Virtual power plant scheduling method and system taking heavy gas turbine as main body
By considering the gas turbine operation and cranking time constraints in the virtual power plant, and adjusting the output plan of the gas turbine and energy storage, the existing technology solves the problems of grid security and low solution efficiency when medium and heavy gas turbines participate in the virtual power plant, and achieves Efficient grid operation.
Patent Information
- Application Number
- CN202410747316.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-11
- Publication Date
- 2024-10-01
AI Technical Summary
When considering the participation of heavy-duty gas turbines, existing virtual power plants fail to effectively consider gas turbine operation constraints and cranking time constraints, resulting in threats to the safe operation of the power grid and low solution efficiency.
A virtual power plant scheduling method based on heavy-duty gas turbines is adopted. By obtaining equipment parameters, in the day-ahead scheduling and real-time scheduling stages, adjustments are made based on gas turbine operation constraints, cranking time constraints, energy storage device operation constraints and new energy constraints. The output plan of the gas turbine and energy storage simplifies the turning time constraints to improve the solution efficiency.
It effectively avoids the harm of gas turbine overload to the power grid, improves the solution efficiency in the day-ahead dispatching and real-time dispatch phases, and realizes the safe and efficient operation of heavy-duty gas turbines in the virtual power plant.
Smart Images

Figure CN118735172A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of virtual power plant scheduling, and in particular relates to a virtual power plant scheduling method and system with heavy-duty gas turbines as the main body. Background Art
[0002] The statements in this section merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] In the context of the increasing proportion of new energy, heavy-duty gas turbines can greatly make up for the defects of new energy output fluctuations and improve system stability due to their fast start-up and strong regulation capabilities. However, due to the high cost of gas, the economic efficiency of independent operation of heavy-duty gas turbines is poor. Therefore, it is urgent to establish accurate physical modeling of heavy-duty gas turbines and explore the operation strategies and profit methods of heavy-duty gas turbines in different scenarios.
[0004] As the utilization value of distributed resources is continuously explored, the operation and scheduling strategy of virtual power plants, as a technology that can integrate distributed resources on the demand side and smooth the volatility of new energy output, is currently a key research direction.
[0005] Combining the resource integration capability of virtual power plants with the rapid adjustment capability of heavy-duty gas turbines, exploring the operation mode of aggregating heavy-duty gas turbines with new energy and other distributed resources into virtual power plants is a promising way to promote heavy-duty gas turbines. However, existing virtual power plants do not consider the operation constraints and cranking time constraints of gas turbines when considering the participation of heavy-duty gas turbines, which not only endangers the safe operation of the power grid, but also has low solution efficiency. Summary of the invention
[0006] In order to solve the technical problems existing in the above-mentioned background technology, the present invention provides a virtual power plant scheduling method and system with heavy-duty gas turbines as the main body, explores the feasibility of virtual power plants with heavy-duty gas turbines as the main body participating in the electricity market, and constrains the operation of the gas turbines and the gas turbine cranking time, effectively avoiding the overload caused by the gas turbines from causing harm to the safe operation of the power grid, and through the assumption of the gas turbine cranking time constraint, the gas turbine cranking time constraint is simplified, thereby improving the solution efficiency of the day-ahead scheduling stage and the real-time scheduling stage.
[0007] In order to achieve the above object, the present invention adopts the following technical solution:
[0008] A first aspect of the present invention provides a virtual power plant scheduling method with a heavy-duty gas turbine as the main body, comprising:
[0009] Get device parameters;
[0010] In the day-ahead dispatch stage, based on equipment parameters, under the constraints of gas turbine operation, gas turbine cranking time, energy storage device operation, new energy operation and ramping auxiliary service, the output plan of gas turbines and energy storage in the virtual power plant, the total power purchase and ramping capacity of the virtual power plant are adjusted, and the total power purchase and ramping capacity are used as the bidding plan to obtain the clearing electricity price;
[0011] In the real-time dispatching stage, based on equipment parameters and clearing electricity prices, the real-time output plans of gas turbines and energy storage are adjusted within the constraints of gas turbine operation, gas turbine cranking time, energy storage device operation, and new energy operation, and the gas turbines and energy storage are dispatched;
[0012] Among them, the assumption of the gas turbine cranking time constraint is that the turbine is only shut down once in each scheduling cycle, and the situation where the shutdown exceeds the day-ahead scheduling cycle is not considered.
