Power grid enterprise engineering project material guarantee cooperation system
By designing an engineering project material support coordination system in a power grid enterprise, the problem of insufficient digital coverage and insufficient data interaction in power grid material supply chain management has been solved. It has achieved efficient management of project managers and monitoring and early warning of supply chain links, and improved the quality of materials. Supply chain management efficiency and risk insight capabilities.
Patent Information
- Application Number
- CN202310349053.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The management of power grid material supply chain suffers from insufficient digital coverage, low accuracy, and insufficient data interaction, which results in the inability to apply data resources conveniently and efficiently, and lacks strong support for project managers to manage all business aspects of the supply chain.
Design a material support coordination system for power grid enterprise engineering projects, including a template building module, a data association module, a query module, an operation reminder module and a to-do module. The project template is built through the template, associated with the material database, and provides progress reminders, material reminders and Early warning function improves the management capabilities of project managers.
Making full use of material big data for project management improves the management efficiency of project managers and the monitoring and early warning capabilities of key links in the supply chain, improves the visibility of the supply chain workflow from a project perspective, and ensures the analysis and risk warning of material supply guarantees.
Smart Images

Figure CN118735147A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power grid material supply chain management, and in particular to a power grid enterprise engineering project material support coordination system. Background Art
[0002] From the current situation of power grid material supply chain management, there are many types of projects and materials, and the material demand is complicated. At the same time, the "digitalization" coverage of the entire power grid supply chain is insufficient, the accuracy needs to be improved, the internal and external data interaction of the business is insufficient, and there is a lack of strategic integration and coordination. The existing data management model has the following defects: first, the huge data resources have not been used conveniently and efficiently; second, the value of data assets has not been fully explored and utilized, and there is a lack of strong support for the project manager's management capabilities of the entire business link of the supply chain.
[0003] The core business system of the modern smart supply chain includes: "3" business chain modules based on the three major smart business chains of intelligent procurement, digital logistics, and panoramic quality control, to achieve intelligent connection of the entire supply chain business; supported by "2" efficient internal and external collaborations, to deepen the cross-business intelligent collaboration within the enterprise internally, and to extend the cross-enterprise intelligent collaboration of upstream and downstream enterprises in the supply chain externally, to improve the service quality and value of each link in the supply chain; with smart operation as "1" important core, relying on the supply chain operation center, to improve the data mining and value creation capabilities of the entire supply chain process, improve the efficiency and benefits of supply chain operations, and achieve orderly and smart operations.
[0004] How to make "material big data" play its "data value" in front-line project management, and effectively help project managers solve front-line problems in the entire life cycle of projects, including initial approval of the project, project procurement, project commencement, electrical installation, equipment testing, and project commissioning, is a key demand that urgently needs to be developed in the current power grid material supply chain. Summary of the invention
[0005] The purpose of the present invention is to overcome the defects of the above-mentioned prior art and provide a power grid enterprise engineering project material support coordination system.
[0006] The purpose of the present invention can be achieved by the following technical solutions:
[0007] A material support coordination system for power grid enterprise engineering projects, comprising:
[0008] A template building module is used to create a project template for the project to be managed. The project template includes the project links related to the supply chain in the project life cycle, the start and end time of each project link, and the material budget of each project link;
[0009] A data association module, which associates the material database or the digital supply chain with the project template;
[0010] A query module is configured to query data of various project links of the project;
[0011] The operation reminder module includes a progress reminder unit and a material reminder unit.
[0012] Furthermore, the template construction module includes multiple pre-set project link components, and the project template is obtained by selecting and combining the multiple pre-set project link components. The process of obtaining the pre-set project link components is: obtaining the full-process business information of multiple projects, extracting the process nodes related to the supply chain in the full-process business information, and combining the process nodes into project link components.
[0013] Furthermore, the process nodes are combined into project link components as follows:
[0014] Traverse each process node according to the project life cycle, define two process nodes with a time interval less than a preset time threshold as adjacent process nodes, define two process nodes with the same material requirements as homologous process nodes, and combine multiple process nodes that are adjacent process nodes and homologous process nodes into a project link component.
[0015] Furthermore, the progress reminder unit is used to obtain the current time and the current project progress. If the current project link in the current project progress has ended, a new link start reminder is issued when the difference between the current time and the start time of the next project link is less than a preset first time threshold. If the current project link in the current project progress has not ended, a project deadline reminder is issued when the difference between the current time and the end time of the current project link is less than a preset second time threshold.
