An integrated monitoring method and system based on 5G-R

Through the 5G-R network, the monitoring status evaluation value and early warning response index are calculated to realize integrated automatic monitoring and response, and the problem of lack of integrated capability of railway monitoring methods in the existing technology is solved, and the railway system is improved The monitoring accuracy and response speed have improved the level of safety management.

CN118714530BActive Publication Date: 2024-11-29TOP XINGDA
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411183538.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-29
Estimated Expiration
2044-08-27

AI Technical Summary

Technical Problem

The existing railway monitoring methods based on 5G technology lack the integrated capabilities, making it difficult to achieve comprehensive evaluation and response to the entire railway system, and cannot meet the monitoring accuracy and real-time requirements of modern high-speed and high-density railway transportation.

Method used

Through the 5G-R network, the monitoring status evaluation value and early warning response index are collected, integrated automatic monitoring and response are realized, abnormal situations are handled in a timely manner, and the safety management level of the railway system is improved.

Benefits of technology

The monitoring accuracy and response speed of the railway system have been improved, comprehensive, real-time monitoring and rapid response to the railway system have been achieved, and the safety management level of the railway system has been significantly improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118714530B_ABST
    Figure CN118714530B_ABST
Patent Text Reader

Abstract

The present invention discloses an integrated monitoring method and system based on 5G-R, the method comprising: collecting sensor data of the working state of the railway system through the 5G-R network; calculating the monitoring state evaluation value of the railway system according to the sensor data; judging the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold, and calculating the early warning response index indicating the degree of abnormality when the railway system is in an abnormal working state; performing integrated automatic monitoring and response on the railway system according to the working state of the railway system and the early warning response index, and sending the monitoring state evaluation value, the working state of the railway system and the early warning response index to the corresponding terminal of the railway system through the 5G-R network, so as to realize visual monitoring and management. By using the embodiments of the present invention, the advantages of the 5G-R network can be utilized to improve the monitoring accuracy and response speed of the railway system, and respond quickly when an abnormality occurs, thereby effectively improving the safety management level of the railway system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of 5G-R technology, and in particular to an integrated monitoring method and system based on 5G-R. Background Art

[0002] With the rapid development of the railway transportation industry, the safety and reliability of the railway system have received increasing attention. In recent years, traditional railway monitoring methods have been insufficient in terms of monitoring accuracy, real-time performance, and response speed, and are unable to meet the needs of modern high-speed and high-density railway transportation. In order to ensure the safe operation of the railway system, an efficient and real-time monitoring method is urgently needed.

[0003] The rapid development of 5G technology has provided new opportunities for railway monitoring. 5G networks have higher bandwidth, lower latency and greater connectivity, and can support data transmission and real-time communication of large-scale sensors, thereby achieving comprehensive monitoring of the railway system. However, existing monitoring methods based on 5G technology are mostly focused on a single monitoring object, lacking integrated monitoring capabilities, and making it difficult to form a comprehensive assessment and response to the entire railway system. Summary of the invention

[0004] The purpose of the present invention is to provide an integrated monitoring method and system based on 5G-R to address the deficiencies in the prior art, to utilize the advantages of the 5G-R network, to improve the monitoring accuracy and response speed of the railway system, and to respond quickly when an abnormality occurs, thereby effectively improving the safety management level of the railway system.

[0005] An embodiment of the present application provides an integrated monitoring method based on 5G-R, the method comprising:

[0006] Collect sensor data on the working status of the railway system through the 5G-R network;

[0007] Calculating a monitoring status evaluation value of the railway system based on the sensor data;

[0008] Based on the monitoring status evaluation value and the preset safety threshold, the working status of the railway system is judged, and when the railway system is in an abnormal working state, an early warning response index indicating the degree of abnormality is calculated;

[0009] According to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminals of the railway system through the 5G-R network to realize visual monitoring and management.