[0013] Furthermore, the gas turbine operation constraints in the day-ahead scheduling stage and the real-time scheduling stage include: gas turbine power upper and lower limit constraints, gas turbine minimum operation time constraints, gas turbine minimum shutdown time constraints and gas turbine ramp constraints.
[0014] Furthermore, the energy storage device operation constraints in the day-ahead scheduling phase include: a charge state continuity constraint of the energy storage device, upper and lower limit constraints of the charge state of the energy storage device, a power constraint of the energy storage device, and a constraint that the charge level of the energy storage device remains unchanged during the scheduling period;
[0015] Alternatively, the energy storage device operation constraints in the real-time scheduling stage include: a state of charge continuity constraint of the energy storage device, upper and lower limit constraints of the state of charge of the energy storage device, and a power constraint of the energy storage device.
[0016] Furthermore, the real-time scheduling stage aims to minimize the real-time total operating cost, and the total operating cost is apportioned according to the contribution of each device within the virtual power plant.
[0017] Furthermore, the goals of the day-ahead dispatch phase are to minimize the total operating cost of the gas turbine, minimize the total operating cost of the energy storage, minimize the electricity purchase cost, maximize the income from electricity sales, and maximize the income from participating in the ramp assist service.
[0018] Furthermore, the ramping auxiliary service constraints include: a constraint that the ramping capacity of the virtual power plant is determined by the baseline load, and bidding constraints for the up-ramp capacity and the down-ramp capacity.
[0019] A second aspect of the present invention provides a virtual power plant dispatching system with a heavy-duty gas turbine as the main body, comprising:
[0020] A data acquisition module is configured to: acquire device parameters;
[0021] The day-ahead dispatch module is configured to: in the day-ahead dispatch stage, based on equipment parameters, under the constraints of gas turbine operation, gas turbine cranking time, energy storage device operation, new energy operation and ramping auxiliary service, adjust the output plan of gas turbines and energy storage in the virtual power plant, the total power purchase and ramping capacity of the virtual power plant, and use the total power purchase and ramping capacity as the bidding plan to obtain the clearing electricity price;
[0022] The real-time dispatching module is configured to: in the real-time dispatching stage, based on the equipment parameters and the clearing electricity price, adjust the real-time output plan of the gas turbine and the energy storage device within the gas turbine operation constraints, the gas turbine cranking time constraints, the energy storage device operation constraints and the new energy operation constraints, and dispatch the gas turbine and the energy storage device;
[0023] Among them, the assumption of the gas turbine cranking time constraint is that the turbine is only shut down once in each scheduling cycle, and the situation where the shutdown exceeds the day-ahead scheduling cycle is not considered.
[0024] A third aspect of the present invention provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps in the virtual power plant scheduling method with heavy-duty gas turbines as the main body as described above.
[0025] The fourth aspect of the present invention provides a computer device, including a computer-readable storage medium, a processor, and a computer program stored on the computer-readable storage medium and executable on the processor, wherein when the processor executes the program, the steps in the virtual power plant scheduling method with heavy-duty gas turbines as the main body as described above are implemented.
[0026] A fifth aspect of the present invention provides a computer program product, which is a computer program product containing a computer program. When a processor executes the computer program, the steps in the virtual power plant scheduling method with heavy-duty gas turbines as the main body as described above are implemented.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] The present invention constructs accurate heavy-duty gas turbine operation constraints based on actual operation data and electrical characteristics of heavy-duty gas turbines, and combines energy storage, new energy and other equipment to construct a virtual power plant with heavy-duty gas turbines as the main body, and fully considers the market clearing mechanism, establishes a day-ahead scheduling model for the virtual power plant, and based on the day-ahead scheduling results, establishes a real-time scheduling model for the virtual power plant, forms a day-ahead-real-time market coupled scheduling model, realizes the scheduling of gas turbines and energy storage in the virtual power plant with heavy-duty gas turbines as the main body, and explores the feasibility of the virtual power plant with heavy-duty gas turbines as the main body participating in the electricity market.