[0016] Furthermore, the material reminder unit is used to obtain the current time, the materials to be supplied and the supply time nodes of various materials to be supplied. If the difference between the current time and the supply time node of a type of material to be supplied is less than the preset supply time threshold of this type of supply material, a material shortage reminder is issued.
[0017] Furthermore, the operation reminder module also includes an early warning unit, which includes a plurality of pre-set early warning rules. If any early warning rule is satisfied during the project life cycle, the early warning corresponding to the early warning rule is triggered.
[0018] Furthermore, the warning rules include:
[0019] Supplier warning: if the supplier of the materials is on the pre-recorded supplier warning list, a supplier risk warning will be issued;
[0020] Material supply shortage warning: if the type of material is on the pre-recorded material supply shortage warning list, a material supply shortage warning will be issued.
[0021] Furthermore, the supplier warning list and the material supply interruption warning list are updated according to a preset update cycle.
[0022] Furthermore, it also includes a to-do list module, which includes a to-do list creation unit and a to-do list reminder unit. The to-do list creation unit is used to create to-do list tasks. The to-do list reminder unit includes an advance reminder unit and a warning unit. The advance reminder unit issues a to-do list reminder before the execution time, and the warning unit issues a to-do list overdue warning after the execution time.
[0023] Furthermore, the to-do task includes a task name, a reminder time, an execution time, a content, and a priority, and the execution time of the to-do task is within the project life cycle.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] Make full use of material big data for project management and monitor all aspects of the project, which improves the project manager's business management capabilities and efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a structural schematic diagram of the present invention. DETAILED DESCRIPTION
[0027] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific operation process are given. Obviously, the described embodiment is only an embodiment of a part of the present invention, not all embodiments, and the protection scope of the present invention is not limited to the following embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work should fall within the scope of protection of the present invention.
[0028] As used herein, "one embodiment" or "embodiment" refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. In the description of the present invention, it is to be understood that the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units that are inherent to these processes, methods, products or devices.
[0029] A material support coordination system for power grid enterprise engineering projects, such as Figure 1 As shown, including:
[0030] (1) Template building module, which creates a project template for the project to be managed. The project template includes the project links related to the supply chain in the project life cycle, the start and end time of each project link, and the material budget of each project link;
[0031] The template construction module includes multiple pre-set project link components. The project template is obtained by selecting and combining multiple pre-set project link components. The process of obtaining the pre-set project link components is: obtaining the full-process business information of multiple projects, extracting the process nodes related to the supply chain in the full-process business information, and combining the process nodes into project link components.
[0032] In order to simplify project management, process nodes are combined into project link components, specifically:
[0033] Traverse each process node according to the project life cycle, define two process nodes with a time interval less than a preset time threshold as adjacent process nodes, define two process nodes with the same material requirements as homologous process nodes, and combine multiple process nodes that are adjacent process nodes and homologous process nodes into a project link component.
[0034] Collect key business information from the entire process, including the early stages of a project, project execution, planning, bidding and procurement, contract supply, warehousing and distribution, and waste disposal, design a visual capability analysis template for key links in the supply chain from a project perspective, then screen the process nodes related to material supply, and further combine the process nodes into project link components. For new projects, you can directly select the appropriate project link component, configure its start and end time and material budget, and conduct a visual capability analysis of key links in the supply chain from a project perspective, supporting project managers to query the business volume of the entire chain of materials, the duration between each business link, etc. from a project perspective according to the dimensions of individual projects, project types, time, etc., and ultimately form a supply chain workflow for project managers from a project perspective, helping project managers to fully grasp the material situation of the project and assisting project managers in improving their analytical capabilities in terms of material supply assurance.
[0035] (2) Data association module, which associates the material database or digital supply chain with the project template;
[0036] The reliability of data is directly related to whether the power grid enterprise engineering project material support collaborative system can operate normally. The various types of business data involved in the project must be accurate and reliable to truly reflect the actual working conditions of the supply chain operation. The existing smart supply chain can be connected to the system, or to a material management database that stores real-time material information. Information such as material transportation in the supply chain can be fed back to the power grid enterprise engineering project material support collaborative system in real time, and the material information of each project link can be updated. The modern smart supply chain has been built, and the embodiment of this application directly connects to the modern smart supply chain, relying on the smart supply chain operation center to provide relevant data information. At the same time, it also expands the application scenarios of the operation center data and gives full play to the "data value".