[0010] Optionally, the calculation formula of the monitoring status evaluation value is:

[0011] Among them, the To monitor the status evaluation value, the is the current collection value of the i-th sensor, is the average value of the historical collected values ​​of the i-th sensor, is the standard deviation of the historical collected values ​​of the i-th sensor, is the importance weight of the i-th sensor, is the nonlinear response index of the i-th sensor, is the number of sensors.

[0012] Optionally, judging the working state of the railway system based on the monitoring state evaluation value and a preset safety threshold value includes:

[0013] When the estimated value of the monitoring state is greater than a preset safety threshold, it is determined that the working state of the railway system is an abnormal state;

[0014] When the monitoring state estimated value is less than or equal to a preset safety threshold, and the difference between the preset safety threshold and the monitoring state estimated value is less than or equal to a preset difference, it is determined that the working state of the railway system is a critical abnormal state;

[0015] When the monitoring state estimated value is less than a preset safety threshold, and the difference between the preset safety threshold and the monitoring state estimated value is greater than a preset difference, it is determined that the working state of the railway system is an abnormal state.

[0016] Optionally, the calculation formula of the early warning response index is:

[0017] Among them, the is the early warning response index, is a preset safety threshold, is the critical value of the i-th sensor, indicating the maximum tolerance value of each sensor. , is the corresponding adjustment coefficient, is a nonlinear adjustment factor, is a nonlinear index used to adjust the sensitivity of the i-th sensor in early warning.

[0018] Another embodiment of the present application provides an integrated monitoring system based on 5G-R, the system comprising:

[0019] The acquisition module is used to collect sensor data on the working status of the railway system through the 5G-R network;

[0020] A calculation module, used for calculating a monitoring status evaluation value of the railway system according to the sensor data;

[0021] A judgment module, used to judge the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold, and calculate an early warning response index indicating the degree of abnormality when the railway system is in an abnormal working state;

[0022] The monitoring module is used to perform integrated automatic monitoring and response to the railway system according to the working status of the railway system and the early warning response index, and send the monitoring status evaluation value, the working status of the railway system and the early warning response index to the corresponding terminal of the railway system through the 5G-R network to realize visual monitoring and management.

[0023] Yet another embodiment of the present application provides a storage medium, wherein the storage medium stores a computer program, wherein the computer program is configured to execute any of the above methods when running.

[0024] Yet another embodiment of the present application provides an electronic device, including a memory and a processor, wherein the memory stores a computer program, and the processor is configured to run the computer program to execute any of the methods described above.

[0025] Compared with the prior art, the present invention provides an integrated monitoring method based on 5G-R, which collects sensor data of the working status of the railway system through the 5G-R network; calculates the monitoring status evaluation value of the railway system based on the sensor data; judges the working status of the railway system based on the monitoring status evaluation value and a preset safety threshold, and calculates an early warning response index representing the degree of abnormality when the railway system is in an abnormal working state; performs integrated automatic monitoring and response to the railway system according to the working status of the railway system and the early warning response index, and sends the monitoring status evaluation value, the working status of the railway system and the early warning response index to the corresponding terminal of the railway system through the 5G-R network, so as to realize visual monitoring and management, thereby being able to utilize the advantages of the 5G-R network, improve the monitoring accuracy and response speed of the railway system, and respond quickly when an abnormality occurs, thereby effectively improving the safety management level of the railway system. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 A hardware structure block diagram of a computer terminal for an integrated monitoring method based on 5G-R provided in an embodiment of the present invention;

[0027] Figure 2 A schematic diagram of a flow chart of an integrated monitoring method based on 5G-R provided in an embodiment of the present invention;

[0028] Figure 3 A schematic diagram of the structure of an integrated monitoring system based on 5G-R provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0029] The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, but should not be construed as limiting the present invention.

[0030] The embodiment of the present invention first provides an integrated monitoring method based on 5G-R, which can be applied to electronic devices such as computer terminals, specifically ordinary computers, etc.

