on adaptive prediction and multi-index decision-making performs well in the routing path decision factors of each virtual power plant. This is mainly because these comparison methods can only select the path with the smallest number of hops or the shortest distance, and cannot apply their ability to dynamically seek the optimal path considering various network characteristics. This makes it difficult to minimize the packet loss rate while maintaining low latency, resulting in reduced applicability of the routing path. However, the proposed method can mitigate this effect by adaptively predicting node network characteristics and making routing decisions based on this information. Therefore, the simulation results can ensure that the proposed routing optimization method can effectively improve the path applicability caused by imperfect communication transmission.
[0188] Step 3: Propose an integrated design method for dynamic power control of virtual power plants and wireless communication network performance under edge collaboration, that is, consider the impact of cloud-edge wireless network performance on the dynamic power control of virtual power plants, and overcome this impact by developing a dynamic power control strategy for the generalized closed loop of "collection-transmission-decision-control" of information-physical collaboration of virtual power plants.
[0189] Step (3) specifically includes the following steps:
[0190] The first-order lag function is used to characterize the active dynamic transfer characteristics of a single renewable energy source. The model is:
[0191] (19)
[0192] in, Indicates Regulating power output of renewable energy sources, and Respectively represent The control signal and time constant of each renewable energy source; similarly, the dynamic model of a single distributed resource is
[0193] (20)
[0194] in, Indicates The regulated power output of distributed resources, and Respectively represent Control signals and time constants for each distributed resource;
[0195] The clustering-based solution is used to establish a dynamic model of virtual power plant aggregation. The main steps are as follows:
[0196] By using the maximum and minimum normalization method, the parameters of various renewable energy sources are normalized to within the range.
[0197] The Ng-Jordan-Weiss spectral clustering method is used to classify renewable energy sources into different categories based on normalization parameters.
[0198] The aggregation parameters of the virtual power plant are calculated according to the geometric center of the same group of renewable energy sources, namely:
[0199] (twenty one)
[0200] (twenty two)
[0201] in, Indicates The collection of renewable energy sources in a virtual power plant, Indicates The inertia coefficient of a virtual power plant, and Respectively represent A virtual power plant and The regulation cost coefficient of renewable energy, and Respectively represent A virtual power plant and renewable energy capacity;
[0202] Based on the above aggregation parameters, the dynamic aggregation model of the virtual power plant with renewable energy is as follows:
[0203] (twenty three)
[0204] in, Indicates A virtual power plant with renewable energy aggregates and regulates power output. Indicates The control signal of a virtual power plant with renewable energy; the aggregate dynamic model of a virtual power plant with distributed resources is as follows:
[0205] (twenty four)
[0206] in, Indicates A virtual power plant with distributed resources aggregates and regulates power output. and Respectively represent Control signals and time constants for a virtual power plant with distributed resources;
[0207] According to the above virtual power plant aggregation dynamic model, the continuous state space model of the entire system can be expressed as
[0208] (25)
[0209] in,
[0210] ,
[0211] , ,
[0212] ;
[0213] The continuous-time model (25) can be discretized as
[0214] (26)
[0215] in, , Indicates sampling time;
[0216] The connection between sensors and virtual power plants is defined as
[0217] (27)
[0218] in, For vector No. elements;
[0219] In the downlink, During the control period, the virtual power plant receives the control signal from the terminal controller. for
[0220] (28)
[0221] in, represents the attenuation gain of the downlink, is Gaussian white noise;
[0222] In the uplink, During the control period, the state estimator receives the sensor Measurements for
[0223] (29)
[0224] in, represents the attenuation gain of the uplink, is Gaussian white noise, For sensor Parameters based on specific multiple access protocols;
[0225] The terminal controller uses the observed noise Generate control signals. However, signal attenuation in the wireless communication network may cause the measured value received by the controller to be inconsistent with the actual power state. Therefore, it is considered to add a state estimation module to the controller to estimate the actual power state. x k The estimation of Precise design.