[0037] (3) a query module, configured to query data of various project links of the project;
[0038] The multi-dimensional query and statistical functions of the entire chain of information support the project manager's ability to apply the relevant scenario functions of the entire chain of project materials, and realize the visualization of the statistical capabilities of the entire chain of project materials information to improve the key links of the supply chain.
[0039] (4) Operation reminder module, including progress reminder unit, material reminder unit and early warning unit.
[0040] (4.1) The progress reminder unit is used to obtain the current time and the current project progress. If the current project link in the current project progress has ended, a new link start reminder is issued when the difference between the current time and the start time of the next project link is less than a preset first time threshold. If the current project link in the current project progress has not ended, a project deadline reminder is issued when the difference between the current time and the end time of the current project link is less than a preset second time threshold.
[0041] (4.2) The material reminder unit is used to obtain the current time, the materials to be supplied, and the supply time nodes of various materials to be supplied. If the difference between the current time and the supply time node of a type of material to be supplied is less than the preset supply time threshold of this type of supply material, a material shortage reminder is issued.
[0042] The progress reminder unit and the material reminder unit support the project manager to carry out monitoring, early warning and exception handling capabilities of key links in the material supply chain from a project perspective. On the one hand, for the advancement of each link of the project, by comparing the current project progress with the expected schedule, the progress reminder unit issues new link start reminders and project deadline reminders; on the other hand, considering that the project links involve supply chain materials, the expected supply time nodes of various materials under each project link are set in advance. If the material supply is not completed at the supply time node, the lack of such materials may affect the advancement of the project, so a material shortage reminder is also set to further help the project manager manage the project in an all-round way.
[0043] (4.3) The early warning unit includes multiple pre-set early warning rules. If any early warning rule is met during the project life cycle, the early warning corresponding to the early warning rule will be triggered.
[0044] The warning rules include:
[0045] Supplier warning: if the supplier of the materials is on the pre-recorded supplier warning list, a supplier risk warning will be issued;
[0046] Material supply shortage warning: if the type of material is on the pre-recorded material supply shortage warning list, a material supply shortage warning will be issued.
[0047] Among them, the supplier warning list and material supply interruption warning list are updated according to the preset update cycle to ensure their accuracy.
[0048] In addition to the progress reminder unit and material reminder unit related to the progress of the project, this application also sets up an early warning unit to provide advance warning for the project based on historical experience. Suppliers that have had problems with supply quality, delivery time, etc. will be included in the supplier early warning list to remind project managers to pay attention to the supplier and make risk plans; materials that have been short of materials, poor quality, and drastically fluctuating prices will be included in the material supply interruption early warning list to remind project managers to focus on such materials and make risk plans.
[0049] Provide early warning of business risk points in each business link, promptly assist project managers in problem solving, accumulate experience in the process, and form pre-warning, in-process control, and overdue warning mechanisms and methods for the entire business process to shorten the overall project supply cycle and improve the efficiency of material supply chain management.
[0050] In addition, other early warning rules can be added as needed to issue timely warnings and prompt relevant personnel for timely intervention based on different types of reasons that lead to delays in project engineering time nodes and when risks occur in material supply (such as: supply interruption according to the agreement, supply interruption from the warehouse, insufficient supplier production capacity, and quality problems with supplied materials), thereby improving the project manager's ability to understand the performance risks of materials not being supplied in a timely manner.
[0051] (5) To-do list module. The to-do list module includes a to-do list creation unit and a to-do list reminder unit. The to-do list creation unit is used to create to-do list tasks. The to-do list reminder unit includes a pre-reminder unit and a warning unit. The pre-reminder unit issues a to-do list reminder before the execution time, and the warning unit issues a to-do list overdue warning after the execution time.
[0052] To-do tasks include item name, reminder time, execution time, content, and priority. The execution time of to-do tasks is within the project life cycle.
[0053] The to-do module supports planning and contract fulfillment, and promptly reminds and eliminates abnormal to-do and business to-do items such as batch submission to-do items, drawing confirmation to-do items, and overlong order processing to-do items. Project managers can also sort out daily to-do task lists, sort out and analyze relevant data, extract relevant factors, design a project perspective supply chain related links to-do task analysis report template, and conduct project perspective supply chain related links to-do task analysis.