[0031] The following describes it in detail by taking running on a computer terminal as an example. Figure 1 The hardware structure block diagram of a computer terminal of an integrated monitoring method based on 5G-R provided in an embodiment of the present invention. Figure 1 As shown, the computer terminal may include one or more ( Figure 1 Only one is shown in the figure) a processor 102 (the processor 102 may include but is not limited to a processing device such as a microprocessor MCU or a programmable logic device FPGA) and a memory 104 for storing data. Optionally, the computer terminal may also include a transmission device 106 for communication functions and an input and output device 108. It can be understood by those skilled in the art that Figure 1 The structure shown is only for illustration and does not limit the structure of the above-mentioned computer terminal. Figure 1 More or fewer components as shown, or with Figure 1 Different configurations are shown.

[0032] The memory 104 can be used to store software programs and modules of application software, such as the program instructions / modules corresponding to the integrated monitoring method based on 5G-R in the embodiment of the present application. The processor 102 executes various functional applications and data processing by running the software programs and modules stored in the memory 104, that is, implementing the above method. The memory 104 may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some instances, the memory 104 may further include a memory remotely arranged relative to the processor 102, and these remote memories can be connected to the computer terminal via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and a combination thereof.

[0033] The transmission device 106 is used to receive or send data via a network. The specific example of the above network may include a wireless network provided by a communication provider of a computer terminal. In one example, the transmission device 106 includes a network adapter (Network Interface Controller, NIC), which can be connected to other network devices through a base station so as to communicate with the Internet. In one example, the transmission device 106 can be a radio frequency (RF) module, which is used to communicate with the Internet wirelessly.

[0034] See also Figure 2 , an embodiment of the present invention provides an integrated monitoring method based on 5G-R, which may include the following steps:

[0035] S201, collecting sensor data of the working status of the railway system through the 5G-R network;

[0036] Specifically, 5G-R (fifth-generation railway dedicated communication network) technology can be used to collect data collected by various sensors in the railway system in real time. These sensors can be deployed in railway tracks, train equipment, signal systems and other related infrastructure to monitor various working status parameters, such as train speed, track status, ambient temperature, humidity, vibration intensity, etc. The high bandwidth and low latency characteristics of the 5G-R network can achieve high-speed data transmission, ensuring the effectiveness of sensor data in terms of real-time and accuracy. One implementation method may include:

[0037] Step 1: Sensor placement and network configuration

[0038] 1. According to the characteristics of the railway system, select appropriate sensor types (such as temperature sensors, acceleration sensors, pressure sensors, etc.) and install them at key locations to ensure coverage.

[0039] 2. Configure 5G-R network base stations to ensure signal coverage of each sensor and set network parameters to optimize data transmission rate and reduce latency.

[0040] Step 2: Data acquisition module development

[0041] 1. Develop a data acquisition module so that each sensor can regularly collect its own working status data and send it to the central data processing system through the 5G-R network.

[0042] 2. Set the data collection frequency to ensure that the system working status can be accurately reflected under high-frequency changes, such as collecting data once per second.

[0043] Step 3: Data encryption and transmission

[0044] 1. To ensure the security of data transmission, advanced encryption algorithms (such as AES-256) are used to encrypt sensor data.

[0045] 2. Send the encrypted data to the server via the 5G-R network to ensure the privacy and integrity of the data during transmission.

[0046] Step 4: Data preprocessing

[0047] 1. In the central data processing system, the received raw data is preprocessed, including noise removal, data format conversion, etc., to facilitate subsequent analysis.

[0048] 2. Use real-time data stream processing frameworks (such as Apache Kafka) to perform stream processing on the collected data to ensure efficient data processing.

[0049] Step 5: Data storage and visualization

[0050] 1. Store the preprocessed data in a high-performance database (such as a NoSQL database) to facilitate subsequent analysis.

[0051] 2. Develop a visual interface to display real-time data, working status evaluation values ​​and sensor status in a graphical way, so that operators can understand the actual situation of the railway system in a timely manner.

[0052] This sensor data collection method through the 5G-R network not only enhances the intelligence and automation of the railway system, but also provides effective data support for subsequent safety assessment and risk management. Through a series of unexpected technical implementation steps, it helps to give full play to the advantages of the 5G-R network and improve the operational efficiency and safety of the railway system. The significance of the role is:

[0053] 1. Real-time monitoring and feedback: The rapid response capability of 5G-R networks can be used to monitor the status of railway systems in real time, and any potential abnormalities can be captured in a timely manner, thereby reducing potential safety hazards.