[0029] The present invention constrains the operation of the gas turbine and the cranking time of the gas turbine, effectively preventing the overload caused by the gas turbine from endangering the safe operation of the power grid, and simplifies the cranking time constraint of the gas turbine through the assumption of the cranking time constraint of the gas turbine, thereby improving the solution efficiency of the day-ahead scheduling stage and the real-time scheduling stage. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0031] Figure 1 is a schematic diagram of a market operation framework of the first embodiment of the present invention;
[0032] Figure 2 It is a structural diagram of a computer device according to a fourth embodiment of the present invention. DETAILED DESCRIPTION
[0033] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0034] It should be noted that the following detailed descriptions are all illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.
[0035] Embodiment 1
[0036] This embodiment provides a virtual power plant scheduling method with heavy-duty gas turbines as the main body.
[0037] This embodiment provides a virtual power plant scheduling method with heavy-duty gas turbines as the main body, constructs an accurate heavy-duty gas turbine operation model and cost function considering the cranking time constraint, takes the electricity market rules as the background, considers the coupling of the electricity market and the ramp auxiliary service market, explores the feasibility and profit model of virtual power plants with heavy-duty gas turbines as the main body participating in the electricity market, and adopts an improved Shapley value method for profit distribution.
[0038] At present, the market-oriented reform of the power industry is deepening, and many regions have established market-oriented power trading models. In the power market, in addition to the day-ahead and real-time power markets, auxiliary service markets have been established to achieve different purposes and functions. Under the market-oriented trend, exploring the participation of demand-side resources such as virtual power plants in the power market interaction is an important part of improving the power market mechanism.
[0039] This embodiment provides a virtual power plant scheduling method with heavy-duty gas turbines as the main body, including the following steps:
[0040] Step 1: Construct accurate heavy-duty gas turbine constraint models, energy storage device constraint models, and new energy constraint models;
[0041] Step 2: Build a market operation framework and a market clearing mechanism model, and establish the day-ahead and real-time dispatch objective functions of a virtual power plant with heavy-duty gas turbines as the main body under the market rules;
[0042] Step 3: After obtaining the real-time operation scheduling results, a weighted Shapley value method is used to distribute the benefits of various entities within the virtual power plant.
[0043] It should be noted that the various devices in a virtual power plant generally belong to different interest entities. The various devices are aggregated into a virtual power plant for the purpose of profit, and the profits obtained need to be distributed after scheduling.
[0044] For the heavy-duty gas turbine constraint model in step 1, the heavy-duty gas turbine operation constraint is expressed as:
[0045]
[0046]
[0047]
[0048] -Δ down,u ≤P u (t)-P u (t-1)≤Δ up,u (4)
[0049] Constraints (1)-(4) are heavy-duty gas turbine operation constraints, which are the upper and lower limits of gas turbine power, the minimum gas turbine operation time, the minimum gas turbine shutdown time, and the gas turbine ramp constraint.
[0050] in, P u and They are the upper and lower limits of heavy-duty gas turbine power respectively; P u (t) is the power of the heavy-duty combustion engine at the tth moment; U u (t) is the binary variable of the engine operation state; U start,u (t), U shut,u (t) are binary variables for the start and stop states of the gas turbine, respectively, U start,u (t) When it is 1, it means the engine starts at time t, U shut,u When (t) is 1, it means the engine is shut down at time t; MOT u 、MDT u are the minimum operating time and the minimum downtime respectively; Δ down,u , Δup,u is the power constraint of the gas turbine for ramping down and ramping up; T represents the scheduling period.
[0051] According to the requirements for starting and stopping heavy-duty gas turbines, the constraint model of heavy-duty gas turbines has the following cranking time constraints: cold start, cranking for more than 6 hours; if the unit is not stopped before starting, it can be started directly without cranking; if the unit is stopped for m hours, it needs to be cranked for 2m hours before starting (if 2m<6, then 6 is taken, if 2m>24, then 24 is taken). In order to simplify the cranking time constraints and improve the solution efficiency, the following reasonable assumptions are made for the cranking time:
[0052] ①Only one suspension is allowed in each scheduling cycle;
[0053] ② Long-term shutdown will cause damage to the gas turbine, and the scheduling cycle of the day-ahead scheduling is only 24 hours, so the situation of shutdown exceeding 24 hours is not considered.