[0226] In summary, by combining formulas (26) and (28), the generalized closed-loop dynamic model of the virtual power plant is:
[0227] (30)
[0228] The power tracking control problem P1 of the virtual power plant can be described as
[0229] (31)
[0230] in, is the power tracking control strategy, To control the number of stages, is the weight factor, is the target power curve, represents a noisy observation history, is the target power dynamic characteristic, The reward function for each stage is defined as
[0231] (32)
[0232] in, and is the weight coefficient matrix;
[0233] The above problem P1 is decomposed into the following two aspects: estimation problem P2 and control problem P3, which are described as follows:
[0234] (33)
[0235] in, and is the estimated state and power control signal sequence;
[0236] (34)
[0237] in, is the feedback control gain, that is:
[0238] (35)
[0239] in, , is a solution to the following equation:
[0240] (36)
[0241] in, ,
[0242] Therefore, to solve P1, a state estimator is first designed to solve the estimation problem (P2) based on the sensor measurements, using a regularized least squares based solution to estimate the power state ,Right now:
[0243] (37)
[0244] in,
[0245] (38)
[0246] State Estimation Set ,in, is the state estimation threshold, yes The cardinality of
[0247] On this basis, by using the optimal solution obtained by solving (34) To design a controller to solve the control problem (P3), namely:
[0248] (39)
[0249] Among them, an online learning algorithm based on stochastic approximation theory is used to determine the unknown variables in formula (39) , the specific process is as follows:
[0250] Formula (36) can be expressed as ,in
[0251] (40)
[0252] (41)
[0253] According to the stochastic approximation theory, the estimated root is updated using the following formula: Come find The root is:
[0254] (42)
[0255] in, Represents a step sequence.
[0256] In this embodiment, Table 1 provides the comparison results of the frequency control performance of the virtual power plant. The comparison method is a frequency control method that allocates power in proportion without considering the influence of the communication network. In addition, the following three commonly used indicators are used to evaluate the frequency control performance: the mean absolute deviation (MAD), root mean square deviation (RMSD) and determination coefficient (DC) between the allocated automatic generation control (AGC) power and the actual AGC power.
[0257] Table 1 Comparison of performance results of different frequency control methods,
[0258]
[0259] It can be seen from Table 1 that compared with the existing methods, the MAD and RMSD of the proposed method are reduced by 81.71% and 81.63% respectively, and the DC is improved by 0.57%. This shows that the proposed method can improve the performance of responding to AGC power by adopting a routing optimization strategy to reduce the impact of the communication network on frequency control. Therefore, according to the simulation results and analysis, the effectiveness of the proposed frequency control method is verified.
[0260] In this embodiment, by Figure 5 The comparison results of power tracking control under different methods in the paper verify the effectiveness of the proposed power tracking control method based on regularized least squares method and stochastic approximation theory. t k =[6.284,5.349,2.662,5.211,4.211,3.644] T As an example, a comparative simulation is conducted using a proportional-integral-differential control method (comparison method) and the proposed power tracking control method based on regularized least squares method and stochastic approximation theory. Figure 5 As shown, it can be seen that the proposed control scheme can adjust the power output of each virtual power plant to the target state, while the output power of the comparison scheme deviates greatly from the target power state. This is mainly because the comparison scheme does not take into account the downlink wireless fading gain, which causes the power state of the virtual power plant to deviate from the target state. In contrast, the input control signal in the scheme proposed in this paper takes into account the situation of wireless damage, which greatly reduces the impact of the attenuation gain on the power tracking control, thereby improving the precise performance of the tracking control. In summary, the effectiveness of the proposed method in tracking control is verified, thereby ensuring the accuracy of the virtual power plant's response to frequency control services.