[0054] 2. Data integration and analysis: The collected data can provide a basis for subsequent analysis. By integrating various sensor data, the working status of the railway system can be comprehensively evaluated and data support can be provided for subsequent decision-making.

[0055] 3. Improve operational safety: By detecting abnormal conditions at an early stage, the possibility of safety accidents can be effectively reduced, and the safety and reliability of railway transportation can be improved.

[0056] S202, calculating a monitoring status evaluation value of the railway system according to the sensor data;

[0057] In this step, the collected sensor data (such as temperature, humidity, vibration, pressure, etc.) is used to calculate a comprehensive monitoring state evaluation value (MSEV). This evaluation value can be used to reflect the overall health and efficiency of the railway system. This calculation not only takes into account the reading of a single sensor, but also integrates the historical data of each sensor, providing higher accuracy and relevance for the evaluation.

[0058] Specifically, a calculation formula for the monitoring status evaluation value can be:

[0059] Among them, the It is the monitoring status evaluation value, which is a comprehensive evaluation indicator of the overall health status of the railway system. is the current collection value of the i-th sensor, reflecting the real-time status. is the average value of the historical collected values ​​of the ith sensor, which is used to determine the deviation of the current value from the historical value. is the standard deviation of the historical data collected by the i-th sensor, reflecting the degree of fluctuation of the historical data. The larger the standard deviation, the more unstable it is. is the importance weight of the ith sensor, reflecting the degree of influence of the sensor on the overall health status. The larger the weight, the more important the sensor. The importance weight of each sensor can be determined by expert evaluation, historical data analysis, etc. For example, different weights can be assigned based on its performance in past accidents or failures. is the nonlinear response index of the ith sensor, which adjusts the sensitivity of the sensor in the overall evaluation and can be flexibly adjusted according to the test and actual situation. is the number of sensors. The significance of formula design: 1. Comprehensiveness: By weighting and processing all sensors, MSEV can comprehensively reflect the status of all aspects of the railway system, rather than being limited to a specific parameter.

[0060] 2. Standardization: Standardization in formulas This enables data from different sensors to be compared dimensionlessly, facilitating comprehensive calculations.

[0061] 3. Nonlinear response: By introducing the nonlinear response index , it is possible to adjust the influence of different sensors on the evaluation value according to the actual situation, ensuring that the evaluation value is more in line with reality.

[0062] Specifically, the calculation involves the following key aspects:

[0063] 1. Normalization: The data from each sensor will be standardized so that parameters of different nature can be compared on the same scale.

[0064] 2. Weight allocation: Different sensors need to be given different weights due to their different importance. In this way, the status of important sensors will have a more significant impact on MSEV.

[0065] 3. Nonlinear response: Different sensors may have different response strengths when facing similar state changes. The nonlinear response index is used to adjust for this difference and ensure that the evaluation value better reflects the actual situation.

[0066] Steps and their significance:

[0067] 1. System health assessment: As a comprehensive indicator of system health, MSEV can help operators quickly determine the overall working status of the railway system and provide a basis for decision-making.

[0068] 2. Anomaly detection: The calculated evaluation value can quickly identify potential abnormal conditions and take timely measures to prevent safety accidents.

[0069] 3. Resource optimization: This value can provide a basis for system optimization and resource allocation, allowing operators to prioritize the most important or urgent issues when resources are limited.

[0070] In short, the design of this evaluation formula takes into account both the diversity and uncertainty of the data and its practicality in actual applications, and can provide strong support for the safety monitoring of the railway system.