[0054] Therefore, the cranking time constraint is expressed as:
[0055]
[0056] U p,start (t)≥U p (t)-U p (t-1) (6)
[0057]
[0058] U u (t)≤x(t)≤U p (t) (9)
[0059] x(t)≥x(t-1) (10)
[0060] Among them, U p (t) is a binary variable for the cranking state of the heavy-duty gas turbine, 1 indicates that the gas turbine is in a rotating state (including cranking and gas turbine operation), and 0 indicates that the turbine is stopped; U p,start (t) is a binary variable for the cranking stop state, 1 indicates the cranking start; x(t) indicates the gas turbine start permission flag, when its value is 1, the gas turbine is allowed to start, M is a sufficiently large positive number, and its role is to assist logical constraints. Taking formula (7) as an example, when 1-U p,start,s When (t) is 0, 0×M=0, and constraint (7) takes effect; when 1-U p,start,s When (t) is 1, 1×M=M, and constraint (7) is meaningless and has no effect.
[0061] Constraint (5) constrains the heavy-duty gas turbine to only be shut down once during the scheduling cycle. Constraint (6) is U p (t) and Up,start (t). Constraint (7) corresponds to the requirement: if the unit is shut down for m hours, it needs to be shut down for 2m hours before starting. Constraint (8) corresponds to the requirement: if 2m<6, then take 6. Constraints (9) and (10) are variables U p (t), x(t), and U p (t) logical relationship constraints.
[0062] In addition to the operation constraints and cranking time constraints, heavy-duty gas turbines need to consider the following costs. The heavy-duty gas turbine constraint model aims to minimize the total operation cost of heavy-duty gas turbines:
[0063]
[0064] Among them, C u is the total operating cost of heavy-duty gas turbine; C fuel,u is the fuel cost; C S,u is the startup cost; C OM,u is the maintenance cost; C e,u C is the environmental cost; DP,u is the depreciation cost; C int is the financial cost, that is, the interest to be repaid on the loan; the rotation state of the engine includes cranking and running state, so U p (t)-U u (t) indicates the working state of the turning motor; K p is the unit time operating cost of the turning motor.
[0065] According to the heavy-duty gas turbine consumption curve, its fuel cost can be expressed as:
[0066]
[0067] Among them, a, b, and c are consumption curve coefficients. The remaining cost calculation formula is:
[0068] C S,u (P u (t)) = S u U start,u (t) (13)
[0069] C OM,u (P u (t)) = K OM,u P u (t)Δt (14)
[0070]
[0071] Among them, S u K is the single start-up cost of the gas turbine; OM,u is the gas turbine operation and maintenance cost coefficient; Δt is the simulation step length; C az,uis the investment cost of the gas turbine; k u is the capacity factor of the gas turbine; n u V is the total annual operating hours of the gas turbine; j is the emission cost per kg of pollutant j; m is the number of pollutant types; Q ij Refers to the amount of pollutants j (kg) generated by the gas turbine for each kilowatt-hour of electricity; C loan 、T loan are respectively the principal of the gas turbine loan and the loan period, year The annual interest rate.
[0072] For the energy storage device constraint model in step 1, it is expressed as:
[0073]
[0074] SOC k (1) = SOC k (T) (21)
[0075] Constraints (18)-(21) are the operating condition constraints of the energy storage device. Among them, constraint (18) is the SOC (state of charge of the energy storage device) continuity constraint; constraint (19) is the SOC upper and lower limit constraints; constraint (20) is the energy storage device power constraint; constraint (21) ensures that the charge level of the energy storage device remains unchanged during the scheduling cycle.
[0076] Where k is the index of the energy storage device; SOC k (t) is the charge level of the energy storage device; SOC k , are the lower and upper limits of the charge level of the energy storage device respectively; P dh,k (t), P ch,k (t) are the discharging and charging power of the energy storage device; E rated,k is the rated capacity of the energy storage device; η dh,k , η ch,k are discharge and charge efficiency respectively; is the self-discharge rate; are the upper limits of charging and discharging power of the energy storage device; P k (t) is the output power of the energy storage device, which is positive for discharge and negative for charge. Its value is equal to P dh,k (t)-P ch,k (t); T is the scheduling period.