[0054] The present invention makes full use of material big data for project management and monitors all aspects of the project, thereby improving the project manager's business management ability and efficiency, and improving the monitoring, early warning and exception handling capabilities of key links in the supply chain, allowing project managers to "manage" their business, and improving the ability to actively remind of pending tasks in related links of the supply chain, making project managers' work efficiency "higher", improving the ability to gain insight into performance risks, and "preventing" business management risks, thereby achieving the company's goals of building a modern intelligent supply chain system, and providing strong operational capability support for improving the security and stability of the supply chain and industrial chain.
[0055] The visual analysis capability improvement, monitoring and early warning reminder mechanism construction and business to-do reminder of the present invention mainly rely on the relevant data information provided by the smart supply chain operation center, so the system security and reliability follow the existing system platform design of the operation center. The various indicator systems and model algorithms involved can run stably.
[0056] The preferred specific embodiments of the present invention are described in detail above. It should be understood that a person skilled in the art can make many modifications and changes based on the concept of the present invention without creative work. Therefore, any technical solution that can be obtained by a person skilled in the art through logical analysis, reasoning or limited experiments based on the concept of the present invention on the basis of the prior art should be within the scope of protection determined by the claims.
Claims
1. A material support coordination system for power grid enterprise engineering projects, characterized in that: include: A template building module is used to create a project template for the project to be managed. The project template includes the project links related to the supply chain in the project life cycle, the start and end time of each project link, and the material budget of each project link; A data association module, which associates the material database or the digital supply chain with the project template; A query module is configured to query data of various project links of the project; The operation reminder module includes a progress reminder unit and a material reminder unit.
2. A power grid enterprise project material support coordination system according to claim 1, characterized in that: The template construction module includes multiple pre-set project link components. The project template is obtained by selecting and combining the multiple pre-set project link components. The process of obtaining the pre-set project link components is: obtaining the full-process business information of multiple projects, extracting the process nodes related to the supply chain in the full-process business information, and combining the process nodes into project link components.
3. A power grid enterprise project material support coordination system according to claim 2, characterized in that: Combining the process nodes into project link components is specifically as follows: Traverse each process node according to the project life cycle, define two process nodes with a time interval less than a preset time threshold as adjacent process nodes, define two process nodes with the same material requirements as homologous process nodes, and combine multiple process nodes that are adjacent process nodes and homologous process nodes into a project link component.
4. A power grid enterprise project material support coordination system according to claim 1, characterized in that: The progress reminder unit is used to obtain the current time and the current project progress. If the current project link in the current project progress has ended, a new link start reminder is issued when the difference between the current time and the start time of the next project link is less than a preset first time threshold. If the current project link in the current project progress has not ended, a project deadline reminder is issued when the difference between the current time and the end time of the current project link is less than a preset second time threshold.
5. A power grid enterprise project material support coordination system according to claim 1, characterized in that: The material reminder unit is used to obtain the current time, the materials to be supplied and the supply time nodes of various materials to be supplied. If the difference between the current time and the supply time node of a type of material to be supplied is less than the preset supply time threshold of this type of supply material, a material shortage reminder is issued.
6. A power grid enterprise project material support coordination system according to claim 1, characterized in that: The operation reminder module also includes an early warning unit, which includes a plurality of pre-set early warning rules. If any early warning rule is satisfied during the project life cycle, the early warning corresponding to the early warning rule is triggered.
7. A power grid enterprise project material support coordination system according to claim 6, characterized in that: The warning rules include: Supplier warning: if the supplier of the materials is on the pre-recorded supplier warning list, a supplier risk warning will be issued; Material supply shortage warning: if the type of material is on the pre-recorded material supply shortage warning list, a material supply shortage warning will be issued.
8. A power grid enterprise project material support coordination system according to claim 7, characterized in that: The supplier warning list and material supply interruption warning list are updated according to a preset update cycle.
9. A power grid enterprise project material support coordination system according to claim 1, characterized in that: It also includes a to-do list module, which includes a to-do list creation unit and a to-do list reminder unit. The to-do list creation unit is used to create to-do list tasks. The to-do list reminder unit includes an advance reminder unit and a warning unit. The advance reminder unit issues a to-do list reminder before the execution time, and the warning unit issues a to-do list overdue warning after the execution time.
10. A power grid enterprise project material support coordination system according to claim 9, characterized in that: The to-do task includes the item name, reminder time, execution time, content, and priority, and the execution time of the to-do task is within the project life cycle.