[0071] S203, judging the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold, and calculating the early warning response index indicating the degree of abnormality when the railway system is in an abnormal working state;

[0072] Specifically, when the monitoring status estimated value is greater than a preset safety threshold, the working state of the railway system is judged to be an abnormal state; when the monitoring status estimated value is less than or equal to the preset safety threshold, and the difference between the preset safety threshold and the monitoring status estimated value is less than or equal to the preset difference, the working state of the railway system is judged to be a critical abnormal state; when the monitoring status estimated value is less than the preset safety threshold, and the difference between the preset safety threshold and the monitoring status estimated value is greater than the preset difference, the working state of the railway system is judged to be an abnormal state.

[0073] Step 1: Determine the working status

[0074] According to the comparison between MSEV and the preset safety threshold T_S, the working status of the railway system is judged as normal, critical abnormal or abnormal. This judgment mechanism can reflect the health status of the system in real time and help to take timely measures to reduce potential risks.

[0075] Step 2: Determine abnormal status

[0076] Further refine the judgment and make clear classifications based on the specific values ​​of MSEV and the preset differentials to ensure that risks are identified and dealt with in a timely manner, thus preventing small problems from developing into major accidents.

[0077] In the above steps, the calculated monitoring state evaluation value (MSEV) is first compared with the pre-set safety threshold (T_S) to determine the working state of the railway system. Specifically, it can be divided into the following judgment situations: 1. Normal state: If MSEV is less than or equal to T_S and the difference is greater than the preset difference, the system is considered to be in a normal state.

[0078] 2. Critical abnormal state: If MSEV is less than or equal to T_S, but the difference is within the set preset difference range, the system is in a critical abnormal state, which means that attention is required, but it has not yet reached a dangerous level.

[0079] 3. Abnormal state: If MSEV is greater than T_S, or MSEV is less than T_S and the difference is greater than the preset difference, the system is in an abnormal working state.

[0080] After confirming that the railway system is in an abnormal or critical abnormal working state, the Warning Response Index (WRI) will be calculated to quantify the degree of abnormality and guide subsequent monitoring and response measures. The WRI provides an intuitive value that can be used to assess the severity of the abnormality and guide subsequent monitoring and response actions.

[0081] Specifically, a calculation formula for the early warning response index can be:

[0082] Among them, the It is an early warning response index, which quantifies the current abnormality of the railway system. It is a preset safety threshold that defines the upper limit of the normal operation of the system. is the critical value of the i-th sensor, indicating the maximum tolerance value of each sensor, which is used to determine whether the parameter exceeds the safety range. The working limit of each sensor can be determined according to the technical specifications and actual application of each sensor to ensure the effectiveness of its monitoring. , are the corresponding adjustment coefficients, which respectively reflect the contribution of MSEV and each sensor data to the warning index. Appropriate coefficient values ​​can be set through system historical data and accident case analysis so that WRI can accurately reflect the abnormality of the system. It is a nonlinear adjustment factor that enhances the effect of MSEV on WRI, making the response more sensitive under abnormal conditions. is a nonlinear index used to adjust the sensitivity of the i-th sensor in the early warning, ensuring that the more important sensors have a more significant impact on the early warning. To achieve the best early warning effect and ensure good prediction capabilities in different situations. The design significance is:

[0083] 1. Comprehensiveness: This formula combines the monitoring status evaluation value with the real-time data of each sensor, and can comprehensively reflect the degree of abnormality of the railway system.

[0084] 2. Flexibility: Parameters The introduction of allows the formula to be flexibly adjusted according to actual conditions to adapt to different types of railway systems and environments.

[0085] 3. Nonlinear response: The nonlinear characteristics in the formula make the response to anomalies more sensitive and can detect potential problems at an early stage.

[0086] Function and significance:

[0087] 1. Real-time monitoring and feedback: By comparing the monitoring status assessment value with the safety threshold, the abnormal status of the railway system can be quickly identified and real-time feedback can be provided for subsequent processing.

[0088] 2. Decision support: After determining the working status, it can provide managers with clear decision-making basis so that they can take appropriate measures to ensure safety.

[0089] 3. Risk warning: By calculating the Warning Response Index (WRI), it is possible to quantify and evaluate the current degree of abnormality and provide effective warning of potential risks.

[0090] S204: According to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminal of the railway system through the 5G-R network to realize visual monitoring and management.