[0077] The cost of the energy storage device takes into account the operation and maintenance cost and depreciation cost, that is, the energy storage device constraint model aims to minimize the total operating cost of the energy storage device:
[0078] C k (P k (t)) = C OM,k (Pk (t))+C DP,k (P k (t)) (22)
[0079] Among them, C k is the total operating cost of energy storage device k; C OM,k and C DP,k are the operation and maintenance cost and depreciation cost of energy storage device k respectively, and the calculation formula is as follows:
[0080] C OM,k (P k (t)) = K OM,k |P k (t)|Δt (23)
[0081] C DP,k (P k,s (t))=(E rated,k C E,k +P rated,k C P,k )L loss,k (twenty four)
[0082] Among them, K OM,k is the operation and maintenance cost coefficient of energy storage device k; E rated,k is the rated capacity of energy storage device k, C E,k is the cost per unit capacity; P rated,k is the power capacity of energy storage device k, and C P,k is the cost per unit capacity; L loss,k is the life loss factor of the energy storage device k.
[0083] For the new energy constraint model in step 1, it is expressed as:
[0084]
[0085] Among them, P wt (t), P pv (t) are wind power and photovoltaic output respectively; are wind power and photovoltaic power forecast values respectively. The power generation cost of new energy is not considered.
[0086] In this embodiment, step 2 specifically includes the following steps:
[0087] (1) Description of the market operation framework.
[0088] In the day-ahead stage, the virtual power plant with heavy-duty gas turbines as the main body is based on the day-ahead predicted electricity price ρ buy (t), wind and solar output (P wt (t), P pv (t)) and load (Pd (t)) to optimize the dispatching on the day ahead and submit the bidding plan (power purchase demand (P buy (t)) and climbing capacity ( and )), the market operator obtains the clearing results based on the bidding information of market participants and clears the market.
[0089] In the real-time operation stage, the virtual power plant is based on future wind and solar power, load power and real-time clearing electricity prices. Perform rolling optimization and purchase unbalanced power from the real-time market, and the winning climbing power ( and ) will be called by the market operator in the real-time operation stage. The constraints in the real-time operation stage are the same as those in the day-ahead stage, but the real-time wind, solar and load power will deviate from the wind, solar and load power predicted the day before.
[0090] The market operation framework used in this embodiment is as follows: Figure 1 shown.
[0091] (2) Day-ahead dispatch of virtual power plants.
[0092] In the day-ahead phase, the virtual power plant alliance participates in both the electricity market and the ramping auxiliary service market. The objective function of the day-ahead optimization dispatch is to minimize the total operating cost of the virtual power plant, as shown in formula (27). The constraints of the day-ahead optimization dispatch include power balance constraints and ramping auxiliary service-related constraints, based on equipment parameters (including upper and lower limits of equipment output, such as the upper and lower limits of the power of the gas turbine). P u , Energy storage device SOC limit SOC k , ), the result of the optimal dispatch is the output plan of the gas turbine and energy storage, as well as the purchase and sale plan and ramp capacity, that is, the variable P u (t), P k (t), P buy (t), P sell (t) and
[0093] The objective function of the day-ahead optimal scheduling is constructed based on the heavy-duty gas turbine constraint model, energy storage device constraint model, and new energy constraint model in step 1.
[0094]
[0095] C buy (t) = P buy (t)×ρ buy(t) (28)
[0096] C sell (t) = P sell (t)×ρ sell (t) (29)
[0097]
[0098] Wherein, formula (27) is the objective function of the day-ahead phase; C buy (t), C sell (t) is the electricity purchase cost and electricity sales revenue; B r (t) is the income from participating in the hill climbing assistance service; ρ buy (t) and ρ sell (t) are the purchase price and sales price of electricity respectively; P buy (t) and P sell (t) are the total power purchase and sales of the virtual power plant. Formula (30) is the power balance constraint, where P d (t) is the total load of the virtual power plant.
[0099] Among them, the relevant constraints of the hill climbing assistance service are as follows:
[0100]
[0101] in, are the down-ramp capacity and up-ramp capacity actually provided by the virtual power plant; L base (t) is the baseline load; They are binary variables of downhill climbing and uphill climbing respectively; are the bidding values of the up-ramp and down-ramp capacity of the virtual power plant, respectively; M is a positive infinite value; are the lower limits of the bidding capacity for the upper and lower ramps, respectively; They are respectively the uphill and downhill climbing opening periods.
