Rubber preparation process

Through the layered molding process and heat treatment, the gap problem caused by untimely supply of raw materials in rubber preparation is solved, the rubber tube is fully formed and produced with good quality, and the processing quality and convenience are improved.

CN118721663AInactive Publication Date: 2024-10-01李秀华
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411054574.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the rubber preparation process, untimely supply of raw materials during primary molding can easily lead to gaps in the rubber tube and affect the processing quality.

Method used

The layered molding process is used to combine the mixing box and the forming tube, and use parts such as push rods, spiral blades and supplementary tubes to add and push the materials in stages to ensure the full forming of the rubber tube, and prevent the material from solidifying through the heating frame. Achieve continuous molding of rubber tubes.

Benefits of technology

It effectively prevents the gap problem caused by untimely supply of raw materials during primary molding, ensures the quality of the rubber tube, and improves the convenience and quality of molding.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118721663A_ABST
    Figure CN118721663A_ABST
Patent Text Reader

Abstract

The invention relates to the field of rubber preparation, in particular to a rubber preparation process. Comprising a material mixing box and a forming pipe fixedly connected to the lower portion of the material mixing box, an expansion pipe is fixedly connected to the discharging end of the forming pipe, an end frame is fixedly connected to the other end of the forming pipe, a supplementing pipe is fixedly connected to the material mixing box and the expansion pipe, a material pushing rod is rotationally connected to the end frame, and an inner expansion pipe corresponding to the expansion pipe is fixedly connected to the material pushing rod. And a plurality of spiral blades I are fixedly connected to the material pushing rod. The process comprises the following steps: 1, adding materials into a material mixing box, mixing and melting into a fluid; 2, pushing the material to form a rubber tube, and cooling the rubber tube; and thirdly, materials are added to the outer wall of the rubber sleeve which is being cooled, and forming of the rubber pipe is further achieved. Rubber pipes can be formed in a layered mode, and the situation that rubber processing is poor due to the fact that material supply is not pushed in time during one-time forming is prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of rubber preparation, and more particularly to a rubber preparation process. Background Art

[0002] Rubber refers to a highly elastic polymer material with reversible deformation. It is elastic at room temperature, can produce large deformation under very small external force, and can return to its original shape after the external force is removed. Rubber products are widely used in various aspects of industry or life. When preparing rubber, the rubber raw material is usually melted into a fluid, and then the material is extruded into various shapes such as sheets, tubes, and rods at one time. The rubber is then processed again according to subsequent needs. However, in the current rubber preparation process, during the process of forming the rubber tube at one time, it is easy for the formed rubber tube to have gaps due to untimely supply of raw materials. Summary of the invention

[0003] In order to improve the deficiencies of the prior art, the present invention provides a rubber preparation process, which can form rubber tubes in layers, thereby preventing the occurrence of poor rubber processing caused by untimely material supply during one-time molding.

[0004] The technical solution adopted by the present invention to solve its technical problem is:

[0005] A rubber preparation device comprises a mixing box and a forming tube fixedly connected to the lower part of the mixing box, an expansion tube is fixedly connected to the discharge end of the forming tube, an end frame is fixedly connected to the other end of the forming tube, a supplementary tube is fixedly connected to the mixing box and the expansion tube, a push rod is rotatably connected to the end frame, an inner expansion tube corresponding to the expansion tube is fixedly connected to the push rod, and a plurality of spiral blades I are fixedly connected to the push rod.

[0006] Furthermore, a push plate is slidably connected to the push rod, two racks are fixedly connected to the push plate, and an end wheel for driving the two racks to slide is rotatably connected to the end frame.

[0007] Furthermore, a heating frame I is fixedly connected to the lower part of the mixing box, a heating frame II is fixedly connected to the lower part of the heating frame I, and the heating frame II is sleeved on the forming tube.

[0008] Furthermore, the mixing box is provided with a top cover, and a pushing rack for pushing the material to move is rotatably connected to the top cover.

[0009] Further, according to the above-mentioned process for preparing rubber by a rubber preparation device, the process comprises the following steps:

[0010] Step 1: Add the materials into the mixing box to mix and melt into a fluid;

[0011] Step 2: Push the material to form a rubber tube and cool it;

[0012] Step 3: Add material to the outer wall of the rubber sleeve that is being cooled to further form the rubber tube.