[0261] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A joint design method for frequency control and transmission communication of virtual power plants under cloud-edge-end collaboration, characterized in that: The following steps are involved: (1) Build a virtual power plant frequency control architecture that collaborates with the cloud, edge, and end, in which the wired transmission communication used by the cloud-edge collaboration and the wireless transmission communication used by the edge-end collaboration form a hybrid communication environment; (2) Design a joint design strategy for virtual power plant power scheduling and wired communication routing optimization under cloud-edge collaboration, that is, consider the impact of cloud-edge communication network uncertainty on virtual power plant power scheduling and overcome this impact by designing a routing optimization strategy; (3) Propose an integrated design method for dynamic power control of virtual power plants and wireless communication network performance under edge-to-edge collaboration. That is, consider the impact of cloud-edge wireless network performance on the dynamic power control of virtual power plants and overcome this impact by developing a dynamic power control strategy for the generalized closed loop of "collection-transmission-decision-control" of information-physical collaboration of virtual power plants. Wherein, step (2) includes the following steps: According to the maximum output power value of each controllable resource and the output power value of the scheduling plan, the regulation capacity of a single controllable resource is calculated: Among them, P i up (t) and P i dn (t) respectively represent the upward and downward adjustment power of the i-th controllable resource at time t, P i max (t) represents the maximum output power of the ith controllable resource at time t, P i dp (t) represents the output power of the i-th controllable resource scheduling plan at time t, and Respectively represent the set of all controllable resources and moments; In a single virtual power plant, its regulation capacity is calculated as: Among them, P i a_up (t) and P i a_dn (t) respectively represent the upward and downward aggregated regulation power of the i-th virtual power plant at time t, and They represent the set of all controllable resources in a single virtual power plant and all virtual power plants respectively; Based on the aggregate regulation capacity of a single virtual power plant, the aggregate regulation capacity of all virtual power plants is calculated: Among them, P up (t) and P dn (t) represents the sum of the upward and downward aggregated regulation powers of all virtual power plants at time t; Based on the regulation capability of the virtual power plant, the regulation task P undertaken by the virtual power plant control center at time t is co (t) can be calculated as: Among them, P AGC (t) represents the regulation power required by the main power grid dispatching center at time t; The control center allocates the regulation tasks to each virtual power plant in proportion based on their respective regulation capabilities, which can be expressed as: in, represents the regulation task assigned to the i-th virtual power plant at time t; Based on the regulation tasks assigned to the i-th virtual power plant and the path decision factor R i,p , the actual regulation task undertaken by the calculation Where F(·) represents the i,p A function of r and β r is the parameter of the function; According to the central controller in the software-defined network control architecture, the topological structure and historical network characteristic information of the communication network are obtained, in which a connected undirected graph is used. Represents the network topology, where and ε represent the set of all nodes and links in the network topology respectively. The obtained network characteristic information includes delay, throughput and packet loss rate; Based on the obtained data information, the gate recursive unit neural network model is used to predict the node network characteristics. Specifically, the network parameter matrix generated by the node characteristic information is used as the input of the gate recursive unit neural network model after minimum-maximum normalization. The main calculation process is as follows: A model reset gate r is used to control the degree to which the system structure ignores previous state information. t Calculated as r t =σ(W r T t +U r h t-1 +b r ) (8) Model update gate z used to control the extent to which the previous state information is moved to the current state t Calculated as z t =σ(W z T t +U z h t-1 +b z ) (9) According to the obtained weights, the candidate hidden states and the current hidden state h t The calculation formula is Finally, the predicted output y of the gate recurrent unit neural network model is t It can be calculated according to formula (12): y t =σ(W y h t +b y ) (12) Where σ represents the sigmoid function, T t =(T ij ) represents an input sequence at time t, T ij represents the jth network feature of the ith network node after normalization, ⊙ represents element-wise multiplication, W r , U r , W z , U z , W h , U h , W y Represent the weight matrix parameters, b r , b z , b h , b y They represent the deviation vector parameters respectively, and tanh is the hyperbolic tangent function; Multi-index entropy decision-making is used to measure the reliability of routing paths. The main steps are as follows: Normalize each decision factor Among them, T j represents the jth network feature, α j represents the influence coefficient of the jth network feature, N0 and M represent the number of network topology nodes and feature indicators respectively; The entropy value E of network feature j j The calculation formula is: Among them, P ij is the ratio of network feature j of node i, that is: Then, according to the entropy theory, we define the entropy weight of network feature j as γ j ,Right now: Finally, according to the entropy weight and normalized value, the path decision factor R that characterizes the suitability of the routing path p is calculated. p ,Right now: Next, the central controller calculates the p Sort all candidate paths and then use R p The lowest path p * As the output decision, that is: Where p represents the candidate path set; Wherein, step (3) includes the following steps: The first-order lag function is used to characterize the active dynamic transfer characteristics of a single renewable energy source. The model is: Where ΔP s,i represents the regulated power output of the i-th renewable energy source, Δu s,i and T s,i denote the control signal and time constant of the i-th renewable energy source respectively; Similarly, the dynamic model of