[0102] Formulas (31)-(32) indicate that the actual ramp capacity needs to be determined by the baseline load; Formulas (33)-(34) constrain the lower limit of the bid for the upper and lower ramp capacities.
[0103] Taking a certain province as an example, the market revenue of the hill climbing assistance service needs to be determined by the actual effective hill climbing capacity. The hill climbing assistance service revenue and the effective hill climbing capacity are determined as follows:
[0104]
[0105] in, are the effective capacity of the uphill and downhill climbs, respectively, which are determined by equations (36) and (37); ρ rUP (t),ρrDN (t) are the up-ramp and down-ramp unit capacity prices of the alliance bidding. In the power market rules of a certain province, the values of τ1, τ2 and τ3 are 1.2, 0.7 and 0.5 respectively.
[0106] However, constraints (36) and (37) are piecewise functions and nonlinear constraints, which are difficult to solve efficiently using commercial solvers. Therefore, auxiliary variables are used to linearize them:
[0107]
[0108] Among them, r1 up , r1 dn and Both are binary auxiliary variables; constraints (36) and (37) correspond to constraints (38) and (39) respectively after linearization.
[0109] The objective function of the day-ahead phase is: (27), and the constraints include: (1)-(26), (28)-(39).
[0110] (3) Real-time dispatch of virtual power plants.
[0111] In the real-time stage, the virtual power plant will adjust the output of internal equipment and power purchase plans based on the actual load, new energy output and real-time electricity prices.
[0112] Compared with the day-ahead stage, the real-time operation stage considers the revenue recovery mechanism. The objective function of the real-time scheduling stage is expressed as:
[0113]
[0114] in, and is the actual operating power of the gas turbine and energy storage; Real-time electricity purchase and sales prices; The real-time imbalance of electricity purchase and sale; C RE (t) is the revenue recovery cost resulting from the change in the power purchase plan, which is calculated as follows:
[0115]
[0116] In the formula, δ0 is the maximum deviation coefficient. Due to the existence of the revenue recovery mechanism, any arbitrage behavior through the day-ahead-real-time electricity price difference cannot be implemented.
[0117] The operating constraints in the real-time phase are the same as those in the day-ahead phase, except for constraint (21) and ramp-related constraints. The result of the real-time operation is the real-time operating power of the gas turbine and energy storage. and Real-time electricity purchase and sale and the total operating cost in real time, i.e., the objective function (40).
[0118] In this embodiment, step 3 specifically includes the following steps:
[0119] Based on the Shapley value definition, the profit or cost to be allocated to each participant in the virtual power plant is:
[0120]
[0121] in, represents the profit or cost shared by participant i in the cooperation; n is the number of participants in the cooperative game; N = {1,…,i,…,n} is the set of participants; Θ is a subset of N; d is the number of participants in subset Θ; v(Θ) is the value of subset Θ.
[0122] Among them, the Shapley value is used to distribute profits based on the contribution of each device within the virtual power plant. Its relationship with the result of real-time scheduling is that the calculation of the Shapley value requires the cost of the real-time scheduling result (the objective function value of real-time scheduling), that is, the calculation of the Shapley value requires the objective function value (cost) of all combinations of these devices participating in the market, that is, the symbol v(Θ). The meaning of v(Θ) is the contribution of the set Θ, that is, the real-time scheduling target cost of the set Θ.
[0123] Since ramping auxiliary services have capacity access conditions, the capacity of each device member within the virtual power plant should also contribute to the profit of the ramping service. However, formula (42) assumes that the proportion of all participants is 1 / n, and does not take into account the proportion of participants. Therefore, weights are introduced in the traditional Shapley value method. According to the consistency game, the weighted Shapley value can be defined as:
[0124]
[0125] in, is a weight vector, which represents the bargaining power of the participants; is the weight of participant i; α Θ It represents the contribution value of the combination containing participant i, which is calculated as:
[0126]
[0127] Where u is the number of participants in set U.
[0128] In this method, the weight vector is the installed capacity proportion of each device in the virtual power plant. Given that participants may make negative contributions to the total profit of the alliance, two bargaining weight vectors are introduced according to the value of the weight vector: and To represent the bargaining power of each participant in the virtual power plant:
[0129]
[0130] Next, the weight of participant i It can be calculated as:
[0131]
[0132] Finally, the weighted Shapley value of each participant in the virtual power plant can be calculated by formula (43).