[0013] The beneficial effects of the rubber preparation process of the present invention are as follows: the rubber tube can be formed in layers, thereby preventing the poor rubber processing caused by the untimely supply of pushing materials during the one-time forming; by heating the material for pushing the material to be extruded and formed, the solidification of the material is prevented from affecting the continuous forming of the rubber tube; and the rubber tube can also be fully formed by reciprocatingly pushing the material. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The present invention is further described in detail below with reference to the accompanying drawings and specific implementation methods.

[0015] Figure 1 It is a schematic diagram of the structure of the rubber preparation device;

[0016] Figure 2 It is a partial cross-sectional view of a rubber preparation device;

[0017] Figure 3 It is a schematic diagram of the structure for loading materials;

[0018] Figure 4 A schematic diagram of the structure for promoting material extrusion;

[0019] Figure 5 A schematic diagram of the structure for promoting material extrusion;

[0020] Figure 6 for Figure 5 A partial enlarged view of the structure shown;

[0021] Figure 7 It is a structural schematic diagram of heating materials;

[0022] Figure 8 A schematic diagram of the structure to promote the movement of materials;

[0023] Fig. 9 A schematic diagram of the structure for promoting the extrusion of materials in the supplementary pipe;

[0024] Fig.10 Schematic diagram of the structure for regulating the pressure in the supplementary pipe.

[0025] In the figure: mixing box 11; forming tube 12; expansion tube 13; supplementary tube 14; pressurizing tube 15; end frame 16; push rod 21; spiral blade Ⅰ22; inner expansion tube 23; push plate 31; rack 32; end wheel 33; heating frame Ⅰ41; heating frame Ⅱ42; top cover 51; push rack 52; mounting table 53; feeding hole 54; cylinder Ⅰ61; push block 62; pressurizing block 71; cylinder Ⅱ72. DETAILED DESCRIPTION

[0026] refer to Figure 1, 2 , 3, 4, 9 and 10, detailed description of the embodiments of pushing the material into shape:

[0027] A rubber preparation device comprises a mixing box 11 and a molding tube 12 fixedly connected to the lower part of the mixing box 11. The mixing box 11 is used to mix raw materials for preparing rubber, and can heat the raw materials at the lower part of the mixing box 11 to fully melt the materials. The melted materials in the mixing box 11 fall into the molding tube 12 at the lower end for molding. The discharging end of the molding tube 12 is fixedly connected to an expansion tube 13, and the other end of the molding tube 12 is fixedly connected to an end frame 16. A supplementary tube 14 is fixedly connected to the mixing box 11 and the expansion tube 13. A push rod 21 is rotatably connected to the end frame 16, and a push rod 21 is fixedly connected to the push rod 21. The inner expansion tube 23 corresponding to the expansion tube 13 has a plurality of spiral blades Ⅰ22 fixedly connected to the push rod 21. The push rod 21 is fixedly connected to the output shaft of the reduction motor Ⅰ. The reduction motor Ⅰ is fixedly connected to the end frame 16. When the reduction motor Ⅰ is started, the reduction motor Ⅰ drives the push rod 21 to rotate. The push rod 21 drives the plurality of spiral blades Ⅰ22 to rotate. The rotating plurality of spiral blades Ⅰ22 push the material falling into the forming tube 12 to be squeezed out from the discharge end, and the rubber tube is formed through the gap between the expansion tube 13 and the inner expansion tube 23. As the rubber tube is initially cooled and formed, the discharge end of the supplementary tube 14 tilts downward. The material in the mixing box 11 flows out from the replenishing pipe 14 and covers the outer wall of the molded rubber tube for secondary molding. The rubber tube molded by multiple cooling can form a partition between the outer wall of the initially molded rubber tube and the secondary cooled rubber tube. The two moldings can prevent gaps caused by insufficient materials in the first molding. The quality of rubber products prepared from rubber raw materials is ensured by adding materials in batches. After use, the rubber tube molded in multiple times can be destroyed layer by layer when it needs to be peeled off, thereby increasing the convenience of peeling off the rubber tube.