[0091] In this step, the system first conducts a comprehensive assessment of the railway system based on the monitoring state evaluation value (MSEV) and the warning response index (WRI). Specifically, the system uses the sensor data collected in real time through the 5G-R network, combined with the working status determined in the previous step, to implement automated monitoring and response. This monitoring and response process is a closed-loop system designed to ensure safe and stable operation of the railway and provide timely information feedback to operation and maintenance personnel.

[0092] - Integrated automatic monitoring: The system will continuously monitor the working status of the railway. After receiving new sensor data, it will recalculate MSEV and WRI to update the system status in real time and automatically execute necessary monitoring measures according to the preset safety thresholds and response strategies. This integrated monitoring method can identify potential risks in a timely manner and ensure the safety of the railway system.

[0093] - Response mechanism: When the working status is abnormal or the early warning response index exceeds the set range, the system can automatically trigger the corresponding response measures. For example, adjust the train speed, issue an alarm, automatically adjust the signal system, etc. to reduce or eliminate potential risks. At the same time, the system can also transmit the execution of these response measures to the relevant monitoring center in real time through the 5G-R network.

[0094] - Visual monitoring management: By sending the monitoring status evaluation value, working status and early warning response index to the corresponding terminal of the railway system, relevant personnel can see the operating status of the railway system in real time on the visual interface. This kind of visual management can help monitoring personnel quickly understand the current situation and make corresponding decisions. The significance of the role is:

[0095] 1. Improve safety: Integrated automatic monitoring can ensure that the railway system responds quickly to potential risks, avoid accidents and enhance safety.

[0096] 2. Real-time feedback and adjustment: By quickly acquiring and analyzing monitoring data, management decisions and adjustments can be made in a timely manner to optimize resource allocation and improve system efficiency.

[0097] 3. Reduced human intervention: Automatic monitoring and response mechanisms reduce reliance on manual operations, reduce the risk of human error, and improve response speed.

[0098] 4. Data-driven decision support: Visual monitoring not only provides real-time data support for operators, but also provides a basis for subsequent decision-making and planning, helping managers optimize operational strategies.

[0099] Through the above steps, automatic monitoring and response of the railway system can be effectively achieved to ensure the safe and efficient operation of the system.

[0100] It can be seen that sensor data of the working status of the railway system is collected through the 5G-R network; based on the sensor data, the monitoring status evaluation value of the railway system is calculated; based on the monitoring status evaluation value and the preset safety threshold, the working status of the railway system is judged, and when the railway system is in an abnormal working state, the early warning response index representing the degree of abnormality is calculated; according to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminals of the railway system through the 5G-R network to realize visual monitoring and management, so as to take advantage of the 5G-R network, improve the monitoring accuracy and response speed of the railway system, and respond quickly when an abnormality occurs, thereby effectively improving the safety management level of the railway system.

[0101] Another embodiment of the present invention provides an integrated monitoring system based on 5G-R, see Figure 3 , the system may include:

[0102] A collection module 301 is used to collect sensor data of the working status of the railway system through the 5G-R network;

[0103] A calculation module 302, used to calculate a monitoring status evaluation value of the railway system according to the sensor data;

[0104] A judgment module 303 is used to judge the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold, and calculate an early warning response index indicating the degree of abnormality when the railway system is in an abnormal working state;

[0105] The monitoring module 304 is used to perform integrated automatic monitoring and response to the railway system according to the working status of the railway system and the early warning response index, and send the monitoring status evaluation value, the working status of the railway system and the early warning response index to the corresponding terminal of the railway system through the 5G-R network to realize visual monitoring and management.

[0106] It can be seen that sensor data of the working status of the railway system is collected through the 5G-R network; based on the sensor data, the monitoring status evaluation value of the railway system is calculated; based on the monitoring status evaluation value and the preset safety threshold, the working status of the railway system is judged, and when the railway system is in an abnormal working state, the early warning response index representing the degree of abnormality is calculated; according to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminals of the railway system through the 5G-R network to realize visual monitoring and management, so as to take advantage of the 5G-R network, improve the monitoring accuracy and response speed of the railway system, and respond quickly when an abnormality occurs, thereby effectively improving the safety management level of the railway system.