[0133] This embodiment provides a virtual power plant scheduling method with heavy-duty gas turbines as the main body. According to the actual operating data and electrical characteristics of the heavy-duty gas turbines, accurate heavy-duty gas turbine operating constraints and cost functions are constructed, and combined with energy storage, new energy and other equipment to construct a scheduling strategy model for the virtual power plant with heavy-duty gas turbines as the main body.
[0134] In addition, the present embodiment provides a virtual power plant dispatching method with heavy-duty gas turbines as the main body, which fully considers the market clearing mechanism and operation framework, establishes a day-ahead dispatching model for the virtual power plant, and establishes a real-time dispatching model for the virtual power plant based on the revenue recovery mechanism and day-ahead dispatching results existing in the actual power market, thus forming a day-ahead-real-time market coupled dispatching model.
[0135] This embodiment provides a virtual power plant dispatching method with heavy-duty gas turbines as the main body. In addition to the electricity market, according to the operating rules of the actual electricity market, a joint electricity and ramp auxiliary service market model is constructed, and the ramp auxiliary service market model is linearized using a corresponding method. After the ramp auxiliary service revenue is obtained through settlement, an improved Shapley value method is used to reasonably distribute the revenue of the ramp auxiliary service, which fully considers the capacity contribution of each device in the virtual power plant.
[0136] Embodiment 2
[0137] This embodiment provides a virtual power plant dispatching system with heavy-duty gas turbines as the main body, which specifically includes:
[0138] A data acquisition module is configured to: acquire device parameters;
[0139] The day-ahead dispatch module is configured to: in the day-ahead dispatch stage, based on equipment parameters, under the constraints of gas turbine operation, gas turbine cranking time, energy storage device operation, new energy operation and ramping auxiliary service, adjust the output plan of gas turbines and energy storage in the virtual power plant, the total power purchase and ramping capacity of the virtual power plant, and use the total power purchase and ramping capacity as the bidding plan to obtain the clearing electricity price;
[0140] The real-time dispatching module is configured to: in the real-time dispatching stage, based on the equipment parameters and the clearing electricity price, adjust the real-time output plan of the gas turbine and the energy storage device within the gas turbine operation constraints, the gas turbine cranking time constraints, the energy storage device operation constraints and the new energy operation constraints, and dispatch the gas turbine and the energy storage device;
[0141] Among them, the assumption of the gas turbine cranking time constraint is that the turbine is only shut down once in each scheduling cycle, and the situation where the shutdown exceeds the day-ahead scheduling cycle is not considered.
[0142] It should be noted here that each module in this embodiment corresponds to each step in Example 1 one by one, and the specific implementation process is the same, which will not be repeated here.
[0143] Embodiment 3
[0144] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps in the virtual power plant scheduling method with heavy-duty gas turbines as the main body as described in the above-mentioned embodiment 1 are implemented.
[0145] Embodiment 4
[0146] This embodiment provides a computer device, such as Figure 2 As shown, it includes a computer-readable storage medium 1003, a processor 1001, a communication interface 1002, and a computer program stored on the computer-readable storage medium 1003 and executable on the processor 1001, wherein the processor 1001, the communication interface 1002, and the computer-readable storage medium 1003 can be connected via a bus or other means. The communication interface 1002 is used to receive and send data, and when the processor 1001 executes the program, the steps in the virtual power plant scheduling method with a heavy-duty gas turbine as the main body as described in the first embodiment above are implemented.
[0147] Embodiment 5
[0148] This embodiment provides a computer program product, which is a computer program product containing a computer program. When a processor executes the computer program, the steps in the virtual power plant scheduling method with heavy-duty gas turbines as the main body as described in the above-mentioned embodiment 1 are implemented.