a single distributed resource is Where ΔP d,i represents the regulated power output of the i-th distributed resource, Δu d,i and T d,i denote the control signal and time constant of the i-th distributed resource respectively; The clustering-based solution is used to establish a dynamic model of virtual power plant aggregation. The main steps are as follows: By using the maximum and minimum normalization method, the parameters of various renewable energy sources are normalized to the range of [0, 1]. The Ng-Jordan-Weiss spectral clustering method is used to classify renewable energy sources into different categories according to normalization parameters. The aggregation parameters of the virtual power plant are calculated according to the geometric center of the same group of renewable energy sources, namely: in, represents the set of renewable energy sources in the i-th virtual power plant, represents the inertia coefficient of the i-th virtual power plant, and α s,j They represent the regulation cost coefficients of the i-th virtual power plant and the j-th renewable energy, and S s,j denote the capacity of the i-th virtual power plant and the j-th renewable energy source respectively; Based on the above aggregation parameters, the dynamic aggregation model of the virtual power plant with renewable energy is as follows: in, represents the aggregated power output of the i-th virtual power plant containing renewable energy, represents the control signal of the i-th virtual power plant with renewable energy; the aggregate dynamic model of the virtual power plant with distributed resources is as follows: in, represents the aggregated power output of the i-th virtual power plant containing distributed resources, and denote the control signal and time constant of the i-th virtual power plant with distributed resources respectively; According to the above virtual power plant aggregation dynamic model, the continuous state space model of the entire system can be expressed as in, The continuous-time model (25) can be discretized as x k+1 =Ax k +Bu k (26) in, T p Indicates the sampling time; The connection between sensors and virtual power plants is defined as Among them, [m i ] j is the vector m i The jth element; In the downlink, the virtual power plant receives the control signal u′ from the terminal controller during the k control period k for in, represents the attenuation gain of the downlink, is Gaussian white noise; In the uplink, the state estimator receives the sensor i measurement value [z k ] i for in, represents the attenuation gain of the uplink, is Gaussian white noise, ε i,k Parameters for sensor i based on a specific multiple access protocol; The terminal controller is based on the observed noise z k =[[z k ]1,[z k ]2,...,[z k ]N S ] T Generate control signals. However, signal attenuation in the wireless communication network may cause the measured value received by the controller to be inconsistent with the actual power state. Therefore, it is considered to add a state estimation module to the controller, and then estimate the actual power state x. k The estimation of helps to control the signal u k Precise design, In summary, by combining formulas (26) and (28), the generalized closed-loop virtual power plant dynamic model is: The power tracking control problem P1 of the virtual power plant can be described as Among them, u * = {u0, u1, ...} is the power tracking control strategy, K is the number of control stages, λ∈(0, 1) is the weight factor, t k is the target power curve, represents the noisy observation history, C is the target power dynamics, J(x k , t k ,u k ) is the reward function for each stage, defined as Among them, Q and R are weight coefficient matrices; The above problem P1 is decomposed into the following two aspects: estimation problem P2 and control problem P3, which are described as follows: in, and is the estimated state and power control signal sequence; Among them, G k is the feedback control gain, that is: in, S is a solution to the following equation: in, Therefore, to solve P1, a state estimator is first designed to solve the estimation problem (P2), using a regularized least squares-based solution to estimate the power state based on the sensor measurements. Right now: in, State Estimation Set Among them, 0<δ<1 is the state estimation threshold, yes The cardinality of On this basis, by using the optimal solution obtained by solving (34) To design a controller to solve the control problem (P3), namely: Among them, an online learning algorithm based on stochastic approximation theory is used to determine the unknown variable G in formula (39): k , the specific process is as follows: Formula (36) is expressed as f(S′)=0, where According to the random approximation theory, the estimated root S′ is updated using the following formula: k To find the root of f(S′)=0, that is: Among them, μ k Represents a step sequence.
2. The method for joint design of frequency control and transmission communication of virtual power plants under cloud-edge-end collaboration according to claim 1 is characterized in that: In step (1), the control architecture constructed includes a terminal layer, an edge layer and a cloud layer. The terminal layer is composed of a virtual power plant that aggregates a large number of resources on the distribution network side, numerous sensors and terminal controllers. The resources include renewable energy, photovoltaic power generation and wind power generation, as well as flexible distributed resource sensors and terminal controllers responsible for monitoring and controlling these resources through wireless communication networks. The edge layer deploys a large number of fusion terminals to aggregate, analyze and process data from the terminal side, and interact with the virtual power plant control center through a wired Ethernet network. The cloud layer is composed of a virtual power plant control center, which is responsible for responding to the main power grid dispatching center and making decisions to support frequency control services.
3. An electronic device, characterized in that: include: processor; a memory for storing instructions executable by the processor; Wherein, the processor is configured to execute the instructions to implement the joint design method of virtual power plant frequency control and transmission communication under cloud-edge-end collaboration as described in any one of claims 1 to 2.
4. A computer-readable storage medium having computer instructions stored thereon, characterized in that: When the computer instructions are executed by the processor, the steps of the method for jointly designing frequency control and transmission communication of a virtual power plant under cloud-edge-end collaboration are implemented as described in any one of claims 1-2.