[0028] refer to Figure 1 , 2 , 3, 5 and 6, detailed description of the embodiment of pushing the material in the forming tube 12 into shape:

[0029] The push rod 21 is slidably connected with a push plate 31, and two racks 32 are fixedly connected to the push plate 31. An end wheel 33 driving the two racks 32 to slide is rotatably connected to the end frame 16. Each end wheel 33 is fixedly connected to the output shaft of the corresponding reduction motor II, and the reduction motor II is fixedly connected to the end frame 16. The two reduction motors II are started, and the two reduction motors II drive the two end wheels 33 to rotate. The two end wheels 33 engage and drive the two racks 32 to slide, and the two racks 32 drive the push plate 31 to slide reciprocatingly. The outer diameter of the push plate 31 coincides with the inner wall diameter of the forming tube 12, and the material in the forming tube 12 can be pushed to be extruded and molded from the discharge end when the push plate 31 slides reciprocatingly to perform cooling and molding of the rubber tube. The rubber can be continuously molded by pulling the molded rubber tube, and the reciprocating sliding of the push plate 31 can ensure that there is enough material in the molded rubber tube.

[0030] refer to Figure 1 and 7 , an embodiment of heating the materials in the mixing box 11 and the forming tube 12 is described in detail:

[0031] A heating frame I41 is fixedly connected to the lower part of the mixing box 11, and a heating frame II42 is fixedly connected to the lower part of the heating frame I41. The heating frame II42 is sleeved on the forming tube 12, and the heating frame I41 and the heating frame II42 are connected. Two connecting pipes are arranged on the heating frame I41 and the heating frame II42, which are connected with an external heating device through the two connecting pipes, so that the circulation supply of high-temperature steam in the heating frame I41 and the heating frame II42 is realized through the heating device, so that the heating frame I41 heats the material in the mixing box 11, and the heating frame II42 can prevent the material in the forming tube 12 from cooling and solidifying, which affects the continuous forming of the material in the forming tube 12.

[0032] refer to Figure 1 , 2 8, detailed description of the embodiment of promoting the mixing of materials in the mixing box 11:

[0033] The mixing box 11 is fixedly connected with a top cover 51, and a pusher 52 for pushing the material is rotatably connected to the top cover 51. The pusher 52 is fixedly connected to the output shaft of the reduction motor III, and the reduction motor III is fixedly connected to the top cover 51. When the reduction motor III is started, the reduction motor III drives the pusher 52 to rotate, and the pusher 52 pushes the material in the mixing box 11 to move. The pusher 52 is provided with a plurality of spiral blades II, and the pusher 52 can rotate forward and reverse around its own axis. Thus, the material can be fully mixed.

[0034] refer to Figure 1 , 2 9, detailed description of the embodiment of pushing the material in the mixing box 11 from the supplementary pipe 14 to the expansion pipe 13 for secondary molding of the rubber tube:

[0035] The top cover 51 is provided with a mounting platform 53 which is coaxial with the replenishing pipe 14, and a cylinder Ⅰ 61 is fixedly connected to the mounting platform 53, and a push block 62 which has the same diameter as the inner wall of the replenishing pipe 14 is fixedly connected to the cylinder rod of the cylinder Ⅰ 61. When the cylinder Ⅰ 61 is started, the cylinder rod of the cylinder Ⅰ 61 drives the push block 62 to slide. When the push block 62 slides into the replenishing pipe 14, the replenishing pipe 14 can be blocked to prevent the material in the mixing box 11 from flowing out of the replenishing pipe 14. When the push block 62 is separated from the replenishing pipe 14, it can ensure that the material in the mixing box 11 flows into the replenishing pipe 14, and the reciprocating sliding of the push block 62 pushes the material to flow out of the replenishing pipe 14 to realize the secondary molding of the rubber tube.

[0036] refer to Figure 1 , 2 10, detailed description of the embodiment of pressurizing the space in the replenishing pipe 14 to ensure that the material in the replenishing pipe 14 is pushed out:

[0037] The replenishing pipe 14 is fixedly connected with a pressurizing pipe 15, and a pressurizing block 71 is slidably connected inside the pressurizing pipe 15. The end of the pressurizing pipe 15 is fixedly connected with a cylinder II 72 which drives the pressurizing block 71 to slide back and forth. When cylinder II 72 is started, the cylinder rod of cylinder II 72 drives the pressurizing block 71 to slide back and forth, thereby changing the space inside the replenishing pipe 14 and the pressurizing pipe 15, thereby realizing the adjustment of the pressure inside the replenishing pipe 14, and then ensuring that the material in the replenishing pipe 14 is fully extruded, and realizing the full molding of the rubber pipe.