[0107] An embodiment of the present invention further provides a storage medium, in which a computer program is stored, wherein the computer program is configured to execute the steps of any of the above method embodiments when running.

[0108] Specifically, in this embodiment, the above storage medium may be configured to store a computer program for performing the following steps:

[0109] S201, collecting sensor data of the working status of the railway system through the 5G-R network;

[0110] S202, calculating a monitoring status evaluation value of the railway system according to the sensor data;

[0111] S203, judging the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold, and calculating the early warning response index indicating the degree of abnormality when the railway system is in an abnormal working state;

[0112] S204: According to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminal of the railway system through the 5G-R network to realize visual monitoring and management.

[0113] It can be seen that sensor data of the working status of the railway system is collected through the 5G-R network; based on the sensor data, the monitoring status evaluation value of the railway system is calculated; based on the monitoring status evaluation value and the preset safety threshold, the working status of the railway system is judged, and when the railway system is in an abnormal working state, the early warning response index representing the degree of abnormality is calculated; according to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminals of the railway system through the 5G-R network to realize visual monitoring and management, so as to take advantage of the 5G-R network, improve the monitoring accuracy and response speed of the railway system, and respond quickly when an abnormality occurs, thereby effectively improving the safety management level of the railway system.

[0114] An embodiment of the present invention further provides an electronic device, including a memory and a processor, wherein the memory stores a computer program, and the processor is configured to run the computer program to execute the steps in any one of the above method embodiments.

[0115] Specifically, the electronic device may further include a transmission device and an input / output device, wherein the transmission device is connected to the processor, and the input / output device is connected to the processor.

[0116] Specifically, in this embodiment, the processor may be configured to perform the following steps through a computer program:

[0117] S201, collecting sensor data of the working status of the railway system through the 5G-R network;

[0118] S202, calculating a monitoring status evaluation value of the railway system according to the sensor data;

[0119] S203, judging the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold, and calculating the early warning response index indicating the degree of abnormality when the railway system is in an abnormal working state;

[0120] S204: According to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminal of the railway system through the 5G-R network to realize visual monitoring and management.

[0121] It can be seen that sensor data of the working status of the railway system is collected through the 5G-R network; based on the sensor data, the monitoring status evaluation value of the railway system is calculated; based on the monitoring status evaluation value and the preset safety threshold, the working status of the railway system is judged, and when the railway system is in an abnormal working state, the early warning response index representing the degree of abnormality is calculated; according to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminals of the railway system through the 5G-R network to realize visual monitoring and management, so as to take advantage of the 5G-R network, improve the monitoring accuracy and response speed of the railway system, and respond quickly when an abnormality occurs, thereby effectively improving the safety management level of the railway system.

[0122] The above describes in detail the structure, features and effects of the present invention based on the embodiments shown in the drawings. The above is only a preferred embodiment of the present invention, but the present invention is not limited to the scope of implementation shown in the drawings. Any changes made according to the concept of the present invention, or modifications to equivalent embodiments with equivalent changes, which still do not exceed the spirit covered by the description and drawings, should be within the protection scope of the present invention.

Claims

1. An integrated monitoring method based on 5G-R, characterized in that: The method comprises: Collect sensor data on the working status of the railway system through the 5G-R network; Calculating a monitoring status evaluation value of the railway system based on the sensor data; Based on the monitoring status evaluation value and the preset safety threshold, the working status of the railway system is judged, and when the railway system is in an abnormal working state, an early warning response index indicating the degree of abnormality is calculated; According to the working status of the railway system and the early warning response index, the railway system is automatically monitored and responded to in an integrated manner, and the monitoring status evaluation value, the working status of the railway system and the early warning response index are sent to the corresponding terminal of the railway system through the 5G-R network to realize visual monitoring and management; The calculation formula of the monitoring status evaluation value is: Among them, the To monitor the status evaluation value, the is the current collection value of the i-th sensor, is the average value of the historical collected values ​​of the i-th sensor, is the standard deviation of the historical collected values ​​of the i-th sensor, is the importance weight of the i-th sensor, is the nonlinear response index of the i-th sensor, is the number of sensors; The calculation formula of the early warning response index is: Among them, the is the early warning response index, is a preset safety threshold, is the critical value of the i-th sensor, indicating the maximum tolerance value of each sensor. , is the corresponding adjustment coefficient, is a nonlinear adjustment factor, is a nonlinear index used to adjust the sensitivity of the i-th sensor in early warning.