[0149] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0150] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0151] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0152] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A virtual power plant dispatching method based on heavy-duty gas turbines, characterized in that: include: Get device parameters; In the day-ahead dispatch stage, based on equipment parameters, under the constraints of gas turbine operation, gas turbine cranking time, energy storage device operation, new energy operation and ramping auxiliary service, the output plan of gas turbines and energy storage in the virtual power plant, the total power purchase and ramping capacity of the virtual power plant are adjusted, and the total power purchase and ramping capacity are used as the bidding plan to obtain the clearing electricity price; In the real-time dispatching stage, based on equipment parameters and clearing electricity prices, the real-time output plans of gas turbines and energy storage are adjusted within the constraints of gas turbine operation, gas turbine cranking time, energy storage device operation, and new energy operation, and the gas turbines and energy storage are dispatched; Among them, the assumption of the gas turbine cranking time constraint is that the turbine is only shut down once in each scheduling cycle, and the situation where the shutdown exceeds the day-ahead scheduling cycle is not considered.
2. A virtual power plant scheduling method based on heavy-duty gas turbines as claimed in claim 1, characterized in that: The gas turbine operation constraints in the day-ahead scheduling stage and the real-time scheduling stage include: gas turbine power upper and lower limit constraints, gas turbine minimum operation time constraints, gas turbine minimum shutdown time constraints and gas turbine ramp constraints.
3. A virtual power plant scheduling method based on heavy-duty gas turbines as claimed in claim 1, characterized in that: The energy storage device operation constraints in the day-ahead scheduling phase include: the energy storage device's state of charge continuity constraint, the energy storage device's state of charge upper and lower limit constraints, the energy storage device's power constraint, and the energy storage device's charge level unchanged constraint within the scheduling period; Alternatively, the energy storage device operation constraints in the real-time scheduling stage include: a state of charge continuity constraint of the energy storage device, upper and lower limit constraints of the state of charge of the energy storage device, and a power constraint of the energy storage device.
4. A virtual power plant scheduling method based on heavy-duty gas turbines as claimed in claim 1, characterized in that: The real-time scheduling stage aims to minimize the real-time total operating cost, and allocates the total operating cost according to the contribution of each device within the virtual power plant.
5. A virtual power plant scheduling method based on heavy-duty gas turbines as claimed in claim 1, characterized in that: The goals of the day-ahead dispatch phase are to minimize the total operating cost of the gas turbine, minimize the total operating cost of the energy storage, minimize the electricity purchase cost, maximize the revenue from electricity sales, and maximize the revenue from participating in the ramp assist service.
6. A virtual power plant dispatching method based on heavy-duty gas turbines as claimed in claim 1, characterized in that: The ramping auxiliary service constraints include: a constraint that the ramping capacity of the virtual power plant is determined by the baseline load, and bidding constraints for the up-ramp capacity and the down-ramp capacity.
7. A virtual power plant dispatching system based on heavy-duty gas turbines, characterized in that: include: A data acquisition module is configured to: acquire device parameters; The day-ahead dispatch module is configured to: in the day-ahead dispatch stage, based on equipment parameters, under the constraints of gas turbine operation, gas turbine cranking time, energy storage device operation, new energy operation and ramping auxiliary service, adjust the output plan of gas turbines and energy storage in the virtual power plant, the total power purchase and ramping capacity of the virtual power plant, and use the total power purchase and ramping capacity as the bidding plan to obtain the clearing electricity price; The real-time dispatching module is configured to: in the real-time dispatching stage, based on the equipment parameters and the clearing electricity price, adjust the real-time output plan of the gas turbine and the energy storage device within the gas turbine operation constraints, the gas turbine cranking time constraints, the energy storage device operation constraints and the new energy operation constraints, and dispatch the gas turbine and the energy storage device; Among them, the assumption of the gas turbine cranking time constraint is that the turbine is only shut down once in each scheduling cycle, and the situation where the shutdown exceeds the day-ahead scheduling cycle is not considered.
8. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps in a virtual power plant scheduling method with a heavy-duty gas turbine as the main body are implemented as described in any one of claims 1-6.
9. A computer device comprising a computer-readable storage medium, a processor, and a computer program stored on the computer-readable storage medium and executable on the processor, characterized in that: When the processor executes the program, the steps in the virtual power plant scheduling method with heavy-duty gas turbines as the main body are implemented as described in any one of claims 1-6.
10. A computer program product, which is a computer program product containing a computer program, characterized in that When the processor executes the computer program, the steps in the virtual power plant scheduling method with heavy-duty gas turbines as the main body as described in any one of claims 1-6 are implemented.