[0038] refer to Fig.10 , an embodiment of adding materials into the mixing box 11 is described in detail:

[0039] The top cover 51 is provided with a feeding hole 54 , so that materials can be added into the mixing box 11 through the feeding hole 54 , thereby ensuring that the materials are fully heated.

[0040] refer to Figure 1 and 2 , an embodiment of rubber preparation is described in detail:

[0041] According to the above-mentioned process for preparing rubber by a rubber preparation device, the process comprises the following steps:

[0042] Step 1: Add materials into the mixing box 11 to mix and melt into a fluid;

[0043] Step 2: Push the material to form a rubber tube and cool it, and preliminarily prepare the rubber tube for forming;

[0044] Step 3: Add materials to the outer wall of the rubber sleeve that is being cooled to further realize the molding of the rubber tube, and then realize secondary molding. At the same time, the cooled and molded rubber tube is pulled by external force for transportation, thereby realizing continuous preparation of rubber.

Claims

1. A rubber preparation device, characterized in that: The invention comprises a mixing box (11) and a forming tube (12) fixedly connected to the lower part of the mixing box (11); the discharge end of the forming tube (12) is fixedly connected to an expansion tube (13); the other end of the forming tube (12) is fixedly connected to an end frame (16); a supplementary tube (14) is fixedly connected to the mixing box (11) and the expansion tube (13); a push rod (21) is rotatably connected to the end frame (16); an inner expansion tube (23) corresponding to the expansion tube (13) is fixedly connected to the push rod (21); and a plurality of spiral blades I (22) are fixedly connected to the push rod (21).

2. A rubber preparation device according to claim 1, characterized in that: The push rod (21) is slidably connected with a push plate (31), two racks (32) are fixedly connected to the push plate (31), and an end wheel (33) for driving the two racks (32) to slide is rotatably connected to the end frame (16).

3. A rubber preparation device according to claim 1), characterized in that: A heating frame I (41) is fixedly connected to the lower part of the mixing box (11), a heating frame II (42) is fixedly connected to the lower part of the heating frame I (41), and the heating frame II (42) is sleeved on the forming tube (12).

4. A rubber preparation device according to claim 1, characterized in that: The mixing box (11) is provided with a top cover (51), and a pushing frame (52) for pushing the material to move is rotatably connected to the top cover (51).

5. A rubber preparation device according to claim 4, characterized in that: The top cover (51) is provided with a mounting platform (53) coaxial with the replenishing pipe (14), the mounting platform (53) is provided with a cylinder I (61), and a push block (62) having the same diameter as the inner wall of the replenishing pipe (14) is fixedly connected to the cylinder rod of the cylinder I (61).

6. A rubber preparation device according to claim 5, characterized in that: The replenishing pipe (14) is fixedly connected with a pressurizing pipe (15), a pressurizing block (71) is slidably connected inside the pressurizing pipe (15), and a cylinder II (72) is fixedly connected to the end of the pressurizing pipe (15) for driving the pressurizing block (71) to slide back and forth.

7. A rubber preparation device according to claim 4, characterized in that: The top cover (51) is provided with a material adding hole (54).

8. A rubber preparation device according to claim 4, characterized in that: The pusher rack (52) is provided with a plurality of spiral blades II, and the pusher rack (52) can rotate forward and reverse around its own axis.

9. The rubber preparation device according to claim 1, characterized in that: The discharge end of the replenishing pipe (14) is inclined downward.

10. A process for preparing rubber using a rubber preparation device according to any one of claims 1 to 9, characterized in that: The process includes the following steps: Step 1: adding materials into a mixing box (11) to mix and melt into a fluid; Step 2: Push the material to form a rubber tube and cool it; Step 3: Add material to the outer wall of the rubber sleeve that is being cooled to further form the rubber tube.