2. The method according to claim 1, characterized in that The determining the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold value includes: When the monitoring status evaluation value is greater than a preset safety threshold, it is determined that the working state of the railway system is an abnormal state; When the monitoring state evaluation value is less than or equal to a preset safety threshold, and the difference between the preset safety threshold and the monitoring state evaluation value is less than or equal to a preset difference, it is determined that the working state of the railway system is a critical abnormal state; When the monitoring status evaluation value is less than a preset safety threshold, and the difference between the preset safety threshold and the monitoring status evaluation value is greater than a preset difference, it is determined that the working state of the railway system is an abnormal state.

3. An integrated monitoring system based on 5G-R, characterized in that: The system comprises: The acquisition module is used to collect sensor data on the working status of the railway system through the 5G-R network; A calculation module, used for calculating a monitoring status evaluation value of the railway system according to the sensor data; A judgment module, used to judge the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold, and calculate an early warning response index indicating the degree of abnormality when the railway system is in an abnormal working state; A monitoring module is used to perform integrated automatic monitoring and response of the railway system according to the working status of the railway system and the early warning response index, and send the monitoring status evaluation value, the working status of the railway system and the early warning response index to the corresponding terminal of the railway system through the 5G-R network to realize visual monitoring and management; The calculation formula of the monitoring status evaluation value is: Among them, the To monitor the status evaluation value, the is the current collection value of the i-th sensor, is the average value of the historical collected values ​​of the i-th sensor, is the standard deviation of the historical collected values ​​of the i-th sensor, is the importance weight of the i-th sensor, is the nonlinear response index of the i-th sensor, is the number of sensors; The calculation formula of the early warning response index is: Among them, the is the early warning response index, is a preset safety threshold, is the critical value of the i-th sensor, indicating the maximum tolerance value of each sensor. , is the corresponding adjustment coefficient, is a nonlinear adjustment factor, is a nonlinear index used to adjust the sensitivity of the i-th sensor in early warning.

4. The system according to claim 3, characterized in that The determining the working state of the railway system based on the monitoring state evaluation value and the preset safety threshold value includes: When the monitoring status evaluation value is greater than a preset safety threshold, it is determined that the working state of the railway system is an abnormal state; When the monitoring state evaluation value is less than or equal to a preset safety threshold, and the difference between the preset safety threshold and the monitoring state evaluation value is less than or equal to a preset difference, it is determined that the working state of the railway system is a critical abnormal state; When the monitoring status evaluation value is less than a preset safety threshold, and the difference between the preset safety threshold and the monitoring status evaluation value is greater than a preset difference, it is determined that the working state of the railway system is an abnormal state.

5. A storage medium, characterized in that: The storage medium stores a computer program, wherein the computer program is configured to execute the method according to any one of claims 1 to 2 when executed.

6. An electronic device comprising a memory and a processor, characterized in that: A computer program is stored in the memory, and the processor is configured to run the computer program to perform the method according to any one of claims 1 to 2.

Citation Information

Patent Citations

  • High-accuracy remote dam safety monitoring system

    CN106790604A

  • Energy storage safety pre-warning system of smart power grid

    CN113205190A

  • Equipment damage assessment method and system for power transmission and transformation multi-source three-dimensional collaborative dynamic monitoring

    CN117664217A

  • Steel frame structure collapse early warning method and system based on composite parameters

    CN118364545A

  • Distributed photovoltaic cluster coordination optimization control method

    CN118432175A